Anda di halaman 1dari 8

ANALISA PERHITUNGAN PENGASPALAN JALAN

Pekerjaan : Pengaspalan diatas Telford atau Macadam

I. ANALISA KEBUTUHAN BAHAN 1 M2


I.1 Batu Pecah ( Split ) 2/3 = = 0.030 M3
I.2 Batu Pecah ( Split ) 1/2 = = 0.009 M3
I.3 Pasir / Abu Batu = = 0.005 M3
I.4 Aspal = = 2.450 Kg

II. ANALISA KEBUTUHAN /PRODUKTIFITAS PEKERJA UNTUK 1M2


II.1 Pekerja = = 0.142 HOK
II.2 Tukang +Mandor + Asphalt Sprayer = = 0.022 HOK

III. ANALISA KEBUTUHAN PERALATAN UNTUK 1M2


III.1 Mesin Gilas = 3 Hari/1800 M2 = 0.002 Hari
III.2 Alat Bantu Manual = 1 Set = Ls

IV. ANALISA UNTUK 2,5 M'


IV.1 Lebar Badan Jalan 2,5 M
IV.1.1. Bahan

IV.1.1.1. Batu Pecah (Split) 2/3 = 0.030 x 280 M = 8.4 M3


IV.1.1.2. Batu Pecah (Split) 1/2 = 0.009 x 280 M = 2.52 M3
IV.1.1.3. Pasir / Abu Batu = 0.005 x 280 M = 1.4 M3
IV.1.1.4. Aspal = 2.450 x 280 M = 686 Kg

IV.1.2. Pekerja

IV.1.2.1. Pekerja = 0.142 x 280.0 M = 39.8 HOK


IV.1.2.2. Tukang = 0.022 x 280.0 M = 6.16 HOK

IV.1.3. Peralatan

IV.1.3.1. Mesin Gilas = 0.002 x 280.0 M = ### Jam


IV.1.3.2. Alat Bantu Manual = 1 x Ls = Hari
V. ANALISA UNTUK 500 M'
V.2 Lebar Badan Jalan 3 M
V.2.1. Bahan

V.2.1.1. Batu Pecah (Split) 2/3 = 0.030 x 2.5 M = 0.08 x 280 = 21 M3


V.2.1.2. Batu Pecah (Split) 1/2 = 0.009 x 2.5 M = 0.02 x 280 = 6 M3
V.2.1.3. Pasir / Abu Batu = 0.005 x 2.5 M = 0.01 x 280 = 4 M3
V.2.1.4. Aspal = 2.450 x 2.5 M = 6.13 x 280 = 1,715 Kg
11 Drm
V.2.2. Pekerja

V.2.2.1. Pekerja = 0.142 x 2.5 M = 0.36 x 280 = 99 HOK


V.2.2.2. Tukang = 0.022 x 2.5 M = 0.06 x 280 = 15 HOK

V.2.3. Peralatan

V.2.3.1. Mesin Gilas = 0.002 x 2.5 M = ### x 280 = 1 Hari


V.2.3.2. Alat Bantu Manual = 1 x Ls = x 280 = - Ls

Keterangan : Tebal padat lapisan pengaspalan = 5 cm, dengan penggilasan 2 X


Pengaspalan tersebut adalah Laburan dua Lapis (K.617 rob)
Mandor & Tukang dan Sewa alat Asphalt Sprayer termasuk dalam kelompok Tukang
Referensi : Analisa Harga Satuan Pekerjaan, DPU Bina Marga tahun 2005

Analisa Pekerjaan
HOK
HOK

Analisa Pekerjaan
ANALISA PERHITUNGAN PRIME COAT
Pekerjaan : Prime Coat diatas Telford atau Macadam

I. ANALISA KEBUTUHAN BAHAN 1 M2


I.1 Aspal = 1020 Kg/1000 M2 = 0.510 Kg
I.2 Minyak tanah = 599 Kg/1000 M2 = 0.599 Ltr

II. ANALISA KEBUTUHAN /PRODUKTIFITAS PEKERJA UNTUK 1M2


II.1 Pekerja (Pekerja+ Alat Mesin) = 9 HK/1000 M2 = 0.012 HOK
II.2 Tukang = 2.5 HK/1000 M2 = 0.003 HOK

III. ANALISA KEBUTUHAN PERALATAN UNTUK 1M2


III.1 Alat Bantu Manual = 1 Set = Ls

IV. ANALISA UNTUK 1M'


IV.1 Lebar Badan Jalan2,5 M
IV.1.1. Bahan

IV.1.1.1. Aspal = 0.510 x 2.5 M = 1.28 Kg


IV.1.1.2. Minyak Tanah = 0.599 x 2.5 M = 1.5 Ltr

IV.1.2. Pekerja

IV.1.2.1. Pekerja = 0.012 x 2.5 M = 0.03 HOK


IV.1.2.2. Tukang = 0.003 x 2.5 M = 0.01 HOK

IV.1.3. Peralatan

IV.1.3.1. Alat bantu manual = 1 x Ls = Ls

V. ANALISA UNTUK 500 M'


V.2 Lebar Badan Jalan 3 M
V.2.1. Bahan

V.1.1.1. Aspal = 0.510 x 280.0 M = 1.28 x 280 = 357 Kg


2 Drum
V.1.1.2. Minyak Tanah = 0.599 x 280.0 M = 1.5 x 280 = 419 Ltr

V.2.2. Pekerja

V.2.2.1. Pekerja = 0.012 x 280.0 M = 0.03 x 280 = 8 HOK


V.2.2.2. Tukang = 0.003 x 280.0 M = 0.93 x 280 = 261 HOK

V.2.3. Peralatan

V.2.3.1. Alat Bantu Manual = 1 x Ls = x 280 = - Ls

Keterangan :
Referensi : Analisa Harga Satuan Pekerjaan, DPU Bina Marga Kab tahun 2005

