REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

NO URAIAN PEKER JAAN VOLUME SATUAN

I PEKERJAAN PERSIAPAN
1.1 PEMBERSIHAN LAHAN 451.5 m2
1.2 PENGUKURAN DAN BOWPLANG 97.5 m
1.3 PENYEDIAAN AIR KERJA 1 ls
1.4 ADMINISTRASI 1 ls
1.5 PAPAN NAMA PROYEK 1 ls
1.6 LISTRIK KERJA HARIAN 1 ls
1.7 PRASASTI PERESMIAN 1 ls
1.8 PEMBUATAN PAGAR PENGAMAN 1 ls
1.9 BIAYA IMB 1 ls

II PEKERJAAN PONDASI
2.1 PONDASI FOOTPLAT
2.1.1 GALIAN TANAH FOOTPLAT 259 m3
2.1.1.1 TYPE 1 62.72 m3
2.1.1.2 TYPE 2 150.92 m3
2.1.1.3 TYPE 3 45.36 m3

2.1.2 URUGAN TANAH KEMBALI FOOTPLAT 225.8 m3


2.1.2.1 TYPE 1 54.467 m3
2.1.2.2 TYPE 2 131.431 m3
2.1.2.3 TYPE 3 39.902 m3

2.1.3 PASIR URUG FOOTPLAT 7.39 m3


2.1.3.1 TYPE 1 1.79 m3
2.1.3.2 TYPE 2 4.31 m3
2.1.3.3 TYPE 3 1.29 m3

2.1.4 LANTAI KERJA FOOTPLAT K 100 3.68 m3


2.1.4.1 TYPE 1 0.89 m3
2.1.4.2 TYPE 2 2.15 m3
2.1.4.3 TYPE 3 0.64 m3

2.1.5 BETON COR PONDASI FOOTPLAT K250 26.585 m3


2.1.5.1 TYPE 1 6.755 m3
2.1.5.2 TYPE 2 15.359 m3
2.1.5.3 TYPE 3 4.471 m3

2.1.6 PEMBESIAN PONDASI FOOTPLAT 1843.721 kg


2.1.6.1 TYPE 1 526.918 kg
2.1.6.2 TYPE 2 1056.176 kg
2.1.6.3 TYPE 3 260.627 kg
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

NO URAIAN PEKER JAAN VOLUME SATUAN

2.1.7 BEKISTING PONDASI FOOTPLAT 22.92 m2


2.1.7.1 TYPE 1 8.64 m2
2.1.7.2 TYPE 2 7.56 m2
2.1.7.3 TYPE 3 6.72 m2

2.2 PONDASI BATU KALI


2.2.1 PAS. BATU BELAH 87.384 m3
2.2.2 AANSTAMPING 39.72 m3
2.2.3 PASIR URUG BATU KALI 19.86 m3
2.2.4 URUGAN TANAH 317.264 m3

PEKERJAAN LANTAI I
III.A PEKERJAAN STRUKTUR
3.1 PEK. SLOOF BETON BERTULANG
3.1.1 TYPE S1
Pembesian 2353.659 kg
Bekisting 154 m2
Beton Cor K-225 15.4 m3
3.1.2 TYPE S2
Pembesian 48.7084 kg
Bekisting 3.9 m2
Beton Cor K-225 0.293 m3

3.2 PEK. KOLOM BETON BERTULANG


3.2.1 TYPE K1
Pembesian 2088.747 kg
Bekisting 104 m2
Beton Cor K-250 8 m3
3.2.2 TYPE K2
Pembesian 2645.564 kg
Bekisting 133.25 m2
Beton Cor K-250 8.328 m3
3.2.4 TYPE K4
Pembesian 339.026 kg
Bekisting 24.8 m2
Beton Cor K-250 2.325 m3
3.2.5 TYPE KP
Pembesian 144.424 kg
Bekisting 18.3 m2
Beton Cor K-250 0.686 m3
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

NO URAIAN PEKER JAAN VOLUME SATUAN

3.3 PEK. BALOK BETON BERTULANG


3.3.1 BALOK INDUK
TYPE B1
Pembesian 2363.235 kg
Bekisting 130.645 m2
Beton Cor K-250 13.395 m3
3.3.2 BALOK ANAK
3.3.2.1 TYPE B2
Pembesian 1743.096 kg
Bekisting 127.7 m2
Beton Cor K-250 10.354 m3
3.3.2.2TYPE B3
Pembesian 102.535 kg
Bekisting 18.33 m2
Beton Cor K-250 0.635 m3
3.2.4 BALOK DAK (B4)
Pembesian 288.776 kg
Bekisting 28.806 m2
Beton Cor K-250 1.879 m3

3.5 PEK. TANGGA


Pembesian 407.504 kg
Bekisting 15.262 m2
Beton Cor K-250 2.865 m3
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

NO URAIAN PEKER JAAN VOLUME SATUAN

3.6 PEK. PLAT LANTAI DAN ATAP


3.6.1 PLAT LANTAI II
Pembesian 2821.872 kg
Bekisting 268.993 m2
Beton Cor K-250 31.344 m3
3.6.2 TOPI TOPI + 3.17
Pembesian 168.127 kg
Bekisting 32.16 m2
Beton Cor K-225 2.898 m3

V.A PEKERJAAN PASANGAN BATU BATA DAN PLESTERAN


5.1 PEK. PASANGAN BATA
5.1.1 Pas. Bata 1:3 13.35 m2
5.1.2 Pas. Bata 1:5 375.588 m2

5.2 PEK. PLESTERAN


5.2.1 Pas. Bata 1:3 13.35 m2
5.2.2 Pas. Bata 1:5 375.588 m2

VI.A PEKERJAAN KUSEN


6.1 PINTU
6.1.1 TYPE PJ 1 (1 BUAH)
6.1.1.1 Kusen Pintu Alumunium 27.75 m
6.1.1.2 Daun Pintu 0.76 m2
6.1.1.3 Kaca T = 8 mm 6.01 m2
6.1.1.4 Handel 4 bh
6.1.1.5 Engsel 12 bh

6.1.2 TYPE P1 (1 BUAH)


6.1.2.1 Kusen Pintu Alumunium 8.3 m
6.1.2.2 Daun Pintu 1.83 m2
6.1.2.3 Kaca T = 5 mm 0.52 m2
6.1.2.4 Kaca T = 8 mm 1.01 m2
6.1.2.5 Handel 4 bh
6.1.2.6 Engsel 4 bh

6.1.4 TYPE P3 (3 BUAH)


6.1.4.1 Kusen Pintu Alumunium 22.8 m
6.1.4.2 Daun Pintu 8.84 m2
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

6.1.4.3 Kaca Buram 0.35 m2


6.1.4.4 Kaca T = 5 mm 1.44 m2
6.1.4.5 Multipleks 1.623 m2
6.1.4.6 Handel 12 bh
6.1.4.7 Engsel 12 bh

NO URAIAN PEKER JAAN VOLUME SATUAN

6.1.5 TYPE P4 (5 BUAH)


6.1.5.1 Kusen Pintu Alumunium 34 m
6.1.5.2 Daun Pintu 11.62 m2
6.1.5.3 Kaca Buram 0.576 m2
6.1.5.4 Kaca T = 5 mm 0.576 m2
6.1.5.5 Multipleks 2.566 m2
6.1.5.6 Handel 10 bh
6.1.5.7 Engsel 10 bh

6.1.6 TYPE P5 (2 BUAH)


6.1.6.1 Kusen Alumunium 9.8 m
6.1.6.2 Daun Pintu 1.070 m2
6.1.6.3 Multipleks 1.731 m2
6.1.6.4 Handle 2 bh
6.1.6.5 Engsel 2 bh

6.1.7 TYPE P6 (1 BUAH)


6.1.7.1 Kusen Alumunium 12.15 m
6.1.7.2 Daun Pintu 10.753 m2
6.1.7.3 Multipleks 6.627 m2
6.1.7.4 Handle 0 bh
6.1.7.5 Engsel 16 bh

6.2 PEMASANGAN JENDELA


6.2.1 TYPE J1 (1 BUAH)
6.2.1.1 Kusen Alumunium 8.7 m
6.2.1.2 Kaca T = 5 mm 0.48 m2
6.2.1.3 Kaca T = 8 mm 1.38 m2

6.2.2 TYPE J2 (2 BUAH)


6.2.2.1 Kusen Alumunium 24.4 m
6.2.2.2 Daun Jendela 18.84 m2
6.2.2.3 Kaca T = 5 mm 1.44 m2
6.2.2.4 Kaca T = 8 mm 2.445 m2
6.2.2.5 Engsel 12 bh

6.2.3 TYPE J3 (1 BUAH)


6.2.3.1 Kusen Alumunium 12.2 m
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

6.2.3.2 Kaca T = 5 mm 0.72 m2


6.2.3.3 Kaca T = 8 mm 2.07 m2

NO URAIAN PEKERJAAN VOLUME SATUAN

6.2.4 TYPE J4 (3 BUAH)


6.2.4.1 Kusen Alumunium 24.3 m
6.2.4.2 Kaca T = 5 mm 5.763 m2
6.2.4.3 Daun Jendela 17.64 m2
6.2.4.4 Engsel 12 bh

6.2.5 TYPE J5 (1 BUAH)


6.2.5.1 Kusen Alumunium 8.1 m
6.2.5.2 Kaca T = 5 mm 0.4 m2
6.2.5.3 Kaca T = 8 mm 1.15 m2

6.2.6 TYPE J6 (1 BUAH)


6.2.6.1 Kusen Alumunium 5.2 m
6.2.6.2 Daun Jendela 0.647 m2
6.2.6.3 Kaca T = 5 mm 3.14 m2
6.2.6.4 Engsel 2 bh

6.2.8 BOUVEN BV1 (2 BUAH)


6.2.8.1 Kusen Alumunium 2.8 m
6.2.8.2 Kaca T = 5 mm 0.32 m2

6.3 PEMASANGAN PARTISI


6.3.1 TYPE PTS1 (1 BUAH)
Kusen Alumunium 5.22 m
Daun Pintu 5.8 m
Multipleks 0.67 m2
Gypsum 2.268 m2
Handle 2 bh
Engsel 2 bh

6.3.2 TYPE PTS2 (1 BUAH)


Kusen Alumunium 4.9 m
Kaca T = 5 mm 0.564 m2
Gypsum 1.688 m2
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

NO URAIAN PEKERJAAN VOLUME SATUAN

VII.A PEKERJAAN MECHANICAL AND ELECTRICAL


7.1 LAMPU TL 40 WATT 20 bh
7.2 LAMPU SL 18 WATT 8 bh
7.3 STOPKONTAK 200 WATT 13 bh
7.4 SAKLAR TUNGGAL 12 bh
7.5 SAKLAR GANDA 2 bh
7.6 INSTALASI STOPKONTAK DAN TITIK LAMPU 41 titik
7.7 SUB PANEL PENERANGAN 1 titik
7.8 PENYAMBUNGAN LISTRIK / TAMBAH DAYA 10 kVA 1 unit
7.9 GENSET 5 Kva 1 unit
7.10 PASANGAN AC 2 PK + INSTALASI LEMGKAP 1 unit

VIII.A PEKERJAAN SANITASI


8.1 CLOSET JONGKOK 2 bh
8.2 WASHTAFEL 5 bh
8.3 BAK MANDI 2 bh
8.4 FLOOR DRAIN 14 bh
8.5 KRAN AIR 7 bh
8.6 PIPA PVC DIAMETER 25" 60 m
8.7 PIPA PVC DIAMETER 4" 35 m
8.8 BAK KONTROL 3 bh
8.9 GROUND RESERVOAR 1 unit
8.10 POMPA AIR LENGKAP INSTALASI 1 unit
8.11 SEPTICTANK
GALIAN TANAH 4.59 m3
AANSTAMPING 1.052 m3
PASIR URUG 0.225 m3
LANTAI KERJA 0.18 m3
PAS. BATA TRASRAAM 1.793 m3
PLAT BETON PENUTUP SEPTICTANK 0.18 m3

IX.A PEKERJAAN FINISHING


9.1 PEKERJAAN PEMASANGAN PLAFON
9.1.1 PLAFON TYPE A (GYSUM BOARD) 248.95 m2
9.1.2 PLAFON TYPE B 4.5 m2
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

9.1.3 PLAFON TYPE C 28.975 m2


9.1.4 LIST LANGIT-LANGIT KAYU PROFIL 192.6 m
9.1.5 RANGKA HOLLOW 248.15 m2

NO URAIAN PEKER JAAN VOLUME SATUAN

9.2 PEKERJAAN PASANGAN KERAMIK LANTAI DAN DINDING


9.2.1 URUGAN PASIR BAWAH ( T = 10 CM ) 25.765 m3
9.2.2 LANTAI KERJA (T = 5 CM) BAWAH LANTAI 12.883 m3
9.2.3 U.PASIR BAWAH LANTAI RABAT BETON KORIDOR (T = 10 CM) 1.858 m3
9.2.4 LANTAI RABAT BETON KORIDOR ( T = 7 CM ) 1.3 m3
9.2.5 PASANGAN KERAMIK LANTAI 30 X 30 CM 261.54 m2
9.2.6 PASANGAN KERAMIK LANTAI 20 X 20 CM (KM/WC) 7.5 m2
9.2.7 PASANGAN KERAMIK TANGGA 30 X 30 CM 14.5 m2
9.2.8 PLINT KERAMIK 10 X 20 CM 149.36 m
9.2.9 KERAMIK DINDING KM/WC 20 X 25 CM 27 m2
9.2.10 DINDING LAPIS KERAMIK 20X20CM (DLM R. LAB DAN PENYIMPANAN DARAH) 25.44 m2

9.3 PEKERJAAN PENGECATAN


9.3.1 CAT TEMBOK EKSTERIOR 419 m2
9.3.2 CAT TEMBOK INTERIOR 628.5 m2
9.3.3 CAT PLAFON 261.2 m2
9.3.4 CAT KUSEN 33.96 m2

PEKERJAAN LANTAI II
III.B PEKERJAAN STRUKTUR
3.2 PEK. KOLOM BETON BERTULANG
3.2.3 TYPE K3
Pembesian 1672.651 kg
Bekisting 123.5 m2
Beton Cor K-250 7.719 m3
3.2.4 TYPE K4
Pembesian 259.738 kg
Bekisting 19 m2
Beton Cor K-250 1.781 m3
3.2.5 TYPE KP
Pembesian 157.445 kg
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

Bekisting 19.95 m2
Beton Cor K-250 0.748 m3

3.4 PEK. BALOK RING


3.4.1 TYPE R1
Pembesian 314.041 kg
Bekisting 39.8 m2
Beton Cor K-250 2.6 m3
3.4.2 TYPE R2
Pembesian 188.361 kg
Bekisting 26.18 m2
Beton Cor K-250 1.617 m3

NO URAIAN PEKER JAAN VOLUME SATUAN

3.4.3 TYPE R3
Pembesian 633.320 kg
Bekisting 70.62 m2
Beton Cor K-250 3.852 m3

3.6 PLAT LANTAI


3.6.1 DAK
Pembesian 2821.872 kg
Bekisting 273.62 m2
Beton Cor K-250 31.344 m3
3.6.3 Topi-topi + 6.30
Pembesian 134.37 kg
Bekisting 26.46 m2
Beton Cor K-225 2.356 m3
V.B PEKERJAAN PASANGAN BATU BATA DAN PLESTERAN
5.1 PEK. PASANGAN BATA
5.1.1 Pas. Bata 1:3 13.35 m2
5.1.2 Pas. Bata 1:5 256.26 m2

5.2 PEK. PLESTERAN


5.2.1 Pas. Bata 1:3 13.35 m2
5.2.2 Pas. Bata 1:5 256.26 m2

VI.B PEKERJAAN KUSEN


6.1 PINTU
6.1.3 TYPE P2 (1 BUAH)
6.1.3.1Kusen Pintu Alumunium 8.6 m
6.1.3.2Daun Pintu 1.88 m2
6.1.3.3 Kaca T = 5 mm 0.58 m2
6.1.3.4 Kaca T = 8 mm 1.27 m2
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

6.1.3.5Handel 4 bh
6.1.3.6Engsel 4 bh

6.1.5 TYPE P4 (7 BUAH)


6.1.5.1Kusen Pintu Alumunium 47.6 m
6.1.5.2Daun Pintu 16.268 m2
6.1.5.3 Kaca Buram 0.806 m2
6.1.5.4Kaca T = 5 mm 0.806 m2
6.1.5.5Multipleks 3.592 m2
6.1.5.6Handel 14 bh
6.1.5.7Engsel 14 bh

NO URAIAN PEKER JAAN VOLUME SATUAN

6.1.6 TYPE P5 (2 BUAH)


6.1.6.1 Kusen Alumunium 9.8 m
6.1.6.2 Daun Pintu 1.070 m2
6.1.6.3 Multipleks 1.731 m2
6.1.6.4 Handle 2 bh
6.1.6.5 Engsel 2 bh

6.2 JENDELA
6.2.2 TYPE J2 (6 BUAH)
6.2.2.1 Kusen Alumunium 73.2 m
6.2.2.2 Daun Jendela 56.52 m2
6.2.2.3 Kaca T = 5 mm 4.32 m2
6.2.2.4 Kaca T = 8 mm 7.334 m2
6.2.2.5 Engsel 36 bh

6.2.4 TYPE J4 (3 BUAH)


6.2.4.1 Kusen Alumunium 24.3 m
6.2.4.2 Kaca T = 5 mm 5.763 m2
6.2.4.3 Daun Jendela 17.64 m2
6.2.4.4 Engsel 12 bh

6.2.6 TYPE J6 (1 BUAH)


6.2.6.1 Kusen Alumunium 5.2 m
6.2.6.2 Kaca T = 5 mm 0.647 m2
6.2.6.3 Daun Jendela 3.14 m2
6.2.6.4 Engsel 2 bh

6.2.7 TYPE J7 (1 BUAH)


6.2.7.1 Kusen Alumunium 28.3 m
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

Kaca T = 8 mm 9.178 m2

6.2.8 BOUVEN BV1 (2 BUAH)


6.2.8.1 Kusen Alumunium 2.8 m
Kaca T = 5 mm 0.32 m2

NO URAIAN PEKER JAAN VOLUME SATUAN

VII.B PEKERJAAN MECHANICAL AND ELECTRICAL


7.1 LAMPU TL 40 WATT 20 bh
7.2 LAMPU SL 18 WATT 11 bh
7.3 STOPKONTAK 200 WATT 5 bh
7.4 SAKLAR TUNGGAL 4 bh
7.5 SAKLAR GANDA 5 bh
7.6 INSTALASI STOPKONTAK DAN TITIK LAMPU 36 titik
7.7 SUB PANEL PENERANGAN 1 titik
7.8 PASANG AC 2 PK + INSTALASI LENGKAP 2 unit
7.9 PENANGKAL PETIR 1 unit
7.10 PASANG AC 2 PK + INSTALASI LENGKAP 1 unit
7.11 PENANGKAL PETIR 2 SPITZ ZARDE 1 unit

