BankSUMUT
PARKIR MOBIL
TOC. -0.20 PAVING BLOCK
TOC. -0.40
B PEKERJAAN LANTAI - 1
I Pekerjaan Bongkaran
1 Finishing Bongkaran Dinding, Kusen Acian 1 : 3
VI Pekerjaan Pengecatan
1 Cat Tembok Exterior Weathershield Jotun, Nippon Paint, Mowilex, Dulux
2 Cat Tembok Interior Jotun, Mowilex, Vinilex, Dulux
3 Cat Minyak Besi, Kusen dan Pintu Beebrand, Danalux, Avian Paint
4 Cat Vernis Stone Care Propan, setara
B PEKERJAAN LANTAI - 2
I Pekerjaan Bongkaran
1 Finishing Bekas Bongkaran Dinding, Kusen Acian 1 : 3
VI Pekerjaan Pengecatan
1 Cat Tembok Exterior Weathershield Jotun, Nippon Paint, Mowilex, Dulux
2 Cat Tembok Interior Jotun, Mowilex, Vinilex, Dulux
3 Cat Minyak Besi, Kusen dan Pintu Beebrand, Danalux, Avian Paint
4 Sealler Jotun, Vinilex, Dulux, Nippon Paint
1 2 3 4
A PEKERJAAN PENDAHULUAN
A.1 PEK. PERSIAPAN 127,442,004.30
A.2 PEK. PEMBONGKARAN 30,075,000.00
JUMLAH - A. 157,517,004.30
B. PEKERJAAN GEDUNG KANTOR
B.1 PEKERJAAN LANTAI - 1
JUMLAH Rp 4,761,978,936.27
PPN 10% Rp 476,197,893.63
JUMLAH TOTAL Rp 5,238,176,829.89
DIBULATKAN Rp 5,238,176,000.00
Terbilang : Lima Milyar Dua Ratus Tiga Puluh Delapan Juta Seratus Tujuh Puluh Enam Ribu Rupiah.
LOKASI : TARUTUNG
No URAIAN PEKERJAAN Volume Satuan Analisa Harga Satuan (Rp) Jumlah (Rp)
1 2 3 4 5 6 7
A PEKERJAAN PENDAHULUAN
A.1 PEK. PERSIAPAN
1 Mobilisasi dan demobilisasi pekerja dan peralatan 1.00 ls Taksir 5,000,000.00 5,000,000.00
2 Pengadaan Peralatan Kesehatan Konstruksi 1.00 Ls Dihitung 18,545,000.00 18,545,000.00
3 Pengukuran dan Pemasangan Bouwplank 84.00 m1 A.2.2.1.4 99,403.13 8,349,862.50
4 Direksikeet (Meja & kursi pengawas), barak dan Gudang 3x9 m2 27.00 m2 A.2.2.1.5. 1,535,087.28 41,447,356.43
5 Papan Nama Proyek 1.00 Ls Taksir 750,000.00 750,000.00
6 Pengadaan air kerja 1.00 Ls Taksir 2,000,000.00 2,000,000.00
7 Pengadaan listrik kerja 1.00 Ls Taksir 3,500,000.00 3,500,000.00
8 Pembuatan Pagar Seng Keliling Proyek t=2,1 m dan pintu 22.00 m1 A.2.2.1.2 393,172.06 8,649,785.38
9 Keamanan dan jaga malam 1.00 ls Taksir 12,000,000.00 12,000,000.00
10 Biaya Tidak Resmi Pengurusan IMB 1.00 ls Taksir 27,200,000.00 27,200,000.00
Jumlah - A 127,442,004.30
Pembongkaran Dinding Bata, Kosen Pintu / Jendela, Kanopi Beton di Lantai 1 dan 2
3 1.00 Ls Taksir 2,000,000.00 2,000,000.00
Gedung Utama
1 Pas. Pintu PJ1 Double Kaca Tempered t=12 mm, Engsel Floor Hight, fitting engsel, 1.00 set Taksir 11,388,003.90 11,388,003.90
Handle As 60 Petak dan Kunci Tanam + Acc
2 Pintu Type P 1 1.00 unit Taksir 3,100,000.00 3,100,000.00
3 Pintu Type P 3 2.00 unit Taksir 2,500,000.00 5,000,000.00
4 Pintu Type P 4 2.00 unit Taksir 1,800,000.00 3,600,000.00
9 Kabel Fider dari Panel PP ke Panel MDP 4x10 mm2 40.00 m1 Taksir 85,000.00 3,400,000.00
10 Panel Penerangan PP-1 (MCCB, 13 groub MCB, lampun indikator, busbar, Volt meter, 1.00 unit Taksir 4,500,000.00 4,500,000.00
3 Kran air (KR) staynless steel 2.00 unit A.5.1.1.19. 201,135.00 402,270.00
4 Kran air Wudhuk Stainless Steel 3.00 unit A.5.1.1.19. 201,135.00 603,405.00
5 Floor Drain (FD) staynless steel 3.00 unit A.5.1.1.14. 396,635.00 1,189,905.00
6 Pipa PVC air bersih 3/4" AW 122.84 m1 A.5.1.1.26 26,634.00 3,271,707.24
7 Pipa PVC air bekas, hujan dan kotor 3" AW 19.60 m1 A.5.1.1.31. 77,090.25 1,510,968.90
8 Pipa PVC air kotor 4" AW 81.90 m1 A.5.1.1.32. 95,720.25 7,839,488.48
9 Pembuatan septicktank kapst.3 m3 1.00 unit Taksir 3,000,000.00 3,000,000.00
10 Pompa air automatis dorong dari PAM ke rooftank 1.00 unit Taksir 2,000,000.00 2,000,000.00
11 Gauge Valve tahan air turun dari rooftank 1.00 unit Taksir 250,000.00 250,000.00
12 Pemasangan acecoris (Elbo, Soket, Tie, lem pipa dll) 1.00 ls Taksir 1,500,000.00 1,500,000.00
1 Inst. Kabel Telephone 4 x 0,6 mm2 ex. Suprame, Pipa. Flexible & Acc 1.00 ttk Taksir 120,000.00 120,000.00
2 Outlet Telephone ex. MK 1.00 bh Taksir 85,000.00 85,000.00
3 Jack Telephone 1.00 set Taksir 12,000.00 12,000.00
4 Jasa Pemasangan 1.00 ttk Taksir 100,000.00 100,000.00
Jumlah - B.1 (XI) 317,000.00
a R. Kluis
- Beton f'c=19,3 Mpa (K-225) 13.44 m3 A.4.1.1.7 1,205,464.55 16,201,443.50
- Besi beton 2,131.73 kg A.4.1.1.17 16,772.75 35,754,961.97
- Bekisting 134.40 m2 A.4.1.1.25 217,203.38 29,192,133.60
b R Jaminan
- Beton f'c=19,3 Mpa (K-225) 14.70 m3 A.4.1.1.7 1,205,464.55 17,720,328.83
- Besi beton 2,277.75 kg A.4.1.1.17 16,772.75 38,204,048.57
- Bekisting 147.00 m2 A.4.1.1.25 217,203.38 31,928,896.13
Jumlah - B.2 (I) 442,838,626.57
II. Pekerjaan Pasangan Dinding
1 Pas. Dinding Bata 1:4 273.00 m2 A.4.4.1.9 136,792.50 37,344,352.50
2 Plesteran Dinding 1:4 546.00 m2 A.4.4.2.4. 75,134.10 41,023,218.60
3 Finishing/pengecapan kolom, balok dan plat expose beton 1.00 ls Taksir 3,500,000.00 3,500,000.00
4 Pasangan Dinding Keramik 20x40 KM/WC dan Wastafel 57.07 m2 A.4.4.3.41.D 47,466.75 2,708,709.25
5 Pasangan Plint dinding keramik 10x60 cm 346.00 m2 A.4.4.3.63 68,143.25 23,577,564.50
6 Pasangan Plin kayu dinding partisi gypsum t=10 cm 118.13 m1 A.4.4.3.63 68,143.25 8,049,421.41
7 Pasangan dinding Keramik R.Jaminan & Kluis 20x40 cm 134.40 m2 A.4.4.3.41.D 47,466.75 6,379,531.62
Jumlah - B.2 (II) 122,582,797.88
15 Pintu kluis (PK) ex. Mosler/setara 1.00 unit Taksir 90,000,000.00 90,000,000.00
Jumlah - B.2 (V) 243,696,300.00
VI. Pekerjaan Pengecatan
1 Cat Tembok Dinding Exterior Weatherbond 342.72 m2 A.4.7.1.10. 50,587.35 17,337,296.59
2 Cat Tembok Dinding Interior 1,361.22 m2 A.4.7.1.10.B 31,899.85 43,422,713.82
4 Kran air (KR) stainless steel 5.00 unit A.5.1.1.19. 201,135.00 1,005,675.00
