Anda di halaman 1dari 1

DAFTAR HADIR KARYAWAN

PT. PRIMA LAYANAN NASIONAL ENJINIRING


PEKERJAAN JASA KONSULTAN UNTUK DESAIN REVIEW DAN SUPERVISI KONSTRUKSI
PEMBANGUNAN PEMBANGKIT MOBILE (MPP) 500 MW TERSEBAR DI WILAYAH PT. PLN (Persero)
NO. KONTRAK : 0074.PJ/613/DIRUT/2016
PERIODE : SEPTEMBER 2016
Supervisi Konstruksi Mobile Power Plant Nias (1 x 25 MW)
Form 1
Tanggal
Total
No Nama Jabatan 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 MM Tanda Tangan
Hari
K J S M S S R K J S K J S M S S R K J S M S S R K J S M S S

1 Ir. Abdul Halim Site Manager X X X X X X X X X X X X X X X X X X X X X X X X X X X 31 1,00


I
d
2 Rudy Ihwan Civil Engineer X X X X X X X X X X X u X X X X X X X X X X X X X X X X 31 1,00
l

A
3 Nurvetri E/M Inspector X X X X X X X X X X X d X X X X X X X X X X X X X X X X 31 1,00
h
a
4 Yusri Octa Indra Civil Inspector X X X X X X X X X X X X X X X X X X X X X X X X X X X 31 1,00

Note :
Site : X Dipersiapkan oleh,
Meeting at Batam : B PT PLN Enjiniring
Meeting at Jakarta : J
Sick Leave : SL
Temporary : TL
Lain-lain : L
Ir. Abdul Halim
Site Manager