ESTIMASI VOLUME ABUTMEN

Project Name : JEMBATAN GIRDER BENTANG 11 METER


Date : 11-Dec-22
BETON ABUTMEN SATUAN VOLUME KET

1 ABUTMEN UTAMA (+BACKWALL) M3 40,2 M3 VOLUME SUDAH MENCAKUP ABUTMEN 1 & 2


2 DUDUKAN BEARING M3 0,495 M3 VOLUME SUDAH MENCAKUP ABUTMEN 1 & 2
3 WINGWALL M3 0,81 M3 VOLUME SUDAH MENCAKUP ABUTMEN 1 & 2
PENULANGAN BETON SATUAN VOLUME KET

1 ABUTMEN UTAMA (+BACKWALL) KG 2410 KG VOLUME SUDAH MENCAKUP ABUTMEN 1 & 2


2 DUDUKAN BEARING KG 50,3 KG VOLUME SUDAH MENCAKUP ABUTMEN 1 & 2
3 WINGWALL KG 70,9 KG VOLUME SUDAH MENCAKUP ABUTMEN 1 & 2