Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA (KASARAN)

PEKERJAAAN PEMBUATAN JALAN 1KM


VOLUME PEKERJAAN
NO ASUMSI PEKERJAAN 1 KM
1 PANJANG 1000 M
2 LEBAR 15 M
3 TINGGI 1.5 M
4 VOLUME 22,500 M3

JENIS UNIT ALAT BERAT

NO PEKERJAAN JENIS UNIT JUMLAH UNIT


1 ALAT GALI EXCAVATOR 2
2 ALAT PEMADAT VIBRO 1
3 ALAT ANGKUT DT R10 6
4 ALAT GRADING GRADER 1
4 ALAT GUSUR DOZER 2

LAHAN

N0 KETERANGAN JARAK/KM LUASAN/M2 LUASAN/HA


1 PEMBEBASAN LAHAN 1 15000 1.5
TOTAL

BIAYA LATERIT

NO KETERANGAN JARAK (KM) VOLUME COST (Rp)


1 LATERIT 1 22,500 10,000.00
TOTAL 225,000,000.00

CONFIGURES

NO KETERANGAN COST/KM (Rp)


1 PEMBEBASAN LAHAN 75,000,000.00
2 LATERIT 225,000,000.00
TOTAL 300,000,000.00
HARGA/HA (Rp)
50,000,000.00
75,000,000.00

Anda mungkin juga menyukai