VIII.B PEKERJAAN SANITASI


8.1 CLOSET JONGKOK 2 bh
8.2 BAK MANDI 2 bh
8.3 FLOOR DRAIN 2 bh
8.4 KRAN AIR 2 bh
8.5 PIPA PVC DIAMETER 4" 35 m
8.6 PIPA PVC DIAMETER 2.5" 40 m

IX.B PEKERJAAN FINISHING


9.1 PEKERJAAN PEMASANGAN PLAFON
9.1.1 PLAFON TYPE A (GYSUM BOARD) 285.95 m2
9.1.2 PLAFON TYPE B 4.5 m2
9.1.3 PLAFON TYPE C 24.188 m2
9.1.4 RANGKA HOLLOW 257.65 m2
9.1.5 LIST LANGIT-LANGIT KAYU PROFIL 235.4 m
REKAPITULASI VOLUME PEKERJAAN PEMBANGUNAN PMI BOYOLALI

9.2 PEKERJAAN PASANGAN KERAMIK LANTAI DAN DINDING


9.2.1 URUGAN PASIR BAWAH ( T = 10 CM ) 24.815 m3
9.2.2 LANTAI KERJA (T = 5 CM) BAWAH LANTAI 12.408 m3
9.2.5 PASANGAN KERAMIK LANTAI 30 X 30 CM 255.5 m2
9.2.6 PASANGAN KERAMIK LANTAI 20 X 20 CM (KM/WC) 7.5 m2
9.2.8 PLINT KERAMIK 10 X 20 CM 112.07 m
9.2.9 KERAMIK DINDING KM/WC 20 X 25 CM 27 m2

9.3 PEKERJAAN PENGECATAN


9.3.1 CAT TEMBOK EKSTERIOR 320 m2
9.3.2 CAT TEMBOK INTERIOR 480 m2
9.3.3 CAT PLAFON 251.56 m2
9.3.4 CAT KUSEN 9.84 m2
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

I PEKERJAAN PERSIAPAN
1.1 PEMBERSIHAN LAHAN
1 m2 Membersihkan Lapangan dan Perataan
A. Tenaga Rp 9,000.00
Pekerja 0.1 OH Rp 55,000.00 Rp 5,500.00
Mandor 0.05 OH Rp 70,000.00 Rp 3,500.00
B. Bahan
C. Peralatan
D. Jumlah ( A+B+C ) Rp 9,000.00
E. Overhead & Profit ( 10% ) Rp 900.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 9,900.00
1.2 PENGUKURAN DAN BOWPLANNK
1 m' Pengukuran dan Pemasangan Bouwplank
A. Tenaga Rp 14,150.00
Pekerja 0.1 OH Rp 55,000.00 Rp 5,500.00
Tukang Kayu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00

B. Bahan Rp 107,060.00
3
Kayu 5/7 x 4m Kayu Kruing 0.012 m Rp 5,400,000.00 Rp 64,800.00
Paku Biasa 2" - 5" 0.02 kg Rp 13,000.00 Rp 260.00
Kayu Papan 3/20 Kruing 0.007 m3 Rp 6,000,000.00 Rp 42,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 121,210.00
E. Overhead & Profit ( 10% ) Rp 12,121.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

F. Harga Satuan Pekerjaan ( D+E ) Rp 133,331.00

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

II. PEKERJAAN PONDASI


2.1 PONDASI FOOTPLAT
2.1.1 GALIAN TANAH FOOTPLAT
1 m3 Menggali Tanah Biasa Sedalam 3 m
A. Tenaga Rp 62,440.00
Pekerja 1.05 OH Rp 55,000.00 Rp 57,750.00
Mandor 0.067 OH Rp 70,000.00 Rp 4,690.00
B. Bahan
C. Peralatan
D. Jumlah ( A+B+C ) Rp 62,440.00
E. Overhead & Profit ( 10% ) Rp 6,244.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 68,684.00

2.1.2 URUGAN TANAH KEMBALI FOOTPLAT


1 m3 Pengurugan Kembali
A. Tenaga Rp 31,000.00
Pekerja 0.5 OH Rp 55,000.00 Rp 27,500.00
Mandor 0.05 OH Rp 70,000.00 Rp 3,500.00
B. Bahan
C. Peralatan
D. Jumlah ( A+B+C ) Rp 31,000.00
E. Overhead & Profit ( 10% ) Rp 3,100.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 34,100.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

2.1.3 PASIR URUG FOOTPLAT


1 m3 Urugan Pasir
A. Tenaga Rp 17,200.00
Pekerja 0.3 OH Rp 55,000.00 Rp 16,500.00
Mandor 0.01 OH Rp 70,000.00 Rp 700.00
B. Bahan Rp 144,000.00
Pasir Urug 1.2 m3 Rp 120,000.00 Rp 144,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 161,200.00
E. Overhead & Profit ( 10% ) Rp 16,120.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 177,320.00
2.2 PONDASI BATU BELAH
2.2.1 PASANGAN BATU BELAH
1 m3 Pemasangan Pondasi Batu Belah 1SP : 5PP
A. Tenaga Rp 150,000.00
Pekerja 1.5 OH Rp 55,000.00 Rp 82,500.00
Tukang Batu 0.75 OH Rp 75,000.00 Rp 56,250.00
Kepala Tukang 0.075 OH Rp 80,000.00 Rp 6,000.00
Mandor 0.075 OH Rp 70,000.00 Rp 5,250.00
B. Bahan Rp 513,600.00
Batu Belah 15/20 1.2 m3 Rp 190,000.00 Rp 228,000.00
Portland Cement 136 kg Rp 1,300.00 Rp 176,800.00
Pasir Pasang 0.544 m3 Rp 200,000.00 Rp 108,800.00
C. Peralatan
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

D. Jumlah ( A+B+C ) Rp 663,600.00


E. Overhead & Profit ( 10% ) Rp 66,360.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 729,960.00
2.2.2 AANSTAMPING
1 m3 Pemasangan Batu Kosong / Anstamping
A. Tenaga Rp 78,000.00
Pekerja 0.78 OH Rp 55,000.00 Rp 42,900.00
Tukang Batu 0.39 OH Rp 75,000.00 Rp 29,250.00
Kepala Tukang 0.039 OH Rp 80,000.00 Rp 3,120.00
Mandor 0.039 OH Rp 70,000.00 Rp 2,730.00
B. Bahan Rp 279,840.00
Batu Belah 15/20 1.2 m3 Rp 190,000.00 Rp 228,000.00
3
Pasir Urug 0.432 m Rp 120,000.00 Rp 51,840.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 357,840.00
E. Overhead & Profit ( 10% ) Rp 35,784.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 393,624.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

III. PEKERJAAN STRUKTUR DAN ATAP


3.1 1 m3 Membuat Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K100), slum (3-6)cm, w/c = 0.87
A. Tenaga Rp 83,020.00
Pekerja 1.2 OH Rp 55,000.00 Rp 66,000.00
Tukang Batu 0.2 OH Rp 75,000.00 Rp 15,000.00
Kepala Tukang 0.02 OH Rp 80,000.00 Rp 1,600.00
Mandor 0.006 OH Rp 70,000.00 Rp 420.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 672,013.91
Portland Semen 230 kg Rp 1,300.00 Rp 299,000.00
Pasir Beton 893 kg Rp 192.86 Rp 172,223.98
Kerikil (Maksimum 30mm) 1027 kg Rp 192.59 Rp 197,789.93
Air 200 ltr Rp 15.00 Rp 3,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 755,033.91
E. Overhead & Profit ( 10% ) Rp 75,503.39
F. Harga Satuan Pekerjaan ( D+E ) Rp 830,537.30
3.2 1 m3 Membuat Beton Mutu f'c = 19.3 Mpa (K225), slum (12±2)cm, w/c = 0.58
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00


Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00

B. Bahan Rp 821,783.01
Portland Semen 371 kg Rp 1,300.00 Rp 482,300.00
Pasir Beton 698 kg Rp 192.86 Rp 134,616.28
Kerikil (Maksimum 30mm) 1047 kg Rp 192.59 Rp 201,641.73
Air 215 ltr Rp 15.00 Rp 3,225.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 941,208.01
E. Overhead & Profit ( 10% ) Rp 94,120.80
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,035,328.81
3.3 1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00

B. Bahan Rp 835,985.13
Portland Semen 384 kg Rp 1,300.00 Rp 499,200.00
Pasir Beton 692 kg Rp 192.86 Rp 133,459.12
Kerikil (Maksimum 30mm) 1039 kg Rp 192.59 Rp 200,101.01
Air 215 ltr Rp 15.00 Rp 3,225.00

C. Peralatan
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

D. Jumlah ( A+B+C ) Rp 955,410.13


E. Overhead & Profit ( 10% ) Rp 95,541.01
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,050,951.14
3.4 10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00

B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

E. Overhead & Profit ( 10% ) Rp 14,336.50


F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
IV. PEKERJAAN BEKISTING
4.1 1 m2 Memasang Bekisting untuk Pondasi
A. Tenaga Rp 52,000.00
Pekerja 0.52 OH Rp 55,000.00 Rp 28,600.00
Tukang Kayu 0.26 OH Rp 75,000.00 Rp 19,500.00
Kepala Tukang 0.026 OH Rp 80,000.00 Rp 2,080.00
Mandor 0.026 OH Rp 70,000.00 Rp 1,820.00

B. Bahan Rp 84,800.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Kayu Klas III (Terentang) 0.04 m3 Rp 2,000,000.00 Rp 80,000.00


Paku Biasa 2" - 5" 0.3 kg Rp 13,000.00 Rp 3,900.00
Minyak Bekisting 0.1 ltr Rp 9,000.00 Rp 900.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 136,800.00
E. Overhead & Profit ( 10% ) Rp 13,680.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 150,480.00
4.2 1 m2 Memasang Bekisting untuk Sloof
A. Tenaga Rp 52,000.00
Pekerja 0.52 OH Rp 55,000.00 Rp 28,600.00
Tukang Kayu 0.26 OH Rp 75,000.00 Rp 19,500.00
Kepala Tukang 0.026 OH Rp 80,000.00 Rp 2,080.00
Mandor 0.026 OH Rp 70,000.00 Rp 1,820.00

B. Bahan Rp 94,800.00
Kayu Klas III (Terentang) 0.045 m3 Rp 2,000,000.00 Rp 90,000.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Paku Biasa 2" - 5" 0.3 kg Rp 13,000.00 Rp 3,900.00


Minyak Bekisting 0.1 ltr Rp 9,000.00 Rp 900.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 146,800.00
E. Overhead & Profit ( 10% ) Rp 14,680.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 161,480.00
4.3 1 m2 Memasang Bekisting untuk Kolom
A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00


Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00

B. Bahan Rp 242,500.00
3
Kayu Klas III (Terentang) 0.04 m Rp 2,000,000.00 Rp 80,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00
Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00
Balok Kayu Klas II 0.015 m3 Rp 5,400,000.00 Rp 81,000.00
Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 2 btg Rp 18,000.00 Rp 36,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 308,500.00
E. Overhead & Profit ( 10% ) Rp 30,850.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 339,350.00
4.4 1 m2 Memasang Bekisting untuk Balok
A. Tenaga Rp 66,000.00

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00


Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00

B. Bahan Rp 258,700.00
Kayu Klas III (Terentang) 0.04 m3 Rp 2,000,000.00 Rp 80,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00
Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Balok Kayu Klas II 0.018 m3 Rp 5,400,000.00 Rp 97,200.00


Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 2 btg Rp 18,000.00 Rp 36,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 324,700.00
E. Overhead & Profit ( 10% ) Rp 32,470.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 357,170.00
4.5 1 m2 Memasang Bekisting untuk Tangga
A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00

B. Bahan Rp 222,050.00
Kayu Klas III (Terentang) 0.03 m3 Rp 2,000,000.00 Rp 60,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00
Minyak Bekisting 0.15 ltr Rp 9,000.00 Rp 1,350.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Balok Kayu Klas II 0.015 m3 Rp 5,400,000.00 Rp 81,000.00


Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 2 btg Rp 18,000.00 Rp 36,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 288,050.00
E. Overhead & Profit ( 10% ) Rp 28,805.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 316,855.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

4.6 1 m2 Memasang Bekisting untuk Lantai


A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00

B. Bahan Rp 314,500.00
3
Kayu Klas III (Terentang) 0.04 m Rp 2,000,000.00 Rp 80,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00
Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00
Balok Kayu Klas II (Borneo) 0.015 m3 Rp 5,400,000.00 Rp 81,000.00
Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 6 btg Rp 18,000.00 Rp 108,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 380,500.00
E. Overhead & Profit ( 10% ) Rp 38,050.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 418,550.00
4.7 1 m2 Memasang Bekisting untuk Atap
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00

B. Bahan Rp 314,500.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Kayu Klas III (Terentang) 0.04 m3 Rp 2,000,000.00 Rp 80,000.00


Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00
Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00
Balok Kayu Klas II (Borneo) 0.015 m3 Rp 5,400,000.00 Rp 81,000.00
Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 6 btg Rp 18,000.00 Rp 108,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 380,500.00
E. Overhead & Profit ( 10% ) Rp 38,050.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 418,550.00
V. PEKERJAAN PASANGAN BATU BATA DAN PLESTERAN
5.1 1 m2 Pemasangan Dinding Bata Merah Ukuran(5x11x22)cm Tebal 1/2 Bata Camp. 1PS : 3PP
A. Tenaga Rp 25,850.00
Pekerja 0.3 OH Rp 55,000.00 Rp 16,500.00
Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.015 OH Rp 70,000.00 Rp 1,050.00

B. Bahan Rp 61,681.00
Bata Merah 5 x 11 x 22 70 Buah Rp 500.00 Rp 35,000.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Portland Semen 14.37 kg Rp 1,300.00 Rp 18,681.00


Pasir Pasang 0.04 m3 Rp 200,000.00 Rp 8,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 87,531.00
E. Overhead & Profit ( 10% ) Rp 8,753.10
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

F. Harga Satuan Pekerjaan ( D+E ) Rp 96,284.10


5.2 2
1 m Pemasangan Dinding Bata Merah Ukuran(5x11x22)cm Tebal 1/2 Bata Camp. 1PS : 5PP
A. Tenaga Rp 25,850.00
Pekerja 0.3 OH Rp 55,000.00 Rp 16,500.00
Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.015 OH Rp 70,000.00 Rp 1,050.00

B. Bahan Rp 56,584.00
Bata Merah 5 x 11 x 22 70 Buah Rp 500.00 Rp 35,000.00
Portland Semen 9.68 kg Rp 1,300.00 Rp 12,584.00
Pasir Pasang 0.045 m3 Rp 200,000.00 Rp 9,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 82,434.00
E. Overhead & Profit ( 10% ) Rp 8,243.40
F. Harga Satuan Pekerjaan ( D+E ) Rp 90,677.40
5.3 1 m2 Pemasangan Plesteran 1PC : 3PP Tebal 20 mm
A. Tenaga Rp 31,810.00
Pekerja 0.26 OH Rp 55,000.00 Rp 14,300.00
Tukang Batu 0.2 OH Rp 75,000.00 Rp 15,000.00
Kepala Tukang 0.02 OH Rp 80,000.00 Rp 1,600.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Mandor 0.013 OH Rp 70,000.00 Rp 910.00

B. Bahan Rp 19,678.40
Portland Semen 10.368 kg Rp 1,300.00 Rp 13,478.40
Pasir Pasang 0.031 m3 Rp 200,000.00 Rp 6,200.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

C. Peralatan
D. Jumlah ( A+B+C ) Rp 51,488.40
E. Overhead & Profit ( 10% ) Rp 5,148.84
F. Harga Satuan Pekerjaan ( D+E ) Rp 56,637.24
5.4 1 m2 Pemasangan Plesteran 1PC : 5PP Tebal 20 mm
A. Tenaga Rp 40,140.00
Pekerja 0.4 OH Rp 55,000.00 Rp 22,000.00
Tukang Batu 0.2 OH Rp 75,000.00 Rp 15,000.00
Kepala Tukang 0.02 OH Rp 80,000.00 Rp 1,600.00
Mandor 0.022 OH Rp 70,000.00 Rp 1,540.00

B. Bahan Rp 15,985.60
Portland Semen 6.912 kg Rp 1,300.00 Rp 8,985.60
3
Pasir Pasang 0.035 m Rp 200,000.00 Rp 7,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 56,125.60
E. Overhead & Profit ( 10% ) Rp 5,612.56
F. Harga Satuan Pekerjaan ( D+E ) Rp 61,738.16
5.5 1 m2 Pemasangan Acian
A. Tenaga Rp 20,000.00
Pekerja 0.2 OH Rp 55,000.00 Rp 11,000.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00


Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.01 OH Rp 70,000.00 Rp 700.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

B. Bahan Rp 4,225.00
Portland Semen 3.25 kg Rp 1,300.00 Rp 4,225.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 24,225.00
E. Overhead & Profit ( 10% ) Rp 2,422.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 26,647.50
VI. PEKERJAAN KUSEN
6.1 1 m2 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III
A. Tenaga Rp 107,660.00
Pekerja 0.35 OH Rp 55,000.00 Rp 19,250.00
Tukang Kayu 1.05 OH Rp 75,000.00 Rp 78,750.00
Kepala Tukang 0.105 OH Rp 80,000.00 Rp 8,400.00
Mandor 0.018 OH Rp 70,000.00 Rp 1,260.00

