Anda di halaman 1dari 14

Management Tata Laksana Proyek

Proyek :
PT. :
No. Kavling :
Coord./Mandor :
Lokasi :

No. Sub. Pekerjaan


I PEK. PERSIAPAN Kayu/Papan/Paku/Benang

II PEK. GALIAN DAN PONDASI Galian Pndasi & Pas. Pondasi

III PEK. BETON DAN STRUKTUR Pabrikasi Besi Beton

IV PEK. PASANGAN BATA DAN PLESTERAN Mobilisasi Pasir, Bata, Semen

V PEK. KUSEN, PINTU DAN JENDELA Pabrikasi Kusen, Pintu & Jendela

VI PEK. KUNCI DAN PENGGANTUNG Pas. Engsel, Kunci

VII PEK. ATAP DAN RANGKA BAJA RINGAN Pabrikasi Rangka Atap, Listplank

VIII PEK. RANGKA DAN PLAFOND Instal rangka & Plafond

IX PEK. MEKANIKAL DAN ELEKTRIKAL ( M/E ) :


A. PEK. MEKANIKAL, PLUMBING, SANITAIR Sparing PVC, In & Outlet
B. PEK. ELEKTRIKAL DAN ARMATUR Sparing PVC, Inbow, Instalasi

X PEK. KERAMIK DAN ORNAMEN Pas. Keramik, WC, Dapur, Ruangan

XI PEK. PENGECATAN DAN FINISHING Cat Kusen, Plafond, Plamir & Dinding

XII PEK. LAIN - LAIN :


A. Pas. Septicktank ( L.80 x P.150 x T. 120 ) Modul Galian & Pas. Bata
B. Pas. Batas Kavling 20/60 Galian dan Pas. Bata
C. Pekerjaan Carport Elevasi dan Cor Beton Tumbuk
D. Pekerjaan taman Sub. Pekerjaan
E. Pekerjaan Fasilatas Sub. Pekerjaan
No. SPK :
Tanggal :
Nilai Rp. :
Periode : s/d

1 2 3 4 5 6 7 8
0% 5% 12% 15% 25% 42% 55% 62%
Bouwplank

Galian
Pas. Pondasi
Sloof Kolom Ringbalk Canopy

Pas. Bata
Plesteran Ornamen Plamir Dalam
Kusen

Rangka Atap & Genteng ListPlank

Plafond Luar

Sparing PVC : 4", 3", 1/2"


Sparing PVC & Inbow Kabel

Keramik Wc Keramik Dapur


Cor Lantai Kerja
Cat Plafond Luar & Ampig

Galian & Pas. Bata, Beton


Galian & Pas. Bata

Papan Pasir Ps. Pasir Btn PVC 4" R. Atap Keramik Gypsum Pasir
Kaso Bata Split 1/2 PVC 3" Genteng Pasir List Profil Bata
Paku Semen Semen PVC 2" Semen Semen F. Kusen Semen
Benang Besi 8mm Kusen PVC 1/2" Bubung Besi Holow Plamir Tbk
Besi 6mm Papan Assesoris GRC Listp. Cat Luar Kabel
Kawat Steiger Lem Grc Plafon Cat Listp.
Pacul Gergaji Drum air Sumur Gali
Blincong Gegep
Ember Stang
Skop
9 10 11 12
70% 80% 95% 100%

Pas. Pintu, Jendela

Rangka & Plafond

Keramik Ruangan

Cat Bag. Dalam & Kusen

alian & Pas. Bata


Pematangan & Cor Beton

Cleaning

Pintu Cat Dalam Perapihan


Kunci Cat Luar Cleanning
Engsel Sanitair Checklist
Cat Plafon Armatur
Bp. Listrik Taman ST. 1 :
Form : Daftar Bahan, Material, Alat
Proyek : No. SPK
PT. : Tanggal
No. Kavling : Nilai Rp.
Coord./Mandor : Periode
Lokasi :
Volume 1
No.
Total
I Bouwplank