5 Floor Drain (FD) stainless steel 5.00 unit A.5.1.1.14. 396,635.00 1,983,175.00
6 Pipa PVC air bersih 3/4" AW 61.00 m1 A.5.1.1.26 26,634.00 1,624,674.00
7 Pipa PVC air kotor dan air Bekas 3" AW 62.00 m1 A.5.1.1.31. 77,090.25 4,779,595.50
8 Pemasangan acecoris (Elbo, Soket, Tie, lem pipa dll) 1.00 ls Taksir 1,500,000.00 1,500,000.00
4 Wall Mounted Rack 9U Double Door Komplit ex. Fortunarack 1.00 unit Taksir 6,500,000.00 6,500,000.00
5 Jasa Pemasangan 26.00 ttk Taksir 250,000.00 6,500,000.00
1 Bungkus Kolom rangka kayu, Plywood 9mm + Rangka Lapis HPL dan cat duco sesuai lo 8.00 unit Taksir 3,500,000.00 28,000,000.00
ruangan teller dan banking hall -
2 Bungkus Portal P-1 dengan ACP + Cat Duco Sesuai Logo rangka besi siku 2.00 unit Taksir 3,500,000.00 7,000,000.00
3 Pembuatan Meja Teller rangka Kayu, dinding blockboard = 18 mm Lapis HPL, Meja dan 10.00 m1 Taksir 4,500,000.00 45,000,000.00
Laci + Acc -
4 Meja Gredenza belakang teller lapis APL + Acc 10.00 m1 Taksir 1,500,000.00 15,000,000.00
5 Lapis dinding wallpaper R.pimpnan dan R.rapat 151.20 m2 A.4.4.3.60 123,438.13 18,663,844.50
6 Handrail Stainless Steel + Kaca Tempered 8 m 111.30 m1 Taksir 2,400,000.00 267,120,000.00
5 Finishing/pengecapan kolom dan balok expose beton pagar 1.00 ls Taksir 2,000,000.00 2,000,000.00
Jumlah - D (III) 5,500,000.00
IV Pekerjaan Pengecatan
1 Cat dinding Exterior ex. Nippon Wheatherbond/Setara 88.00 m2 A.4.7.1.10. 50,587.35 4,451,686.80
2 Cat minyak besi untuk pintu gerbang dan pagar besi hollow 70.40 m2 A.4.7.1.16. 37,076.00 2,610,150.40
Jumlah - D (IV) 7,061,837.20
3 Pemasangan Besi Siku L 50 x 50 x 3 mm untuk RAM 4.00 set Taksir 250,000.00 1,000,000.00
Pemasangan tiang bendera pipa staynless steel dia.2" t=6 m include dudukan, tarikan,
4 1.00 set Taksir 2,500,000.00 2,500,000.00
tali dan bendera
5 Pemasangan Lampu Hias Kolom + instalasi 6.00 unit Taksir 450,000.00 2,700,000.00
Jumlah - E. 32,075,000.00
F. PEKERJAAN AKHIR
1 Photo Dokumentasi dan Laporan 1.00 ls Taksir 2,500,000.00 2,500,000.00
2 Pembersihan Akhir 1.00 ls Taksir 7,500,000.00 7,500,000.00
3 Gambar As Built Drawing 1.00 ls Taksir 4,300,000.00 4,300,000.00
Jumlah - F. 14,300,000.00
No Jenis Pekerjaan Pro Unit Jlh Pjg Lbr Tgg BJ K1 K2 Vol Vol + Volume Satuan
5.00% ###
A PEKERJAAN PENDAHULUAN
A.1 PEK. PERSIAPAN
1 Mobilisasi dan demobilisasi pekerja dan peralatan 1.00 ls
2 Pengadaan Peralatan Kesehatan Konstruksi 1.00 Ls
3 Pengukuran dan Pemasangan Bouwplank 42.00 2.00 84.00 84.00 84.00 m1
4 Direksikeet (Meja & kursi pengawas), barak dan Gudang 3x9 m2 3.00 9.00 27.00 27.00 27.00 m2
5 Papan Nama Proyek 1.00 Ls
6 Pengadaan air kerja 1.00 Ls
7 Pengadaan listrik kerja 1.00 Ls
8 Pembuatan Pagar Seng Keliling Proyek t=2,1 m 22.00 22.00 22.00 22.00 m1
9 Keamanan dan jaga malam 1.00 ls
10 Biaya Tidak Resmi Pengurusan IMB 1.00 ls
Stump 6.00 - - -
- Besi beton 1,376.78 1,445.62 1,445.62 kg
PR1 15.00 1.00 1.00 0.50
Tapak 15.00 8.00 3.15 1.21 456.75 479.59
15.00 8.00 3.15 1.21 456.75 479.59
Stump 15.00 - - -
PR2 6.00 1.20 1.20 0.50
Tapak 6.00 9.00 3.55 1.21 231.64 243.22
6.00 9.00 3.55 1.21 231.64 243.22
Stump 6.00 - - -
- Bekisting 44.40 46.62 46.62 m2
PR1 15.00 1.00 1.00 0.50
Tapak 15.00 4.00 0.50 30.00 31.50
Stump - -
PR2 6.00 1.20 1.20 0.50
Tapak 6.00 4.80 0.50 14.40 15.12
Stump - -
3 Sloof SF1- 20x15 cm 29.72 0.15 0.20
- Beton f'c=19,3 Mpa (K-225) 29.72 0.15 0.20 0.89 0.94 0.94 m3
- Besi beton 206.78 217.12 217.12 kg
2.00 29.72 1.21 71.82 75.41
2.00 29.72 1.21 71.82 75.41
200.00 0.80 0.39 63.13 66.29
- Bekisting 2.00 29.72 0.20 11.89 12.48 12.48 m2
4 Sloof SF2- 20x30 cm 265.40 0.20 0.30
- Beton f'c=19,3 Mpa (K-225) 265.40 0.20 0.30 15.92 16.72 16.72 m3
- Besi beton 3,334.19 3,500.90 3,500.90 kg
3.00 265.40 1.21 962.08 1,010.18
2.00 265.40 1.21 641.39 673.46
3.00 265.40 1.21 962.08 1,010.18
1,771.00 1.10 0.39 768.64 807.07
- Bekisting 2.00 265.40 0.30 159.24 167.20 167.20 m2
5 Kolom
- Beton f'c=19,3 Mpa (K-225) 3.12 3.28 3.28 m3
K1 21.00 0.40 0.40 0.85 2.86 3.00
K2 4.00 0.25 0.25 0.65 0.16 0.17
KP 7.00 0.15 0.15 0.65 0.10 0.11
- Besi beton 1,018.07 1,068.98 1,068.98 kg
K1 21.00 0.40 0.40 0.85
21.00 8.00 2.85 1.58 755.66 793.44
21.00 7.00 1.70 0.39 98.60 103.53
K2 4.00 0.25 0.25 0.65
4.00 8.00 2.65 1.04 88.35 92.77
4.00 6.00 1.10 0.39 10.42 10.94
KP 7.00 0.15 0.15 0.65
7.00 4.00 2.15 0.89 53.44 56.12
7.00 6.00 0.70 0.39 11.60 12.18
- Bekisting 33.89 35.58 35.58 m2
9 Urugan tanah kembali bekas galian 15.37 0.40 6.15 6.45 6.45 m3
10 Tanah urug peninggian lantai (dalam Bangunan) + pemadatan 232.00 243.60 243.60 m3
Bgn Utm Lvl -0.2 688.00 0.30 206.40 216.72 216.72
Lvl -0.0 128.00 0.20 25.60 26.88 26.88
Tangga Ramp/Dipable
L Bgn Lama
L Bgn Baru/ Parkir
R Arsip Utm
R Dinas
3 Finishing/pengecapan kolom, balok dan plat expose beton 1.00 1.00 1.00 1.00 ls
4 Pasangan Dinding Keramik 20x40 KM/WC dan Wastafel 30.87 32.41 32.41 m2
2.00 5.60 2.10 23.52
3.50 2.10 7.35
VI. Pekerjaan Pasangan Kusen, Pintu, Jendela dan Partisi Lt1 Lt2
1 Pas. Pintu PJ1 Double Kaca Tempered t=12 mm, Engsel Floor High 2.00 2.00 2.00 2.00 set
Handle As 60 Petak dan Kunci Tanam + Acc
2 Pintu P 1 1.00 1.00 1.00 1.00 unit
3 Pintu P 3 2.00 2.00 2.00 2.00 unit
4 Pintu P 4 2.00 2.00 2.00 2.00 unit
5 Pintu P 6 2.00 2.00 2.00 2.00 unit
6 Jendela J 1 2.00 2.00 2.00 2.00 unit
7 Jendela J 2 2.00 2.00 2.00 2.00 unit
8 Jendela J 3 3.00 3.00 3.00 3.00 unit
9 Jendela J 5 2.00 2.00 2.00 2.00 unit
10 Jendela J 6 2.00 2.00 2.00 2.00 unit
11 Jendela J 7 1.00 1.00 1.00 1.00 unit
12 Jendela J 8a 1.00 1.00 1.00 1.00 unit
