JUMLAH HARGA
NO URAIAN PEKERJAAN
(Rp)
TOTAL 19.561.237.608,04
PEMBULATAN 19.561.237.600,00
PEKERJAAN PERSIAPAN PAKET 2
Proyek : Pembangunan SPAM Regional Kota Medan-Paket 2
TA : 2017
HARGA
No. SATUAN PEKERJAAN STANDAR
Rp.
A. PEKERJAAN PENYAMBUNGAN PIPA BAJA AHS. PP-GIP-2015
A.10. 1 M' Penyambungan Pipa GIP/Steel Ø 350 mm AHS. PP-GIP-2015 227.053,00
A.11. 1 M' Penyambungan Pipa GIP/Steel Ø 400 mm AHS. PP-GIP-2015 262.301,00
A.12. 1 M' Penyambungan Pipa GIP/Steel Ø 450 mm AHS. PP-GIP-2015 300.110,00
A.13. 1 M' Penyambungan Pipa GIP/Steel Ø 500 mm AHS. PP-GIP-2015 340.981,00
A.14. 1 M' Penyambungan Pipa GIP/Steel Ø 600 mm AHS. PP-GIP-2015 409.177,00
A.15 1 M' Penyambungan Pipa GIP/Steel Ø 700 mm AHS. PP-GIP-2015 482.792,00
A.16. 1 M' Penyambungan Pipa GIP/Steel Ø 800 mm AHS. PP-GIP-2015 562.910,00
A.17. 1 M' Penyambungan Pipa GIP/Steel Ø 900 mm AHS. PP-GIP-2015 650.832,00
A.18. 1 M' Penyambungan Pipa GIP/Steel Ø 1000 mm AHS. PP-GIP-2015 748.115,00
B. PEKERJAAN PENYAMBUNGAN PIPA PVC AHS. PP-PVC-2015
B.01 1 M' Penyambungan Pipa PVC Ø50 mm AHS. PP-PVC-2015 3.947,00
B.02 1 M' Penyambungan Pipa PVC Ø 75 mm AHS. PP-PVC-2015 5.611,00
B.03. 1 M' Penyambungan Pipa PVC Ø 100 mm AHS. PP-PVC-2015 7.690,00
B.04. 1 M' Penyambungan Pipa PVC Ø 150 mm AHS. PP-PVC-2015 12.035,00
C. PEKERJAAN PENYAMBUNGAN PIPA HDPE AHS. PP-HDPE-2015
C.01. 1 M' Penyambungan Pipa HDPE Ø 40 mm AHS. PP-HDPE-2015 8.530,00
C.02. 1 M' Penyambungan Pipa HDPE Ø 50 mm AHS. PP-HDPE-2015 47.181,00
C.03. 1 M' Penyambungan Pipa HDPE Ø 75 mm AHS. PP-HDPE-2015 64.242,00
C.04. 1 M' Penyambungan Pipa HDPE Ø 100 mm AHS. PP-HDPE-2015 81.244,00
C.05. 1 M' Penyambungan Pipa HDPE Ø 150 mm AHS. PP-HDPE-2015 111.831,00
C.06. 1 M' Penyambungan Pipa HDPE Ø 200 mm AHS. PP-HDPE-2015 142.418,00
C.07. 1 M' Penyambungan Pipa HDPE Ø 250 mm AHS. PP-HDPE-2015 178.022,00
C.08. 1 M' Penyambungan Pipa HDPE Ø 300 mm AHS. PP-HDPE-2015 213.629,00
C.09. 1 M' Penyambungan Pipa HDPE Ø 350 mm AHS. PP-HDPE-2015 256.758,00
C.10. 1 M' Penyambungan Pipa HDPE Ø 400 mm AHS. PP-HDPE-2015 299.878,00
C.11. 1 M' Penyambungan Pipa HDPE Ø 450 mm 326.972,00
C.12. 1 M' Penyambungan Pipa HDPE Ø 500 mm 340.519,00
C.13. 1 M' Penyambungan Pipa HDPE Ø 600 mm 457.946,00
D PEKERJAAN PENYAMBUNGAN ACCESSORIES AHS. PA-PHG-2015
D.01. 1 Unit Penyambungan Accessories Ø 50 mm AHS. PA-PHG-2015 87.034,00
D.02. 1 Unit Penyambungan Accessories Ø 75 mm AHS. PA-PHG-2015 93.723,00
D.03. 1 Unit Penyambungan Accessories Ø 100 mm AHS. PA-PHG-2015 101.739,00
D.04. 1 Unit Penyambungan Accessories Ø 150 mm AHS. PA-PHG-2015 108.428,00
D.05. 1 Unit Penyambungan Accessories Ø 200 mm AHS. PA-PHG-2015 121.117,00
D.06. 1 Unit Penyambungan Accessories Ø 250 mm AHS. PA-PHG-2015 139.051,00
D.07. 1 Unit Penyambungan Accessories Ø 300 mm AHS. PA-PHG-2015 151.095,00
D.08. 1 Unit Penyambungan Accessories Ø 350 mm AHS. PA-PHG-2015 160.965,00
D.09. 1 Unit Penyambungan Accessories Ø 400 mm AHS. PA-PHG-2015 180.894,00
D.10. 1 Unit Penyambungan Accessories Ø 450 mm AHS. PA-PHG-2015 217.072,00
D.11. 1 Unit Penyambungan Accessories Ø 500 mm AHS. PA-PHG-2015 260.487,00
D.12. 1 Unit Penyambungan Accessories Ø 600 mm AHS. PA-PHG-2015 312.588,00
D.13. 1 Unit Penyambungan Accessories Ø 700 mm AHS. PA-PHG-2015 375.105,00
D.14. 1 Unit Penyambungan Accessories Ø 800 mm AHS. PA-PHG-2015 450.119,00
D.15. 1 Unit Penyambungan Accessories Ø 900 mm AHS. PA-PHG-2015 540.153,00
D.16. 1 Unit Penyambungan Accessories Ø 1000 mm AHS. PA-PHG-2015 648.178,00
D.17. 1 Unit Penyambungan Accessories Ø 1100 mm AHS. PA-PHG-2015 777.811,00
D.18. 1 Unit Penyambungan Accessories Ø 1200 mm AHS. PA-PHG-2015 933.375,00
HARGA
No. SATUAN PEKERJAAN STANDAR
Rp.
HARGA
No. SATUAN PEKERJAAN STANDAR
Rp.
