: 001/IKN/I/2024
QUOTATION
Quotation No. : 001-I-IKN-2024
Date : 16 Januari 2024
Prepared By : GUSTAF
TO :
Attention To :
Phone :
Email :
c. Grounding Pentanahan
- Grounding (Pit) kedalaman 15 m 3 ttk 7,696,978
- Grounding Rod tembaga 18 M1 1,048,096
- Grounding Klem 9 Bh 62,886
- Kabel BC 70 mm 55 M1 161,891
-
d. Instalasi Genset Tangki, Pemipaan Bahan Bakar -
- Tangki bahan bakar ( 2000 liter) tebal 4,5 mm + dudukan 1 M1 38,698,944
- Pemipaan pembuangan asap / Cerobong 1 M1 14,658,838
- Muffier dan Flexibel unit, Joint Valve 1 M1 32,633,038
- Pompa Otomatis bahan bakar + Fiting 1 M1 6,718,567
- Pompa Rotari Hand (Wing Pump) 1 M1 525,661
- Pas. Pipa Galpanis 3/4 " 20 Lot 3,837,645
II TRANSFOEMER
a. 1 Unit 448,320,838
Pengadaan dan Pemasangan Trafo Distribusi 1600 kVA / Tegangan Primary 20,000V,
Tegangan Sekunder 400 VAC,50HZ , Insulasi menggunakan Oli, DYN 5, Dilengkapi
Proteksi DGPT , Bushing ,Grounding Transformer 1 Titik ,BC 70 dan Rod Pentanahan
b. Pengadaan dan Pemasangan MV Switchgear 20kV, Incoming cubicle dan Outgoing 1 unit 170,787,453
Cubicle ( LBS )
QUOTATION
Quotation No. : 001-I-IKN-2024
Date : 16 Januari 2024
Prepared By : GUSTAF
TO :
- Ampermeter 0-200 A / 5A 1 bh 835,406
- CT 2000 A / 5A 3 bh 334,489
- CT 1500 A / 5A 3 bh 285,539
- CT 800 A / 5A 3 bh 195,718
- CT 200 A / 5A 3 bh 148,480
- Voltmeter 0-500 V 1 bh 136,406
- VSS 7 posisi 1 bh 407,913
- Frekuensi meter 47-53 Hz, 220 Vac : 4 bh 1 bh 239,853
- Time switch 24 hours, 220 Vac 1 bh 1,468,487
- Relay / Drycontact Intervacing dg F/A (Fire Alarm) 1 bh 4,894,956
- Panelbox Freestanding uk. 2000 x (800x5) x 800 ( 5 sel ) 5 bh 23,985,283
- Busbar 1 unit 12,384,238
- Internal wiring 1 unit 5,555,775
- Testing & Commisioning 1 Lot 4,894,956
TOTAL :
NOTE PPN 10% :
GRAND TOTAL :
Terms of payment
1. Spesifikasi Pekerjaan Sesuai dengan Penawaran
2. Franco JAKARTA
Reff No. : 001/IKN/I/2024
QUOTATION
Quotation No. : 001-I-IKN-2024
Date : 16 Januari 2024
Prepared By : GUSTAF
TO :
3. Harga Berlaku 1 Minggu dari Penawaran Di terima dan Sewaktu - waktu akan berubah
4. Pembayaran DP 50% dan progres Pekerjaan dan Material Onsite
Approved
Sales Manager
TOTAL PRICE
IDR
3,733,300,000
4,050,000,000
23,090,934
18,865,735
565,972
8,903,982
38,698,944
14,658,838
32,633,038
6,718,567
525,661
76,752,906
448,320,838
170,787,453
75,260,517
63,469,058
52,440,396
10,904,167
13,699,595
18,271,484
6,276,558
231,042
231,042
1,156,189
362,227
171,323
2,506,217
2,506,217
2,506,217
835,406
1,003,466
856,617
587,153
445,441
136,406
407,913
239,853
1,468,487
4,894,956
119,926,416
12,384,238
5,555,775
4,894,956
145,696,918
17,209,129
1,794,817
1,794,817
1,224,171
98,831,076
34,418,257
1,794,817
1,794,817
1,224,171
2,367,258
9,214,034
680,111
680,111
453,407
453,407
172,514
70,737
70,737
63,346
1,393,623
1,029,092
480,166
1,330,276
66,322,926
38,391,810
342,071,025
18,410,792
2,601,429
3,854,538
158,366
101,354
939,640
11,517,543
11,517,543
36,891,650
29,513,320
56,113,162
9,970,099,108
-