13 Jendela J 8b 1.00 1.00 1.00 1.00 unit
14 Jendela J 8c 1.00 1.00 1.00 1.00 unit
Lantai - -
b R Jaminan
- Beton f'c=19,3 Mpa (K-225) 14.00 14.70 14.70 m3
Lantai 4.75 4.00 0.18 3.42 3.59
Dinding 17.50 4.00 0.20 14.00 14.70
- Besi beton 2,169.28 2,277.75 2,277.75 kg
Dinding 17.50 0.20 4.00
Vrtcl 89.00 8.60 1.21 924.86 971.11
Hrzt 21.00 35.55 0.89 662.76 695.90
Lantai 4.00 4.00 0.15
x,y 2.00 4.00 28.00 1.50 0.89 149.14 156.60
x,y 2.00 2.00 28.00 4.50 0.89 223.72 234.90
x,y 2.00 2.00 28.00 4.20 0.89 208.80 219.24
- Bekisting 140.00 147.00 147.00 m2
Dinding 2.00 17.50 4.00 140.00 147.00
Lantai - -
1 Pas. Pintu PJ2 Kaca Tempered t=12 mm, Engsel Floor Hight, fitting engsel, 2.00 2.00 2.00 2.00 unit
Handle As 60 Petak dan Kunci Tanam + Acc
2 Pas. Pintu PJ3 Kaca Tempered t=12 mm, Engsel Floor Hight, fitting engsel, 4.00 4.00 4.00 4.00 unit
Handle As 60 Petak dan Kunci Tanam + Acc
3 Pintu P 1 3.00 3.00 3.00 3.00 unit
4 Pintu P 2 1.00 1.00 1.00 1.00 unit
5 Pintu P 3 2.00 2.00 2.00 2.00 unit
6 Pintu P 5 2.00 2.00 2.00 2.00 unit
7 Pintu P 6 5.00 5.00 5.00 5.00 unit
8 Jendela J 1 7.00 7.00 7.00 7.00 unit
9 Jendela J 4 6.00 6.00 6.00 6.00 unit
10 Jendela J 5 5.00 5.00 5.00 5.00 unit
11 Jendela J 6 2.00 2.00 2.00 2.00 unit
12 Jendela Type J 9 1.00 1.00 1.00 unit
13 Jendela Type J 9' 1.00 1.00 1.00 unit
14 Partisi PTG-1 rangka C canal, double panel gypsum t=9 mm 225.00 236.25 236.25 m2
Lt1 - - -
Lt2 R Tangga Dpn 4.00 4.00 16.00 16.80 16.80
R H Teller / Teller 6.50 4.00 26.00 27.30 27.30
R Hub/Data 4.00 4.00 16.00 16.80 16.80
R Pimp Cab 17.50 4.00 70.00 73.50 73.50
R W Pim Cab 15.50 4.00 62.00 65.10 65.10
R Rapat 8.75 4.00 35.00 36.75 36.75
15 Pintu kluis (PK) ex. Mosler/setara 1.00 1.00 1.00 1.00 unit
Luas Tanah
-
Bgn Utm Lvl -0.2
R Arsip Utm
R Dinas
7 Pemasangan Paving Block K-225 t = 6 cm + sirtu lapisan bawah dan pasir ut 845.00 845.00 887.25 887.25 m2
8 Pembuatan saluran tertutup plat beton, dinding bata 1:4 40.00 40.00 42.00 42.00 m1
3 Urugan pasir alas pondasi t = 5cm 22.15 0.70 0.05 0.78 0.81 0.81 m3
4 Cor rabat beton alas pondasi t= 5cm Beton 22.15 0.70 0.05 0.78 0.81 0.81 m3
5 Cor tapak pondasi beton bertulang K-175 6.00 ###
Beton normal K-175 6.00 1.00 1.00 0.40 2.40 2.52 2.52 m3
Besi beton polos 2.40 200.00 480.00 504.00 504.00 kg
Bekisting 6.00 4.00 0.40 9.60 10.08 10.08 m2
6 Cor Sloof 20/20 beton bertulang K-175 22.15 ###
Beton normal K-175 22.15 0.30 0.20 1.33 1.40 1.40 m3
Besi beton polos 1.33 300.00 398.70 418.64 418.64 kg
Bekisting 22.15 0.40 8.86 9.30 9.30 m2
7 Cor sloof 15/30 dan plat RAM beton bertulang ###
Beton normal K-175 1.35 2.00 2.70 2.84 2.84 m3
Besi beton polos 217.50 2.00 435.00 456.75 456.75 kg
Bekisting 3.60 2.00 7.20 7.56 7.56 m2
12 Pondasi Pas. Batu Padas 1:3 pagar dan trap pembatas timbunan 22.15 0.45 0.65 6.48 6.80 6.80 m3
IV Pekerjaan Pengecatan
1 Cat dinding Exterior ex. Nippon Wheatherbond/Setara 2.00 22.00 2.00 88.00 88.00 88.00 m2
2 Cat minyak besi untuk pintu gerbang dan pagar besi ho 2.00 22.00 2.00 0.80 70.40 70.40 70.40 m2
G. PEKERJAAN AKHIR
1 Photo Dokumentasi dan Laporan 1.00 ls
2 Pembersihan Akhir 1.00 ls
3 Gambar As Built Drawing 1.00 ls
HARGA SATUAN
NO JENIS TENAGA KERJA SATUAN
(RP/HARI)
1 2 3 4
1 2 3 4
1 2 3 4
3 Rangka Furing m' 5,000.00
4 Kawat Beton kg 20,400.00
5 Kawat Las Dos 148,750.00
6 Jerjak besi biasa m2 390,000.00
7 Jerjak besi bermotif m2 450,000.00
8 Jendela besi m2 420,000.00
9 Paku Biasa kg 18,000.00
10 Paku sekrup kg 25,000.00
11 Paku sekrup 1'' bh 200.00
12 Paku sekrup 3'' bh 500.00
13 Paku seng kg 36,040.00
14 Profil Pintu Aluminium 4'' m' 90,000.00
15 Frame Profil Aluminium m' 63,750.00
16 Aluminium composit panel ( ACP) m2 300,000.00
17 Dinabolt dia 10mm bh 6,800.00
18 Seallent m' 9,500.00
19 Pagar BRC 120 polos m2 605,000.00
20 Rangka Atap kanopi besi hollow terpasang m2 500,000.00
21 Baja ringan canal C75 m' 13,500.00
Bahan-Bahan Penutup Lantai
1 Ubin Granit 30x30 cm bh 40,000.00
2 Conblock #6cm bh 1,600.00
3 Conblock #8cm bh 1,900.00
4 Keramik 20x20 cm bh 2,250.00
5 Keramik 20x25 cm bh 3,500.00
6 Keramik 20x40 cm bh 10,000.00
7 Keramik 30x30 cm bh 6,650.00
8 Keramik 33x33 cm bh 7,310.00
9 Keramik 40x40 cm bh 12,975.00
10 Keramik 60x60 cm bh 56,100.00
11 Keramik Warna Polos 20x20 cm bh 2,250.00
12 Keramik siku ( bon bon) m' 11,000.00
13 Plint keramik 10x 10 cm bh 1,075.00
14 Plint keramik 10x 20 cm bh 1,700.00
15 Plint keramik 10x 30 cm bh 2,210.00
16 Plint keramik 10x 40 cm bh 3,230.00
17 Plint keramik 10 x 60 cm bh 8,415.00
18 Plint Keramik 5x 20 cm bh 1,000.00
19 Wallpaper biasa m' 20,000.00
20 Wallpaper lux bermotif m' 25,000.00
1 2 3 4
8 Rabung Genteng beton Keping 10,200.00
9 Rabung Genteng Metal # 0,30 m' 44,000.00
10 Rabung Zincalume #0,30 Gelombang m' 33,000.00
11 Atap Alumunium Gelambang Tebal 0.55 m2
11 Politur Jadi kg 51,000.00
12 Dempul kg 16,500.00
13 Filler kg 20,000.00
14 Plamur kg 7,500.00
15 Flinkote kg 37,000.00
16 Soda Api kg 18,000.00
17 Residu/ kolter ltr 8,400.00
18 Thinner ltr 25,000.00
19 Sabun kg 12,000.00
20 Teak OIL ltr 65,000.00
21 Kapur Sirih kg 12,000.00
22 Alang -alang ikt 10,000.00
Bahan-Bahan Listrik
1 Instalasi titik nyala titik 121,000.00
2 Instalasi stop kontak titik 121,000.00
3 Lampu SL 24 watt komplet set 44,000.00
4 Lampu SL 18 watt komplet set 35,200.00
5 Lampu SL 10 watt komplet set 31,900.00
6 Lampu TL 1x20 watt komplek kotak set 93,500.00
7 Lampu TL 1x40 watt komplek kotak set 143,000.00
8 Lampu TL 2x20 watt komplek kotak set 187,000.00
9 Lampu TL 2x40 watt komplek kotak set 286,000.00
