Anda di halaman 1dari 3

RENCANA ANGGARAN BIAYA KOMISI

SARANA DAN PRASARANA tahap i


No. Description QTY UOM Unit Price (IDR) Total Price (IDR)
PEKERJAAN RUANG MULTIMEDIA
I UKURAN 22 MTR X 4 MTR = 8,8 M2
1. UPAH KERJA
-Cor lantai 1 Ls 750,000 750,000
-Pasang Keramik 8.8 m2 90,000 792,000
-Bongkar pasang partisi 1 Ls 500,000 500,000
2. MATERIAL
-Semen Conch 3 Sak 66,000 198,000
-Pasir 1 kubik 1 Kbk 400,000 400,000
TOTAL I 2,640,000

PEKERJAAN RUANG SEKOLAH MINGGU & GUDANG INVENTARIS GEREJA


II & PWGT
LUAS 3,2 X 14 MTR = 44,8 M2 (45 M2)
1. UPAH KERJA
-Pasang Keramik (45 m2) 45 m2 90,000 4,050,000
-Pasang partisi GRC 6mm 82 m2 95,000 7,790,000
-Ganti atap seng @5pcs dan pengacatan dinding luar 1 Ls 750,000 750,000
2. MATERIAL
-GRC 6MM 30 Lbr 125,000 3,750,000
-Balok 5/10 banci 1 Kbk 2,500,000 2,500,000
-Paku biasa 3" 10 Kg 19,000 190,000
-Paku beton 3 kotak 3 Ktk 20,000 60,000
-Paku GRC 5 kotak 5 Ktk 23,000 115,000
-Kompon gipsum 10 Kg 5,000 50,000
-Pasir 3 kubik 3 Kbk 400,000 1,200,000
-Cat putih @20ltr 1 Gln 570,000 570,000
-Kuas, etc 1 Ls 150,000 150,000
-Pintu 1 Set 800,000 800,000
-Jendela 1 Set 400,000 400,000
TOTAL II 22,375,000

III PEKERJAAN RUANG SERBA GUNA DAN TERAS DEPAN PASTORI (7,5 X
12MTR)
1. UPAH KERJA
-Pasang Keramik (26 m2) 26 m2 90,000 2,340,000
-Pasang partisi GRC 36M2 36 m2 95,000 3,420,000
-Pasang Bata & plaster luar/dalam 18m2 18 m2 150,000 2,700,000
-Cor Lantai teras 20 m2 1 Ls 750,000 750,000
-Pasang kembali atap teras 1 LS 750,000 750,000
-Cat dinding bagian luar 1 Ls 500,000 500,000
2. MATERIAL
-GRC 6MM 16 Lbr 125,000 2,000,000
-Balok 5/10 banci 0.5 Kbk 2,500,000 1,250,000
-Semen 12 Sak 66,000 792,000
-Paku biasa 3" 6 Kg 19,000 114,000
-Paku GRC 3 kotak 3 Ktk 23,000 69,000
-Paku beton 2 Ktk 20,000 40,000
-Kompon gipsum 10 Kg 5,000 50,000
-Bata 1000 Pcs 900 900,000
-Pasir 2 kubik 2 Kbk 400,000 800,000
-Cat putih @20ltr 1 Gln 570,000 570,000
-Kuas, etc 1 Ls 150,000 150,000
-Pintu 1 Set 800,000 800,000
-Jendela 2 Set 400,000 800,000
TOTAL III 18,795,000

TOTAL I + TOTAL II + TOTAL III 43,810,000

Disiapkan Oleh Komisi Sarana & Prasarana Disetujui Oleh PMJ


( ) ( )
RENCANA ANGGARAN BIAYA KOMISI
SARANA DAN PRASARANA tahap II
No. Description QTY UOM Unit Price (IDR) Total Price (IDR)
I PEKERJAAN PARIT & PENGUATAN SIRING ATAS
1. UPAH KERJA
-Kepala tukang 30 Hr 250,000 7,500,000
-Pembantu tukang I (3 org) @100rb/org 30 Hr 300,000 9,000,000
-Pengawas Lapangan 1 Ls 4,000,000 4,000,000
-Meals 5 org - @25rb/org 30 Hr 75,000 2,250,000
2. MATERIAL
-Besi 10" 24 Btg 86,000 2,064,000
-Besi 8" 10 Btg 55,000 550,000
-Semen Conch 80 Sak 65,000 5,200,000
-Pasir 2 Trk 1,400,000 2,800,000
-Coral 2 Trk 1,700,000 3,400,000
-Pipa 10" 3 EA 900,000 2,700,000
-Pipa 6" 2 EA 350,000 700,000
-Elbow 6" 6 EA 55,000 330,000
-Bata 2000 Pcs 1,000 2,000,000
TOTAL I 42,494,000

II PEKERJAAN PERBAIKAN & PENAMBAHAN PAGAR DEPAN RUMAH


PASTORI DAN SAMPING GEREJA
-Penambahan pagar depan rumah pastori 12 Mtr 550,000 6,600,000
-Perbaikan pagar samping gereja 10 Mtr 250,000 2,500,000
TOTAL II 9,100,000

TOTAL I + TOTAL II 51,594,000

Disiapkan Oleh Komisi Sarana & Prasarana Disetujui Oleh PMJ

( ) ( )