A PEKERJAAN PERSIAPAN RSNI T12-2002
A-02 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m RSNI T12-2002 551.533,00
A-04 1 M2 Pengukuran Dan Pasang Bouwplank RSNI T12-2002 114.613,00
A-05 1 M2 Pembuatan Kantor Sementara dgn Lantai Diplester RSNI T12-2002 1.796.382,00
A-06 1 M2 Pembuatan Gudang Semen dan Alat-alat RSNI T12-2002 1.659.333,00
A-07 1 M2 Pembuatan Bedeng Buruh RSNI T12-2002 1.545.686,00
A-08 1 M2 Membersihkan Lapangan dan Perataan RSNI T12-2002 15.350,00
A-09 1M2 Pembuatan Jalan Sementara RSNI T12-2002 153.357,00
A-10 1 M3 Bongkaran Asphalt/Hotmix RSNI T12-2002 648.032,00
A-11 1 M3 Bongkaran Beton Bertulang RSNI T12-2002 678.327,00
A-12 1 M3 Bongkaran Dinding Tembok Bata Merah RSNI T12-2002 643.827,00
A-18 1 M' Cerucuk Dolken RSNI T12-2002 73.375,00
A-19 1 M2 Rekondisi Jalan Hotmix RSNI T12-2002 542.000,00
B PEKERJAAN TANAH SNI 2835 2008
B-01 1 M3 Galian Tanah Biasa sedalam 1 m SNI 2835 2008 74.875,00
B-02 1 M3 Galian Tanah Biasa Sedalam 2 m SNI 2835 2008 91.575,00
B-03 1 M3 Galian Tanah Lumpur SNI 2835 2008 120.375,00
B-04 1 M3 Galian Tanah Keras Sedalam 1 m SNI 2835 2008 99.680,00
B-05 1 M3 Galian Tanah Berbatu/Cadas SNI 2835 2008 150.900,00
B-06 1 M3 Urugan Tanah Kembali SNI 2835 2008 24.958,00
B-07 1 M3 Buangan Tanah SNI 2835 2008 32.830,00
C PEKERJAAN PONDASI SNI 2836 2008
C-01 1 M3 Urugan Pasir SNI 2836 2008 170.575,00
C-02 1 M3 Urugan Sirtu SNI 2836 2008 188.500,00
C-03 1 M3 Pasanag Pondasi batu Kali adk 1pc : 3 ps SNI 2836 2008 772.344,00
C-04 1 M3 Pasang Pondasi Batu kali adk 1pc : 4ps SNI 2836 2008 727.401,00
C-05 1 M3 Pasang Pondasi Batu kali adk 1pc : 5ps SNI 2836 2008 696.252,00
C-06 1 M3 Pasang Pondasi Batu Kosong (aanstamping) SNI 2836 2008 391.668,00
D. PEKERJAAN BETON SNI 7394 2008
D-01 1 M3 Beton Rabat, slump (12 ± 2) cm SNI 7394 2008 811.996,00
D-02 1 M3 Beton K.100, slump (12 ± 2) cm SNI 7394 2008 889.772,00
D-03 1 M3 Beton K.225, slump (12 ± 2) cm SNI 7394 2008 955.327,00
D-04r 1 Kg pekerjaan besi beton SNI 7394 2008 12.406,00
D-04s 1 M2 Begesting biasa SNI 7394 2008 289.647,00
D-06s 1 M2 Begesting Sloof SNI 7394 2008 313.182,00
D-07s 1 M2 Begesting Kolom SNI 7394 2008 519.811,00
D-08s 1 M2 Begesting Balok SNI 7394 2008 413.381,00
D-09s 1 M2 Begesting Lantai SNI 7394 2008 398.981,00
D-10s 1 M2 Begesting Dinding SNI 7394 2008 665.169,00
D-11s 1 M2 Begesting Plat Atap SNI 7394 2008 610.863,00
D-17r2 1 M1 Turap Galian Pipa SNI 7394 2008 630.869,00
E PEKERJAAN DINDING SNI 6897 2008
E-01 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 3ps SNI 6897 2008 255.946,00
E-02 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 4ps SNI 6897 2008 248.009,00
E-05 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 4ps SNI 6897 2008 120.715,00
F. PEKERJAAN PLESTERAN SNI 2837:2008
F-01 1 M2 Plesteran adk. 1pc : 2ps Tebal 15 mm SNI 2837:2008 53.020,00
F-03 1 M2 Plesteran adk. 1pc : 4ps Tebal 15 mm SNI 2837:2008 49.197,00
F-11 1 M2 Acian Plesteran SNI 2837:2008 33.722,00
HARGA
No. SATUAN PEKERJAAN STANDAR
Rp.
HARGA
NO URAIAN SATUAN
(Rp)
A. UPAH KERJA
1 Mandor Org/hr 115.000,00
2 Kepala Tukang Org/hr 127.000,00
3 Tukang Batu Org/hr 115.000,00
4 Tukang Kayu Org/hr 115.000,00
5 Tukang Besi/Baja Org/hr 115.000,00
6 Tukang cat Org/hr 115.000,00
7 Tukang Listrik Org/hr 115.000,00
8 Tukang Pipa Org/hr 115.000,00
9 Tukang Plitur Org/hr 115.000,00
10 Tukang Taman Org/hr 115.000,00
11 Tukang gali Org/hr 115.000,00
12 Pembantu Tukang Org/hr 70.000,00
13 Pekerja Org/hr 96.000,00
14 Penjaga Malam Org/hr 72.300,00
15 Sopir Org/hr 115.000,00
16 Operator Org/hr 127.000,00
17 Mekanik Org/hr 125.000,00
18 Pembantu Sopir Org/hr 80.000,00
19 Pembantu Operator Org/hr 110.000,00
20 Pembantu Mekanik Org/hr 110.000,00
B SEWA ALAT
1 Pressure Pump Hari 275.000
2 Jack hammer Hari 180.000
3 Concrete mixer & vibrator Hari 160.000
4 Stamper Hari 180.000
5 Excavator Jam 75.000
6 Mesin las Hari 200.000
7 sewa mesin las pipa GIP Hari 400.000
8 Peralatan perpipaan (tracker&katrol) Hari 150.000
9 Walls Jam 150.000
10 Sprayer Jam 80.000
HARGA DASAR MATERIAL
Proyek : Pembangunan SPAM Regional Kota Medan
TA : 2017
HARGA
NO URAIAN SATUAN
(Rp)
A. AGREGAT KASAR, BAHAN PEREKAT & BAHAN JADINYA
1 Pasir Urug M3 110.000,00
2 Tanah Urug Pilihan M3 110.000,00
3 Sirtu M3 127.500,00
4 Pasir Pasang Kali M3 150.000,00
5 Pasir Beton M3 150.000,00
6 Abu Batu M3 259.000,00
7 Batu Gosok ( Apung ) kg 29.600,00
8 Batu Pecah Mesin 1/2 M3 246.000,00
9 Batu Pecah Mesin 2/3 - 5/7 M3 238.000,00
10 Batu Belah Pondasi M3 191.250,00
11 Batu Bronjol ( Untuk Bronjong ) M3 148.750,00
12 Batu Koral Beton Kali M3 148.750,00
13 Batako Kecil 8 x 10 x 20 Bh 3.500,00
14 Con Blok 8 x 20 x 40 Bh 5.400,00
15 Bata Merah Bakar kelas I Bh 775,00
16 Roster Beton 20 x 20 Bh 14.800,00
17 Canstin Paving Blok M1 34.900,00
18 Semen PC /50 kg Zak 64.350,00
19 Semen Putih Zak 92.700,00