10 Lampu pijar 5 watt + fitting set 19,250.00
11 Lampu pijar 10 watt + fitting set 24,200.00
12 Lampu pijar 20 watt + fitting set 30,250.00
13 Lampu pijar 40 watt + fitting set 42,350.00
14 Lampu pijar 100 watt + fitting set 49,500.00
15 Saklar tunggal bh 14,300.00
16 Saklar dobel bh 18,700.00
-- Upah dan Bahan -- Hal. 39
HARGA SATUAN
NO URAIAN/JENIS BAHAN BANGUNAN SATUAN ( RP)
1 2 3 4
17 Saklar tripel bh 22,000.00
18 Stop kontak tanam bh 18,150.00
19 Downlight bh 65,000.00
20 MCB 2A bh 42,350.00
21 MCB 4A bh 49,500.00
22 MCB 6A bh 77,000.00
23 MCB 8A bh 10,500.00
24 Box Zekering 1 grup unit 49,500.00
25 Box Zekering 2 grup unit 60,500.00
26 Box Zekering 3 grup unit 66,000.00
27 Box Zekering 4 grup unit 71,500.00
28 Kabel listrik NYA 1,5mm m' 3,300.00
29 Kabel listrik NYA 2,5mm m' 7,150.00
30 Kabel listrik NYA 4 mm m' 12,100.00
31 Kabel listrik NYA 2x1,5mm m' 6,050.00
32 Kabel listrik NYA 2x2,5mm m' 12,100.00
33 Kabel listrik NYA 2x4 mm m' 24,200.00
34 Kabel NYA 3x2,5 mm2 M1 24,750.00
35 Kabel NYA 4x 10 mm2 M1 104,500.00
36 Conduit Btg 9,350.00
37 Lampu Berat M1 291,500.00
Bahan Pendukung
1 Amplas lbr 3,500.00
2 Kuas bh 24,000.00
Lokasi : TARUTUNG
7 P3K
Peralatan P3K (Kotak P3K, Tandu, Tabung
a Ls 1.00 1.00
Oksigen, Obat Luka, Perban,dll)
b Ruang P3K (Tempat Tidur Pasien, Stetoskop, Timbang Berat Badan, Tensi Meter Ls
2,500,000
2,500,000
7,500.00 300,000.00 12,500
- 1,500,000
- 1,500,000
- 25,000
- 20000
- 100000
25000
225,000.00 675,000.00 225,000
95,000.00 95,000.00 95,000
550,000.00 550,000.00 990,000
- 750,000
- 3,500,000
- 3,500,000
- 3,500,000
- 2,750,000
- 2,250,000
- 2,250,000
Terbilang : Empat Milyar Delapan Ratus Dua Puluh Delapan Juta Enam Ratus Lima Ribu Rupiah,-
diketahui oleh:
CV. BINA PRATAMA REKAYASA dibuat oleh:
Amri Edi Lubis, ST Sahli Priono, ST
Direktur Tenaga Ahli
REKAPITULASI
ENGINEER ESTIMATE (EE)
diketahui oleh:
CV. BINA PRATAMA REKAYASA dibuat oleh:
Pekerjaan : Pembuatan Landscape, ATM, Pos Satpam dan Pagar PT. Bank Sumut Salak
Lokasi : Pakpak Bharat
Alamat : Jl. Sikadang Njandi, Salak - Pakpak Bharat
SUB JUMLAH HARGA
JUMLAH HARGA
NO REKAPITULASI
(Rp.)
(Rp.)
1 2 3 4
Terbilang : "Satu Milyar Empat Ratus Lima Puluh Enam Juta Dua Ratus Sembilan Puluh Tiga Ribu Rupiah,-"
diketahui oleh:
CV. BINA PRATAMA REKAYASA dibuat oleh:
HARGA JUMLAH
NO. URAIAN/ PEKERJAAN VOLUME SATUAN ANALISA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6 7
A. PEKERJAAN PERSIAPAN
1 Pembersihan rumpur dan pengupasan tanah humus 1.00 ls Taksir 2,500,000.00 2,500,000.00
2 Perancah Kerja 1.00 ls Taksir 2,600,000.00 2,600,000.00
Total - A 64,520,000.00
B. PEKERJAAN LANTAI - 1
I. Pekerjaan Tanah dan Pondasi
1 Galian tanah pondasi setempat dan menerus 119.15 m3 PT 6.4. 114,320.00 13,621,228.00
2 Urugan Pasir Alas Pondasi dan Lantai t=5 cm 17.93 m3 PT 6.10. 171,820.00 3,080,732.60
3 Cor Tapak Pondasi Beton Bertulang K-225 14.69 m3 PB 6.23.A 4,998,490.00 73,427,818.10
4 Cor Tapak Pondasi Menerus Kluis Beton Bertulang K-225 5.76 m3 PB 6.23.A 4,998,490.00 28,791,302.40
5 Pas. pondasi menerus bt.belah 1:4 42.28 m3 PP 6.2. 836,880.00 35,383,286.40
6 Cor Leher Pondasi Beton Bertulang K-225 5.95 m3 PB 6.25.C 7,046,970.00 41,929,471.50
7 Cor Sloof 20/45 Beton Bertulang K-225 10.41 m3 PB 6.23.A 4,998,490.00 52,034,280.90
8 Cor Sloof 15/20 Beton Bertulang K-225 0.44 m3 PB 6.23.A 4,998,490.00 2,199,335.60
9 Urugan Tanah Peninggian Lantai t=40 cm 246.00 m3 PT 6.11. 157,060.00 38,636,760.00
10 Cor Rabat Beton Lantai t=10 cm Beton Normal K-175 27.33 m3 PB 6.1.A 826,150.00 22,578,679.50
Hal. 53
HARGA JUMLAH
NO. URAIAN/ PEKERJAAN VOLUME SATUAN ANALISA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6 7
Sub Total - B.VIII 72,507,711.50
IX. Pekerjaan Mekanikal dan Elektrikal
1 Instalasi Titik Lampu Kabel NYM 3 x 1,5 mm2 45.00 ttk Taksir 120,000.00 5,400,000.00
2 Instalasi Titik Stop Kontak Kabel NYM 3 x 2,5 mm 2 40.00 ttk Taksir 160,000.00 6,400,000.00
3 Pasang Lampu RM Glossy 2 x 36 watt 3.00 bh Taksir 341,000.00 1,023,000.00
4 Pasang Lampu Roset XL 25 watt 6.00 bh Taksir 75,000.00 450,000.00
5 Pasang Lampu RD 175 E27 23 watt 6.00 bh Taksir 181,500.00 1,089,000.00
6 Pasang Lampu RD 125 E27 11 watt 6.00 bh Taksir 121,000.00 726,000.00
7 Pasang Lampu Indirect Fuji Light 21 watt 16.00 bh Taksir 42,900.00 686,400.00
8 Pasang Lampu Sorot 500 watt diatap Kanopy View ACP Fasat Depan 2.00 bh Taksir 302,500.00 605,000.00
9 Pasang Stop Kontak 7.00 bh Taksir 25,630.00 179,410.00
10 Pasang Saklar Tunggal 2.00 bh Taksir 14,740.00 29,480.00
11 Pasang Saklar Ganda 3.00 bh Taksir 20,000.00 60,000.00
12 Pasang Saklar Triple 1.00 bh Taksir 25,000.00 25,000.00
Total - E 354,567,528.00
F. PEKERJAAN PENATAAN LANSEKAP DAN PARKIR
1 Galian tanah Keras utk Taman 30.00 m3 PT 6.4. 114,320.00 3,429,600.00
2 Pas. Kanstin Pembatas Tanaman 73.50 m1 Taksir 75,000.00 5,512,500.00
3 Urugan Tanah Humus 30.00 m3 Taksir 220,000.00 6,600,000.00
4 Penanaman Rumput Gajah Mini 30.00 m2 Taksir 65,000.00 1,950,000.00
5 Penanaman Pohon Pelindung 9.00 pkk Taksir 450,000.00 4,050,000.00
6 Bongkaran paving Block existing 135.00 m2 Taksir 15,000.00 2,025,000.00
7 Penggantian/sisip paving blcok halaman parkir 135.00 m1 PPL 6.13.A 158,440.00 21,389,400.00
Total - F 44,956,500.00
G PEKERJAAN AKHIR
1 Photo Dokumentasi dan Laporan 1.00 Ls Taksir 6,500,000.00 6,500,000.00
2 Pembersihan Akhir 1.00 Ls Taksir 4,500,000.00 4,500,000.00
3 Gambar As Built Drawing 1.00 Ls Taksir 7,500,000.00 7,500,000.00
Total - C 18,500,000.00
Total Seluruh Pekerjaan #REF!