Analisa Pekerjaan
Analisa Pekerjaan
RENCANA ANGGARAN BIAYA PRASARANA

Propinsi : Jawa Barat No. RAB


Kabupaten : Program
Kecamatan : Jenis Kegiatan
Desa : Ukuran/Dimensi
Volume
No URAIAN Satuan
Total Dari DD Dari DD Dari DD

B A H A N

1 Batu belah 2/3 Cm 21 21 M3 264,600 5,556,600


2 Batu belah 1/2 Cm 6 6 M3 300,700 1,804,200
3 Pasir Aspal /Abu batu 4 4 M3 237,300 949,200
4 Aspal 14 14 Drum 1,500,000 21,000,000
5 Minyak tanah 419 419 Ltr 10,000 4,190,000
7 Kayu bakar 2 2 M3 630,400 1,260,800
Sub Total 1) 34,760,800
A L A T
1 Papan proyek - Unit 150,000 -
2 Sapu lidi 10 10 buah 5,000 50,000
3 Sekop 3 3 buah 75,000 225,000
4 Gayung - buah 10,000 -
5 Ember 16 16 buah 15,000 240,000
6 Cangkul 6 6 buah 75,000 450,000
7 Gacok 2 2 buah 75,000 150,000
8 Pengki 10 10 buah 25,000 250,000
9 Meteran 5 M' 1 1 buah 15,000 15,000
10 Mesin Gilas 1 1 Hari 1,220,800 1,220,800
11 Mob./Demob. Mesin Gilas 1 1 Ls 1,500,000 1,500,000
Sub Total 2) 4,100,800
U P A H
1 Pekerja Konstruksi 108 108 HOK 100,000 10,800,000
2 Tukang 15 15 HOK 150,000 2,250,000
Sub Total 3) 13,050,000
TOTAL BIAYA 51,911,600

51,911,600

54,507,200
40% 60%
1,557,348 2,336,022

Disetujui Oleh :
RENCANA ANGGARAN BIAYA PRASARANA

1 Bidang : Bidang Pelaksanaan Pembangunan Desa


2 Kegiatan : Pemeliharaan Jalan Desa Gapura rw. 03 - bapak idik
3 Waktu Pelaksanaan : 3 Bulan
4 Sumber Dana :
5 Output/Keluaran : Pemeliharaan Jalan Desa Gapura rw. 03 - bapak idik
6 Rincian Pendanaan :

ANGGARAN
Kode No URAIAN
SUMBER
Rek DANA VOLUME SATUAN Harga Satuan Jumlah

Belanja Desa
Belanja Barang dan Jasa 1,491,900
Belanja Alat Tulis Kantor
1 Kertas F4 3 Rim 65,000 195,000
2 Fotokopi dan Penggandaan 1 Ls 454,900 454,900
3 Materai 22 Ls 11,000 242,000
4 Papan Proyek 1 Bh 100,000 100,000
5 Mamin Rapat 1 Ls 500,000 500,000

Belanja Honorarium Tim Panitia 1,850,000


1 Honor Ketua 1 OB 600,000 600,000
2 Honor Sekretaris 1 OB 500,000 500,000
3 Honor Anggota 3 OB 250,000 750,000

Belanja Modal 34,760,800


1 Batu belah 2/3 Cm 21 M3 264,600 5,556,600
2 Batu belah 1/2 Cm 6 M3 300,700 1,804,200
3 Pasir Aspal /Abu batu 4 M3 237,300 949,200
4 Aspal 14 Drum 1,500,000 21,000,000
5 Minyak tanah 419 Ltr 10,000 4,190,000
6 Kayu bakar 2 M3 630,400 1,260,800

ALAT 4,100,800
1 Sapu lidi 10 buah 5,000 50,000
2 Sekop 3 buah 75,000 225,000
3 Ember 16 buah 15,000 240,000
4 Cangkul 6 buah 75,000 450,000
5 Gacok 2 buah 75,000 150,000
6 Pengki 10 buah 25,000 250,000
7 Meteran 5 M' 1 buah 15,000 15,000
8 Mesin Gilas 1 Hari 1,220,800 1,220,800
9 Mob./Demob. Mesin Gilas 1 Ls 1,500,000 1,500,000

UPAH 13,050,000
1 Pekerja Konstruksi 108 HOK 100,000 10,800,000
2 Tukang 15 HOK 150,000 2,250,000

TOTAL BIAYA 55,253,500


Mekarsari, 2022
Disretujui/Mengesahkan
Kepala Desa Mekarsari Sekretaris Desa Pelaksana Kegiatan

KRISNO HADI H. DUDIN ABDUL MAJID NURAENI