B. Bahan Rp 304,650.00
Kayu Klas II (Kamfer) papan 0.04 m3 Rp 7,600,000.00 Rp 304,000.00
Paku Biasa 2" - 5" 0.05 kg Rp 13,000.00 Rp 650.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 412,310.00
E. Overhead & Profit ( 10% ) Rp 41,231.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 453,541.00
6.2 1m' Pemasangan Kusen Pintu Allumunium
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

A. Tenaga Rp 6,081.00
Pekerja 0.043 OH Rp 55,000.00 Rp 2,365.00
Tukang Besi 0.043 OH Rp 75,000.00 Rp 3,225.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Kepala Tukang 0.0043 OH Rp 80,000.00 Rp 344.00


Mandor 0.0021 OH Rp 70,000.00 Rp 147.00

B. Bahan Rp 92,500.00
Profil Allumunium 1.1 m' Rp 80,000.00 Rp 88,000.00
Skrup Fixer 2 bh Rp 750.00 Rp 1,500.00
Seatant 0.06 tube Rp 50,000.00 Rp 3,000.00
3
C. Peralatan
D. Jumlah ( A+B+C ) Rp 98,581.00
E. Overhead & Profit ( 10% ) Rp 9,858.10
F. Harga Satuan Pekerjaan ( D+E ) Rp 108,439.10
6.3 1 m2 Pemasangan Pintu Kaca Rangka Allumunium
A. Tenaga Rp 12,120.00
Pekerja 0.085 OH Rp 55,000.00 Rp 4,675.00
Tukang Besi 0.085 OH Rp 75,000.00 Rp 6,375.00
Kepala Tukang 0.009 OH Rp 80,000.00 Rp 720.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00

B. Bahan Rp 388,000.00
Pintu Allumunium 4.4 m' Rp 80,000.00 Rp 352,000.00
Profil Kaca 4.5 bh Rp 5,000.00 Rp 22,500.00
Seatant 0.27 tube Rp 50,000.00 Rp 13,500.00
3
C. Peralatan
D. Jumlah ( A+B+C ) Rp 400,120.00

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

E. Overhead & Profit ( 10% ) Rp 40,012.00


F. Harga Satuan Pekerjaan ( D+E ) Rp 440,132.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

6.4 1 Buah Pemasangan Engsel Pintu


A. Tenaga Rp 13,800.00
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.0075 OH Rp 70,000.00 Rp 525.00

B. Bahan Rp 6,000.00
Engsel Pintu 1 bh Rp 6,000.00 Rp 6,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 19,800.00
E. Overhead & Profit ( 10% ) Rp 1,980.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 21,780.00
6.5 1 m2 Pemasangan Kaca tebal 5 mm
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50

B. Bahan Rp 77,000.00
2
Kaca Tebal 5 mm 1.1 m Rp 70,000.00 Rp 77,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 90,327.50
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

E. Overhead & Profit ( 10% ) Rp 9,032.75


DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

F. Harga Satuan Pekerjaan ( D+E ) Rp 99,360.25


6.6 1 m2 Pemasangan Kaca tebal 8 mm
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50

B. Bahan Rp 154,000.00
2
Kaca Tebal 8 mm 1.1 m Rp 140,000.00 Rp 154,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 167,327.50
E. Overhead & Profit ( 10% ) Rp 16,732.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 184,060.25
6.7 1 Buah Pemasangan Handle Pintu HINGE ES SL 9″ SN
A. Tenaga Rp 13,800.00
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.0075 OH Rp 70,000.00 Rp 525.00

B. Bahan Rp 50,000.00
Handle Pintu 1 bh Rp 50,000.00 Rp 50,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 63,800.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

E. Overhead & Profit ( 10% ) Rp 6,380.00


F. Harga Satuan Pekerjaan ( D+E ) Rp 70,180.00
6.8 1 m2 Pemasangan Kaca Buram T = 5 mm
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50

B. Bahan Rp 68,750.00
Kaca Buram T = 5 mm 1.1 m2 Rp 62,500.00 Rp 68,750.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 82,077.50
E. Overhead & Profit ( 10% ) Rp 8,207.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 90,285.25
6.9 1 m2 Pembuatan & Pemasangan Pintu Kayu Lapis ( Plywood ) Rangkap Rangka Kayu Klass II ( lbr s/d 90 cm )
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50

B. Bahan Rp 297,390.00
3
Kayu Klas II (Kamfer) papan 0.025 m Rp 7,600,000.00 Rp 190,000.00
Paku Biasa 1/2" - 1" 0.03 kg Rp 13,000.00 Rp 390.00
Lem Kayu 0.5 lbr Rp 18,000.00 Rp 9,000.00
Multipleks ( 9 mm ) 1 lbr Rp 98,000.00 Rp 98,000.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

C. Peralatan
D. Jumlah ( A+B+C ) Rp 310,717.50
E. Overhead & Profit ( 10% ) Rp 31,071.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 341,789.25
VII. PEKERJAAN MECHANICAL AND ELECTRICAL
VIII. PEKERJAAN SANITASI
8.1 1 Unit Memasang Closet Jongkok Porselen
A. Tenaga Rp 298,700.00
Pekerja 1 OH Rp 55,000.00 Rp 55,000.00
Tukang Batu 1.5 OH Rp 75,000.00 Rp 112,500.00
Kepala Tukang 1.5 OH Rp 80,000.00 Rp 120,000.00
Mandor 0.16 OH Rp 70,000.00 Rp 11,200.00

B. Bahan Rp 149,800.00
Kloset Jongkok 1 bh Rp 140,000.00 Rp 140,000.00
Portland Semen 6 kg Rp 1,300.00 Rp 7,800.00
Pasir Pasang 0.01 m3 Rp 200,000.00 Rp 2,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 448,500.00
E. Overhead & Profit ( 10% ) Rp 44,850.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 493,350.00
8.2 1 Unit Memasang Wastafel
A. Tenaga Rp 95,875.00
Pekerja 1.2 OH Rp 55,000.00 Rp 66,000.00
Tukang Batu 0.145 OH Rp 75,000.00 Rp 10,875.00
Kepala Tukang 0.15 OH Rp 80,000.00 Rp 12,000.00
Mandor 0.1 OH Rp 70,000.00 Rp 7,000.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 367,300.00
Wastafel 1 bh Rp 275,000.00 Rp 275,000.00
Perlengkapan 30% Harga Wastafel 0.3 Rp 275,000.00 Rp 82,500.00
Portland Semen 6 kg Rp 1,300.00 Rp 7,800.00
Pasir Pasang 0.01 m3 Rp 200,000.00 Rp 2,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 463,175.00
E. Overhead & Profit ( 10% ) Rp 46,317.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 509,492.50
8.3 1 Unit Memasang Bak Mandi Batu Bata Vol. 0.30 m3
A. Tenaga Rp 581,100.00
Pekerja 6 OH Rp 55,000.00 Rp 330,000.00
Tukang Batu 3 OH Rp 75,000.00 Rp 225,000.00
Kepala Tukang 0.3 OH Rp 80,000.00 Rp 24,000.00
Mandor 0.03 OH Rp 70,000.00 Rp 2,100.00

B. Bahan Rp 529,392.00
Batu Bata 150 bh Rp 500.00 Rp 75,000.00
Portland Semen 120 kg Rp 1,300.00 Rp 156,000.00
Pasir Pasang 0.3 m3 Rp 200,000.00 Rp 60,000.00
Porselen 11 x 11 cm 360 bh Rp 512.20 Rp 184,392.00
Semen Nat 6 kg Rp 9,000.00 Rp 54,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 1,110,492.00
E. Overhead & Profit ( 10% ) Rp 111,049.20
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

F. Harga Satuan Pekerjaan ( D+E ) Rp 1,221,541.20

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH


8.4 1 Buah Pemasangan Floor Drain
A. Tenaga Rp 9,200.00
Pekerja 0.01 OH Rp 55,000.00 Rp 550.00
Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00

B. Bahan Rp 15,000.00
Floor Drain 1 bh Rp 15,000.00 Rp 15,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 24,200.00
E. Overhead & Profit ( 10% ) Rp 2,420.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 26,620.00
8.5 1 Buah Pemasangan Bak Kontrol Pas. Batu Bata 45 x 45 tinggi 50 cm
A. Tenaga Rp 264,250.00
Pekerja 3.2 OH Rp 55,000.00 Rp 176,000.00
Tukang Batu 1.15 OH Rp 75,000.00 Rp 86,250.00
Kepala Tukang 0.011 OH Rp 80,000.00 Rp 880.00
Mandor 0.016 OH Rp 70,000.00 Rp 1,120.00

B. Bahan Rp 203,100.00
Batu Bata 70 bh Rp 500.00 Rp 35,000.00
Portland Semen 77 kg Rp 1,300.00 Rp 100,100.00
Pasir Pasang 0.13 m3 Rp 200,000.00 Rp 26,000.00
3
Pasir Beton 0.09 m Rp 270,000.00 Rp 24,300.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Kerikil 0.02 m3 Rp 125,000.00 Rp 2,500.00


Baja Tulangan 1.6 kg Rp 9,500.00 Rp 15,200.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

C. Peralatan
D. Jumlah ( A+B+C ) Rp 467,350.00
E. Overhead & Profit ( 10% ) Rp 46,735.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 514,085.00
8.6 1 Buah Pemasangan Kran diameter 1/2" atau 3/4"
A. Tenaga Rp 34,100.00
Pekerja 0.01 OH Rp 55,000.00 Rp 550.00
Tukang Batu 0.4 OH Rp 75,000.00 Rp 30,000.00
Kepala Tukang 0.04 OH Rp 80,000.00 Rp 3,200.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00

B. Bahan Rp 15,009.75
Kran Air 1 bh Rp 15,000.00 Rp 15,000.00
Sealtape 0.0025 kg Rp 3,900.00 Rp 9.75

C. Peralatan
D. Jumlah ( A+B+C ) Rp 49,109.75
E. Overhead & Profit ( 10% ) Rp 4,910.98
F. Harga Satuan Pekerjaan ( D+E ) Rp 54,020.73
8.7 1 m' Pemasangan Pipa PVC tipe AW diameter 2.5"
A. Tenaga Rp 15,940.00
Pekerja 0.081 OH Rp 55,000.00 Rp 4,455.00
Tukang Batu 0.135 OH Rp 75,000.00 Rp 10,125.00
Kepala Tukang 0.0135 OH Rp 80,000.00 Rp 1,080.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

B. Bahan Rp 51,666.66
Pipa PVC diameter 2.5" 1.2 m' Rp 33,333.33 Rp 40,000.00
Perlengkapan 35% x pipa 0.35 Ls Rp 33,333.33 Rp 11,666.67
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

C. Peralatan
D. Jumlah ( A+B+C ) Rp 67,606.66
E. Overhead & Profit ( 10% ) Rp 6,760.67
F. Harga Satuan Pekerjaan ( D+E ) Rp 74,367.33
8.8 1 m' Pemasangan Pipa PVC tipe AW diameter 4"
A. Tenaga Rp 7,100.00
Pekerja 0.036 OH Rp 55,000.00 Rp 1,980.00
Tukang Batu 0.06 OH Rp 75,000.00 Rp 4,500.00
Kepala Tukang 0.006 OH Rp 80,000.00 Rp 480.00
Mandor 0.002 OH Rp 70,000.00 Rp 140.00

B. Bahan Rp 77,500.00
Pipa PVC diameter 4" 1.2 m' Rp 50,000.00 Rp 60,000.00
Perlengkapan 35% x pipa 0.35 Ls Rp 50,000.00 Rp 17,500.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 84,600.00
E. Overhead & Profit ( 10% ) Rp 8,460.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 93,060.00
IX. PEKERJAAN FINISHING
9.1 1 m2 Memasang Langit-Langit Gypsum Board, Uk (120x240) tebal 9 mm
A. Tenaga Rp 10,070.00
Pekerja 0.1 OH Rp 55,000.00 Rp 5,500.00
Tukang Kayu 0.05 OH Rp 75,000.00 Rp 3,750.00
Kepala Tukang 0.005 OH Rp 80,000.00 Rp 400.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Mandor 0.006 OH Rp 70,000.00 Rp 420.00

B. Bahan Rp 25,310.00
Gypsum Board 0.364 lbr Rp 65,000.00 Rp 23,660.00

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Paku Sekrup 0.11 kg Rp 15,000.00 Rp 1,650.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 35,380.00
E. Overhead & Profit ( 10% ) Rp 3,538.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 38,918.00
9.2 1 m2 Pemasangan Rangka Besi Hollow 1 x 40.40.2 mm; Modul 60x60 cm dinding plafond
A. Tenaga Rp 49,560.00
Pekerja 0.35 OH Rp 55,000.00 Rp 19,250.00
Tukang Besi 0.35 OH Rp 75,000.00 Rp 26,250.00
Kepala Tukang 0.035 OH Rp 80,000.00 Rp 2,800.00
Mandor 0.018 OH Rp 70,000.00 Rp 1,260.00

B. Bahan Rp 120,000.00
Rangka Metal Hollow 40.40.2 mm 4 m Rp 15,000.00 Rp 60,000.00
Aksessoris (perkuatan, las, dll ) 1 Rp 60,000.00 Rp 60,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 169,560.00
E. Overhead & Profit ( 10% ) Rp 16,956.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 186,516.00
9.3 1 m List Langit-Langit Kayu Profil
A. Tenaga Rp 7,110.00
Pekerja 0.05 OH Rp 55,000.00 Rp 2,750.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Tukang Kayu 0.05 OH Rp 75,000.00 Rp 3,750.00


Kepala Tukang 0.005 OH Rp 80,000.00 Rp 400.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00

B. Bahan Rp 5,170.00

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

List Kayu Profil 1.05 m Rp 4,800.00 Rp 5,040.00


Paku 0.01 kg Rp 13,000.00 Rp 130.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 12,280.00
E. Overhead & Profit ( 10% ) Rp 1,228.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 13,508.00
9.4 1 m2 Pemasangan Lantai Keramik 20 x 20 cm
A. Tenaga Rp 70,000.00
Pekerja 0.7 OH Rp 55,000.00 Rp 38,500.00
Tukang Batu 0.35 OH Rp 75,000.00 Rp 26,250.00
Kepala Tukang 0.035 OH Rp 80,000.00 Rp 2,800.00
Mandor 0.035 OH Rp 70,000.00 Rp 2,450.00

B. Bahan Rp 94,340.00
Ubin Keramik 20 x 20 cm 26.5 bh Rp 2,160.00 Rp 57,240.00
Portland Semen 10.4 kg Rp 1,300.00 Rp 13,520.00
Semen Warna 1.62 kg Rp 9,000.00 Rp 14,580.00
Pasir Pasang 0.045 m3 Rp 200,000.00 Rp 9,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 164,340.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

E. Overhead & Profit ( 10% ) Rp 16,434.00


F. Harga Satuan Pekerjaan ( D+E ) Rp 180,774.00
9.5 1 m2 Pemasangan Lantai Keramik 30 x 30 cm
A. Tenaga Rp 70,000.00
Pekerja 0.7 OH Rp 55,000.00 Rp 38,500.00
Tukang Batu 0.35 OH Rp 75,000.00 Rp 26,250.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Kepala Tukang 0.035 OH Rp 80,000.00 Rp 2,800.00


Mandor 0.035 OH Rp 70,000.00 Rp 2,450.00

B. Bahan Rp 91,612.69
Keramik 30 x 30 cm 11.87 bh Rp 4,727.27 Rp 56,112.69
Portland Semen 10 kg Rp 1,300.00 Rp 13,000.00
Semen Warna 1.5 kg Rp 9,000.00 Rp 13,500.00
Pasir Pasang 0.045 m3 Rp 200,000.00 Rp 9,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 161,612.69
E. Overhead & Profit ( 10% ) Rp 16,161.27
F. Harga Satuan Pekerjaan ( D+E ) Rp 177,773.96
9.6 1 m' Pemasangan Plint Keramik Ukuran 10 x 20 cm
A. Tenaga Rp 12,770.00
Pekerja 0.09 OH Rp 55,000.00 Rp 4,950.00
Tukang Batu 0.09 OH Rp 75,000.00 Rp 6,750.00
Kepala Tukang 0.009 OH Rp 80,000.00 Rp 720.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00

B. Bahan Rp 15,557.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Ubin Keramik 5.3 bh Rp 2,500.00 Rp 13,250.00


Portland Semen 1.14 kg Rp 1,300.00 Rp 1,482.00
Pasir Pasang 0.003 m3 Rp 200,000.00 Rp 600.00
Semen Warna 0.025 kg Rp 9,000.00 Rp 225.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 28,327.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

E. Overhead & Profit ( 10% ) Rp 2,832.70


F. Harga Satuan Pekerjaan ( D+E ) Rp 31,159.70
9.7 1 m2 Pemasangan Dinding Keramik 20 x 20 cm
A. Tenaga Rp 90,000.00
Pekerja 0.9 OH Rp 55,000.00 Rp 49,500.00
Tukang Batu 0.45 OH Rp 75,000.00 Rp 33,750.00
Kepala Tukang 0.045 OH Rp 80,000.00 Rp 3,600.00
Mandor 0.045 OH Rp 70,000.00 Rp 3,150.00

B. Bahan Rp 83,070.00
Keramik 20 x 20 26 bh Rp 1,920.00 Rp 49,920.00
Portland Semen 9.3 kg Rp 1,300.00 Rp 12,090.00
Pasir Pasang 0.018 m3 Rp 200,000.00 Rp 3,600.00
Semen Warna 1.94 kg Rp 9,000.00 Rp 17,460.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 173,070.00
E. Overhead & Profit ( 10% ) Rp 17,307.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 190,377.00
9.8 1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Eksterior )
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00

B. Bahan Rp 89,500.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00


Cat Penutup 2 Kali ( Dulux Weather Shield 2.5 liter ) 1 ltr Rp 86,000.00 Rp 86,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 96,039.00
E. Overhead & Profit ( 10% ) Rp 9,603.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 105,642.90
9.9 1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Interior )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00

B. Bahan Rp 58,300.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00
Cat Penutup 2 Kali ( Dulux 2.5 liter ) 1 ltr Rp 54,800.00 Rp 54,800.00