Hal. 57
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
B Bahan
Pasir urug 1.2000 110,000.00 132,000.00
Jumlah harga bahan 132,000.00
D JUMLAH (A+B+C) 188,000.00
E Overhead & profit ( contoh 15%) 15% X D 28,200.00
F Harga Satuan pekerjaan ( D+E) 216,200.00
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFESIEN HARGA SATUAN (RP)
(RP)
A TENAGA
Pekerja L.01 OH 1.5000 100,000.00 150,000.00
Tukang Batu L.02 OH 0.7500 120,000.00 90,000.00
Kepala tukang L.03 OH 0.0750 130,000.00 9,750.00
Mandor L.04 OH 0.0750 120,000.00 9,000.00
JUMLAH TENAGA KERJA 258,750.00
B Bahan
Batu Belah m3 1.2000 191,250.00 229,500.00
Semen Portland kg 202.0000 1,600.00 323,200.00
Pasir Pasang m3 0.4850 150,000.00 72,750.00
JUMLAH HARGA BAHAN 625,450.00
C PERALATAN
C PERALATAN
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFESIEN HARGA SATUAN (RP)
( RP)
A TENAGA
Pekerja L.01 1.5000 100,000.00 150,000.00
Tukang Batu L.02 0.7500 120,000.00 90,000.00
Kepala tukang L.03 0.0750 130,000.00 9,750.00
Mandor L.04 0.0750 120,000.00 9,000.00
JUMLAH TENAGA KERJA 258,750.00
B Bahan
Batu Belah m3 1.2000 191,250.00 229,500.00
Semen Portlan kg 136.0000 1,600.00 217,600.00
Pasir Pasang m3 0.5440 150,000.00 81,600.00
Jumlah harga bahan 528,700.00
D JUMLAH (A+B+C) 787,450.00
E Overhead & profit ( contoh 15%) 15% X D 118,117.50
F Harga Satuan pekerjaan ( D+E) 905,567.50
A.3.2.1.6 Pemasangan 1 m3 pondasi batu pecah belah campuran 1SP: 1KP : 2PP
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFESIEN HARGA SATUAN (RP)
( RP)
A TENAGA
Pekerja L.01 1.5000 100,000.00 150,000.00
Tukang Batu L.02 0.7500 120,000.00 90,000.00
Kepala tukang L.03 0.0750 130,000.00 9,750.00
Mandor L.04 0.0750 120,000.00 9,000.00
JUMLAH TENAGA KERJA 258,750.00
B Bahan
Batu Belah m3 1.2000 191,250.00 229,500.00
Semen Portlan kg 0.1700 1,600.00 272.00
Pasir Pasang m3 0.3400 150,000.00 51,000.00
Jumlah harga bahan 280,772.00
D JUMLAH (A+B+C) 539,522.00
E Overhead & profit ( contoh 15%) 15% X D 80,928.30
F Harga Satuan pekerjaan ( D+E) 620,450.30
Analisa K Membuat 1 m1 Tiang Pondasi Bor Pile dia.40 cm Beton bertulang K-250
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFESIEN HARGA SATUAN (RP)
( RP)
A TENAGA
Pekerja L.01 Jam 0.0130 100,000.00 1,295.18
Tukang L.02 Jam 0.0065 120,000.00 777.11
Mandor L.04 Jam 0.0022 120,000.00 259.04
Jumlah harga Upah 2,331.33
B BAHAN
Beton K-250 A.4.1.1.7 m3 0.1257 1,227,214.13 154,216.28
Besi Beton Ulir A.4.1.1.17 B kg 18.8496 17,376.50 327,539.31
Casing m2 1.2566 12,000.00 15,079.64
Jumlah harga bahan 496,835.23
C PERALATAN
Bor Pile E.33 Jam 0.0022 216,253.00 466.81
Molen/Mixer Beton E.28 Jam 0.0237 54,412.57 1,287.21
Alat Bantu Ls 1.0000 10,000.00 10,000.00
Jumlah harga peralatan 11,754.03
D JUMLAH (A+B+C) 510,920.58
E Overhead & profit ( contoh 15%) 15% X D 76,638.09
F Harga Satuan pekerjaan ( D+E) 587,558.67
Analisa K Membuat 1 m1 Tiang Pondasi Bor Pile dia.60 cm Beton bertulang K-250
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFESIEN HARGA SATUAN (RP) ( RP)
A TENAGA
Pekerja L.01 Jam 0.0130 100,000.00 1,295.18
Tukang L.02 Jam 0.0065 120,000.00 777.11
Mandor L.04 Jam 0.0022 120,000.00 259.04
Jumlah harga Upah 2,331.33
B BAHAN
Beton K-250 0 m3 0.2827 1,227,214.13 346,986.62
Besi Beton Ulir 0 kg 42.4115 17,376.50 736,963.44
Casing m2 1.8850 12,000.00 22,619.47
Jumlah harga bahan 1,106,569.53
C PERALATAN
Bor Pile E.33 Jam 0.0022 216,253.00 466.81
Molen/Mixer Beton E.28 Jam 0.0568 54,412.57 3,089.32
Alat Bantu Ls 1.0000 10,000.00 10,000.00
Jumlah harga peralatan 13,556.13
D JUMLAH (A+B+C) 1,122,456.98
E Overhead & profit ( contoh 15%) 15% X D 168,368.55
F Harga Satuan pekerjaan ( D+E) 1,290,825.53
A.4.1.1 HARGA SATUAN PEKERJAAN BETON
A.4.1.1.5 Membuat 1 m3 beton mutu p = 14.5 Mpa (K175). Slump ( 12 ± 2) cm. w/c = 0.66
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP)
( RP)
A TENAGA
Pekerja L.01 OH 1.6500 100,000.00 165,000.00
Tukang Batu L.02 OH 0.2750 120,000.00 33,000.00
Kepala tukang L.03 OH 0.0280 130,000.00 3,640.00
Mandor L.04 OH 0.0830 120,000.00 9,960.00
JUMLAH TENAGA KERJA 211,600.00
B Bahan
Semen Portland kg 326.0000 1,600.00 521,600.00
Pasir Beton kg 760.0000 107.14 81,426.40
Kerikil ( Maks 30 mm) kg 1,029.0000 155.56 160,071.24
Air Liter 215.0000 25.00 5,375.00
Jumlah harga bahan 768,472.64
D JUMLAH (A+B+C) 980,072.64
E Overhead & profit ( contoh 15%) 15% X D 147,010.90
F Harga Satuan pekerjaan ( D+E) 1,127,083.54
A.4.1.1.7 Membuat 1 m3 beton mutu p = 19.3 Mpa ( k 225). Slump ( 12 ± 2) cm. w/c =0.58
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP)
( RP)
A TENAGA
Pekerja L.01 OH 1.6500 100,000.00 165,000.00
Tukang Batu L.02 OH 0.2750 120,000.00 33,000.00
Kepala tukang L.03 OH 0.0280 130,000.00 3,640.00
Mandor L.04 OH 0.0830 120,000.00 9,960.00
JUMLAH TENAGA KERJA 211,600.00
B Bahan
Semen Portland kg 371.0000 1,600.00 593,600.00
Pasir Beton kg 698.0000 107.14 74,783.72
Kerikil ( Maks 30 mm) kg 1,047.0000 155.56 162,871.32
Air Liter 215.0000 25.00 5,375.00
Jumlah harga bahan 836,630.04
D JUMLAH (A+B+C) 1,048,230.04
E Overhead & profit ( contoh 15%) 15% X D 157,234.51
F Harga Satuan pekerjaan ( D+E) 1,205,464.55
A TENAGA
Pekerja L.01 OH 0.5200 100,000.00 52,000.00
Tukang Batu L.02 OH 0.2600 120,000.00 31,200.00
Kepala tukang L.03 OH 0.0260 130,000.00 3,380.00
Mandor L.04 OH 0.0260 120,000.00 3,120.00
JUMLAH TENAGA KERJA 89,700.00
B Bahan
Kayu Kelas III m3 0.0400 3,272,500.00 130,900.00
Paku 5-10 cm kg 0.3000 18,000.00 5,400.00
Minyak bekisting liter 0.1000 29,000.00 2,900.00
Jumlah Harga Bahan 139,200.00
D JUMLAH (A+B+C) 228,900.00
E Overhead & profit ( contoh 15%) 15% X D 34,335.00
F Harga Satuan pekerjaan ( D+E) 263,235.00
Bekisting 2 x pakai 131,617.50
A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.5200 100,000.00 52,000.00
Tukang Batu L.02 OH 0.2600 120,000.00 31,200.00
Kepala tukang L.03 OH 0.0260 130,000.00 3,380.00
