RENCANA ANGGARAN BIAYA

No. Uraian Volume Satuan Harga Satuan (Rp.) Jumalah (Rp.)

1 Batu 3 Truk 1,500,000 4,500,000


2 Pasir Pasang 7 Truk 1,500,000 10,500,000
3 Pasir Cor 1 Truk 1,750,000 1,750,000
4 Split 2 Truk 1,120,000 2,240,000
5 Besi 10 50 batang 90,000 4,500,000
6 Besi 8 50 batang 60,000 3,000,000
7 Besi 6 20 Batang 40,000 800,000
8 Kawat Beton 15 Kg 25,000 375,000
9 Bata Merah 5000 Buah 1,200 6,000,000
10 Semen 150 Sak 80,000 12,000,000
11 Kayu Gisting 5 Kubik 1,000,000 5,000,000
12 Kayu Pelapon 4 Kubik 1,000,000 4,000,000
13 Kayu Kaso 5 Kubik 1,200,000 6,000,000
14 Genteng 3000 Biji 5,000 15,000,000
15 Grc 30 Biji 120,000 3,600,000
16 Paku 50 Kg 30,000 1,500,000
17 Keramik 90 Dus 90,000 8,100,000
18 Lespang 15 Biji 150,000 2,250,000
19 Kusen Kaca 4 Buah 3,000,000 12,000,000
20 Kusen atas pentilasi 8 Buah 1,250,000 10,000,000
21 Pintu 2 Buah 3,000,000 6,000,000
22 Daun Pintu 4 Buah 500,000 2,000,000
23 Kaca 6 Lembar 300,000 1,800,000
24 Reng Kayu 25 Ikat 110,000 2,750,000
25 Bambu Gisting 120 Batang 25,000 3,000,000
26 Cat Kayu,Cat Tembik 5 Galon 1,000,000 5,000,000
27 Koas 5 Buah 20,000 100,000
28 Roll 4 Buah 30,000 120,000
29 Tatakan 3 Buah 19,000 58,000
30 Pegangan Pintu 2 Buah 120,000 240,000
31 Engsel Pintu 8 Buah 15,000 120,000
32 Engsel Jendela 6 Buah 12,000 72,000
33 Kabel 1 Rol 500,000 500,000
34 Stop kontak 3 Biji 25,000 75,000
35 Piting lampu 2 Biji 25,000 50,000
36 Upah Kerja Sealama 1 Bulan 150 Hok 100,000 15,000,000
5 Orang x 30 Hari
Jumlah Total Rp 150,000,000
Seratus Lima Puluh Juta Rupiah
Garut, 29 Agustus 2022
Ketua Bendahara

Abdul Hay Aal Alawi