C. Peralatan
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

D. Jumlah ( A+B+C ) Rp 64,839.00


E. Overhead & Profit ( 10% ) Rp 6,483.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 71,322.90
9.10 1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Plafond )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Mandor 0.003 OH Rp 70,000.00 Rp 210.00

B. Bahan Rp 58,300.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00
Cat Penutup 2 Kali ( Dulux 2.5 liter ) 1 ltr Rp 54,800.00 Rp 54,800.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 64,839.00
E. Overhead & Profit ( 10% ) Rp 6,483.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 71,322.90
9.11 1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Kusen )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00

B. Bahan Rp 43,500.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00


Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00
Cat Penutup 2 Kali ( Dulux 1 liter ) 1 kg Rp 40,000.00 Rp 40,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 50,039.00
E. Overhead & Profit ( 10% ) Rp 5,003.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 55,042.90
DAFTAR HARGA SATUAN BAHAN DAN UPAH
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

NO.
URAIAN HARGA SATUAN ( Rp. )
ANALISA
LANTAI II
III.B PEKERJAAN STRUKTUR
3.2 PEKERJAAN KOLOM
10 Kg Pembesian dg Besi Polos atau Besi Ulir Rp 157,701.50
1 m2 Memasang Bekisting untuk Kolom Rp 339,350.00
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56 Rp 1,050,951.14

3.4 PEKERJAAN BALOK RING


10 Kg Pembesian dg Besi Polos atau Besi Ulir Rp 157,701.50
1 m2 Memasang Bekisting untuk Balok Rp 357,170.00
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56 Rp 1,050,951.14

3.6 PEKERJAAN PLAT LANTAI DAN ATAP


3.6.1 DAK K250
10 Kg Pembesian dg Besi Polos atau Besi Ulir Rp 157,701.50
1 m2 Memasang Bekisting untuk Atap Rp 418,550.00
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56 Rp 1,050,951.14

3.6.2 TOPI - TOPI +6.30


10 Kg Pembesian dg Besi Polos atau Besi Ulir Rp 157,701.50
1 m3 Membuat Beton Mutu f'c = 19.3 Mpa (K225), slum (12±2)cm, w/c = 0.58 Rp 1,035,328.81
DAFTAR HARGA SATUAN BAHAN DAN UPAH
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

V.B PEKERJAAN PASANGAN BATA DAN PLESTERAN


5.1 PASANGAN BATU BATA
1 m2 Pemasangan Dinding Bata Ukuran (5x11x22)cm Tbl 1/2 Bata Camp. 1PS : 3PP Rp 96,284.10
1 m2 Pemasangan Dinding Bata Ukuran (5x11x22)cm Tbl 1/2 Bata Camp. 1PS : 5PP Rp 90,677.40

5.2 PLESTERAN
1 m2 Pemasangan Plesteran 1PC : 3PP Tebal 20 mm Rp 56,637.24
1 m2 Pemasangan Plesteran 1PC : 5PP Tebal 20 mm Rp 61,738.16

VI.B PEKERJAAN KUSEN


1m' Pemasangan Kusen Pintu Allumunium Rp 108,439.10
1 m2 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III Rp 453,541.00
1 m2 Pemasangan Kaca tebal 8 mm Rp 184,060.25
1 m2 Pemasangan Kaca tebal 5 mm Rp 99,360.25
1 Buah Pemasangan Handle Pintu HINGE ES SL 9″ SN Rp 70,180.00
1 m2 Pemasangan Kaca Buram T = 5 mm Rp 90,285.25
1 Buah Pemasangan Engsel Pintu Rp 21,780.00
1 m2 Pembuatan & Pemasangan Pintu Kayu Lapis ( Plywood ) Rangkap Rangka Kayu Klass II ( lbr s/d 90 cm ) Rp 341,789.25
1 m2 Pemasangan Pintu Kaca Rangka Allumunium Rp 440,132.00

VII.B PEKERJAAN MECHANICAL AND ELECTRICAL


VIII.B PEKERJAAN SANITASI
1 Unit Memasang Closet Jongkok Porselen Rp 493,350.00
1 Unit Memasang Wastafel Rp 509,492.50
1 Unit Memasang Bak Mandi Batu Bata Vol. 0.30 m 3 Rp 1,221,541.20
1 Buah Pemasangan Floor Drain Rp 26,620.00
DAFTAR HARGA SATUAN BAHAN DAN UPAH
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

NO.
URAIAN HARGA SATUAN ( Rp. )
ANALISA
1 Buah Pemasangan Kran diameter 1/2" atau 3/4" Rp 54,020.73
1 m' Pemasangan Pipa PVC tipe AW diameter 2.5" Rp 74,367.33
1 m' Pemasangan Pipa PVC tipe AW diameter 4" Rp 93,060.00
1 Buah Pemasangan Bak Kontrol Pas. Batu Bata 45 x 45 tinggi 50 cm Rp 514,085.00

IX.B PEKERJAAN FINISHING


9.1 PEKERJAAN PEMASANGAN PLAFON
1 m2 Memasang Langit-Langit Gypsum Board, Uk (120x240) tebal 9 mm Rp 38,918.00
2
1 m Pemasangan Rangka Besi Hollow 1 x 40.40.2 mm; Modul 60x60 cm dinding plafond Rp 186,516.00
1 m List Langit-Langit Kayu Profil Rp 13,508.00

9.2 PEKERJAAN PASANGAN KERAMIK LANTAI DAN DINDING


1 m2 Pemasangan Lantai Keramik 20 x 20 cm Rp 180,774.00
2
1 m Pemasangan Lantai Keramik 30 x 30 cm Rp 177,773.96
1 m' Pemasangan Plint Keramik Ukuran 10 x 20 cm Rp 31,159.70
2
1 m Pemasangan Dinding Keramik 20 x 20 cm Rp 190,377.00

9.3 PEKERJAAN PENGECATAN


1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Eksterior ) Rp 105,642.90
2
1 m Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Interior ) Rp 71,322.90
2
1 m Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Plafond ) Rp 71,322.90
1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Kusen ) Rp 55,042.90
DAFTAR HARGA BAHAN DAN UPAH
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

NO. URAIAN SATUAN HARGA SATUAN ( Rp. )

A. UPAH
1 Pekerja OH Rp 55,000.00
2 Tukang Kayu, Batu, Besi OH Rp 75,000.00
3 Kepala Tukang Kayu, Batu, Besi OH Rp 80,000.00
4 Mandor OH Rp 70,000.00

B. BAHAN
1 Kayu 5/7 x 4m Kayu Kruing m3 Rp 5,400,000.00
2 Paku Biasa 2" - 5" kg Rp 13,000.00
3 Kayu Papan 3/20 Kruing m3 Rp 6,000,000.00
4 Pasir Urug m3 Rp 120,000.00
3
5 Batu Belah 15/20 m Rp 190,000.00
6 Portland Cement kg Rp 1,300.00
7 Pasir Pasang m3 Rp 200,000.00
8 Pasir Beton kg Rp 192.86
9 Kerikil (Maksimum 30mm) kg Rp 192.59
10 Air ltr Rp 15.00
11 Besi Beton (polos/ulir) kg Rp 12,500.00
12 Kawat Beton ltr Rp 14,500.00
13 Kayu Klas III (Terentang) m3 Rp 2,000,000.00
14 Minyak Bekisting ltr Rp 9,000.00
15 Balok Kayu Klas II m3 Rp 5,400,000.00
16 Plywood tebal 9mm lbr Rp 110,000.00
17 Dolken Kayu Galam diameter 8-10 cm / 4 m btg Rp 18,000.00
18 Bata Merah 5 x 11 x 22 Buah Rp 500.00
19 Kayu Klas II (Kamfer) papan m3 Rp 7,600,000.00
20 Profil Allumunium m' Rp 80,000.00
21 Skrup Fixer bh Rp 750.00
22 Seatant tube Rp 50,000.00
23 Profil Kaca bh Rp 5,000.00
24 Engsel Pintu bh Rp 6,000.00
25 Handle Pintu bh Rp 50,000.00
26 Kaca Tebal 5 mm m2 Rp 70,000.00
27 Kaca Tebal 8 mm m2 Rp 140,000.00
28 Gypsum Board lbr Rp 65,000.00
29 Paku Sekrup kg Rp 15,000.00
30 Rangka Metal Hollow 40.40.2 mm m Rp 15,000.00
31 Aksessoris (perkuatan, las, dll ) Rp 60,000.00

DAFTAR HARGA SATUAN BAHAN DAN UPAH


GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG

NO. URAIAN SATUAN HARGA SATUAN ( Rp. )

32 List Kayu Profil m Rp 4,800.00


33 Semen Warna kg Rp 9,000.00
34 Keramik 30 x 30 cm bh Rp 4,727.27
35 Ubin Keramik bh Rp 2,500.00
36 Keramik 20 x 20 bh Rp 1,920.00
37 Plamir kg Rp 20,000.00
38 Cat Dasar kg Rp 15,000.00
39 Cat Penutup 2 Kali Eksterior ( Dulux 2.5 liter ) ltr Rp 215,000.00
40 Cat Penutup 2 Kali Interior ( Dulux 2.5 liter ) ltr Rp 137,000.00
41 Cat Penutup 2 Kali Plafond ( Dulux 2.5 liter ) ltr Rp 137,000.00
42 Cat Penutup 2 Kali Kusen ( Dulux 1 liter ) ltr Rp 40,000.00
43 Kloset Jongkok bh Rp 140,000.00
44 Wastafel bh Rp 275,000.00
45 Perlengkapan 30% Harga Wastafel Rp 275,000.00
46 Porselen 11 x 11 cm bh Rp 512.20
47 Semen Nat kg Rp 9,000.00
48 Floor Drain bh Rp 15,000.00
49 Kerikil m3 Rp 125,000.00
50 Baja Tulangan kg Rp 9,500.00
51 Kran Air bh Rp 15,000.00
52 Sealtape kg Rp 3,900.00
53 Pipa PVC diameter 2.5" m' Rp 33,333.33
54 Perlengkapan 35% x pipa diameter 2.5" Ls Rp 33,333.33
55 Pipa PVC diameter 4" m' Rp 50,000.00
56 Perlengkapan 35% x pipa diameter 4" Ls Rp 50,000.00
57 Paku Biasa 1/2" - 1" kg Rp 13,000.00
58 Lem Kayu lbr Rp 18,000.00
59 Multipleks ( 9 mm ) lbr Rp 98,000.00
60 Handle Pintu bh Rp 50,000.00
61 Kaca Buram T = 5 mm m2 Rp 62,500.00
62 Kaca Tebal 8 mm m2 Rp 140,000.00
63 Lampu TL 40w bh Rp 150,000.00
64 Lampu SL 18w bh Rp 50,000.00
65 Stopkontak 200w bh Rp 25,000.00
66 Saklar Tunggal bh Rp 25,000.00
67 Saklar Ganda bh Rp 30,000.00
68 Subpanel Penerangan unit Rp 500,000.00
69 Genjet 5 kVa pkt Rp 10,000,000.00
70 Pompa Air Lengkap Instalasi unit Rp 1,500,000.00
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

I PEKERJAAN PERSIAPAN
1.1 PEMBERSIHAN LAHAN 451.5 m2 Rp 9,900.00 Rp 4,469,850.00
1.2 PENGUKURAN DAN BOWPLANG 97.5 m Rp 133,331.00 Rp 12,999,772.50
1.3 ADMINISTRASI 1 ls Rp 8,000,000.00 Rp 8,000,000.00
TOTAL Rp 25,469,622.50
PEKERJAAN PERSIAPAN Rp 25,469,622.50
II PEKERJAAN PONDASI
2.1 PONDASI FOOTPLAT
2.1.1 GALIAN TANAH FOOTPLAT 259 m3 Rp 68,684.00 Rp 17,789,156.00
3
2.1.2 URUGAN TANAH KEMBALI FOOTPLAT 225.8 m Rp 34,100.00 Rp 7,699,780.00
3
2.1.3 PASIR URUG FOOTPLAT 7.39 m Rp 177,320.00 Rp 1,310,394.80
2.1.4 LANTAI KERJA FOOTPLAT K 100 3.68 m3 Rp 830,537.30 Rp 3,056,377.27
2.1.5 BETON COR PONDASI FOOTPLAT K250 26.585 m3 Rp 1,050,951.14 Rp 27,939,536.14
2.1.6 PEMBESIAN PONDASI FOOTPLAT 1843.721 kg Rp 157,701.50 Rp 29,075,756.73
2.1.7 BEKISTING PONDASI FOOTPLAT 22.92 m2 Rp 150,480.00 Rp 3,449,001.60
TOTAL Rp 90,320,002.53
2.2 PONDASI BATU BELAH
2.2.1 PAS. BATU BELAH 87.384 m3 Rp 729,960.00 Rp 63,786,824.64
3
2.2.2 AANSTAMPING 39.72 m Rp 393,624.00 Rp 15,634,745.28
3
2.2.3 PASIR URUG BATU BELAH 19.86 m Rp 177,320.00 Rp 3,521,575.20
2.2.4 URUGAN TANAH 317.264 m3 Rp 34,100.00 Rp 10,818,702.40
TOTAL Rp 93,761,847.52
PEKERJAAN PONDASI Rp 184,081,850.05
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

III.A PEKERJAAN STRUKTUR


PEKERJAAN LANTAI 1
3.1 PEK. SLOOF BETON BERTULANG LT. 1
Pembesian 2402.3674 kg Rp 157,701.50 Rp 37,885,694.25
Bekisting 157.9 m2 Rp 161,480.00 Rp 25,497,692.00
3
Beton Cor K-225 15.693 m Rp 1,035,328.81 Rp 16,247,415.03
TOTAL Rp 79,630,801.28
3.2 PEK. KOLOM BETON BERTULANG LT. 1
Pembesian 5217.761 kg Rp 157,701.50 Rp 82,284,873.63
Bekisting 280.35 m2 Rp 339,350.00 Rp 95,136,772.50
3
Beton Cor K-250 19.339 m Rp 1,050,951.14 Rp 20,324,344.15
TOTAL Rp 197,745,990.29
3.3 PEK. BALOK BETON BERTULANG LT. 1
BALOK INDUK (B1)
Pembesian 2363.235 kg Rp 157,701.50 Rp 37,268,570.44
2
Bekisting 130.645 m Rp 357,170.00 Rp 46,662,474.65
Beton Cor K-250 13.395 m3 Rp 1,050,951.14 Rp 14,077,490.56
Rp 98,008,535.65
BALOK ANAK (B2,B3,B4)
Pembesian 2134.407 kg Rp 157,701.50 Rp 33,659,910.67
2
Bekisting 174.836 m Rp 357,170.00 Rp 62,446,174.12
3
Beton Cor K-250 12.868 m Rp 1,050,951.14 Rp 13,523,639.31
Rp 109,629,724.09
TOTAL Rp 207,638,259.74
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

3.5 PEK. TANGGA


Pembesian 407.504 kg Rp 157,701.50 Rp 6,426,399.21
2
Bekisting 15.262 m Rp 316,855.00 Rp 4,835,841.01
3
Beton Cor K-250 2.865 m Rp 1,050,951.14 Rp 3,010,975.02
TOTAL Rp 14,273,215.24
3.6 PEK. PLAT LANTAI DAN ATAP
PLAT LANTAI II
Pembesian 2821.872 kg Rp 157,701.50 Rp 44,501,344.72
Bekisting 268.993 m2 Rp 418,550.00 Rp 112,587,020.15
3
Beton Cor K-250 31.344 m Rp 1,050,951.14 Rp 32,941,012.63
Rp 190,029,377.50
TOPI - TOPI + 3.17
Pembesian 168.127 kg Rp 157,701.50 Rp 2,651,388.01
2
Bekisting 32.16 m Rp 418,550.00 Rp 13,460,568.00
Beton Cor K-225 2.898 m3 Rp 1,035,328.81 Rp 3,000,382.89
Rp 19,112,338.90
TOTAL Rp 209,141,716.40
PEKERJAAN STRUKTUR LT. 1 Rp 708,429,982.95
V.A PEKERJAAN BATU BATA DAN PLESTERAN
5.1 PEK. PASANGAN BATU BATA
Pas. Bata 1 : 3 13.35 kg Rp 96,284.10 Rp 1,285,392.74
Pas. Bata 1 : 5 375.588 m2 Rp 90,677.40 Rp 34,057,343.31
TOTAL Rp 35,342,736.05
5.2 PEK. PLESTERAN
Pas. Bata 1 : 3 13.35 kg Rp 56,637.24 Rp 756,107.15
2
Pas. Bata 1 : 5 375.588 m Rp 61,738.16 Rp 23,188,112.04
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

TOTAL Rp 23,944,219.19
PEKERJAAN BATU BATA DAN PLESTERAN LANTAI 1 Rp 59,286,955.24

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

VI.A PEKERJAAN KUSEN


PEMASANGAN PINTU
TYPE PJ 1 (1 BUAH)
Kusen Pintu Alumunium 27.75 m Rp 108,439.10 Rp 3,009,185.03
Daun Pintu 0.76 m 2
Rp 453,541.00 Rp 344,691.16
Kaca T = 8 mm 6.01 m 2
Rp 184,060.25 Rp 1,106,202.10
handel 4 bh Rp 70,180.00 Rp 280,720.00
Engsel 12 bh Rp 21,780.00 Rp 261,360.00
Rp 5,002,158.29
TYPE P1 (1 BUAH)
Kusen Pintu Alumunium 8.3 m Rp 108,439.10 Rp 900,044.53
Daun Pintu 1.83 m 2
Rp 453,541.00 Rp 829,980.03
Kaca T = 8 mm 1.01 m2 Rp 184,060.25 Rp 185,900.85
Kaca T = 5 mm 0.52 m 2
Rp 99,360.25 Rp 51,667.33
Handel 4 bh Rp 70,180.00 Rp 280,720.00
Engsel 4 bh Rp 21,780.00 Rp 87,120.00
Rp 2,335,432.74
TYPE P3 (3 BUAH)
Kusen Pintu Alumunium 22.8 m Rp 108,439.10 Rp 2,472,411.48
Daun Pintu 8.84 m 2
Rp 453,541.00 Rp 4,009,302.44
Kaca T = 5 mm 1.44 m 2
Rp 99,360.25 Rp 143,078.76
Kaca Buram 0.35 m2 Rp 90,285.25 Rp 31,599.84
Multipleks 1.623 m 2
Rp 341,789.25 Rp 554,723.95
Handel 12 bh Rp 70,180.00 Rp 842,160.00
Engsel 12 bh Rp 21,780.00 Rp 261,360.00
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