Mandor L.04 OH 0.0260 120,000.00 3,120.00
JUMLAH TENAGA KERJA 89,700.00
B Bahan
Kayu Kelas III m3 0.0450 3,272,500.00 147,262.50
Paku 5-10 cm kg 0.3000 18,000.00 5,400.00
Minyak bekisting liter 0.1000 29,000.00 2,900.00
Jumlah Harga Bahan 155,562.50
D JUMLAH (A+B+C) 245,262.50
E Overhead & profit ( contoh 15%) 15% X D 36,789.38
F Harga Satuan pekerjaan ( D+E) 282,051.88
Bekisting 2 x pakai 141,025.94
A.4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.6600 100,000.00 66,000.00
Tukang Batu L.02 OH 0.3300 120,000.00 39,600.00
Kepala tukang L.03 OH 0.0330 130,000.00 4,290.00
Mandor L.04 OH 0.0330 120,000.00 3,960.00
JUMLAH TENAGA KERJA 113,850.00
B Bahan
Kayu Kelas III m3 0.0400 3,272,500.00 130,900.00
Paku 5-10 cm kg 0.4000 18,000.00 7,200.00
Minyak bekisting liter 0.2000 29,000.00 5,800.00
Balok Kayu kelas III m3 0.0150 3,272,500.00 49,087.50
Plywood tebal 9 mm Lbr 0.3500 112,200.00 39,270.00
Dolken Kayu Ø8-10cm-panj 4m Batang 2.0000 16,000.00 32,000.00
Jumlah Harga Bahan 264,257.50
D JUMLAH (A+B+C) 378,107.50
E Overhead & profit ( contoh 15%) 15% X D 56,716.13
F Harga Satuan pekerjaan ( D+E) 434,823.63
Bekisting 2 x pakai 217,411.81
A.4.1.1.23 Pemasangan 1 m2 bekisting untuk balok
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.6600 100,000.00 66,000.00
Tukang Batu L.02 OH 0.3300 120,000.00 39,600.00
Kepala tukang L.03 OH 0.0330 130,000.00 4,290.00
Mandor L.04 OH 0.0330 120,000.00 3,960.00
JUMLAH TENAGA KERJA 113,850.00
B Bahan
Kayu Kelas III m3 0.0400 3,272,500.00 130,900.00
Paku 5-10 cm kg 0.4000 18,000.00 7,200.00
Minyak bekisting liter 0.2000 29,000.00 5,800.00
Balok Kayu kelas III m3 0.0180 3,272,500.00 58,905.00
Plywood tebal 9 mm Lbr 0.3500 112,200.00 39,270.00
Dolken Kayu Ø8-10cm-panj 4m Batang 2.0000 16,000.00 32,000.00
Jumlah Harga Bahan 274,075.00
D JUMLAH (A+B+C) 387,925.00
E Overhead & profit ( contoh 15%) 15% X D 58,188.75
F Harga Satuan pekerjaan ( D+E) 446,113.75
Bekisting 2 x pakai 223,056.88
A.4.1.1.24 Pemasangan 1 m2 bekisting untuk lantai
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.6600 100,000.00 66,000.00
Tukang Batu L.02 OH 0.3300 120,000.00 39,600.00
Kepala tukang L.03 OH 0.0330 130,000.00 4,290.00
Mandor L.04 OH 0.0330 120,000.00 3,960.00
JUMLAH TENAGA KERJA 113,850.00
B Bahan
Kayu Kelas III m3 0.0400 3,272,500.00 130,900.00
Paku 5-10 cm kg 0.4000 18,000.00 7,200.00
Minyak bekisting liter 0.2000 29,000.00 5,800.00
Balok Kayu kelas III m3 0.0150 3,272,500.00 49,087.50
Plywood tebal 9 mm Lbr 0.3500 112,200.00 39,270.00
Dolken Kayu Ø8-10cm-panj 4m Batang 6.0000 16,000.00 96,000.00
Jumlah Harga Bahan 328,257.50
D JUMLAH (A+B+C) 442,107.50
E Overhead & profit ( contoh 15%) 15% X D 66,316.13
F Harga Satuan pekerjaan ( D+E) 508,423.63
Bekisting 2 x pakai 254,211.81
A.4.1.1.25 Pemasangan 1 m2 bekisting untuk dinding
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.6600 100,000.00 66,000.00
Tukang Batu L.02 OH 0.3300 120,000.00 39,600.00
Kepala tukang L.03 OH 0.0330 130,000.00 4,290.00
Mandor L.04 OH 0.0330 120,000.00 3,960.00
JUMLAH TENAGA KERJA 113,850.00
B Bahan
Kayu Kelas III m3 0.0300 3,272,500.00 98,175.00
Paku 5-10 cm kg 0.4000 18,000.00 7,200.00
Minyak bekisting liter 0.2000 29,000.00 5,800.00
Balok Kayu kelas III m3 0.0200 3,272,500.00 65,450.00
Plywood tebal 9 mm Lbr 0.3500 112,200.00 39,270.00
Dolken Kayu Ø8-10cm-panj 4m Batang 3.0000 16,000.00 48,000.00
Jumlah Harga Bahan 263,895.00
D JUMLAH (A+B+C) 377,745.00
E Overhead & profit ( contoh 15%) 15% X D 56,661.75
F Harga Satuan pekerjaan ( D+E) 434,406.75
Bekisting 2 x pakai 217,203.38
A.4.1.1.26 Pemasangan 1 m2 bekisting untuk tangga
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.6600 100,000.00 66,000.00
Tukang Batu L.02 OH 0.3300 120,000.00 39,600.00
Kepala tukang L.03 OH 0.0330 130,000.00 4,290.00
Mandor L.04 OH 0.0330 120,000.00 3,960.00
JUMLAH TENAGA KERJA 113,850.00
B Bahan
Kayu Kelas III m3 0.0300 3,272,500.00 98,175.00
Paku 5-10 cm kg 0.4000 18,000.00 7,200.00
Minyak bekisting liter 0.1500 29,000.00 4,350.00
Balok Kayu kelas III m3 0.0150 3,272,500.00 49,087.50
Plywood tebal 9 mm Lbr 0.3500 112,200.00 39,270.00
Dolken Kayu Ø8-10cm-panj 4m Batang 2.0000 16,000.00 32,000.00
Jumlah Harga Bahan 230,082.50
D JUMLAH (A+B+C) 343,932.50
E Overhead & profit ( contoh 15%) 15% X D 51,589.88
F Harga Satuan pekerjaan ( D+E) 395,522.38
Bekisting 2 x pakai 197,761.19
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.3 Pemasangan 1 m2 dinding bata merah ( 5x11x 22) cm tebal 1 batu campuran 1SP :4PP
JUMLAH HARGA (
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP)
RP)
A TENAGA
Pekerja L.01 OH 0.6000 100,000.00 60,000.00
Tukang Batu L.02 OH 0.2000 120,000.00 24,000.00
Kepala Tukang L.03 OH 0.0200 130,000.00 2,600.00
Mandor L.04 OH 0.0300 120,000.00 3,600.00
JUMLAH TENAGA KERJA 90,200.00
B BAHAN
Bata merah bh 140.0000 700.00 98,000.00
Semen portlan kg 26.5500 1,600.00 42,480.00
Pasir pasang m3 0.0930 150,000.00 13,950.00
JUMLAH HARGA BAHAN 154,430.00
A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ bata campuran 1SP :4PP
JUMLAH HARGA (
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP)
RP)
A TENAGA
Pekerja L.01 OH 0.3000 100,000.00 30,000.00
Tukang Batu L.02 OH 0.1000 120,000.00 12,000.00
Kepala Tukang L.03 OH 0.0100 130,000.00 1,300.00
Mandor L.04 OH 0.0150 120,000.00 1,800.00
JUMLAH TENAGA KERJA 45,100.00
B BAHAN
Bata merah bh 70.0000 700.00 49,000.00
Semen portlan kg 11.5000 1,600.00 18,400.00
Pasir pasang m3 0.0430 150,000.00 6,450.00
JUMLAH HARGA BAHAN 73,850.00
A.4.5.1.7 Pemasangan 1 m2 langit langit gypsum board ukuran ( 120x240x9) mm. tebal 9 mm
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP)
( RP)
A TENAGA
Pekerja L.01 OH 0.1000 100,000.00 10,000.00
Tukang Kayu L.02 OH 0.0500 120,000.00 6,000.00
Kepala Tukang L.03 OH 0.0050 130,000.00 650.00
Mandor L.04 OH 0.0050 120,000.00 600.00