20 Kapur Pasang / Kapur Tembok M3 353.300,00
21 Semen Warna Kg 15.700,00
22 Air M3 3.000,00
B LABURAN,PENGISI DAN ALATNYA
1 Plamir Tembok Kg 25.000,00
2 Cat Tembok Vinilex Kg 25.000,00
3 Cat dasar tetmbok Kg 30.000,00
4 Cat tembok tahan asam Ltr 40.000,00
5 Water Profing Membrance Bh 62.500,00
6 Rool Cat Tembok Bh 32.500,00
7 Kwas 3" Bh 16.000,00
8 Oker Bks 22.000,00
9 Oyan Bks 5.200,00
10 Spirtus Kg 15.000,00
11 Bahan Pelitur Kripik ( Sirlak India ) Kg 110.000,00
12 Dempul Jadi Kg 35.800,00
13 Politur Jadi Ltr 112.700,00
14 Terpentin Kg 19.500,00
15 Tiner A Kg 23.900,00
16 Kumpon Lbr 30.800,00
17 Melamik Kg 52.500,00
18 Dempul Plastik Kg 39.200,00
19 Ampelas Lbr 5.000,00
20 Dempul Kayu Cap Kucing Kg 24.400,00
21 Meni Kayu / Besi Kg 30.400,00
22 Sincromat Kg 40.900,00
23 Cat Kayu Sieve Kg 41.700,00
24 Cat Besi Ltr 44.000,00
25 Cat Bron Kg 67.700,00
26 Karet lis Bh 3.300,00
27 Minyak cat Kg 38.400,00
C BAHAN KAYU BERIKUT BAHAN JADINYA
1 Bambu 5 s.d 7 Bt. 17.700,00
2 Bambu 7 s.d 10 Bt. 20.000,00
3 Balok Kayu Damar Laut M3 12.500.000,00
4 Papan Kayu Damar Laut M3 12.300.000,00
5 Balok Kayu Meranti Batu M3 10.500.000,00
6 Papan Kayu Meranti Batu M3 11.300.000,00
7 Kayu Balok Bekisting M3 4.800.000,00
8 Kayu Papan Bekisting M3 4.800.000,00
HARGA
NO URAIAN SATUAN
(Rp)
9 Kayu Kaso 5/7 Kruing M3 2.356.800,00
10 Kayu Reng 3/4 Kruing M3 2.852.000,00
11 Dolken 5 s/d 7 Bt. 16.000,00
12 Dolken 7 s/d 10 Bt. 18.000,00
13 Tali Ijuk Kg 32.725,00
14 Lapisan Ijuk tebal 10 cm M2 32.000,00
15 Plywood 120 x 240 x 0,4 cm Lbr 235.000,00
16 Atap Asbes Gelombang 300 cm x 105 cm x 4 mm M2 80.000,00
D BAHAN LOGAM DAN BAHAN JADINYA
1 Besi Beton U-24 Rata-rata Kg 10.000,00
2 Besi Beton U-39 / U-32 Rata-rata Kg 20.700,00
3 Pagar BRC lengkap tiang ( Tanpa Pondasi ) Lbr 171.300,00
4 Besi WF Ex DN SII Kg 10.500,00
5 Besi siku L 50.50.5 Kg 10.500,00
6 Kawat Beton Kg 20.400,00
7 Kawat Duri Kg 63.500,00
8 Kawat Pengikat M1 1.000,00
9 Kawat Bronjong 4 mm Kg 28.200,00
10 Ram Nyamuk Hijau M2 13.400,00
11 Ram Kawat 1 x 1 cm M2 15.300,00
12 Kawat Las Listrik Kg 23.600,00
13 Plat Strip Bt 18.200,00
14 Besi Strip Kg 26.800,00
15 Kusen Alumunium Natural 1.3 mm t= 1,3 mm ( 4 " ) M1 151.100,00
16 Plat Alumunium 0.6 mm M2 171.800,00
17 Plat Besi Tipis 1 mm Kg 16.800,00
18 Plat Besi Tipis 0.5 mm Kg 17.700,00
19 Lem Fox Kg 23.900,00
20 Lem Vinyl Kg 44.000,00
21 Besi Strip Kaca Nako Kg 11.000,00
22 Besi siku L 30.30.3 Kg 24.000,00
23 Jendela nako kaca bening + tralis 10 klips Set 300.000,00
24 Kaca Polos 3 mm ( ASAHI ) M2 87.400,00
25 Kaca Rayband 5 mm ( ASAHI ) M2 148.700,00
26 Kunci Tanam 2 Slaag Kg 350.000,00
E BAHAN PAKU DAN MUR BAUT
1 Paku 1/2" s/d 2" Kg 23.800,00
2 Paku 2" s/d 5" Kg 23.400,00
3 Paku 8 cm s/d 15 cm Kg 20.000,00
4 Paku Beton 2 cm s/d 5 cm bh 1.600,00
5 Paku Kait Lengkap bh 900,00
6 Paku seng Kg 23.800,00
7 Duk Angker Bh 7.500,00
8 Angker Mur Baut dia. 19 / Panjang 60 cm Bh 71.800,00
9 Mur Baut HTB dia. 19 s/d 16 ( 5 cm ) Bh 15.900,00
10 Mur Baut Biasa dia. 19 s/d 16 ( 5 cm ) Bh 9.300,00
11 Piser dia.12 s/d 20 cm Bh 5.300,00
12 Paku skrup 3" Bh 800,00
13 Dynabol dia 12 x 120 mm Bh 1.500,00
14 Baut Besar Bh 600,00
15 Baut Kecil Bh 300,00
16 Paku GRC Kg 35.000,00
17 Paku gypsum Kg 17.500,00
F BAHAN PERPIPAAN DAN SANITAIR
1 Pipa GIP Medium A 1/2" ( 6 m1 ) Bt 109.100,00
2 Pipa GIP Medium A 1" ( 6 m1 ) Bt 181.500,00
3 Macam2 Sambungan GIP 1/2" Bh 6.300,00
4 Pipa PVC RUCIKA type AW 1/2" M1 6.683,00
5 Lem Paralon Tube 10.100,00
6 Solatip Ledeng gl 4.200,00
7 Pipa PVC 4" Berlobang Jenis AW M1 36.700,00
8 PVC Waterstop lebar 150 M1 53.500,00
9 Stop Kran 3/4" KIT Bh 103.900,00
10 Stop Kran 1 1/2" KIT Bh 208.000,00
11 Check Valve 1/2" Bh 86.400,00
HARGA
NO URAIAN SATUAN
(Rp)
12 Double Neple 1/2" Bh 32.400,00
13 Water Mur 1/2" Bh 40.200,00
14 Gate walve 1/2" Bh 55.500,00
P BAHAN ALAT PENGANTUNG DAN KUNCI
1 Minyak Tanah Ltr 18.000,00
2 Bahan Bakar Residu Ltr 28.435,00
3 Minyak Solar Ltr 7.150,00
4 Bensin Premium Ltr 7.800,00
5 Oil Mesran 40 SAE Ltr 55.000,00
6 Minyak Bekisting Ltr 40.500,00
7 Soda Api Kg 35.600,00
HARGA PIPA, FITTING DAN PERLENGKAPANNYA
Proyek : Pembangunan SPAM Regional Kota Medan
TA : 2017
HARGA
NO URAIAN SATUAN
(Rp)
A. PIPA PVC DAN ACCESSORIES
1 Pipa PVC - Klas AW-S.10 - ND 25 mm M1 11.650,00
2 Pipa PVC - Klas AW-S.10 - ND 40 mm M1 17.500,00
3 Pipa PVC - Klas AW-S.10 - ND 50 mm M1 37.150,00
4 Pipa PVC - Klas AW-S.10 - ND 75 mm M1 75.850,00
5 Pipa PVC - Klas AW-S.10 - ND 100 mm M1 109.900,00
6 Pipa PVC - Klas AW-S.10 - ND 125 mm M1 204.000,00
7 Repair socket PVC-AW ND 50 mm Bh 64.500,00
8 Repair socket PVC-AW ND 75 mm Bh 102.000,00
9 Repair socket PVC-AW ND 100 mm Bh 145.650,00
10 Repair socket PVC-AW ND 150 mm Bh 274.750,00
11 Street Box DCI Bh 243.350,00
12 Reducer Socket PVC ND 40 x 25 mm Bh 18.100,00
13 Reducer Socket PVC ND 50 x 40 mm Bh 27.900,00