No Jenis Material Volume Harga Satuan Total Harga


1 Pek. Begisting
a. benang 5 bh 3,000 15,000
b. ember 6 bh 7,500 45,000
c. paku 2'' 1 kg 15,000 15,000
d. paku 2,5'' 1 kg 15,000 15,000
e. papan 2/20 0.3 m³ 1,900,000 570,000
f. Kayu 4/6 0.3 m³ 1,900,000 570,000
Total
2 Pek. Pondasi.
a. batu bata 120 25.75 m³ 520 1,606,800
b. semen 0.37 25.75 m³ 68,000 647,870
c. pasir 0.11 25.75 m³ 65,000 184,113
Total
3 Pek. Cor Sloof ( 12x15 ) 72.5
a.semen 5.07 1.305 m³ 68,000 449,912
b.pasir 1.1 1.305 m³ 65,000 93,308
c.kerkil 0.5 1.305 m³ 400,000 261,000
d.besi D-8 @ 12 KS 27 btg 45,000 1,215,000
e.besi D-6 @ 10 25 btg 15,000 375,000
f. kawat ikat 2 kg 20,000 40,000
Total 2.624
4 Pek. Dinding
a. batu bata 73 266.5 m² 520 10,116,340
b. semen 0.22 266.5 m² 68,000 3,986,840
c. pasir 0.07 266.5 m² 65,000 1,212,575
Total
5 Pek.Konsen
a. konsen pintu & jendela 99.04 m² 40,000
Total
6 Pek. Ventilasi ( 1x10 )
a. ventilasi kayu 18 m² 80,000
Total
7 Pek. Cor Tiang ( 12x12 ) 73.5
a. semen 5.07 1.059 m³ 68,000 365,101
b. pasir 1.1 1.059 m³ 65,000 75,719
c. kerikil 0.5 1.059 m³ 400,000 211,800
d. besi D-8 @ 12 KS 25 btg 45,000 1,125,000
e. besi D-6 @ 10 18 btg 15,000 270,000
f. Kawat ikat 2 kg 20,000 40,000
Total
8 Pek. Cor Ring Balok ( 12x15 )
a. semen 5.07 1.305 m³ 68,000 449,912
b. pasir 1.1 1.305 m³ 65,000 93,308
c. kerikil 0.5 1.305 m³ 400,000 261,000
d. besi D-8 @ 12 KS 25 btg 45,000 1,125,000
e. besi D-6 @ 10 23 btg 15,000 345,000
f. Kawat ikat 2 kg 20,000 40,000
Total

9 Pek. Penutup Atap.


a. kayu 5/10/4 0.91 m³ 1,900,000 1,729,000
b. kayu 4/6/4 0.9449 m³ 1,900,000 1,795,310
c. kayu 3/3/4 0.47 m³ 1,900,000 893,000
d. papan 2/20/4 0.2021 m³ 1,900,000 383,990
e. papan 2/10/4 0.176 m³ 1,900,000 334,400
f. genteng metal 178 kpg 30,000 5,340,000
g. prabung metal 15 kpg 25,000 375,000
h. paku 2'' 4 kg 15,000 60,000
I. paku 2,5'' 10 kg 15,000 150,000
j. paku 3,5'' 10 kg 15,000 150,000
k. paku 4'' 5 kg 15,000 75,000
l. Paku seng metal 5 kg 20,000 100,000
Total
10 Pek. Plester Dinding.
a. semen 0.175 529.35 m² 68,000 6,299,265
b. pasir 0.024 529.35 m² 65,000 825,786
Total
11 Pek. Cor Lantai T. 0.5.
a. semen 5.07 3.575 m³ 68,000 1,232,517
b. pasir 1.1 3.575 m³ 65,000 255,613
c. kerikil 0.5 3.575 m³ 400,000 715,000
Total
12 Pek. Plamir Dinding
a. semen putih 4 sak 85,000 340,000
b. cat tembok putih/plamir 3 faill 135,000 405,000
c. lempox 5 bks 20,000 100,000
Total
13 Pek. Plapon / Dek.
a. triplek / GRC 4 ml 34 kpg 60,000 2,040,000
b. kayu 4/6/4 1.3336 m³ 1,900,000 2,533,840
c. list siku ( Gipsum ) 50 btg 25,000 1,250,000
d. list propil petak ( Kayu ) 26 btg 20,000 520,000
e. paku 3/4 5 kg 20,000 100,000
f. paku 2'' 4 kg 15,000 60,000
g. paku 2,5'' 5 kg 15,000 75,000
h. paku 3'' 5 kg 15,000 75,000
Total
14 Pek. Keramik Induk
a. keramik 40x40 68 m² 75,000 5,100,000
b. semen 8.35 3.0375 m³ 68,000 1,724,693
c. pasir 1.1 3.0375 m³ 65,000 217,181
d. semen oker 6 bks 12,000 72,000
Total
15 Pek. Keramik Teras
a. keramik 40x40 8 m² 75,000 600,000
b. semen 8.35 0.275 m³ 68,000 156,145
c. pasir 1.1 0.275 m³ 65,000 19,663
d. semen oker 2 bks 12,000 24,000
Total
16 Pek. Keramik KM/WC
a. semen 8.35 1 m³ 68,000 567,800
b. keramik 20x20 6 m² 65,000 390,000
c. keramik 20x25 22 m² 65,000 1,430,000
d. stonosing 60 kpg 2,500 150,000
e. semen oker 4 bks 12,000 48,000
Total