JUMLAH TENAGA KERJA 17,250.00
B BAHAN
Gypsum board Lembar 0.3640 72,250.00 26,299.00
Paku skrup Kg 0.1100 25,000.00 2,750.00
JUMLAH HARGA BAHAN 29,049.00
A.4.5.1.8 Pemasangan 1 m2 langit langit akustik ukuran ( 60 x120) cm berikut rangka aluminium
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.5000 100,000.00 50,000.00
Tukang Batu L.02 OH 0.5000 120,000.00 60,000.00
Kepala Tukang L.03 OH 0.0500 130,000.00 6,500.00
Mandor L.04 OH 0.0250 120,000.00 3,000.00
JUMLAH TENAGA KERJA 119,500.00
B BAHAN
Profil allum ''T'' m 3.6000 25,000.00 90,000.00
Kawat dia 4 mm kg 0.1500 7,200.00 1,080.00
Ramset Buah 1.0500 2,900.00 3,045.00
Akustik 60x120 Lembar 1.5000 30,000.00 45,000.00
JUMLAH HARGA BAHAN 139,125.00
A.4.2.1.22. Pemasangan 1 m2 atap pelana rangka atap baja canal ringan profil C75
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.7340 100,000.00 73,400.00
Tukang L.02 OH 0.7340 120,000.00 88,080.00
Kepala Tukang L.03 OH 0.0730 130,000.00 9,490.00
Mandor L.04 OH 0.0370 120,000.00 4,440.00
JUMLAH TENAGA KERJA 175,410.00
B BAHAN
Baja ringan canal ringan C75 3.0650 13,500.00 41,377.50
JUMLAH HARGA BAHAN 41,377.50
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP)
( RP)
A TENAGA
Pekerja L.01 OH 0.2000 100,000.00 20,000.00
Tukang Batu L.02 OH 0.1000 120,000.00 12,000.00
Kepala Tukang L.03 OH 0.0100 130,000.00 1,300.00
Mandor L.04 OH 0.0010 120,000.00 120.00
JUMLAH TENAGA KERJA 33,420.00
B BAHAN
Genteng Metal bh 1.0200 82,000.00 83,640.00
Paku Biasa ½''-1'' kg 0.2000 18,000.00 3,600.00
JUMLAH HARGA BAHAN 87,240.00
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.1600 100,000.00 16,000.00
Tukang Batu L.02 OH 0.1600 120,000.00 19,200.00
Kepala Tukang L.03 OH 0.0160 130,000.00 2,080.00
Mandor L.04 OH 0.0030 120,000.00 360.00
JUMLAH TENAGA KERJA 37,640.00
B BAHAN
Vernis L 0.1500 51,000.00 7,650.00
Dempul Kg 0.0500 16,500.00 825.00
Ampelas Lbr 0.1000 3,500.00 350.00
JUMLAH HARGA BAHAN 8,825.00
D JUMLAH (A+B+C) 46,465.00
E Overhead & profit ( contoh 15%) 15% X D 6,969.75
F Harga Satuan pekerjaan ( D+E) 53,434.75
A.4.7.1.10. Pengecatan 1 m² tembok baru (1 lapis plamur,1 lapis cat dasar,2 lapis cat penutup) Wheathershield
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.0200 100,000.00 2,000.00
Tukang Batu L.02 OH 0.0630 120,000.00 7,560.00
Kepala Tukang L.03 OH 0.0063 130,000.00 819.00
Mandor L.04 OH 0.0030 120,000.00 360.00
JUMLAH TENAGA KERJA 10,739.00
B BAHAN
Plamur Kg 0.1000 7,500.00 750.00
Cat dasar Kg 0.1000 65,000.00 6,500.00
Cat Penutup Wheatershild Kg 0.2600 100,000.00 26,000.00
JUMLAH HARGA BAHAN 33,250.00
D JUMLAH (A+B+C) 43,989.00
E Overhead & profit ( contoh 15%) 15% X D 6,598.35
F Harga Satuan pekerjaan ( D+E) 50,587.35
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.0200 100,000.00 2,000.00
Tukang Batu L.02 OH 0.2000 120,000.00 24,000.00
Kepala Tukang L.03 OH 0.0200 130,000.00 2,600.00
Mandor L.04 OH 0.0025 120,000.00 300.00
JUMLAH TENAGA KERJA 28,900.00
B BAHAN
Menie besi Kg 0.1000 31,000.00 3,100.00
Kwas Bh 0.0100 24,000.00 240.00
JUMLAH HARGA BAHAN 3,340.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA ( RP)
(RP)
A TENAGA
Pekerja L.01 OH 0.0100 100,000.00 1,000.00
Tukang Batu L.02 OH 0.4000 120,000.00 48,000.00
Kepala Tukang L.03 OH 0.0400 130,000.00 5,200.00
Mandor L.04 OH 0.0050 120,000.00 600.00
JUMLAH TENAGA KERJA 54,800.00
B BAHAN
Stop Kran ½'' atau ¾'' bh 1.0000 23,000.00 23,000.00
Sealtape Buah 0.0250 4,000.00 100.00
JUMLAH HARGA BAHAN 23,100.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.0540 100,000.00 5,400.00
Tukang Batu L.02 0.0900 120,000.00 10,800.00
Kepala Tukang L.03 0.0090 130,000.00 1,170.00
Mandor L.04 OH 0.0270 120,000.00 3,240.00
JUMLAH TENAGA KERJA 20,610.00
B BAHAN
Pipa Galvanis 3/4 '' M 1.2000 40,000.00 48,000.00
Perlengkapan % 35%xpipa 16,800.00 16,800.00
JUMLAH HARGA BAHAN 64,800.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA ( RP)
(RP)
A TENAGA
Pekerja L.01 OH 0.0540 100,000.00 5,400.00
Tukang Batu L.02 0.0900 120,000.00 10,800.00
Kepala Tukang L.03 0.0090 130,000.00 1,170.00
Mandor L.04 OH 0.0270 120,000.00 3,240.00
JUMLAH TENAGA KERJA 20,610.00
B BAHAN
Pipa Galvanis 1'' M 1.2000 50,000.00 60,000.00
Perlengkapan % 35%xpipa 21,000.00 21,000.00
JUMLAH HARGA BAHAN 81,000.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA ( RP)
(RP)
A TENAGA
Pekerja L.01 OH 0.1080 100,000.00 10,800.00
Tukang Batu L.02 0.1800 120,000.00 21,600.00
Kepala Tukang L.03 0.0180 130,000.00 2,340.00
Mandor L.04 OH 0.0050 120,000.00 600.00
JUMLAH TENAGA KERJA 35,340.00
B BAHAN
Pipa Galvanis 11/2'' M 1.2000 75,000.00 90,000.00
Perlengkapan % 35%xpipa 31,500.00 31,500.00
JUMLAH HARGA BAHAN 121,500.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA ( RP)
(RP)
A TENAGA
Pekerja L.01 OH 0.036 100,000.00 3,600.00
Tukang Batu L.02 0.060 120,000.00 7,200.00
Kepala Tukang L.03 0.006 130,000.00 780.00
Mandor L.04 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 11,820.00
B BAHAN
Pipa PVC 1/2” M 1.2000 5,000.00 6,000.00
Perlengkapan % 35%xpipa 2,100.00 2,100.00
JUMLAH HARGA BAHAN 8,100.00
D JUMLAH (A+B+C) 19,920.00
E Overhead & profit ( contoh 15%) 15% X D 2,988.00
F Harga Satuan pekerjaan ( D+E) 22,908.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA ( RP)
(RP)
A TENAGA
Pekerja L.01 OH 0.036 100,000.00 3,600.00
Tukang Batu L.02 0.060 120,000.00 7,200.00
Kepala Tukang L.03 0.006 130,000.00 780.00
Mandor L.04 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 11,820.00
B BAHAN
Pipa PVC 3/4” M 1.2000 7,000.00 8,400.00
Perlengkapan % 35%xpipa 2,940.00 2,940.00
JUMLAH HARGA BAHAN 11,340.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA ( RP)
(RP)
A TENAGA
Pekerja L.01 OH 0.0360 100,000.00 3,600.00
Tukang Batu L.02 0.0600 120,000.00 7,200.00
Kepala Tukang L.03 0.0060 130,000.00 780.00
Mandor L.04 OH 0.0020 120,000.00 240.00
JUMLAH TENAGA KERJA 11,820.00
B BAHAN
Pipa PVC 1'' M 1.2000 9,000.00 10,800.00
Perlengkapan % 35%xpipa 3,780.00 3,780.00
JUMLAH HARGA BAHAN 14,580.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.0540 100,000.00 5,400.00
Tukang Batu L.02 0.0900 120,000.00 10,800.00
Kepala Tukang L.03 0.0090 130,000.00 1,170.00
Mandor L.04 OH 0.0030 120,000.00 360.00
JUMLAH TENAGA KERJA 17,730.00
B BAHAN
Pipa PVC 11/2'' M 1.2000 12,000.00 14,400.00
Perlengkapan % 35%xpipa 5,040.00 5,040.00
JUMLAH HARGA BAHAN 19,440.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.0540 100,000.00 5,400.00
Tukang Batu L.02 0.0900 120,000.00 10,800.00
Kepala Tukang L.03 0.0090 130,000.00 1,170.00
Mandor L.04 OH 0.0030 120,000.00 360.00
JUMLAH TENAGA KERJA 17,730.00
B BAHAN
Pipa PVC 2'' M 1.2000 16,000.00 19,200.00
Perlengkapan % 35%xpipa 6,720.00 6,720.00
JUMLAH HARGA BAHAN 25,920.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN (RP) JUMLAH HARGA ( RP)
A TENAGA
Pekerja L.01 OH 0.0810 100,000.00 8,100.00
Tukang Batu L.02 0.1350 120,000.00 16,200.00
Kepala Tukang L.03 0.0135 130,000.00 1,755.00
Mandor L.04 OH 0.0040 120,000.00 480.00
JUMLAH TENAGA KERJA 26,535.00
B BAHAN
Pipa PVC 21/2'' M 1.2000 20,000.00 24,000.00
Perlengkapan % 35%xpipa 8,400.00 8,400.00
JUMLAH HARGA BAHAN 32,400.00
PK Supl.3
Pasang 1 buah Lampu TL 2 X40watt
Kebutuhan Satuan Indeks Harga satuan bahan( Rp) Harga Satuan Upah ( Rp) Jumlah Harga Jumlah Harga Upah
Bahan ( Rp) (Rp)
Bahan Lampu TL 2X 40 Watt M' 1.0000 286,000.00 286,000.00
Alat Bantu Ls 1.0000 1,000.00 1,000.00
Tenaga Pekerja Oh 0.1000 100,000.00 10,000.00
Tukang Listrik Oh 0.1000 120,000.00 12,000.00
Kepala Tukang Oh 0.0100 130,000.00 1,300.00
Mandor Oh 0.0010 120,000.00 120.00
287,000.00 23,420.00
D Jumlah(A+B+C) 310,420.00
E Overhead & Profit (contoh 15%) 15% x D 46,563.00
F Harga Satuan Pekerjaan ( D+ E) 356,983.00
PK Supl.4
Pasang 1 buah Down Light
Kebutuhan Satuan Indeks Harga satuan bahan( Rp) Harga Satuan Upah ( Rp) Jumlah Harga Jumlah Harga Upah
Bahan ( Rp) (Rp)
Bahan Downlight M' 1.0000 65,000.00 65,000.00
Alat Bantu Ls 1.0000 1,000.00 1,000.00
Tenaga Pekerja Oh 0.1000 100,000.00 10,000.00
Tukang Listrik Oh 0.1000 120,000.00 12,000.00
Kepala Tukang Oh 0.0100 130,000.00 1,300.00
Mandor Oh 0.0010 120,000.00 120.00
66,000.00 23,420.00
D Jumlah(A+B+C) 89,420.00
E Overhead & Profit (contoh 15%) 15% x D 13,413.00
F Harga Satuan Pekerjaan ( D+ E) 102,833.00
PK Supl.5
Pasang 1 buah Lampu Baret
Jumlah Harga Jumlah Harga Upah
Kebutuhan Satuan Indeks Harga satuan bahan( Rp) Harga Satuan Upah ( Rp)
Bahan ( Rp) (Rp)
Bahan Lampu Baret M' 1.0000 291,500.00 291,500.00
Alat Bantu Ls 1.0000 1,000.00 1,000.00
Tenaga Pekerja Oh 0.1000 100,000.00 10,000.00
Tukang Listrik Oh 0.1000 120,000.00 12,000.00
Kepala Tukang Oh 0.0100 130,000.00 1,300.00
Mandor Oh 0.0010 120,000.00 120.00
292,500.00 23,420.00
D Jumlah(A+B+C) 315,920.00
E Overhead & Profit (contoh 15%) 15% x D 47,388.00
F Harga Satuan Pekerjaan ( D+ E) 363,308.00
PK Supl.6
Pasang 1 buah Stop kontak
Jumlah Harga Jumlah Harga Upah
Kebutuhan Satuan Indeks Harga satuan bahan( Rp) Harga Satuan Upah ( Rp)
Bahan ( Rp) (Rp)
Bahan Stop Kontak Tanam M' 1.0000 18,150.00 18,150.00
Alat Bantu Ls 1.0000 1,000.00 1,000.00
Tenaga Pekerja Oh 0.1000 100,000.00 10,000.00
Tukang Listrik Oh 0.1000 120,000.00 12,000.00
Kepala Tukang Oh 0.0100 130,000.00 1,300.00
Mandor Oh 0.0010 120,000.00 120.00
19,150.00 23,420.00
D Jumlah(A+B+C) 42,570.00
E Overhead & Profit (contoh 15%) 15% x D 6,385.50
F Harga Satuan Pekerjaan ( D+ E) 48,955.50
PK Supl.7
Pasang 1 buah Saklar Tunggal
Jumlah Harga Jumlah Harga Upah
Kebutuhan Satuan Indeks Harga satuan bahan( Rp) Harga Satuan Upah ( Rp)
Bahan ( Rp) (Rp)
Bahan Saklar Tunggal M' 1.0000 14,300.00 14,300.00
Alat Bantu Ls 1.0000 1,000.00 1,000.00
Tenaga Pekerja Oh 0.1000 100,000.00 10,000.00
Tukang Listrik Oh 0.1000 120,000.00 12,000.00
Kepala Tukang Oh 0.0100 130,000.00 1,300.00
Mandor Oh 0.0010 120,000.00 120.00
15,300.00 23,420.00
D Jumlah(A+B+C) 38,720.00
E Overhead & Profit (contoh 15%) 15% x D 5,808.00
F Harga Satuan Pekerjaan ( D+ E) 44,528.00
PK Supl.8
Pasang 1 buah Saklar Ganda
Jumlah Harga Jumlah Harga Upah
Kebutuhan Satuan Indeks Harga satuan bahan( Rp) Harga Satuan Upah ( Rp)
Bahan ( Rp) (Rp)
Bahan Saklar Ganda M' 1.0000 18,700.00 18,700.00
Alat Bantu Ls 1.0000 1,000.00 1,000.00
Tenaga Pekerja Oh 0.1000 100,000.00 10,000.00
Tukang Listrik Oh 0.1000 120,000.00 12,000.00
Kepala Tukang Oh 0.0100 130,000.00 1,300.00
Mandor Oh 0.0010 120,000.00 120.00
19,700.00 23,420.00
D Jumlah(A+B+C) 43,120.00
E Overhead & Profit (contoh 15%) 15% x D 6,468.00
F Harga Satuan Pekerjaan ( D+ E) 49,588.00
PK Supl.9
Pasang 1 Buah Saklar Triple
Jumlah Harga Jumlah Harga Upah
Kebutuhan Satuan Indeks Harga satuan bahan( Rp) Harga Satuan Upah ( Rp)
Bahan ( Rp) (Rp)
Bahan Stop Triple M' 1.0000 22,000.00 22,000.00
Alat Bantu Ls 1.0000 1,000.00 1,000.00
Tenaga Pekerja Oh 0.1000 100,000.00 10,000.00
Tukang Listrik Oh 0.1000 120,000.00 12,000.00
Kepala Tukang Oh 0.0100 130,000.00 1,300.00
Mandor Oh 0.0010 120,000.00 120.00
23,000.00 23,420.00
D Jumlah(A+B+C) 46,420.00
E Overhead & Profit (contoh 15%) 15% x D 6,963.00
F Harga Satuan Pekerjaan ( D+ E) 53,383.00
PK Supl.10
Pasang 1 M' kabel feeder NYY 4 x 10 mm³
Kebutuhan Satuan Indeks Harga satuan bahan( Rp) Harga Satuan Upah ( Rp) Jumlah Harga Jumlah Harga Upah
Bahan ( Rp) (Rp)
Bahan Kabel NYY 4 x 16 mm² M' 1.0000 104,500.00 104,500.00
Alat Bantu Ls 1.0000 1,000.00 1,000.00
Tenaga Pekerja Oh 0.1000 100,000.00 10,000.00
Tukang Listrik Oh 0.1000 120,000.00 12,000.00
Kepala Tukang Oh 0.0100 130,000.00 1,300.00
Mandor Oh 0.0010 120,000.00 120.00
105,500.00 23,420.00
D Jumlah(A+B+C) 128,920.00
E Overhead & Profit (contoh 15%) 15% x D 19,338.00
F Harga Satuan Pekerjaan ( D+ E) 148,258.00
BACKUP DATA
RENOVASI GEDUNG KANTOR BANK SUMUT CABANG TARUTUNG
BankSUMUT
PARKIR MOBIL
TOC. -0.20 PAVING BLOCK
TOC. -0.40