14 Reducer Socket PVC ND 75 x 40 mm Bh 38.950,00
15 Reducer Socket PVC ND 75 x 50 mm Bh 64.500,00
16 Reducer Socket PVC ND 100 x 50 mm Bh 108.050,00
17 Reducer Socket PVC ND 100 x 75 mm Bh 109.050,00
18 Reducer Socket PVC ND 150 x 50 mm Bh 310.850,00
19 Reducer Socket PVC ND 150 x 75 mm Bh 291.050,00
20 Reducer Socket PVC ND 150 x 100 mm Bh 281.400,00
21 Tee All Socket PVC ND 40 x 25 mm Bh 32.400,00
22 Tee All Socket PVC ND 40 x 40 mm Bh 54.100,00
23 Tee All Socket PVC ND 50 x 50 mm Bh 77.300,00
24 Tee All Socket PVC ND 75 x 50 mm Bh 169.100,00
25 Tee All Socket PVC ND 75 x 75 mm Bh 170.600,00
26 Tee All Socket PVC ND 100 x 50 mm Bh 519.450,00
27 Tee All Socket PVC ND 100 x 75 mm Bh 526.350,00
28 Tee All Socket PVC ND 100 x 100 mm Bh 400.400,00
29 Tee All Socket PVC ND 150 x 75 mm Bh 1.107.200,00
30 Tee All Socket PVC ND 150 x 100 mm Bh 1.035.150,00
31 Tee All Socket PVC ND 150 x 150 mm Bh 1.165.750,00
32 Elbow 900 Socket PVC ND 50 mm Bh 51.450,00
33 Elbow 900 Socket PVC ND 75 mm Bh 144.150,00
34 Elbow 900 Socket PVC ND 100 mm Bh 238.150,00
35 Elbow 900 Socket PVC ND 150 mm Bh 432.950,00
36 Elbow 900 Socket PVC ND 200 mm Bh 874.050,00
37 Elbow 900 Socket PVC ND 250 mm Bh 2.913.450,00
38 Elbow 900 Socket PVC ND 300 mm Bh 4.578.350,00
39 Elbow 450 Socket PVC ND 50 mm Bh 114.450,00
40 Elbow 450 Socket PVC ND 75 mm Bh 131.450,00
41 Elbow 450 Socket PVC ND 100 mm Bh 200.400,00
42 Elbow 450 Socket PVC ND 150 mm Bh 362.150,00
43 Elbow 450 Socket PVC ND 200 mm Bh 705.450,00
44 Elbow 450 Socket PVC ND 250 mm Bh 2.289.150,00
45 Elbow 450 Socket PVC ND 300 mm Bh 3.017.500,00
46 DOP PVC ND 40 mm Bh 16.700,00
47 DOP PVC ND 50 mm Bh 37.550,00
48 DOP PVC ND 75 mm Bh 53.950,00
49 DOP PVC ND 100 mm Bh 190.050,00
50 DOP PVC ND 150 mm Bh 364.450,00
51 DOP PVC ND 200 mm Bh 607.600,00
52 DOP PVC ND 250 mm Bh 779.550,00
53 DOP PVC ND 300 mm Bh 1.023.450,00
54 Flange Spigot PVC ND 50 mm Bh 162.550,00
55 Flange Spigot PVC ND 75 mm Bh 223.950,00
56 Flange Spigot PVC ND 100 mm Bh 281.400,00
HARGA
NO URAIAN SATUAN
(Rp)
57 Flange Spigot PVC ND 150 mm Bh 628.450,00
58 Flange Spigot PVC ND 200 mm Bh 888.300,00
59 Flange Spigot PVC ND 250 mm Bh 1.701.650,00
60 Flange Spigot PVC ND 300 mm Bh 2.766.550,00
61 Flange Socket PVC ND 50 mm Bh 153.550,00
62 Flange Socket PVC ND 75 mm Bh 193.700,00
63 Flange Socket PVC ND 100 mm Bh 231.050,00
64 Flange Socket PVC ND 150 mm Bh 554.550,00
65 Flange Socket PVC ND 200 mm Bh 838.250,00
66 Valve Socket PVC ND 25 mm Bh 16.350,00
67 Valve Socket PVC ND 40 mm Bh 28.550,00
68 Valve Socket PVC ND 50 mm Bh 154.450,00
69 Faucet Socket PVC ND 13 mm Bh 13.550,00
70 Faucet Socket PVC ND 25 mm Bh 17.150,00
71 Faucet Socket PVC ND 40 mm Bh 29.950,00
72 Faucet Socket PVC ND 50 mm Bh 162.150,00
B PIPA GIP, STEEL DAN ACCESSORIES -
1 Pipa GIP - Medium Class ND 13 mm M1 33.900,00
2 Pipa GIP - Medium Class ND 25 mm M1 109.300,00
3 Pipa GIP - Medium Class ND 40 mm M1 136.600,00
4 Pipa GIP - Medium Class ND 50 mm M1 111.600,00
5 Pipa GIP - Medium Class ND 75 mm M1 205.350,00
6 Pipa GIP - Medium Class ND 100 mm M1 323.150,00
7 Pipa GIP - Medium Class ND 125 mm M1 424.800,00
8 Pipa GIP - Medium Class ND 150 mm M1 526.500,00
9 Pipa GIP - Medium Class ND 200 mm M1 747.500,00
10 Pipa GIP - Medium Class ND 250 mm M1 995.400,00
11 Pipa GIP - Medium Class ND 300 mm M1 2.112.350,00
12 Pipa GIP - Medium Class ND 400 mm M1 2.908.500,00
13 Pipa Steel - CTE.CL ND 150 mm M1 1.066.650,00
14 Pipa Steel - CTE.CL ND 200 mm M1 1.422.500,00
15 Pipa Steel - CTE.CL ND 250 mm M1 1.777.850,00
16 Pipa Steel - CTE.CL ND 300 mm M1 2.133.150,00
17 Pipa Steel - CTE.CL ND 350 mm M1 2.681.100,00
18 Pipa Steel - CTE.CL ND 400 mm M1 2.861.450,00
19 Pipa Steel - CTE.CL ND 450 mm M1 3.292.350,00
20 Pipa Steel - CTE.CL ND 500 mm M1 3.578.000,00
21 Pipa Steel - CTE.CL ND 600 mm M1 4.203.700,00
22 Pipa Steel - CTE.CL ND 700 mm M1 4.595.550,00
23 Pipa Steel - CTE.CL ND 800 mm M1 5.425.000,00
24 Pipa Steel - CTE.CL ND 900 mm M1 5.922.600,00
25 Pipa Steel - CTE.CL ND 1000 mm M1 6.586.200,00
26 Tee All Flange CI ND 50 x 50 mm Bh 226.800,00
27 Tee All Flange CI ND 75 x 50 mm Bh 267.100,00
28 Tee All Flange CI ND 75 x 75 mm Bh 456.100,00
29 Tee All Flange CI ND 100 x 50 mm Bh 340.200,00
30 Tee All Flange CI ND 100 x 75 mm Bh 375.450,00
31 Tee All Flange CI ND 100 x 100 mm Bh 412.000,00
32 Tee All Flange CI ND 150 x 75 mm Bh 592.200,00
33 Tee All Flange CI ND 150 x 100 mm Bh 612.350,00
34 Tee All Flange CI ND 150 x 150 mm Bh 675.350,00
35 Tee All Flange CI ND 200 x 100 mm Bh 892.050,00
36 Tee All Flange CI ND 200 x 150 mm Bh 942.450,00
37 Tee All Flange CI ND 200 x 200 mm Bh 1.030.650,00
38 Tee All Flange CI ND 250 x 150 mm Bh 1.341.900,00
39 Tee All Flange CI ND 250 x 200 mm Bh 1.403.600,00
40 Tee All Flange CI ND 250 x 250 mm Bh 1.484.250,00
41 Tee All Flange CI ND 300 x 200 mm Bh 1.738.800,00
42 Tee All Flange CI ND 300 x 250 mm Bh 1.542.200,00
43 Tee All Flange CI ND 300 x 300 mm Bh 1.927.800,00
44 Tee All Flange CI ND 350 x 250 mm Bh 2.312.100,00
45 Tee All Flange CI ND 350 x 300 mm Bh 2.889.150,00
HARGA
NO URAIAN SATUAN
(Rp)
46 Tee All Flange CI ND 350 x 350 mm Bh 3.612.400,00
47 Tee All Flange CI ND 400 x 300 mm Bh 4.515.800,00
48 Tee All Flange CI ND 400 x 400 mm Bh 5.644.800,00
49 Tee All Flange CI ND 450 x 450 mm Bh 7.338.200,00
50 Tee All Flange CI ND 500 x 500 mm Bh 9.539.650,00
51 Tee All Flange CI ND 600 x 600 mm Bh 12.401.600,00
Tee All Flange CI ND 700 x 400 mm Bh 15.315.950,00
52 Tee All Flange CI ND 700 x 700 mm Bh 16.122.050,00
53 Tee All Flange CI ND 800 x 800 mm Bh 20.958.700,00
54 Tee All Flange CI ND 900 x 900 mm Bh 27.246.300,00
55 Tee All Flange CI ND 1000 x 1000 mm Bh 35.420.250,00
56 Bend 900 All Flange CI ND 50 mm Bh 158.750,00
57 Bend 900 All Flange CI ND 75 mm Bh 236.850,00
58 Bend 900 All Flange CI ND 100 mm Bh 288.500,00
59 Bend 900 All Flange CI ND 150 mm Bh 515.300,00
60 Bend 900 All Flange CI ND 200 mm Bh 732.050,00
61 Bend 900 All Flange CI ND 250 mm Bh 1.091.150,00
62 Bend 900 All Flange CI ND 300 mm Bh 3.071.350,00
63 Bend 900 All Flange CI ND 350 mm Bh 3.364.500,00
64 Bend 900 All Flange CI ND 400 mm Bh 3.657.600,00
65 Bend 900 All Flange CI ND 450 mm Bh 4.023.350,00
66 Bend 900 All Flange CI ND 500 mm Bh 4.425.750,00
67 Bend 900 All Flange CI ND 600 mm Bh 4.868.300,00
68 Bend 900 All Flange CI ND 700 mm Bh 5.355.150,00
69 Bend 900 All Flange CI ND 800 mm Bh 5.890.700,00
70 Bend 900 All Flange CI ND 900 mm Bh 6.479.750,00
71 Bend 900 All Flange CI ND 1000 mm Bh 7.127.700,00
72 Bend 450 All Flange CI ND 50 mm Bh 153.700,00
73 Bend 450 All Flange CI ND 75 mm Bh 226.800,00
74 Bend 450 All Flange CI ND 100 mm Bh 270.900,00
75 Bend 450 All Flange CI ND 150 mm Bh 493.900,00
76 Bend 450 All Flange CI ND 200 mm Bh 710.600,00
77 Bend 450 All Flange CI ND 250 mm Bh 1.030.650,00
78 Bend 450 All Flange CI ND 300 mm Bh 2.799.450,00
79 Bend 450 All Flange CI ND 350 mm Bh 2.819.650,00
80 Bend 450 All Flange CI ND 400 mm Bh 2.839.850,00
81 Bend 450 All Flange CI ND 450 mm Bh 3.123.900,00
82 Bend 450 All Flange CI ND 500 mm Bh 3.436.250,00
83 Bend 450 All Flange CI ND 600 mm Bh 3.779.850,00
84 Bend 450 All Flange CI ND 700 mm Bh 4.157.850,00
85 Bend 450 All Flange CI ND 800 mm Bh 4.573.650,00
86 Bend 450 All Flange CI ND 900 mm Bh 5.031.050,00
87 Bend 450 All Flange CI ND 1000 mm Bh 5.534.150,00
88 Bend 22½0 All Flange CI ND 100 mm Bh 216.700,00
89 Bend 22½0 All Flange CI ND 150 mm Bh 395.100,00
90 Bend 22½0 All Flange CI ND 200 mm Bh 568.450,00
91 Bend 22½0 All Flange CI ND 250 mm Bh 893.300,00
92 Bend 22½0 All Flange CI ND 300 mm Bh 2.666.600,00
93 Bend 22½0 All Flange CI ND 350 mm Bh 3.173.900,00
94 Bend 22½0 All Flange CI ND 400 mm Bh 3.681.400,00
95 Reducer All Flange CI ND 75 x 50 mm Bh 180.150,00
96 Reducer All Flange CI ND 100 x 50 mm Bh 195.300,00
97 Reducer All Flange CI ND 100 x 75 mm Bh 205.350,00
98 Reducer All Flange CI ND 150 x 75 mm Bh 355.300,00
99 Reducer All Flange CI ND 150 x 100 mm Bh 376.700,00
100 Reducer All Flange CI ND 200 x 75 mm Bh 438.450,00
101 Reducer All Flange CI ND 200 x 100 mm Bh 463.650,00
102 Reducer All Flange CI ND 200 x 150 mm Bh 488.850,00
103 Reducer All Flange CI ND 250 x 100 mm Bh 643.850,00
104 Reducer All Flange CI ND 250 x 150 mm Bh 670.300,00
105 Reducer All Flange CI ND 250 x 200 mm Bh 737.100,00
106 Reducer All Flange CI ND 300 x 150 mm Bh 1.009.950,00
HARGA
NO URAIAN SATUAN
(Rp)
107 Reducer All Flange CI ND 300 x 200 mm Bh 1.262.600,00
108 Reducer All Flange CI ND 300 x 250 mm Bh 1.703.100,00
109 Reducer All Flange CI ND 350 x 250 mm Bh 1.788.150,00
110 Reducer All Flange CI ND 350 x 300 mm Bh 2.503.450,00
111 Reducer All Flange CI ND 400 x 300 mm Bh 3.504.800,00
112 Reducer All Flange CI ND 500 x 400 mm Bh 4.556.250,00
113 Reducer All Flange CI ND 500 x 300 mm Bh 5.011.900,00
114 Reducer All Flange CI ND 600 x 500 mm Bh 5.923.150,00
115 Reducer All Flange CI ND 600 x 400 mm Bh 6.219.350,00
116 Reducer All Flange CI ND 700 x 600 mm Bh 7.107.800,00
117 Reducer All Flange CI ND 700 x 500 mm Bh 7.818.600,00
118 Reducer All Flange CI ND 800 x 700 mm Bh 9.240.150,00
119 Reducer All Flange CI ND 800 x 600 mm Bh 9.794.600,00
120 Reducer All Flange CI ND 900 x 800 mm Bh 12.012.250,00
121 Reducer All Flange CI ND 900 x 700 mm Bh 12.612.850,00
122 Reducer All Flange CI ND 1000 x 900 mm Bh 15.615.900,00
123 Reducer All Flange CI ND 1000 x 800 mm Bh 16.552.850,00
124 Flange adaptor GI ND 75 mm Bh 6.050.250,00
125 Flange adaptor GI ND 100 mm Bh 7.304.550,00
126 Flange adaptor GI ND 150 mm Bh 8.411.300,00
127 Flange adaptor GI ND 200 mm Bh 9.695.150,00
128 Flange adaptor GI ND 250 mm Bh 11.395.200,00
129 Flange adaptor GI ND 300 mm Bh 13.354.850,00
130 Flange adaptor GI ND 350 mm Bh 16.025.850,00
131 Flange adaptor GI ND 400 mm Bh 19.231.050,00
132 Flange adaptor GI ND 450 mm Bh 21.154.150,00
133 Flange adaptor GI ND 500 mm Bh 25.385.050,00
134 Flange adaptor GI ND 600 mm Bh 27.923.500,00
135 Flange adaptor GI ND 700 mm Bh 33.508.250,00
136 Flange adaptor GI ND 800 mm Bh 36.859.050,00
137 Flange adaptor GI ND 900 mm Bh 44.230.900,00
138 Flange adaptor GI ND 1000 mm Bh 48.654.000,00
139 Flange Spigot CI ND 50 mm Bh 289.600,00
140 Flange Spigot CI ND 75 mm Bh 362.250,00
141 Flange Spigot CI ND 100 mm Bh 413.850,00
142 Flange Spigot CI ND 150 mm Bh 655.550,00
143 Flange Spigot CI ND 200 mm Bh 1.065.600,00
144 Flange Spigot CI ND 250 mm Bh 1.448.200,00
145 Flange Spigot CI ND 300 mm Bh 1.944.650,00
146 Flange Spigot CI ND 350 mm Bh 2.333.600,00
147 Flange Spigot CI ND 400 mm Bh 2.800.350,00
148 Flange Spigot CI ND 450 mm Bh 3.220.400,00
149 Flange Spigot CI ND 500 mm Bh 3.703.450,00
150 Flange Spigot CI ND 600 mm Bh 4.258.950,00
151 Flange Spigot CI ND 700 mm Bh 4.897.800,00
152 Flange Spigot CI ND 800 mm Bh 5.632.500,00
153 Flange Spigot CI ND 900 mm Bh 6.477.350,00
154 Flange Spigot CI ND 1000 mm Bh 7.449.000,00
155 Dop/Blank Flange CI ND 75 mm Bh 170.100,00
156 Dop/Blank Flange CI ND 100 mm Bh 195.300,00
157 Dop/Blank Flange CI ND 150 mm Bh 257.000,00
158 Dop/Blank Flange CI ND 200 mm Bh 385.550,00
159 Dop/Blank Flange CI ND 250 mm Bh 539.750,00
160 Dop/Blank Flange CI ND 300 mm Bh 755.550,00
161 Dop/Blank Flange CI ND 350 mm Bh 1.057.850,00
162 Dop/Blank Flange CI ND 400 mm Bh 1.481.100,00
163 Foot Valve CI ND 75 mm Bh 459.650,00
164 Foot Valve CI ND 150 mm Bh 1.149.300,00
165 Foot Valve CI ND 300 mm Bh 1.838.900,00
166 Foot Valve CI ND 400 mm Bh 2.574.450,00
167 Check Valve Wafer Type ND 50 mm Bh 1.101.200,00
168 Check Valve Wafer Type ND 75 mm Bh 1.780.350,00
HARGA
NO URAIAN SATUAN
(Rp)
169 Check Valve Wafer Type ND 100 mm Bh 2.550.200,00
170 Check Valve Wafer Type ND 150 mm Bh 5.579.250,00
171 Check Valve Wafer Type ND 200 mm Bh 18.907.550,00
172 Check Valve Wafer Type ND 250 mm Bh 29.398.300,00
173 Check Valve Wafer Type ND 300 mm Bh 41.144.000,00
174 Check Valve Wafer Type ND 350 mm Bh 52.889.750,00
175 Check Valve Wafer Type ND 400 mm Bh 102.531.200,00
176 Gate Valve CI PN.10 ND 50 mm Bh 1.304.100,00
177 Gate Valve CI PN.10 ND 75 mm Bh 1.738.800,00
178 Gate Valve CI PN.10 ND 100 mm Bh 2.028.600,00
179 Gate Valve CI PN.10 ND 150 mm Bh 2.390.850,00
180 Gate Valve CI PN.10 ND 200 mm Bh 4.419.450,00
181 Gate Valve CI PN.10 ND 250 mm Bh 10.143.000,00
182 Gate Valve CI PN.10 ND 300 mm Bh 23.356.050,00
183 Gate Valve CI PN.10 ND 350 mm Bh 29.737.450,00
184 Gate Valve CI PN.10 ND 400 mm Bh 36.119.000,00
185 Gate Valve CI PN.10 ND 450 mm Bh 46.954.700,00
186 Gate Valve CI PN.10 ND 500 mm Bh 56.345.650,00
187 Gate Valve CI PN.10 ND 600 mm Bh 73.249.350,00
188 Gate Valve CI PN.10 ND 700 mm Bh 87.899.250,00
189 Gate Valve CI PN.10 ND 800 mm Bh 114.269.000,00
190 Gate Valve CI PN.10 ND 900 mm Bh 148.549.700,00
191 Gate Valve CI PN.10 ND 1000 mm Bh 178.259.700,00
192 Single Air Valve CI ND 25 mm Bh 714.400,00
193 Single Air Valve CI ND 50 mm Bh 1.031.150,00
194 Doble Air Valve CI ND 50 mm Bh 1.288.950,00
195 Doble Air Valve CI ND 75 mm Bh 2.087.800,00
196 Doble Air Valve CI ND 100 mm Bh 2.991.200,00
197 Giboult Joint CI ND 50 mm Bh 128.500,00
198 Giboult Joint CI ND 75 mm Bh 195.300,00
199 Giboult Joint CI ND 100 mm Bh 257.000,00
200 Giboult Joint CI ND 150 mm Bh 385.550,00
201 Giboult Joint CI ND 200 mm Bh 578.300,00
202 Giboult Joint CI ND 250 mm Bh 747.150,00
203 Giboult Joint CI ND 300 mm Bh 1.745.550,00
204 Giboult Joint CI ND 350 mm Bh 1.386.900,00
205 Giboult Joint CI ND 400 mm Bh 2.888.550,00
206 Collar ND 450 mm Bh 3.755.100,00
207 Collar ND 500 mm Bh 4.881.600,00
208 Collar ND 600 mm Bh 6.346.050,00
209 Collar ND 700 mm Bh 8.249.950,00
210 Collar ND 800 mm Bh 10.724.950,00
211 Collar ND 900 mm Bh 13.942.450,00
212 Collar ND 1000 mm Bh 18.125.200,00
213 Flexible Joint (Double) ND 50 mm Bh 283.500,00
214 Flexible Joint (Double) ND 75 mm Bh 574.550,00
215 Flexible Joint (Double) ND 100 mm Bh 777.400,00
216 Flexible Joint (Double) ND 150 mm Bh 909.700,00
217 Flexible Joint (Double) ND 200 mm Bh 1.157.900,00
218 Flexible Joint (Double) ND 250 mm Bh 1.505.250,00
219 Flexible Joint (Double) ND 300 mm Bh 2.032.100,00
220 Flexible Joint (Double) ND 350 mm Bh 2.540.150,00
221 Dismalting Joint (CI) ND 50 mm Bh 471.300,00
222 Dismalting Joint (CI) ND 75 mm Bh 785.600,00
223 Dismalting Joint (CI) ND 100 mm Bh 942.450,00
224 Dismalting Joint (CI) ND 150 mm Bh 1.538.450,00
225 Dismalting Joint (CI) ND 200 mm Bh 2.382.650,00
226 Dismalting Joint (CI) ND 250 mm Bh 3.327.650,00
227 Dismalting Joint (CI) ND 300 mm Bh 4.524.650,00
228 Dismalting Joint (CI) ND 350 mm Bh 5.881.650,00
229 Dismalting Joint (CI) ND 400 mm Bh 7.645.650,00
C PIPA HDPE DAN ACCESSORIES
HARGA
NO URAIAN SATUAN
(Rp)
1 Pipa HDPE - SDR11.PN10 ND 13 mm M1 9.200,00
2 Pipa HDPE - SDR11.PN10ND 19 mm M1 11.850,00
3 Pipa HDPE - SDR11.PN10 ND 25 mm M1 19.350,00
4 Pipa HDPE - SDR11.PN10 ND 40 mm M1 46.500,00
5 Pipa HDPE - SDR11.PN10 ND 50 mm M1 73.550,00
6 Pipa HDPE - SDR11.PN10 ND 75 mm M1 88.900,00
7 Pipa HDPE - SDR11.PN10 ND 100 mm M1 139.850,00
8 Pipa HDPE - SDR11.PN10ND 130 mm M1 167.800,00
9 Pipa HDPE - SDR11.PN10 ND 150 mm M1 292.000,00
10 Pipa HDPE - SDR17.PN10 ND 200 mm M1 455.550,00
11 Pipa HDPE - SDR11.PN10 ND 250 mm M1 708.400,00
12 Pipa HDPE - SDR11.PN10 ND 300 mm M1 1.126.750,00
13 Pipa HDPE - SDR11.PN10 ND 350 mm M1 1.434.050,00
14 Pipa HDPE - SDR11.PN10 ND 400 mm M1 1.812.050,00
15 Pipa HDPE - SDR11.PN10 ND 450 mm M1 2.663.200,00
16 Pipa HDPE - SDR11.PN10 ND 500 mm M1 3.281.000,00
17 Pipa HDPE - SDR11.PN10ND 550 mm M1 4.122.800,00
18 Pipa HDPE - SDR11.PN10 ND 600 mm M1 5.208.800,00
19 Tee HDPE ND 75 x 75 mm Bh 481.750,00
20 Tee HDPE ND 110 x 75 mm Bh 945.000,00
21 Tee HDPE ND 110 x 110 mm Bh 602.250,00
22 Tee HDPE ND 160 x 110 mm Bh 1.438.600,00
23 Tee HDPE ND 160 x 160 mm Bh 926.400,00
24 Tee HDPE ND 200 x 110 mm Bh 1.764.000,00
25 Tee HDPE ND 200 x 160 mm Bh 1.928.600,00
26 Tee HDPE ND 200 x 200 mm Bh 2.457.000,00
Tee HDPE ND 250 x 100 mm Bh 4.422.600,00
Tee HDPE ND 250 x 150 mm Bh 4.238.300,00
Tee HDPE ND 250 x 200 mm Bh 4.054.050,00
Tee HDPE ND 250 x 250 mm Bh 3.685.500,00
Tee HDPE ND 300 x 150 mm Bh 6.633.900,00
27 Tee HDPE ND 300 x 200 mm Bh 6.357.450,00
Tee HDPE ND 300 x 250 mm Bh 6.081.050,00
28 Tee HDPE ND 300 x 300 mm Bh 5.528.250,00
Tee HDPE ND 400 x 250 mm Bh 9.536.200,00
29 Tee HDPE ND 400 x 300 mm Bh 9.121.600,00
30 Tee HDPE ND 400 x 400 mm Bh 8.292.350,00
31 Tee HDPE ND 500 x 300 mm Bh 12.936.100,00
32 Tee HDPE ND 500 x 350 mm Bh 12.397.050,00
33 Tee HDPE ND 500 x 400 mm Bh 11.858.050,00
34 Tee HDPE ND 500 x 500 mm Bh 10.780.050,00
35 Reducer HDPE ND 100 x 75 mm Bh 107.100,00
36 Reducer HDPE ND 160 x 110 mm Bh 241.900,00
37 Reducer HDPE ND 200 x 110 mm Bh 383.000,00
38 Reducer HDPE ND 200 x 160 mm Bh 447.300,00
39 Reducer HDPE ND 250 x 160 mm Bh 897.100,00
40 Reducer HDPE ND 250 x 200 mm Bh 945.000,00
41 Reducer HDPE ND 300 x 200 mm Bh 1.480.500,00
42 Reducer HDPE ND 300 x 250 mm Bh 1.606.500,00
43 Reducer HDPE ND 400 x 300mm Bh 2.803.500,00
44 Reducer HDPE ND 400 x 350 mm Bh 3.083.850,00
45 Bend 900 HDPE ND 75 mm Bh 219.500,00
46 Bend 900 HDPE ND 110 mm Bh 578.900,00
47 Bend 900 HDPE ND 160 mm Bh 1.294.000,00
48 Bend 900 HDPE ND 200 mm Bh 2.305.150,00
49 Bend 900 HDPE ND 250 mm Bh 2.766.150,00
HARGA
NO URAIAN SATUAN
(Rp)
50 0
Bend 90 HDPE ND 300 mm Bh 3.319.400,00
51 0
Bend 90 HDPE ND 400 mm Bh 3.983.300,00
52 0
Bend 45 HDPE ND 75 mm Bh 144.650,00
53 0
Bend 45 HDPE ND 100 mm Bh 408.650,00
54 0
Bend 45 HDPE ND 150 mm Bh 817.100,00
55 0
Bend 45 HDPE ND 200 mm Bh 1.374.000,00
56 Bend 450 HDPE ND 250 mm Bh 1.648.800,00
57 0
Bend 45 HDPE ND 300 mm Bh 1.978.550,00
58 Bend 450 HDPE ND 400 mm Bh 2.374.300,00
59 Stub Flange HDPE ND 75 mm Bh 435.400,00
60 Stub Flange HDPE ND 110 mm Bh 867.000,00
61 Stub Flange HDPE ND 160 mm Bh 1.040.450,00
62 Stub Flange HDPE ND 200 mm Bh 1.352.600,00
63 Stub Flange HDPE ND 250 mm Bh 1.623.100,00
64 Stub Flange HDPE ND 300 mm Bh 2.110.050,00
65 Stub Flange HDPE ND 400 mm Bh 2.532.100,00
66 Stub Flange HDPE ND 500 mm Bh 3.291.750,00
67 Dop HDPE ND 200 mm Bh 739.050,00
68 Dop HDPE ND 160 mm Bh 471.850,00
69 Dop HDPE ND 110 mm Bh 267.400,00
70 Dop HDPE ND 75 mm Bh 213.900,00
71 Blind Flange ND 300 mm Bh 385.100,00
72 Blind Flange ND 350 mm Bh 500.650,00
73 Blind Flange ND 400 mm Bh 650.850,00
74 Blind Flange ND 500 mm Bh 846.100,00
1 Pemasangan Pipa Volume
Pipa Steel - CTE.CL Ø 700 mm m 606,00
Pipa HDPE SDR11, PN-10 Ø 500 mm m 448,00
Pipa HDPE SDR11, PN-10 Ø 400 mm m 4.618,00
2 Fitting Jalur
Elbow 45° HDPE Ø 400 mm Bh 3
Elbow 90° HDPE Ø 400 mm Bh 3
CROSSING JALAN ASPHALT m 18
3 Junction DJ10
All Flange Tee CI Ø 700 x 400 mm Bh 1
All Flange Reducer CI Ø 700 x 500 mm Bh 1
All Flange Gate Valve CI Ø 500 mm Bh 1
All Flange Gate Valve CI Ø 400 mm Bh 1
Collar Ø 700 mm Bh 1
Collar Ø 500 mm Bh 1
Collar Ø 400 mm Bh 1
4 Junction DJ11
Tee All Flange HDPE Ø 500 x 400 mm Bh 1
All Flange Gate Valve CI Ø 500 mm Bh 1
All Flange Gate Valve CI Ø 400 mm Bh 1
Stube Flange HDPE Ø 500 mm Bh 1
Stube Flange HDPE Ø 400 mm Bh 1
Collar Ø 500 mm Bh 1
Collar Ø 400 mm Bh 1
Blind Flange HDPE Ø 500 mm Bh 1
5 Junction DJ12
Tee All Flange HDPE Ø 400 x 400 mm Bh 1
All Flange Reducer CI Ø 400 x 300 mm Bh 1
All Flange Gate Valve CI Ø 400 mm Bh 1
All Flange Gate Valve CI Ø 300 mm Bh 1
Stube Flange HDPE Ø 400 mm Bh 1
Stube Flange HDPE Ø 300 mm Bh 1
Collar Ø 400 mm Bh 1
Collar Ø 300 mm Bh 1
6 Junction DJ13
All Flange Reducer CI Ø 400 x 250 mm Bh 1
All Flange Gate Valve CI Ø 250 mm Bh 1
Stube Flange HDPE Ø 400 mm Bh 1
Stube Flange HDPE Ø 250 mm Bh 1
Collar Ø 400 mm Bh 1
Collar Ø 250 mm Bh 1
7 Junction DJ14
Tee All Flange HDPE Ø 400 x 100 mm Bh 1
Tee All Socket PVC Ø 100 x 100 mm Bh 1
All Flange Gate Valve CI Ø 100 mm Bh 1
Stube Flange HDPE Ø 100 mm Bh 1
Flange Spigot CI Ø 100 mm Bh 1
Collar Ø 400 mm Bh 1
Collar Ø 100 mm Bh 1
8 Junction DJ15
Tee All Flange HDPE Ø 400 x 400 mm Bh 1
Tee All Socket PVC Ø 100 x 100 mm Bh 1
All Flange Reducer CI Ø 400 x 100 mm Bh 1
All Flange Gate Valve CI Ø 400 mm Bh 1
All Flange Gate Valve CI Ø 100 mm Bh 1
Stube Flange HDPE Ø 400 mm Bh 1
Stube Flange HDPE Ø 100 mm Bh 1
Flange Spigot CI Ø 100 mm Bh 1
Collar Ø 400 mm Bh 1
Collar Ø 100 mm Bh 1
Blind Flange HDPE Ø 400 mm Bh 1
1,1 1,2 1,3 1,4 1,5 1,6 1,65 1,7 1,75 1,8 1,85 1,9 1,95 2 2,05 2,1
PENANAMAN PIPA 0,25 0,3 0,3 0,3 0,35 0,4 0,45 0,5 0,55 0,6 0,65 0,7 0,75 0,8 0,85 0,9
VOLUME GALIAN, TIBUNAN DAN REKONDISI
TIPE PENANAMAN
Ø 40 mm Ø 50 mm Ø 75 mm Ø 100 mm Ø 150 mm Ø 200 mm Ø 250 mm Ø 300 mm Ø 350 mm Ø 400 mm Ø 500 mm Ø 600 mm Ø 700 mm Ø 800 mm Ø 900 mm Ø 1000 mm
PADA TANAH KERAS
Galian 0,53 0,59 0,63 0,68 0,77 0,87 0,98 1,09 1,20 1,32 1,58 1,85 2,15 2,46 2,60 2,80
Urugan Pasir 0,07 0,09 0,10 0,11 0,14 0,17 0,20 0,23 0,26 0,29 0,36 0,44 0,52 0,60 0,66 0,72
Timbunan & Padatkan 0,33 0,35 0,38 0,40 0,45 0,50 0,55 0,60 0,65 0,70 0,80 0,90 1,00 1,10 1,20 1,30
Buangan Tanah 0,07 0,09 0,10 0,12 0,16 0,20 0,25 0,30 0,36 0,42 0,56 0,72 0,90 1,10 1,20 13,00
PADA BERM JALAN 0,3 0,3 0,3 0,3 0,3 0,3 0,3 0,3 0,3 0,3 0,3 0,3 0,3 0,3 0,3 0,3
0,80 0,90 1,00 1,10 1,20 1,30 1,35 1,40 1,45 1,50 1,55 1,60 1,65 1,70 1,75 1,80
Galian Tanah Berbatu 0,08 0,09 0,09 0,09 0,11 0,12 0,14 0,15 0,17 0,18 0,20 0,21 0,23 0,24 0,26 0,27
Galian Tanah Normal 0,20 0,27 0,30 0,33 0,42 0,52 0,61 0,70 0,80 0,90 1,01 1,12 1,24 1,36 1,49 1,62
Timbunan &Padatkan 0,28 0,36 0,39 0,42 0,53 0,64 0,74 0,85 0,96 1,08 1,20 1,33 1,46 1,60 1,74 1,89
Urugan Pasir 0,17 0,20 0,22 0,24 0,29 0,33 0,37 0,42 0,47 0,51 0,61 0,72 0,83 0,91 1,00 1,10
Buangan Tanah 0,30 0,36 0,39 0,43 0,50 0,57 0,65 0,74 0,83 0,92 1,13 1,35 1,60 1,86 2,05 2,25
PADA JALAN ASPAL/HOTMIX
0,25 0,25 0,25 0,25 0,25 0,25 0,25 0,25 0,25 0,25 0,25 0,25 0,25 0,25 0,25 0,25
0,85 0,95 1,05 1,15 1,25 1,35 1,40 1,45 1,50 1,55 1,60 1,65 1,70 1,75 1,80 1,85
Pengbongkaran Hotmix 0,06 0,08 0,08 0,08 0,09 0,10 0,11 0,13 0,14 0,15 0,16 0,18 0,19 0,20 0,21 0,23
Galian Tanah Keras 0,21 0,29 0,32 0,35 0,44 0,54 0,63 0,73 0,83 0,93 1,04 1,16 1,28 1,40 1,53 1,67
Timbunan tanah 0,21 0,23 0,24 0,25 0,28 0,30 0,33 0,35 0,38 0,40 0,45 0,50 0,55 0,60 0,60 0,60
Buangan Tanah 0,41 0,49 0,53 0,57 0,66 0,74 0,84 0,94 1,05 1,15 1,39 1,64 1,91 2,21 2,43 2,67
Rekondisi Jalan Hotmix 0,25 0,30 0,30 0,30 0,35 0,40 0,45 0,50 0,55 0,60 0,65 0,70 0,75 0,80 0,88 0,97
PADA JALAN BETON
Galian Tanah Berbatu 0,40 0,44 0,48 0,52 0,61 0,70 0,80 0,90 1,01 1,12 1,36 1,62 1,90 2,20 2,42 2,66
Pengbongkaran beton 0,17 0,20 0,22 0,24 0,29 0,33 0,37 0,42 0,47 0,51 0,61 0,72 0,83 0,94 1,03 1,13
Timbunan tanah 0,21 0,23 0,24 0,25 0,28 0,30 0,33 0,35 0,38 0,40 0,45 0,50 0,55 0,60 0,66 0,73
Buangan Tanah 0,41 0,49 0,53 0,57 0,66 0,74 0,84 0,94 1,05 1,15 1,39 1,64 1,91 2,21 2,43 2,67
Rekondisi Jalan Beton 0,25 0,30 0,35 0,40 0,45 0,50 0,55 0,60 0,65 0,70 0,75 0,85 0,95 1,05 1,16 1,27
Turap 1,96 2,31 2,71 3,19 3,76 4,42 5,20
TRUST BLOCK
VOLUME BETON
ACCESSORIES PIPA
ND 40 ND 50 ND 75 ND 100 ND 150 ND 200 ND 250 ND 300 ND350 ND 400 ND 500 ND 600 ND 700 ND 800 ND 900 ND 1000 ND 1100 ND 1200
Elbow - Beton (M3) 0,03 0,04 0,06 0,08 0,12 0,17 0,25 0,35 0,50 0,72 1,15 1,78 2,49 3,58 5,06 8,93 9,82 10,80
Bekisting (m2) 0,11 0,15 0,21 0,31 0,44 0,63 0,89 1,28 1,82 2,60 3,72 5,94 9,10 12,26 19,44 24,48 33,05 46,27
Besi beton (kg) 39,00 56,00 80,00 128,00 199,00 279,00 400,00 567,00 999,00 1.099,00 1.209,00
Reducer Beton (m3) 0,02 0,02 0,04 0,05 0,07 0,10 0,15 0,21 0,30 0,43 0,69 1,07 1,50 2,15 3,04 5,36 5,89 6,48
Bekisting (m2) 0,08 0,12 0,17 0,25 0,35 0,50 0,71 1,02 1,46 2,08 2,98 4,75 7,28 9,81 15,55 19,58 26,44 37,01
Besi beton (kg) 23,00 33,00 48,00 77,00 119,00 167,00 240,00 340,00 599,00 659,00 725,00
Tee Beton (m3) 0,04 0,05 0,08 0,11 0,16 0,22 0,32 0,46 0,66 0,94 1,49 2,32 3,24 4,65 6,58 11,60 12,76 14,04
Bekisting (m2) 0,18 0,25 0,36 0,51 0,73 1,05 1,50 2,14 3,06 4,37 6,24 8,45 10,27 12,10 15,12 17,54 22,81 29,65
Besi beton (kg) 51,00 73,00 104,00 167,00 259,00 363,00 520,00 737,00 1.299,00 1.429,00 1.572,00
Gate Valve - Beton (M3) 0,02 0,04 0,05 0,07 0,10 0,15 0,21 0,30 0,43 0,61 0,97 1,51 2,11 3,02 4,28 7,54 8,30 9,13
Bekisting (m2) 0,14 0,20 0,29 0,41 0,59 0,84 1,20 1,71 2,45 3,49 4,99 6,76 8,22 9,68 12,10 14,04 18,25 23,72
Besi beton (kg) 33,00 47,00 68,00 108,00 168,00 236,00 338,00 479,00 844,00 929,00 1.022,00
Turap 0,50 0,60 0,70 0,80 0,90 1,00 1,10 1,20