17 Pek. Cor Dak Teras


a. semen 5.07 0.804 m³ 68,000 277,187
b. pasir 1.1 0.804 m³ 65,000 57,486
c. kerikil 0.5 0.804 m³ 400,000 160,800
d. besi D-10 @ 12 KS 10 btg 45,000 450,000
e. kawat ikat 2 kg 20,000 40,000
f. papan 2/20/4 1 m³ 1,900,000 1,900,000
g. kayu 4/6/4 0.288 m³ 1,900,000 547,200
h. triplek 4 ml 2 kpg 60,000 120,000
i. paku 2'' 1 kg 15,000 15,000
j. paku 2,5'' 1 kg 15,000 15,000
k. paku 3'' 1 kg 15,000 15,000
Total
18 Pek. Cat - Catan
a. cat tembok 20 kg 4 faiil 750,000 3,000,000
b. cat tembok 5 kg 3 gln 150,000 450,000
c. cat tembok 20 kg 1 faiil 750,000 750,000
d. cat minyak 1 kg 15 kg 40,000 600,000
e. minyak cat / tinner 4 gln 60,000 240,000
f. Kuas 4'' 4 bh 22,000 88,000
g. kuas 1.5'' 4 bh 10,000 40,000
h. tepung singkuit 8 kg 20,000 160,000
i. Amplas halus 8 lbr 5,000 40,000
j. cornice / conpon 2 krg 80,000 160,000
Total
19 Pek. Cor Dak Knopi
a. semen 5.07 0.6904 m³ 68,000 46,947
b. pasir 1.1 0.6904 m³ 65,000 44,876
c. kerikil 0.5 0.6800 m³ 400,000 272,000
d. besi D-8 @ 12 KS 6 btg 45,000 270,000
e. kawat ikat 0.5 kg 20,000 10,000
f. papan 2/20/4 0.096 m³ 1,900,000 182,400
g. kayu 4/6/4 0.096 m³ 1,900,000 182,400
h. triplek 4 ml 2 kpg 60,000 120,000
Total
20 Pek. Septitang ( 1x1,5x1,5 )
a. batu bata 73 2.25 m³ 520 85,410
b. semen 5.07 2.25 m³ 68,000 775,710
c. pasir 1.1 2.25 m³ 65,000 160,875
d. kerikil 0.45 2.25 m³ 400,000 405,000
e. besi D-8 @ 12 KS 2 btg 45,000 90,000
f. Kawat ikat 0.5 kg 20,000 10,000
g. besi saringan hawa 1 bh 30,000 30,000
Total

21 Pek. Sanitasi
a. kloset duduk 1 bh 250,000 250,000
b. Kloset jongkok 1 bh 450,000 450,000
c. pipa 4'' 3 btg 60,000 180,000
d. pipa 2'' 6 btg 40,000 240,000
e. elbo 4'' 2 bh 8,000 16,000
f. elbo 2'' 6 bh 6,000 36,000
g. pintu fiber 2 bh 190,000 380,000
h. lem pipa 3 ktk 5,000 15,000
i. pipa bak 2 bh 10,000 20,000
j. saringan air 2 bh 35,000 70,000
k. kran air ½'' 2 bh 6,000 12,000
l. kran air ½'' ( stanlis ) 1 bh 35,000 35,000
m. pipa ½'' 6 btg 12,000 72,000
n.elbo ½'' 6 bh 3,000 18,000
o. sok drat dalam ½'' 3 bh 3,000 9,000
p. isolatip 3 bh 1,000 3,000
q. Pipa T 4" 1 bh 8,000 8,000
r. pipa T 2'' 1 bh 5,000 5,000
s. pipa T ½'' 2 bh 3,000 6,000
Total

22 Pek. Pintu & Jendela


a. daun pintu 6 bh 600,000 3,600,000
b. daun jendela 10 bh 200,000 2,000,000
c. kaca polos ( 20x60 ) 4 kpg 40,000 160,000
d. kaca polos ( 50x160 ) 2 kpg 200,000 400,000
Total
23 Pek. Penising
a. kunci pintu depan 2 set 120,000 240,000
b. kunci pintu kamar 4 set 80,000 320,000
c. engsel 4'' 18 pcs 20,000 360,000
d. engsel 3'' 10 pcs 15,000 150,000
e. tarikan jendela 10 bh 6,000 60,000
f. gerendel 10 bh 6,000 60,000
g. hak angin 10 bh 6,000 60,000
h. baut sekrup 1'' 190 bh 150 28,500
i. baut sekrup ½'' 190 bh 150 28,500
Total
24 Pek. Meja Dapur
a. semen 5.07 0.18 m³ 68,000 62,057
b. pasir 1.1 0.18 m³ 65,000 12,870
c. kerikil 0.5 0.18 m³ 400,000 36,000
d. besi D-8 @ 12 KS 3 btg 45,000 135,000
e. keramik 20x25 5 ktk 65,000 325,000
f. Stonosing 15 kpg 2,500 37,500
g. bak cuci piring 1 set 150,000 150,000
Total
25 Pek. Relip
a. semen 5 sak 68,000 340,000
Total
26 Pek. Carpot
a. semen 5.07 0.835 sak 68,000 344,760
b. pasir 1.1 0.835 m³ 65,000 71,500
c. kerikil 0.5 0.835 m³ 400,000 200,000
Total
Bobot / Prosentase
Total
Upah
Pekerjaan Sumur dan Mesin Air
Turap Rumah
Total Keseluruhan
Pemeliharaan 10%
Jumlah
Pembulatan
:
:
: