JUMLAH HARGA
No URAIAN SATUAN JUMLAH
ORANG VOLUME SATUAN
A BIAYA PERSONIL
1 Team leader 1 4 OB 37,250,000 149,000,000
2 Supervision Engineer -
a Ahli arsitektur bangunan 1 4 OB 28,750,000 115,000,000
b Ahli struktur bangunan gedung 1 4 OB 28,750,000 115,000,000
c Ahli geoteknik (opsional) 1 4 OB 28,750,000 115,000,000
d Ahli mekanikal elektrikal dan plumbing 1 4 OB 28,750,000 115,000,000
3 Quality Engineer
a Ahli arsitektur bangunan 1 4 OB 24,250,000 97,000,000
b Ahli struktur bangunan gedung 1 4 OB 21,000,000 84,000,000
c Ahli geoteknik (opsional) 1 4 OB 21,000,000 84,000,000
d Ahli bahan bangunan/konstruksi 1 4 OB 21,000,000 84,000,000
e Ahli mekanikal elektrikal dan plumbing 1 4 OB 21,000,000 84,000,000
aaa bbb
KERTAS KERJA HARGA PERKIRAAN SENDIRI
PENGADAAN JASA KONSULTANSI
JUMLAH HARGA
No URAIAN SATUAN JUMLAH
ORANG VOLUME SATUAN
A BIAYA PERSONIL
1 Team leader 1 4 OB 7,074,700 28,298,800
2 Supervision Engineer -
a Ahli arsitektur bangunan 1 4 OB 5,460,350 21,841,400
b Ahli struktur bangunan gedung 1 4 OB 5,460,350 21,841,400
c Ahli geoteknik (opsional) 1 4 OB 5,460,350 21,841,400
d Ahli mekanikal elektrikal dan plumbing 1 4 OB 5,460,350 21,841,400
3 Quality Engineer
a Ahli arsitektur bangunan 1 4 OB 4,605,700 18,422,800
b Ahli struktur bangunan gedung 1 4 OB 3,988,400 15,953,600
c Ahli geoteknik (opsional) 1 4 OB 3,988,400 15,953,600
d Ahli bahan bangunan/konstruksi 1 4 OB 3,988,400 15,953,600
e Ahli mekanikal elektrikal dan plumbing 1 4 OB 3,988,400 15,953,600