Pemakaian Batching Plan Bulan Mei 2022

N0 Waktu pengecoran
1 22/05/2022
2 14/05/2022
3 18/5/2022
4 1/5/2022
5 12/5/2022
6 23/05/2022
7 13/05/2022
8 15/05/2022
9 17/05/2022
Total
Biaya X 2200

ARUS START PADA BATCHING PLANT

Kapasitas Batching Plant =


Tegangan =

V*1.73 =

I = S/V*1.73
Batching Plan Bulan Mei 2022

durasi pengecoran daya KWH


8 jam 1120
8 jam 1120
8 jam 1120
4 jam 560
4 jam 560
8 jam 1120
8 jam 1120
8 jam 1120
8 jam 1120
64 8960
19712000

US START PADA BATCHING PLANT SAFETY SAAT START


ARUS BATCHING PLANT
56000 VA SAFETY 120 %
400 V Batching Plant 56 KVA
1.73 START SAFETY 67.2 KVA
692 ARUS SAFETY 97.10983 A

80.9248554913295 A

36-40 A

45-55 A