Rp 8,314,636.47

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

TYPE P4 (5 BUAH)
Kusen Pintu Alumunium 34 m Rp 108,439.10 Rp 3,686,929.40
Daun Pintu 11.62 m2 Rp 453,541.00 Rp 5,270,146.42
Kaca T = 5 mm 0.576 m 2
Rp 99,360.25 Rp 57,214.94
Kaca Buram 0.576 m 2
Rp 90,285.25 Rp 51,989.26
Multipleks 2.566 m2 Rp 341,789.25 Rp 876,974.25
Handel 10 bh Rp 70,180.00 Rp 701,800.00
Engsel 10 bh Rp 21,780.00 Rp 217,800.00
Rp 10,862,854.27
TYPE P5 (2 BUAH)
Kusen Alumunium 9.8 m Rp 108,439.10 Rp 1,062,703.18
Daun Pintu 1.070 m2 Rp 453,541.00 Rp 485,062.10
Multipleks 1.731 m 2
Rp 341,789.25 Rp 591,466.30
Handle 2 bh Rp 70,180.00 Rp 140,360.00
Engsel 2 bh Rp 21,780.00 Rp 43,560.00
Rp 2,323,151.58
TYPE P6 (1 BUAH)
Kusen Alumunium 12.15 m Rp 108,439.10 Rp 1,317,535.07
Daun Pintu 10.753 m2 Rp 453,541.00 Rp 4,876,926.37
Multipleks 6.627 m 2
Rp 341,789.25 Rp 2,265,037.36
Handle 0 bh Rp 70,180.00 Rp -
Engsel 16 bh Rp 21,780.00 Rp 348,480.00
Rp 8,807,978.80
TOTAL Rp 37,646,212.15
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

PEMASANGAN JENDELA
TYPE J1 (1 BUAH)
Kusen Alumunium 8.7 m Rp 108,439.10 Rp 943,420.17
Kaca T = 5 mm 0.48 m2 Rp 99,360.25 Rp 47,692.92
Kaca T = 8 mm 1.38 m 2
Rp 184,060.25 Rp 254,003.15
Rp 1,245,116.24
TYPE J2 (2 BUAH)
Kusen Alumunium 24.4 m Rp 108,439.10 Rp 2,645,914.04
Daun Jendela 18.84 m2 Rp 453,541.00 Rp 8,544,712.44
Kaca T = 5 mm 1.44 m2 Rp 99,360.25 Rp 143,078.76
Kaca T = 8 mm 2.445 m 2
Rp 184,060.25 Rp 449,935.28
Engsel 12 bh Rp 21,780.00 Rp 261,360.00
Rp 12,045,000.52
TYPE J3 (1 BUAH)
Kusen Alumunium 12.2 m Rp 108,439.10 Rp 1,322,957.02
Kaca T = 5 mm 0.72 m 2
Rp 99,360.25 Rp 71,539.38
Kaca T = 8 mm 2.07 m2 Rp 184,060.25 Rp 381,004.72
Rp 1,775,501.12
TYPE J4 (3 BUAH)
Kusen Alumunium 24.3 m Rp 108,439.10 Rp 2,635,070.13
Daun Jendela 17.64 m 2
Rp 453,541.00 Rp 8,000,463.24
Kaca T = 5 mm 5.763 m2 Rp 99,360.25 Rp 572,613.12
Engsel 12 bh Rp 21,780.00 Rp 261,360.00
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

Rp 11,469,506.49
TYPE J5 (1 BUAH)
Kusen Alumunium 8.1 m Rp 108,439.10 Rp 878,356.71
Kaca T = 5 mm 0.4 m 2
Rp 99,360.25 Rp 39,744.10
Kaca T = 8 mm 1.15 m2 Rp 184,060.25 Rp 211,669.29
Rp 1,129,770.10
NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

TYPE J6 (1 BUAH)
Kusen Alumunium 5.2 m Rp 108,439.10 Rp 563,883.32
Daun Jendela 0.647 m2 Rp 453,541.00 Rp 293,441.03
Kaca T = 5 mm 3.14 m 2
Rp 99,360.25 Rp 311,991.19
Engsel 2 bh Rp 21,780.00 Rp 43,560.00
Rp 1,212,875.53
BOUVEN BV1 (2 BUAH)
Kusen Alumunium 2.8 m Rp 108,439.10 Rp 303,629.48
Kaca T = 5 mm 0.32 m 2
Rp 99,360.25 Rp 31,795.28
Rp 335,424.76
TOTAL Rp 29,213,194.75
PEMASANGAN PARTISI
TYPE PTS1 (1 BUAH)
Kusen Alumunium 5.22 m Rp 108,439.10 Rp 566,052.10
Daun Pintu 5.8 m Rp 453,541.00 Rp 2,630,537.80
Multipleks 0.67 m2 Rp 341,789.25 Rp 228,998.80
Gypsum 2.268 m 2
Rp 38,918.00 Rp 88,266.02
Handle 2 bh Rp 70,180.00 Rp 140,360.00
Engsel 2 bh Rp 21,780.00 Rp 43,560.00
Rp 3,697,774.72
TYPE PTS2 (1 BUAH)
Kusen Alumunium 4.9 m Rp 108,439.10 Rp 531,351.59
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

Kaca T = 5 mm 0.564 m2 Rp 99,360.25 Rp 56,039.18


Gypsum 1.688 m 2
Rp 38,918.00 Rp 65,693.58
Rp 653,084.36
TOTAL Rp 4,350,859.08
TOTAL PEKERJAAN KUSEN LANTAI I Rp 71,210,493.84

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

VII.A PEKERJAAN MECHANICAL DAN ELECTRICAL


7.1 LAMPU TL 40 WATT 20 bh Rp 150,000.00 Rp 3,000,000.00
7.2 LAMPU SL 18 WATT 8 bh Rp 50,000.00 Rp 400,000.00
7.3 STOPKONTAK 200 WATT 13 bh Rp 25,000.00 Rp 325,000.00
7.4 SAKLAR TUNGGAL 12 bh Rp 25,000.00 Rp 300,000.00
7.5 SAKLAR GANDA 2 bh Rp 30,000.00 Rp 60,000.00
7.6 INSTALASI STOPKONTAK DAN TITIK LAMPU 41 titik Rp 80,000.00 Rp 3,280,000.00
7.7 SUB PANEL PENERANGAN 1 titik Rp 500,000.00 Rp 500,000.00
7.8 PENYAMBUNGAN LISTRIK / TAMBAH DAYA 10 kV 1 unit Rp 12,500,000.00 Rp12,500,000.00
7.9 GENSET 5 Kva 1 unit Rp 10,000,000.00 Rp10,000,000.00
7.10 PASANG AC 2 PK + INSTALASI LENGKAP 1 unit Rp 12,500,000.00 Rp12,500,000.00
TOTAL Rp 42,865,000.00
TOTAL PEKERJAAN MECHANICAL AND ELECTRICAL LANTAI I Rp 42,865,000.00
VIII.A PEKERJAAN SANITASI
8.1 CLOSET JONGKOK 2 bh Rp 493,350.00 Rp 986,700.00
8.2 WASHTAFEL 5 bh Rp 509,492.50 Rp 2,547,462.50
8.3 BAK MANDI 2 bh Rp 1,221,541.20 Rp 2,443,082.40
8.4 FLOOR DRAIN 14 bh Rp 26,620.00 Rp 372,680.00
8.5 KRAN AIR 7 bh Rp 54,020.73 Rp 378,145.08
8.6 PIPA PVC DIAMETER 2.5" 60 m Rp 74,367.33 Rp 4,462,039.66
8.7 PIPA PVC DIAMETER 4" 35 m Rp 93,060.00 Rp 3,257,100.00
8.8 BAK KONTROL 3 bh Rp 514,085.00 Rp 1,542,255.00
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

8.9 GROUND RESERVOAR 1 unit Rp 6,500,000.00 Rp 6,500,000.00


8.10 POMPA AIR LENGKAP INSTALASI 1 unit Rp 1,500,000.00 Rp 1,500,000.00
8.11 SEPTICTANK
GALIAN TANAH 4.59 m3 Rp 68,684.00 Rp 315,259.56
AANSTAMPING 1.052 m3 Rp 393,624.00 Rp 414,092.45
LANTAI KERJA 0.18 m3 Rp 830,537.30 Rp 149,496.71
3
PAS. BATA TRASRAAM 1.793 m Rp 96,284.10 Rp 172,637.39
PLAT BETON PENUTUP SEPTICTANK 0.18 m3 Rp 1,035,328.81 Rp 186,359.19
NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

PASIR URUG 0.225 m3 Rp 177,320.00 Rp 39,897.00


TOTAL PEKERJAAN SANITASI LANTAI I Rp 25,267,206.93
IX.A PEKERJAAN FINISHING
9.1 PEKERJAAN PEMASANGAN PLAFON
PLAFON TYPE A, B, DAN C (GYSUM BOARD) 282.425 m2 Rp 38,918.00 Rp 10,991,416.15
2
RANGKA HOLLOW 248.15 m Rp 186,516.00 Rp 46,283,945.40
LIST LANGIT-LANGIT KAYU PROFIL 192.6 m Rp 13,508.00 Rp 2,601,640.80
TOTAL Rp 59,877,002.35
9.2 PEKERJAAN PASANGAN KERAMIK LANTAI DAN DINDING
URUGAN PASIR BAWAH ( T = 10 CM ) 25.765 m3 Rp 177,320.00 Rp 4,568,649.80
LANTAI KERJA (T = 5 CM) BAWAH LANTAI 12.883 m3 Rp 830,537.30 Rp 10,699,812.05
URUGAN PASIR BAWAH LANTAI RABAT BETON KORIDOR 1.858 m3 Rp 177,320.00 Rp 329,460.56
LANTAI RABAT BETON KORIDOR ( T = 7 CM ) 1.3 m3 Rp 830,537.30 Rp 1,079,698.49
PASANGAN KERAMIK LANTAI & TANGGA UK. 30 X 30 CM 276.04 m2 Rp 177,773.96 Rp 49,072,725.13
PASANGAN KERAMIK LANTAI 20 X 20 CM (KM/WC) 7.5 m2 Rp 180,774.00 Rp 1,355,805.00
PLINT KERAMIK 10 X 20 CM 149.36 m Rp 31,159.70 Rp 4,654,012.79
KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM 25.44 m2 Rp 190,377.00 Rp 4,843,190.88
TOTAL Rp 76,603,354.70
9.3 PEKERJAAN PENGECATAN
CAT TEMBOK EKSTERIOR 419 m2 Rp 105,642.90 Rp 44,264,375.10
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

CAT TEMBOK INTERIOR 628.5 m2 Rp 71,322.90 Rp 44,826,442.65


2
CAT PLAFON 261.2 m Rp 71,322.90 Rp 18,629,541.48
2
CAT KUSEN 33.96 m Rp 55,042.90 Rp 1,869,256.88
TOTAL Rp 109,589,616.11
TOTAL PEKERJAAN FINISHING LANTAI I Rp 246,069,973.17

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

III.B PEKERJAAN STRUKTUR


PEKERJAAN LANTAI 2
3.2 PEK. KOLOM BETON BERTULANG
Pembesian 2089.834 kg Rp 157,701.50 Rp 32,956,995.66
Bekisting 162.45 m2 Rp 339,350.00 Rp 55,127,407.50
3
Beton Cor K-250 10.248 m Rp 1,050,951.14 Rp 10,770,147.31
TOTAL Rp 98,854,550.47
3.4 PEK. BALOK RING
Pembesian 1135.722 kg Rp 157,701.50 Rp 17,910,506.30
Bekisting 136.6 m2 Rp 357,170.00 Rp 48,789,422.00
3
Beton Cor K-250 8.069 m Rp 1,050,951.14 Rp 8,480,124.77
TOTAL Rp 75,180,053.07
3.6 PEK. PLAT LANTAI
DAK
Pembesian 2821.872 kg Rp 157,701.50 Rp 44,501,344.72
2
Bekisting 273.62 m Rp 418,550.00 Rp 114,523,651.00
Beton Cor K-250 31.344 m3 Rp 1,050,951.14 Rp 32,941,012.63
Rp 191,966,008.35
TOPI - TOPI + 6.30
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

Pembesian 134.37 kg Rp 157,701.50 Rp 2,119,035.06


Bekisting 26.46 m2 Rp 418,550.00 Rp 11,074,833.00
Beton Cor K-225 2.356 m3 Rp 1,035,328.81 Rp 2,439,234.68
Rp 15,633,102.73
TOTAL Rp 207,599,111.08
TOTAL PEKERJAAN STRUKTUR LANTAI 2 Rp 381,633,714.62

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

V.B PEKERJAAN PAS. BATU BATA DAN PLESTERAN


5.1 PEK. PASANGAN BATU BATA
Pas. Bata 1 : 3 13.35 kg Rp 96,284.10 Rp 1,285,392.74
Pas. Bata 1 : 5 256.26 m2 Rp 90,677.40 Rp 23,236,990.52
TOTAL Rp 24,522,383.26
5.2 PEK. PLESTERAN
Pas. Bata 1 : 3 13.35 kg Rp 56,637.24 Rp 756,107.15
2
Pas. Bata 1 : 5 256.26 m Rp 61,738.16 Rp 15,821,020.88
TOTAL Rp 16,577,128.04
PEKERJAAN PASANGAN BATU BATA DAN PLESTERAN LANTAI 2 Rp 41,099,511.29
VI.B PEKERJAAN KUSEN
PEMASANGAN PINTU
TYPE P2 (1 BUAH)
Kusen Pintu Alumunium 8.6 m Rp 108,439.10 Rp 932,576.26
Daun Pintu 1.88 m Rp2
453,541.00 Rp 852,657.08
Kaca T = 5 mm 0.58 m2 Rp 99,360.25 Rp 57,628.95
Kaca T = 8 mm 1.27 m2 Rp 184,060.25 Rp 233,756.52
handel 4 bh Rp 70,180.00 Rp 280,720.00
Engsel 4 bh Rp 21,780.00 Rp 87,120.00
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

Rp 2,444,458.80
TYPE P4 (7 BUAH)
Kusen Pintu Alumunium 47.6 m Rp 108,439.10 Rp 5,161,701.16
Daun Pintu 16.268 m Rp2
453,541.00 Rp 7,378,204.99
Kaca T = 5 mm 0.806 m2 Rp 99,360.25 Rp 80,100.92
Kaca Buram 0.806 m2 Rp 90,285.25 Rp 72,784.96
Multipleks 3.592 m2 Rp 341,789.25 Rp 1,227,763.95
handel 14 bh Rp 70,180.00 Rp 982,520.00
Engsel 14 bh Rp 21,780.00 Rp 304,920.00
Rp 15,207,995.98

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

TYPE P5 (2 BUAH)
Kusen Pintu Alumunium 9.8 m Rp 108,439.10 Rp 1,062,703.18
Daun Pintu 1.070 m2 Rp 453,541.00 Rp 485,062.10
Multipleks 1.731 m2 Rp 341,789.25 Rp 591,466.30
handel 2 bh Rp 70,180.00 Rp 140,360.00
Engsel 2 bh Rp 21,780.00 Rp 43,560.00
Rp 2,323,151.58
TOTAL Rp 19,975,606.36
PEMASANGAN JENDELA
TYPE J2 (6 BUAH)
Kusen Alumunium 73.2 m Rp 108,439.10 Rp 7,937,742.12
Daun Jendela 56.52 m2 Rp 453,541.00 Rp 25,634,137.32
Kaca T = 5 mm 4.32 m 2
Rp 99,360.25 Rp 429,236.28
Kaca T = 8 mm 7.334 m 2
Rp 184,060.25 Rp 1,349,805.84
Engsel 36 bh Rp 21,780.00 Rp 784,080.00
Rp 36,135,001.56
TYPE J4 (3 BUAH)
Kusen Alumunium 24.3 m Rp 108,439.10 Rp 2,635,070.13
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

Daun Jendela 17.64 m2 Rp 453,541.00 Rp 8,000,463.24


Kaca T = 5 mm 5.763 m 2
Rp 99,360.25 Rp 572,613.12
Engsel 12 bh Rp 21,780.00 Rp 261,360.00
Rp 11,469,506.49
TYPE J6 (1 BUAH)
Kusen Alumunium 5.2 m Rp 108,439.10 Rp 563,883.32
Daun Jendela 0.647 m 2
Rp 453,541.00 Rp 293,441.03
Kaca T = 5 mm 3.14 m2 Rp 99,360.25 Rp 311,991.19
Engsel 2 bh Rp 21,780.00 Rp 43,560.00
Rp 1,212,875.53

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

TYPE J7 (1 BUAH)
Kusen Alumunium 28.3 m Rp 108,439.10 Rp 3,068,826.53
Kaca T = 8 mm 9.178 m2 Rp 184,060.25 Rp 1,689,304.97
Rp 4,758,131.50
BOUVEN (2 BUAH)
Kusen Alumunium 2.8 m Rp 108,439.10 Rp 303,629.48
Kaca T = 5 mm 0.32 m 2
Rp 99,360.25 Rp 31,795.28
Rp 335,424.76
TOTAL Rp 53,910,939.85
TOTAL PEKERJAAN KUSEN LANTAI 2 Rp 73,886,546.21
VII.B PEKERJAAN MECHANICAL DAN ELECTRICAL
7.1 LAMPU TL 40 WATT 20 bh Rp 150,000.00 Rp 3,000,000.00
7.2 LAMPU SL 18 WATT 11 bh Rp 50,000.00 Rp 550,000.00
7.3 STOPKONTAK 200 WATT 5 bh Rp 25,000.00 Rp 125,000.00
7.4 SAKLAR TUNGGAL 4 bh Rp 25,000.00 Rp 100,000.00
7.5 SAKLAR GANDA 5 bh Rp 30,000.00 Rp 150,000.00
7.6 INSTALASI STOPKONTAK DAN TITIK LAMPU 36 titik Rp 80,000.00 Rp 2,880,000.00
7.7 SUB PANEL PENERANGAN 1 titik Rp 500,000.00 Rp 500,000.00
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

7.8 PASANG AC 2 PK + INSTALASI LENGKAP 1 unit Rp 12,500,000.00 Rp 12,500,000.00


7.9 PENANGKAL PETIR 1 unit Rp 2,500,000.00 Rp 2,500,000.00
TOTAL Rp 22,305,000.00
TOTAL PEKERJAAN MECHANICAL AND ELECTRICAL LANTAI 2 Rp 22,305,000.00
VIII.B PEKERJAAN SANITASI
8.1 CLOSET JONGKOK 2 bh Rp 493,350.00 Rp 986,700.00
8.2 BAK MANDI 2 bh Rp 1,221,541.20 Rp 2,443,082.40
8.3 FLOOR DRAIN 2 bh Rp 26,620.00 Rp 53,240.00
8.4 KRAN AIR 2 bh Rp 54,020.73 Rp 108,041.45
8.5 PIPA PVC DIAMETER 2.5" 35 m Rp 74,367.33 Rp 2,602,856.47
8.6 PIPA PVC DIAMETER 4" 40 m Rp 93,060.00 Rp 3,722,400.00
TOTAL PEKERJAAN SANITASI LANTAI 2 Rp 9,916,320.32
NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. JUMLAH Rp.

IX.B PEKERJAAN FINISHING


9.1 PEKERJAAN PEMASANGAN PLAFON
PLAFON TYPE A, B, DAN C (GYSUM BOARD) 314.638 m2 Rp 38,918.00 Rp 12,245,081.68
RANGKA HOLLOW 257.65 m2 Rp 186,516.00 Rp 48,055,847.40
LIST LANGIT-LANGIT KAYU PROFIL 235.4 m Rp 13,508.00 Rp 3,179,783.20
TOTAL Rp 63,480,712.28
9.2 PEKERJAAN PASANGAN KERAMIK LANTAI DAN DINDING
URUGAN PASIR BAWAH ( T = 10 CM ) 24.815 m3 Rp 177,320.00 Rp 4,400,195.80
LANTAI KERJA (T = 5 CM) BAWAH LANTAI 12.408 m3 Rp 830,537.30 Rp 10,305,306.83
PASANGAN KERAMIK LANTAI UK. 30 X 30 CM 255.5 m2 Rp 177,773.96 Rp 45,421,247.90
PASANGAN KERAMIK LANTAI 20 X 20 CM (KM/WC) 7.5 m2 Rp 180,774.00 Rp 1,355,805.00
PLINT KERAMIK 10 X 20 CM 112.07 m Rp 31,159.70 Rp 3,492,067.58
KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM 27 m2 Rp 190,377.00 Rp 5,140,179.00
TOTAL Rp 70,114,802.11
9.3 PEKERJAAN PENGECATAN
CAT TEMBOK EKSTERIOR 320 m2 Rp 105,642.90 Rp 33,805,728.00
CAT TEMBOK INTERIOR 480 m2 Rp 71,322.90 Rp 34,234,992.00
ANALISA RENCANA ANGGARAN BIAYA ( RAB )
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

CAT PLAFON 251.56 m2 Rp 71,322.90 Rp 17,941,988.72


2
CAT KUSEN 9.84 m Rp 55,042.90 Rp 541,622.14
TOTAL Rp 86,524,330.86
TOTAL PEKERJAAN FINISHING LANTAI 2 Rp 220,119,845.26
DAFTAR REKAPITULASI RENCANA ANGGARAN BIAYA ( RAB )
PEMBANGUNAN GEDUNG PMI BOYOLALI

NO URAIAN PEKERJAAN BIAYA

I PEKERJAAN PERSIAPAN : Rp 25,469,622.50


II PEKERJAAN PONDASI Rp 184,081,850.05
III PEKERJAAN STRUKTUR Rp 1,090,063,697.57
IV PEKERJAAN PAS. BT. BATA DA PLESTERAN Rp 100,386,466.53
V PEKERJAAN KUSEN Rp 145,097,040.05
VI PEKERJAAN MECHANICAL AND ELECTRICAL Rp 65,170,000.00
VII PEKERJAAN SANITASI Rp 35,183,527.25
VIII PEKERJAAN FINISHING Rp 466,189,818.42

JUMLAH Rp 2,111,642,022.38
PPN 10% Rp 211,164,202.24
JUMLAH ( SETELAH PPN) Rp 2,322,806,224.62
DIBULATKAN Rp 2,322,806,000.00

Terbilang : Dua Milyar Tiga Ratus Dua Puluh Dua Juta Delapan Ratus Enam Ribu Rupiah
REKAPITULASI PERHITUNGAN PERSENTASE BOBOT
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. BOBOT

I PEKERJAAN PERSIAPAN

1.1 PEMBERSIHAN LAHAN 451.5 m2 Rp 9,900.00 Rp 4,469,850.00 0.212%


1.2 PENGUKURAN DAN BOWPLANG 97.5 m Rp 133,331.00 Rp 12,999,772.50 0.616%
1.3 ADMINISTRASI 1 ls Rp 8,000,000.00 Rp 8,000,000.00 0.379%

II PEKERJAAN PONDASI
2.1 PONDASI FOOTPLAT
2.1.1 GALIAN TANAH FOOTPLAT 259 m3 Rp 68,684.00 Rp 17,789,156.00 0.842%
3
2.1.2 URUGAN TANAH KEMBALI FOOTPLAT 225.8 m Rp 34,100.00 Rp 7,699,780.00 0.365%
2.1.3 PASIR URUG FOOTPLAT 7.39 m3 Rp 177,320.00 Rp 1,310,394.80 0.062%
3
2.1.4 LANTAI KERJA FOOTPLAT K 100 3.68 m Rp 830,537.30 Rp 3,056,377.27 0.145%
3
2.1.5 BETON COR PONDASI FOOTPLAT K250 26.585 m Rp 1,050,951.14 Rp 27,939,536.14 1.323%
2.1.6 PEMBESIAN PONDASI FOOTPLAT 1843.721 kg Rp 157,701.50 Rp 29,075,756.73 1.377%
2.1.7 BEKISTING PONDASI FOOTPLAT 22.92 m2 Rp 150,480.00 Rp 3,449,001.60 0.163%

2.2 PONDASI BATU KALI


2.2 1 PAS. BATU BELAH 87.384 m3 Rp 729,960.00 Rp 63,786,824.64 3.021%
2.2 2 AANSTAMPING 39.72 m3 Rp 393,624.00 Rp 15,634,745.28 0.740%
3
2.2 3 PASIR URUG 19.86 m Rp 177,320.00 Rp 3,521,575.20 0.167%
3
2.2 4 URUGAN TANAH KEMBALI 317.264 m Rp 34,100.00 Rp 10,818,702.40 0.512%

III.A PEKERJAAN STRUKTUR


PEKERJAAN LANTAI 1
3.1 PEK. SLOOF BETON BERTULANG
Pembesian 2402.3674 kg Rp 157,701.50 Rp 37,885,694.25 1.794%
2
Bekisting 157.9 m Rp 161,480.00 Rp 25,497,692.00 1.207%
Beton Cor K-225 15.693 m3 Rp 1,035,328.81 Rp 16,247,415.03 0.769%

3.2 PEK. KOLOM BETON BERTULANG


Pembesian 5217.761 kg Rp 157,701.50 Rp 82,284,873.63 3.897%
Bekisting 280.35 m2 Rp 339,350.00 Rp 95,136,772.50 4.505%
3
Beton Cor K-250 19.339 m Rp 1,050,951.14 Rp 20,324,344.15 0.962%

3.3 PEK. BALOK BETON BERTULANG


BALOK INDUK (B1)
Pembesian 2363.235 kg Rp 157,701.50 Rp 37,268,570.44 1.765%
2
Bekisting 130.645 m Rp 357,170.00 Rp 46,662,474.65 2.210%
3
Beton Cor K-250 13.395 m Rp 1,050,951.14 Rp 14,077,490.56 0.667%
REKAPITULASI PERHITUNGAN PERSENTASE BOBOT
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. BOBOT

BALOK ANAK (B2, B3, dan B4)


Pembesian 2134.407 kg Rp 157,701.50 Rp 33,659,910.67 1.594%
2
Bekisting 174.836 m Rp 357,170.00 Rp 62,446,174.12 2.957%
3
Beton Cor K-250 12.868 m Rp 1,050,951.14 Rp 13,523,639.31 0.640%

3.5 PEK. TANGGA


Pembesian 407.504 kg Rp 157,701.50 Rp 6,426,399.21 0.304%
2
Bekisting 15.262 m Rp 316,855.00 Rp 4,835,841.01 0.229%
3
Beton Cor K-250 2.865 m Rp 1,050,951.14 Rp 3,010,975.02 0.143%

3.6 PEK. PLAT LANTAI DAN ATAP


PLAT LANTAI II
Pembesian 2821.872 kg Rp 157,701.50 Rp 44,501,344.72 2.107%
Bekisting 268.993 m2 Rp 418,550.00 Rp 112,587,020.15 5.332%
3
Beton Cor K-250 31.344 m Rp 1,050,951.14 Rp 32,941,012.63 1.560%

TOPI - TOPI + 3.17


Pembesian 168.127 kg Rp 157,701.50 Rp 2,651,388.01 0.126%
2
Bekisting 32.16 m Rp 418,550.00 Rp 13,460,568.00 0.637%
3
Beton Cor K-225 2.898 m Rp 1,035,328.81 Rp 3,000,382.89 0.142%

V.A PEKERJAAN PASANGAN BATU BATA DAN PLESTERAN


5.1 PEK. PASANGAN BATA
Pas. Bata 1:3 13.35 m2 Rp 96,284.10 Rp 1,285,392.74 0.061%
2
Pas. Bata 1:5 375.588 m Rp 90,677.40 Rp 34,057,343.31 1.613%

5.2 PEK. PLESTERAN


Pas. Bata 1:3 13.35 m2 Rp 56,637.24 Rp 756,107.15 0.036%
2
Pas. Bata 1:5 375.588 m Rp 61,738.16 Rp 23,188,112.04 1.098%

VI.A KUSEN
PEK. PEMASANGAN PINTU DAN JENDELA
KUSEN ALMUNIUM 210.620 m2 Rp 108,439.10 Rp 22,839,443.24 1.082%
2
DAUN KUSEN 77.800 m Rp 453,541.00 Rp 35,285,263.03 1.671%
KACA BURAM T = 5 MM 0.926 m2 Rp 90,285.25 Rp 83,589.09 0.004%
KACA T = 5 MM 15.363 m 2
Rp 99,360.25 Rp 1,526,454.96 0.072%
KACA T = 8 MM 14.065 m 2
Rp 184,060.25 Rp 2,588,715.39 0.123%
GYSUM 3.956 m2 Rp 38,918.00 Rp 153,959.61 0.007%
MULTIPLEKS 13.217 m2 Rp 341,789.25 Rp 4,517,428.52 0.214%
HANDEL 34 bh Rp 70,180.00 Rp 2,386,120.00 0.113%
REKAPITULASI PERHITUNGAN PERSENTASE BOBOT
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

ENGSEL 84 bh Rp 21,780.00 Rp 1,829,520.00 0.087%

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. BOBOT

VII.A PEKERJAAN MECHANICAL DAN ELEKTRICAL


LAMPU TL 40 WATT 20 bh Rp 150,000.00 Rp 3,000,000.00 0.142%
LAMPU SL 18 WATT 8 bh Rp 50,000.00 Rp 400,000.00 0.019%
STOPKONTAK 200 WATT 13 bh Rp 25,000.00 Rp 325,000.00 0.015%
SAKLAR TUNGGAL 12 bh Rp 25,000.00 Rp 300,000.00 0.014%
SAKLAR GANDA 2 bh Rp 30,000.00 Rp 60,000.00 0.003%
INSTALASI STOPKONTAK DAN TITIK LAMPU 41 titik Rp 80,000.00 Rp 3,280,000.00 0.155%
SUB PANEL PENERANGAN 1 titik Rp 500,000.00 Rp 500,000.00 0.024%
PENYAMBUNGAN LISTRI /TAMBAH DAYA 10 KVA 1 unit Rp 12,500,000.00 Rp 12,500,000.00 0.592%
GENSET 5 KVA 1 unit Rp 10,000,000.00 Rp 10,000,000.00 0.474%
PASANG AC 2 K + INSTALASI LENGKAP 1 unit Rp 12,500,000.00 Rp 12,500,000.00 0.592%

VIII.A PEKERJAAN SANITASI


CLOSET JONGKOK 2 bh Rp 493,350.00 Rp 986,700.00 0.047%
WASHTAFEL 5 bh Rp 509,492.50 Rp 2,547,462.50 0.121%
BAK MANDI 2 bh Rp 1,221,541.20 Rp 2,443,082.40 0.116%
FLOOR DRAIN 14 bh Rp 26,620.00 Rp 372,680.00 0.018%
KRAN AIR 7 bh Rp 54,020.73 Rp 378,145.08 0.018%
PIPA PVC DIAMETER 2.5" 60 m Rp 74,367.33 Rp 4,462,039.66 0.211%
PIPA PVC DIAMETER 4" 35 m Rp 93,060.00 Rp 3,257,100.00 0.154%
BAK KONTROL 3 m2 Rp 514,085.00 Rp 1,542,255.00 0.073%
GROUND RESERVOAR 1 m2 Rp 6,500,000.00 Rp 6,500,000.00 0.308%
POMPA AIR LENGKAP INSTALASI 1 m2 Rp 1,500,000.00 Rp 1,500,000.00 0.071%
SEPTICTANK 1 Rp 1,277,742.30 Rp 1,277,742.30 0.061%

IX.A PEKERJAAN FINISHING


9.1 PEKERJAAN PEMASANGAN PLAFON
PLAFON TYPE A,B DAN C (GYSUM BOARD) 282.425 m2 Rp 38,918.00 Rp 10,991,416.15 0.521%
RANGKA HOLLOW 248.15 m2 Rp 186,516.00 Rp 46,283,945.40 2.192%
LIST LAGIT - LANGIT KAYU PROFIL 192.6 m Rp 13,508.00 Rp 2,601,640.80 0.123%

9.2 PEKERJAAN PASANGAN KERAMIK LANTAI DAN DINDING


URUGAN PASIR BAWAH (T=10 CM) 25.765 m3 Rp 177,320.00 Rp 4,568,649.80 0.216%
LANTAI KERJA (T=5 CM) BAWAH LANTAI 12.883 m 3 Rp 830,537.30 Rp 10,699,812.05 0.507%
URUGAN PASIR BAWAH LANTAI RABAT BETON KORIDOR 1.858 m 3
Rp 177,320.00 Rp 329,460.56 0.016%
LANTAI RABAT BETON KORIDOR (T=7 CM) 1.3 m 3 Rp 830,537.30 Rp 1,079,698.49 0.051%
PAS.KERAMIK LANTAI & TANGGA 30X30 CM 276.04 m2 Rp 177,773.96 Rp 49,072,725.13 2.324%
PAS.KERAMIK LANTAI 20X0 CM (KM/WC) 7.5 m2 Rp 180,774.00 Rp 1,355,805.00 0.064%
REKAPITULASI PERHITUNGAN PERSENTASE BOBOT
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

PLINT KERAMIK 10X20 CM 149.36 m Rp 31,159.70 Rp 4,654,012.79 0.220%


KERAMIK DINDING KM/WC & LAB 20X20 CM 25.44 m2 Rp 190,377.00 Rp 4,843,190.88 0.229%

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. BOBOT

9.3 PEKERJAAN PENGECATAN


CAT TEMBOK EXTERIOR 419 m2 Rp 105,642.90 Rp 44,264,375.10 2.096%
CAT TEMBOK INTERIOR 628.5 m2 Rp 71,322.90 Rp 44,826,442.65 2.123%
2
CAT PLAFON 261.2 m Rp 71,322.90 Rp 18,629,541.48 0.882%
2
CAT KUSEN 33.96 m Rp 55,042.90 Rp 1,869,256.88 0.089%

III.B PEKERJAAN STRUKTUR


PEKERJAAN LANTAI 2
3.2 PEK. KOLOM BETON BERTULANG
Pembesian 2089.834 kg Rp 157,701.50 Rp 32,956,995.66 1.561%
2
Bekisting 162.45 m Rp 339,350.00 Rp 55,127,407.50 2.611%
Beton Cor K-250 10.248 m3 Rp 1,050,951.14 Rp 10,770,147.31 0.510%

3.4 PEK. BALOK RING


Pembesian 1135.722 kg Rp 157,701.50 Rp 17,910,506.30 0.848%
Bekisting 136.6 m2 Rp 357,170.00 Rp 48,789,422.00 2.310%
3
Beton Cor K-250 8.069 m Rp 1,050,951.14 Rp 8,480,124.77 0.402%

3.5 PLAT LANTAI


Dak
Pembesian 2821.872 kg Rp 157,701.50 Rp 44,501,344.72 2.107%
2
Bekisting 273.62 m Rp 418,550.00 Rp 114,523,651.00 5.423%
Beton Cor K-250 31.344 m3 Rp 1,050,951.14 Rp 32,941,012.63 1.560%

Topi-topi + 6.30
Pembesian 134.37 kg Rp 157,701.50 Rp 2,119,035.06 0.100%
Bekisting 26.46 m2 Rp 418,550.00 Rp 11,074,833.00 0.524%
3
Beton Cor K-225 2.356 m Rp 1,035,328.81 Rp 2,439,234.68 0.116%

V.B PEKERJAAN PASANGAN BATU BATA DAN PLESTERAN LT.2


5.1 PEK. PASANGAN BATA
Pas. Bata 1:3 13.35 m2 Rp 96,284.10 Rp 1,285,392.74 0.061%
2
Pas. Bata 1:5 256.26 m Rp 90,677.40 Rp 23,236,990.52 1.100%

5.2 PEK. PLESTERAN


Pas. Bata 1:3 13.35 m2 Rp 56,637.24 Rp 756,107.15 0.036%
REKAPITULASI PERHITUNGAN PERSENTASE BOBOT
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

Pas. Bata 1:5 256.26 m2 Rp 61,738.16 Rp 15,821,020.88 0.749%

VI.B PEKERJAAN KUSEN LT.2


KUSEN ALMUNIUM 199.800 m Rp 108,439.10 Rp 21,666,132.18 1.026%
2
DAUN KUSEN 94.025 m Rp 453,541.00 Rp 42,643,965.75 2.019%
KACA BURAM T = 5 MM 0.806 m 2
Rp 90,285.25 Rp 72,784.96 0.003%
KACA T = 5 MM 14.929 m 2
Rp 99,360.25 Rp 1,483,365.73 0.070%

NO URAIAN PEKER JAAN VOLUME HARGA SATUAN Rp. JUMLAH HARGA Rp. BOBOT

KACA T = 8 MM 17.782 m2 Rp 184,060.25 Rp 3,272,867.34 0.155%


MULTIPLEKS 5.323 m 2
Rp 341,789.25 Rp 1,819,230.25 0.086%
HANDEL 20 bh Rp 70,180.00 Rp 1,403,600.00 0.066%
ENGSEL 70 bh Rp 21,780.00 Rp 1,524,600.00 0.072%

VII.B PEKERJAAN MECHANICAL AND ELECTRICAL LT. 2


LAMPU TL 40 WATT 20 bh Rp 150,000.00 Rp 3,000,000.00 0.142%
LAMPU SL 18 WATT 11 bh Rp 50,000.00 Rp 550,000.00 0.026%
STOPKONTAK 200 WATT 5 bh Rp 25,000.00 Rp 125,000.00 0.006%
SAKLAR TUNGGAL 4 bh Rp 25,000.00 Rp 100,000.00 0.005%
SAKLAR GANDA 5 bh Rp 30,000.00 Rp 150,000.00 0.007%
INSTALASI STOPKONTAK DAN TITIK LAMPU 36 titik Rp 80,000.00 Rp 2,880,000.00 0.136%
SUB PANEL PENERANGAN 1 titik Rp 500,000.00 Rp 500,000.00 0.024%
PASANG AC 2 K + INSTALASI LENGKAP 1 unit Rp 12,500,000.00 Rp 12,500,000.00 0.592%
PENANGKAL PETIR 1 unit Rp 2,500,000.00 Rp 2,500,000.00 0.118%

VIII.B PEKERJAAN SANITASI LT.2


CLOSET JONGKOK 2 bh Rp 493,350.00 Rp 986,700.00 0.047%
BAK MANDI 2 bh Rp 1,221,541.20 Rp 2,443,082.40 0.116%
FLOOR DRAIN 2 bh Rp 26,620.00 Rp 53,240.00 0.003%
KRAN AIR 2 bh Rp 54,020.73 Rp 108,041.45 0.005%
PIPA PVC DIAMETER 2.5" 35 m Rp 74,367.33 Rp 2,602,856.47 0.123%
PIPA PVC DIAMETER 4" 40 m Rp 93,060.00 Rp 3,722,400.00 0.176%

IX.B PEKERJAAN FINISHING LT. 2


PEKERJAAN PEMASANGAN PLAFON
PLAFON TYPE A, B, DAN C (GYSUM BOARD) 314.638 m2 Rp 38,918.00 Rp 12,245,081.68 0.580%
2
RANGKA HOLLOW 257.65 m Rp 186,516.00 Rp 48,055,847.40 2.276%
LIST LANGIT-LANGIT KAYU PROFIL 235.4 m Rp 13,508.00 Rp 3,179,783.20 0.151%

PEKERJAAN PASANGAN KERAMIK LANTAI DAN DINDING

URUGAN PASIR BAWAH ( T = 10 CM ) 24.815 m3 Rp 177,320.00 Rp 4,400,195.80 0.208%


LANTAI KERJA (T = 5 CM) BAWAH LANTAI 12.408 m3 Rp 830,537.30 Rp 10,305,306.83 0.488%
PEMASANGAN KERAMIK LANTAI 30X30 CM 255.5 m 2
Rp 177,773.96 Rp 45,421,247.90 2.151%
PASANGAN KERAMIK LANTAI 20 X 20 CM (KM/WC) 7.5 m 2
Rp 180,774.00 Rp 1,355,805.00 0.064%
PLINT KERAMIK 10 X 20 CM 112.07 m Rp 31,159.70 Rp 3,492,067.58 0.165%
REKAPITULASI PERHITUNGAN PERSENTASE BOBOT
GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM 27 m2 Rp 190,377.00 Rp 5,140,179.00 0.243%

PEKERJAAN PENGECATAN
CAT TEMBOK EKSTERIOR 320 m2 Rp 105,642.90 Rp 33,805,728.00 1.601%
CAT TEMBOK INTERIOR 480 m2 Rp 71,322.90 Rp 34,234,992.00 1.621%
2
CAT PLAFON 251.56 m Rp 71,322.90 Rp 17,941,988.72 0.850%
2
CAT KUSEN 9.84 m Rp 55,042.90 Rp 541,622.14 0.026%

JUMLAH Rp 2,111,642,022.38 100.000%


TIME SCHEDULE (KURVA S) PEMBANGUNAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

DURASI BULAN KE- 1 BULAN KE- 2 BULAN KE- 3 BULAN KE- 4 BULAN KE- 5 BULAN KE- 6
NO JENIS PEKERJAAN URAIAN PEKER JAAN BOBOT
(MINGGU) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
I PEKERJAAN PERSIAPAN ADMINISTRASI 0.379% 24 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016%
PEMBERSIHAN LAHAN 0.212% 1 0.212%
PENGUKURAN DAN BOWPLANG 0.616% 1 0.616%
II PEKERJAAN PONDASI GALIAN TANAH FOOTPLAT 0.842% 2 0.421% 0.421%
PASIR URUG FOOTPLAT 0.062% 1 0.062%
LANTAI KERJA FOOTPLAT K 100 0.145% 1 0.145%
PEK.PONDASI FOOTPLAT 2.863% 3 0.818% 0.545% 1.500%
URUGAN TANAH KEMBALI FOOTPLAT 0.365% 1 0.365%
PASIR URUG BATU KALI 0.167% 1 0.167%
AANSTAMPING 0.740% 1 0.740%
PAS. BATU BELAH 3.021% 2 1.599% 1.422%
URUGAN TANAH BATU KALI 0.512% 2 0.293% 0.220%
III PEKERJAAN STRUKTUR PEKERJAAN SLOOF K-225 3.770% 2 2.011% 1.759%
PEKERJAAN LANTAI 1 PEKERJAAN KOLOM K-250 9.364% 3 3.121% 6.087% 0.156%
PEKERJAAN BALOK K-250 9.833% 2 5.450% 4.383%
PEKERJAAN TANGGA K-250 0.676% 2 0.254% 0.423%
PEK.PLAT LANTAI II K-250 8.999% 3 0.409% 8.181% 0.409%
PEK.TOPI-TOPI +3.17 K-225 0.905% 1 0.905%
PEKERJAAN LANTAI 2 PEKERJAAN KOLOM K-250 4.682% 3 2.417% 2.114% 0.151%
PEKERJAAN BALOK RING K-250 3.560% 2 0.668% 2.893%
PEK.PLAT ATAP K-250 9.090% 4 8.636% 0.152% 0.152% 0.152%
PEK.TOPI-TOPI+6.30 K-225 0.740% 2 0.342% 0.398%
V PEK. PAS.BT. BATA & PLESTERAN PAS. BATA 2.835% 7 1.575% 0.315% 0.315% 0.315% 0.315%
PLESTERAN 1.919% 5 0.384% 0.209% 0.872% 0.384% 0.070%
VI PEKERJAAN KUSEN KUSEN ALMUNIUM 2.108% 2 1.756% 0.351%
DAUN KUSEN 3.690% 2 3.339% 0.351%
KACA BURAM, T 5 MM, T 8 MM 0.428% 1 0.428%
GYSUM 0.007% 2 0.005% 0.002%
MULTIPLEK 0.300% 2 0.225% 0.075%
AKSESORIES KUSEN 0.338% 1 0.338%
VII PEKERJAAN M & E PROPERTIES DAN INSTALASI M & E 3.086% 2 1.715% 1.372%
VIII PEKERJAAN SANITASI INSTALASI PIPA AIR BERSIH 0.335% 1 0.335%
INSTALASI PIPA AIR KOTOR 0.331% 1 0.331%
SEPTICTANK 0.061% 1 0.061%
PEMASANGAN PROPERTIES SANITASI 0.941% 4 0.470% 0.059% 0.353% 0.059%
IX PEKERJAAN FINISHING RANGKA HOLLOW 4.468% 3 0.670% 2.010% 1.787%
PLAFON TYPE A, B, DAN C (GYSUM BOARD) 1.100% 2 0.110% 0.990%
LIST LANGIT-LANGIT KAYU PROFIL 0.274% 1 0.274%
URUGAN PASIR BAWAH ( T = 10 CM ) 0.425% 1 0.425%
LANTAI KERJA ( T = 5 CM ) BAWAH LANTAI 0.995% 2 0.332% 0.663%
PLINT KERAMIK 10 X 20 CM 0.386% 2 0.193% 0.193%
KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM 0.601% 1 0.601%
PEMASANGAN KERAMIK LANTAI RUANGAN DAN KM/WC 4.475% 4 0.195% 2.140% 1.946% 0.195%
URUGAN PASIR BAWAH LANTAI RABAT BETON KORIDO 0.016% 1
LANTAI RABAT BETON KORIDOR ( T = 7 CM ) 0.051% 1
CAT TEMBOK, PLAFON DAN KUSEN 9.287% 4 1.114% 2.229%
JUMLAH 100.00% 0.227% 0.631% 1.255% 1.250% 1.880% 2.815% 3.668% 4.896% 7.677% 5.936% 7.929% 11.489% 4.885% 2.776% 3.569% 8.651% 5.691% 4.141% 3.619% 4.189% 4.066% 2.713%
JUMLAH KUMULATIF 0.227% 0.859% 2.114% 3.364% 5.244% 8.059% 11.726% 16.623% 24.300% 30.236% 38.166% 49.655% 54.540% 57.316% 60.885% 69.537% 75.228% 79.369% 82.988% 87.176% 91.243% 93.956%
MBANGUNAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

BULAN KE- 6
23 24
0.016% 0.016%

0.016%
0.051%
4.644% 1.300%
4.675% 1.367%
98.631% 100.00%
TIME SCHEDULE ( KURVA S ) PEMBANGUNAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

DURASI BULAN KE- 1 BULAN KE- 2 BULAN KE- 3 BULAN KE- 4 BULAN KE- 5 BULAN KE- 6
NO JENIS PEKERJAAN URAIAN PEKER JAAN BOBOT
(MINGGU) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
A PEKERJAAN PERSIAPAN ADMINISTRASI 0.379% 26 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015%
PEMBERSIHAN LAHAN 0.212% 1 0.212%
PENGUKURAN DAN BOWPLANG 0.616% 1 0.616%
B PEKERJAAN PONDASI GALIAN TANAH FOOTPLAT 0.842% 2 0.421% 0.421%
PASIR URUG FOOTPLAT 0.062% 1 0.062%
LANTAI KERJA FOOTPLAT K 100 0.145% 1 0.145%
PEMBESIAN PONDASI FOOTPLAT 1.377% 2 0.688% 0.688%
BEKISTING PONDASI FOOTPLAT 0.163% 2 1.323% 1.323%
BETON COR PONDASI FOOTPLAT K250 1.323% 1 1.323%
URUGAN TANAH KEMBALI FOOTPLAT 0.365% 1 0.365%
GALIAN TANAH BATU KALI Err:509 2 Err:509 Err:509
PASIR URUG BATU KALI 0.740% 1 0.740%
AANSTAMPING 0.167% 1 0.167%
PAS. BATU BELAH 0.512% 2 0.256% 0.256%
URUGAN TANAH BATU KALI 3.021% 1 3.021%
C PEKERJAAN STRUKTUR SLOOF Pembesian 1.794% 2 0.897% 0.897%
C.1 PEKERJAAN LANTAI 1 SLOOF Bekisting 1.207% 2 1.207% 1.207%
SLOOF Beton Cor K-225 0.769% 1 0.769%
KOLOM Pembesian 3.897% 3 1.299% 1.299% 1.299%
KOLOM Bekisting 4.505% 3 1.502% 1.502% 1.502%
KOLOM Beton Cor K-250 0.962% 2 0.481% 0.481%
BALOK Bekisting 5.167% 2 2.584% 2.584%
BALOK Pembesian 3.359% 2 1.679% 1.679%
BALOK Beton Cor K-225 1.307% 1 1.307%
TANGGA Bekisting 0.229% 1 0.229%
TANGGA Pembesian 0.304% 1 0.304%
TANGGA Beton Cor K-250 0.143% 1 0.143%
PLAT LT. II Bekisting 5.332% 2 2.666% 2.666%
PLAT LT. II Pembesian 2.107% 2 1.054% 1.054%
PLAT LT. II Beton Cor K-250 1.560% 1 1.560%
DAK + 3.17 Bekisting 0.637% 1 0.637%
DAK + 3.17 Pembesian 0.126% 1 0.126%
DAK + 3.17 Beton Cor K-225 0.142% 1 0.142%
C.2 PEKERJAAN LANTAI 2 KOLOM Pembesian 1.561% 3 0.520% 0.520% 0.520%
KOLOM Bekisting 2.611% 3 0.870% 0.870% 0.870%
KOLOM Beton Cor K-250 0.510% 2 0.255% 0.255%
BALOK RING Pembesian 0.848% 2 0.424% 0.424%
BALOK RING Bekisting 2.310% 2 1.155% 1.155%
BALOK RING Beton Cor K-225 0.402% 1 0.402%
PLAT ATAP Bekisting 5.423% 2 2.712% 2.712%
PLAT ATAP Pembesian 2.107% 2 1.054% 1.054%
PLAT ATAP Beton Cor K-250 1.560% 1 1.560%
TOPI-TOPI +6.30 Bekisting 0.524% 1 0.524%
TOPI-TOPI +6.30 Pembesian 0.100% 1 0.100%
TOPI-TOPI +6.30 Beton Cor K-225 0.116% 1 0.116%
D PEK. PAS.BT. BATA & PLESTERAN PAS. BATA 1.161% 7 0.166% 0.166% 0.166% 0.166% 0.166% 0.166% 0.166%
PLESTERAN 1:3 0.785% 5 0.157% 0.157% 0.157% 0.157% 0.157%
SPONENGAN 0.000% 3 0.000% 0.000% 0.000%
E PEKERJAAN KUSEN KUSEN ALMUNIUM 1.026% 2 0.513% 0.513%
DAUN KUSEN Err:509 2 Err:509 Err:509
KACA BURAM, T 5 MM, T 8 MM 0.229% 1 0.229%
AKSESORIES KUSEN 0.139% 1 0.139%
F PEKERJAAN SANITASI INSTALASI PIPA AIR KOTOR 0.116% 5 0.023% 0.023% 0.023% 0.023% 0.023%
SEPTICTANK 0.003% 1 0.003%
INSTALASI PIPA AIR BERSIH Err:509 1 Err:509 Err:509 Err:509 Err:509 Err:509
PEMASANGAN PROPERTIES SANITASI 0.047% 1 0.047%
G PEKERJAAN M & E PROPERTIES DAN INSTALASI M & E LT. 1 Err:509 2 Err:509 Err:509
H PEKERJAAN FINISHING RANGKA HOLLOW 2.276% 3 0.759% 0.759% 0.759%
PLAFON TYPE A, B, DAN C (GYSUM BOARD) 0.580% 2 0.290% 0.290%
LIST LANGIT-LANGIT KAYU PROFIL 0.151% 1 0.151%
URUGAN PASIR BAWAH ( T = 10 CM ) 0.208% 1 0.208%
LANTAI KERJA ( T = 5 CM ) BAWAH LANTAI 0.488% 2 0.244% 0.244%
PLINT KERAMIK 10 X 20 CM 0.165% 2 0.083% 0.083%
KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM 0.243% 1 0.243%
PEMASANGAN KERAMIK LANTAI RUANGAN DAN KM/WC 2.215% 4 0.554% 0.554% 0.554% 0.554%
URUGAN PASIR BAWAH LANTAI RABAT BETON KORIDOR Err:509 1 Err:509
LANTAI RABAT BETON KORIDOR ( T = 7 CM ) Err:509 1 Err:509
CAT TEMBOK, PLAFON DAN KUSEN 4.097% 4 1.024% 1.024% 1.024% 1.024%
JUMLAH Err:509 0.226% 0.630% 0.436% 2.657% Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 5.460% 2.705% 2.756% 3.645% 6.824% Err:509 Err:509 Err:509 1.617% 2.033% 1.593% 1.039% 1.039%
JUMLAH KUMULATIF 0.226% 0.856% 1.292% 3.949% Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA
HARI ( OH ) ( OH ) ( ORANG ) PEK.
A PEKERJAAN PERSIAPAN
A.1 PEMBERSIHAN LAHAN 451.500 m2 7 Pekerja 0.1 45.150 6.450 7 11
Mandor 0.05 22.575 3.225 4

A.2 PENGUKURAN DAN BOWPLANG 97.500 m 7 Pekerja 0.1 9.750 1.393 2 6


Tukang Kayu 0.1 9.750 1.393 2
Kepala Tukang 0.01 0.975 0.139 1
Mandor 0.005 0.488 0.070 1

B. PEKERJAAN PONDASI
B.1 PONDASI FOOTPLAT
B.1.1 GALIAN TANAH FOOTPLAT 259.000 m3 14 Pekerja 1.05 271.950 19.425 20 22
Mandor 0.067 17.353 1.240 2

B.1.2 PASIR URUG FOOTPLAT 7.390 m3 7 Pekerja 0.3 2.217 0.317 1 2


Mandor 0.01 0.074 0.011 1

B.1.3 LANTAI KERJA FOOTPLAT K 100 3.680 m3 7 Pekerja 1.200 4.416 0.631 1 4
Tukang Batu 0.200 0.736 0.105 1
Kepala Tukang 0.020 0.074 0.011 1
Mandor 0.006 0.022 0.003 1

B.1.4 PEMBESIAN PONDASI FOOTPLAT 1843.721 kg 14 Pekerja 0.070 129.060 9.219 10 22


Tukang Besi 0.070 129.060 9.219 10
Kepala Tukang 0.007 12.906 0.922 1
Mandor 0.004 7.375 0.527 1

B.1.5 BEKISTING PONDASI FOOTPLAT 22.920 m2 14 Pekerja 0.520 11.918 0.851 1 4


Tukang Kayu 0.260 5.959 0.426 1
Kepala Tukang 0.026 0.596 0.043 1
Mandor 0.026 0.596 0.043 1

B.1.6 BETON COR PONDASI FOOTPLAT K250 26.585 m3 7 Pekerja 1.650 43.865 6.266 7 11
Tukang Batu 0.275 7.311 1.044 2
Kepala Tukang 0.028 0.744 0.106 1
Mandor 0.083 2.207 0.315 1

B.1.7 URUGAN TANAH KEMBALI FOOTPLAT 225.800 m3 7 Pekerja 0.500 112.900 16.129 17 19
Mandor 0.050 11.290 1.613 2
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA
HARI ( OH ) ( OH ) ( ORANG ) PEK.
B.2 PONDASI BATU KALI
B.2.2 PASIR URUG BATU KALI 19.860 7 Pekerja 0.300 5.958 0.851 1 7
Mandor 0.010 0.199 0.028 1

B.2.3 AANSTAMPING 39.720 7 Pekerja 0.78 30.982 4.426 5 10


Tukang Batu 0.39 15.491 2.213 3
Kepala Tukang 0.039 1.549 0.221 1
Mandor 0.039 1.549 0.221 1

B.2.4 PAS. BATU BELAH 87.384 14 Pekerja 1.500 131.076 9.363 10 17


Tukang Batu 0.750 65.538 4.681 5
Kepala Tukang 0.075 6.554 0.468 1
Mandor 0.075 6.554 0.468 1

B.2.5 URUGAN TANAH BATU KALI 317.264 14 Pekerja 0.500 158.632 11.331 12 14
Mandor 0.050 15.863 1.133 2

C. PEKERJAAN STRUKTUR
C.1 PEKERJAAN LANTAI 1
C.1.1 SLOOF Pembesian 2402.367 kg 14 Pekerja 0.070 168.166 12.012 13 29
Tukang Besi 0.070 168.166 12.012 13
Kepala Tukang 0.007 16.817 1.201 2
Mandor 0.004 9.609 0.686 1

C.1.2 SLOOF Bekisting 157.900 m2 14 Pekerja 0.520 82.108 5.865 6 11


Tukang Kayu 0.260 41.054 2.932 3
Kepala Tukang 0.026 4.105 0.293 1
Mandor 0.026 4.105 0.293 1

C.1.3 SLOOF Beton Cor K-225 15.693 m3 7 Pekerja 1.650 25.893 3.699 4 7
Tukang Batu 0.275 4.316 0.617 1
Kepala Tukang 0.028 0.439 0.063 1
Mandor 0.083 1.303 0.186 1

C.1.4 KOLOM Pembesian 5217.761 kg 21 Pekerja 0.070 365.243 17.393 18 39


Tukang Besi 0.070 365.243 17.393 18
Kepala Tukang 0.007 36.524 1.739 2
Mandor 0.004 20.871 0.994 1

C.1.5 KOLOM Bekisting 280.350 m2 21 Pekerja 0.660 185.031 8.811 9 16


Tukang Kayu 0.330 92.516 4.406 5
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Kepala Tukang 0.033 9.252 0.441 1


Mandor 0.033 9.252 0.441 1
WKT KOEF. JUMLAH MAN POWER TTL
NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
C.1.6 KOLOM Beton Cor K-250 19.339 m3 14 Pekerja 1.650 31.909 2.279 3 6
Tukang Batu 0.275 5.318 0.380 1
Kepala Tukang 0.028 0.541 0.039 1
Mandor 0.083 1.605 0.115 1

C.1.7 BALOK Bekisting 305.481 m2 14 Pekerja 0.660 201.617 14.401 15 25


Tukang Kayu 0.330 100.809 7.201 8
Kepala Tukang 0.033 10.081 0.720 1
Mandor 0.033 10.081 0.720 1

C.1.8 BALOK Pembesian 4497.642 kg 14 Pekerja 0.070 314.835 22.488 23 51


Tukang Besi 0.070 314.835 22.488 23
Kepala Tukang 0.007 31.483 2.249 3
Mandor 0.004 17.991 1.285 2

C.1.9 BALOK Beton Cor K-225 26.263 m3 7 Pekerja 1.650 43.334 6.191 7 11
Tukang Batu 0.275 7.222 1.032 2
Kepala Tukang 0.028 0.735 0.105 1
Mandor 0.083 2.180 0.311 1

C.1.10 TANGGA Bekisting 15.262 m2 7 Pekerja 0.660 10.073 1.439 2 5


Tukang Kayu 0.330 5.036 0.719 1
Kepala Tukang 0.033 0.504 0.072 1
Mandor 0.033 0.504 0.072 1

C.1.11 TANGGA Pembesian 407.504 kg 7 Pekerja 0.070 28.525 4.075 5 12


Tukang Besi 0.070 28.525 4.075 5
Kepala Tukang 0.007 2.853 0.408 1
Mandor 0.004 1.630 0.233 1

C.1.12 TANGGA Beton Cor K-250 2.865 m3 7 Pekerja 1.650 4.727 0.675 1 4
Tukang Batu 0.275 0.788 0.113 1
Kepala Tukang 0.028 0.080 0.011 1
Mandor 0.083 0.238 0.034 1

C.1.13 PLAT LT. II Bekisting 268.993 m2 14 Pekerja 0.660 177.535 12.681 13 22


Tukang Kayu 0.330 88.768 6.341 7
Kepala Tukang 0.033 8.877 0.634 1
Mandor 0.033 8.877 0.634 1
C.1.14 PLAT LT. II Pembesian 2821.872 kg 14 Pekerja 0.070 197.531 14.109 15 33
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Tukang Besi 0.070 197.531 14.109 15


Kepala Tukang 0.007 19.753 1.411 2
Mandor 0.004 11.287 0.806 1
WKT KOEF. JUMLAH MAN POWER TTL
NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
C.1.15 PLAT LT. II Beton Cor K-250 31.344 m3 7 Pekerja 1.650 51.718 7.388 8 12
Tukang Batu 0.275 8.620 1.231 2
Kepala Tukang 0.028 0.878 0.125 1
Mandor 0.083 2.602 0.372 1

C.1.16 TOPI - TOPI + 3.17 Bekisting 32.160 m2 7 Pekerja 0.660 21.226 3.032 4 8
Tukang Kayu 0.330 10.613 1.516 2
Kepala Tukang 0.033 1.061 0.152 1
Mandor 0.033 1.061 0.152 1

C.1.17 TOPI - TOPI + 3.17 Pembesian 168.127 kg 7 Pekerja 0.070 11.769 1.681 2 6
Tukang Besi 0.070 11.769 1.681 2
Kepala Tukang 0.007 1.177 0.168 1
Mandor 0.004 0.673 0.096 1

C.1.18 TOPI - TOPI + 3.17 Beton Cor K-225 2.898 m3 7 Pekerja 1.650 4.782 0.683 1 4
Tukang Batu 0.275 0.797 0.114 1
Kepala Tukang 0.028 0.081 0.012 1
Mandor 0.083 0.241 0.034 1

C.2 PEKERJAAN STRUKTUR LT. 2


C.2.1 KOLOM Pembesian 2089.834 kg 21 Pekerja 0.07 146.288 6.966 7 16
Tukang Besi 0.07 146.288 6.966 7
Kepala Tukang 0.007 14.629 0.697 1
Mandor 0.004 8.359 0.398 1

C.2.2 KOLOM Bekisting 162.450 m2 21 Pekerja 0.660 107.217 5.106 6 11


Tukang Kayu 0.330 53.609 2.553 3
Kepala Tukang 0.033 5.361 0.255 1
Mandor 0.033 5.361 0.255 1

C.2.3 KOLOM Beton Cor K-250 10.248 m3 14 Pekerja 1.650 16.909 1.208 2 5
Tukang Batu 0.275 2.818 0.201 1
Kepala Tukang 0.028 0.287 0.020 1
Mandor 0.083 0.851 0.061 1

C.2.4 BALOK RING Pembesian 1135.722 kg 14 Pekerja 0.07 79.501 5.679 6 14


Tukang Besi 0.07 79.501 5.679 6
Kepala Tukang 0.007 7.950 0.568 1
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Mandor 0.004 4.543 0.324 1

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
C.2.5 BALOK RING Bekisting 136.600 m2 14 Pekerja 0.660 90.156 6.440 7 13
Tukang Kayu 0.330 45.078 3.220 4
Kepala Tukang 0.033 4.508 0.322 1
Mandor 0.033 4.508 0.322 1

C.2.6 BALOK RING Beton Cor K-225 8.069 m3 7 Pekerja 1.650 13.314 1.902 2 5
Tukang Batu 0.275 2.219 0.317 1
Kepala Tukang 0.028 0.226 0.032 1
Mandor 0.083 0.670 0.096 1

C.2.7 PLAT ATAP Bekisting 273.620 m2 14 Pekerja 0.660 180.589 12.899 13 22


Tukang Kayu 0.330 90.295 6.450 7
Kepala Tukang 0.033 9.029 0.645 1
Mandor 0.033 9.029 0.645 1

C.2.8 PLAT ATAP Pembesian 2821.872 kg 14 Pekerja 0.070 197.531 14.109 15 33


Tukang Besi 0.070 197.531 14.109 15
Kepala Tukang 0.007 19.753 1.411 2
Mandor 0.004 11.287 0.806 1

C.2.9 PLAT ATAP Beton Cor K-250 31.344 m3 7 Pekerja 1.650 51.718 7.388 8 12
Tukang Batu 0.275 8.620 1.231 2
Kepala Tukang 0.028 0.878 0.125 1
Mandor 0.083 2.602 0.372 1

C.2.10 TOPI-TOPI +6.30 Bekisting 26.460 m2 7 Pekerja 0.660 17.464 2.495 3 7


Tukang Kayu 0.330 8.732 1.247 2
Kepala Tukang 0.033 0.873 0.125 1
Mandor 0.033 0.873 0.125 1

C.2.11 TOPI-TOPI +6.30 Pembesian 134.370 kg 7 Pekerja 0.070 9.406 1.344 2 6


Tukang Besi 0.070 9.406 1.344 2
Kepala Tukang 0.007 0.941 0.134 1
Mandor 0.004 0.537 0.077 1

C.2.12 TOPI-TOPI +6.30 Beton Cor K-225 2.356 m3 7 Pekerja 1.650 3.887 0.555 1 4
Tukang Batu 0.275 0.648 0.093 1
Kepala Tukang 0.028 0.066 0.009 1
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Mandor 0.083 0.196 0.028 1

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
D. PEKERJAAN PASANGAN BATU BATA DAN PLESTERAN
D.1 PAS. BATA 658.548 m2 49 Pekerja 0.300 197.564 4.032 5 9
Tukang Batu 0.100 65.855 1.344 2
Kepala Tukang 0.010 6.585 0.134 1
Mandor 0.015 9.878 0.202 1

D.2 PLESTERAN 658.548 m2 35 Pekerja 0.260 171.222 4.892 5 11


Tukang Batu 0.200 131.710 3.763 4
Kepala Tukang 0.020 13.171 0.376 1
Mandor 0.013 8.561 0.245 1

E. PEKERJAAN KUSEN
E.1 KUSEN ALMUNIUM 410.420 m 14 Pekerja 0.043 17.648 1.261 2 6
Tukang Besi 0.043 17.648 1.261 2
Kepala Tukang 0.004 1.765 0.126 1
Mandor 0.002 0.862 0.062 1

E.2 DAUN KUSEN 171.825 m2 14 Pekerja 0.350 60.139 4.296 5 21


Tukang Kayu 1.050 180.416 12.887 13
Kepala Tukang 0.105 18.042 1.289 2
Mandor 0.018 3.093 0.221 1

E.3 KACA BURAM, T 5 MM, T 8 MM 63.871 m2 7 Pekerja 0.015 0.958 0.137 1 5


Tukang Kayu 0.150 9.581 1.369 2
Kepala Tukang 0.015 0.958 0.137 1
Mandor 0.001 0.048 0.007 1

GYSUM 3.956 m2 14 Pekerja 0.100 0.396 0.028 1 4


Tukang Kayu 0.050 0.198 0.014 1
Kepala Tukang 0.005 0.020 0.001 1
Mandor 0.006 0.024 0.002 1

MULTIPLEKS 18.540 m2 14 Pekerja 0.015 0.278 0.020 1 4


Tukang Kayu 0.150 2.781 0.199 1
Kepala Tukang 0.015 0.278 0.020 1
Mandor 0.00075 0.014 0.001 1
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

E.4 AKSESORIES KUSEN 208.000 bh 7 Pekerja 0.015 3.120 0.446 1 8


Tukang Kayu 0.150 31.200 4.457 5
Kepala Tukang 0.015 3.120 0.446 1
Mandor 0.008 1.560 0.223 1

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
G. PEKERJAAN MECHANICAL AND ELECTRICAL
PROPERTIES DAN INSTALASI M & E LT. 184 ttk 7 Pekerja 0.48 88.320 12.617 13 17
Tukang Listrik 0.048 8.832 1.262 2
Kepala Tukang 0.048 8.832 1.262 2

F. PEKERJAAN SANITASI
F.1 INSTALASI PIPA AIR KOTOR 75.000 m 7 Pekerja 0.036 2.700 0.386 1 4
Tukang Batu 0.06 4.500 0.643 1
Kepala Tukang 0.006 0.450 0.064 1
Mandor 0.002 0.150 0.021 1

F.2 SEPTICTANK 7.795 m3 7 Pekerja 1.65 12.862 1.837 2 5


Tukang Batu 0.275 2.144 0.306 1
Kepala Tukang 0.028 0.218 0.031 1
Mandor 0.083 0.647 0.092 1

F.3 INSTALASI PIPA AIR BERSIH 95.000 m 7 Pekerja 0.081 7.695 1.099 2 6
Tukang Batu 0.135 12.825 1.832 2
Kepala Tukang 0.0135 1.283 0.183 1
Mandor 0.004 0.380 0.054 1

F.4 PEMASANGAN PROPERTIES SANITASI 38 bh 28 Pekerja 6 228.000 8.143 9 16


Tukang Batu 3 114.000 4.071 5
Kepala Tukang 0.3 11.400 0.407 1
Mandor 0.03 1.140 0.041 1

H. PEKERJAAN FINISHING
PEKERJAAN PEMASANGAN PLAFON
H.1 RANGKA HOLLOW 505.800 m2 21 Pekerja 0.350 177.030 8.430 9 20
Tukang Besi 0.350 177.030 8.430 9
Kepala Tukang 0.035 17.703 0.843 1
Mandor 0.018 9.104 0.434 1

H.2 PLAFON TYPE A, B, DAN C (GYSUM 597.063 m2 14 Pekerja 0.1 59.706 4.265 5 10
Tukang Kayu 0.05 29.853 2.132 3
Kepala Tukang 0.005 2.985 0.213 1
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Mandor 0.006 3.582 0.256 1

H.3 LIST LANGIT-LANGIT KAYU PROFIL 428.000 m 7 Pekerja 0.050 21.400 3.057 4 10
Tukang Kayu 0.050 21.400 3.057 4
Kepala Tukang 0.005 2.140 0.306 1
Mandor 0.003 1.284 0.183 1

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA
HARI ( OH ) ( OH ) ( ORANG ) PEK.
PEKERJAAN PASANGAN KERAMIK LANTAI DAN DINDING
H.4 URUGAN PASIR BAWAH ( T = 10 CM 50.580 m3 7 Pekerja 0.300 15.174 2.168 3 4
Mandor 0.010 0.506 0.072 1

H.5 LANTAI KERJA ( T = 5 CM ) BAWAH 25.291 m3 14 Pekerja 1.200 30.349 2.168 3 6


Tukang Batu 0.200 5.058 0.361 1
Kepala Tukang 0.020 0.506 0.036 1
Mandor 0.006 0.152 0.011 1
H.6 PLINT KERAMIK 10 X 20 CM 261.430 m 14 Pekerja 0.090 23.529 1.681 2 6
Tukang Batu 0.090 23.529 1.681 2
Kepala Tukang 0.009 2.353 0.168 1
Mandor 0.005 1.307 0.093 1

H.7 KERAMIK DINDING KM/WC&LAB. UK 20 52.440 m2 7 Pekerja 0.900 47.196 6.742 7 13


Tukang Batu 0.450 23.598 3.371 4
Kepala Tukang 0.045 2.360 0.337 1
Mandor 0.045 2.360 0.337 1

H.8 P.KERAMIK LANTAI RUANGAN DAN KM/WC 546.540 m2 28 Pekerja 0.700 382.578 13.664 14 23
Tukang Batu 0.350 191.289 6.832 7
Kepala Tukang 0.035 19.129 0.683 1
Mandor 0.035 19.129 0.683 1

H.9 URUGAN PASIR BAWAH LANTAI RABAT BETON 1.858 m3 7 Pekerja 0.300 0.557 0.080 1 2
Mandor 0.010 0.019 0.003 1

H.10 LANTAI RABAT BETON KORIDOR ( T = 7 CM ) 1.300 m3 7 Pekerja 1.200 1.560 0.223 1 4
Tukang Batu 0.200 0.260 0.037 1
Kepala Tukang 0.020 0.026 0.004 1
Mandor 0.006 0.008 0.001 1

PEKERJAAN PENGECATAN
H.11 CAT TEMBOK, PLAFON DAN KUSEN 2404.060 m2 28 Pekerja 0.020 48.081 1.717 2 10
Tukang Batu 0.063 151.456 5.409 6
Kepala Tukang 0.006 15.146 0.541 1
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Mandor 0.003 7.212 0.258 1


GRAFIK MAN POWER PEMBANGUNAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

JUMLAH DURASI BULAN KE- 1 BULAN KE- 2 BULAN KE- 3 BULAN KE- 4 BULAN KE- 5 BULAN KE- 6
NO JENIS PEKERJAAN URAIAN PEKER JAAN
PEKERJA (MINGGU) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
I PEKERJAAN PERSIAPAN ADMINISTRASI 20 24 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
PEMBERSIHAN LAHAN 55 1 55
PENGUKURAN DAN BOWPLANG 30 1 30
II PEKERJAAN PONDASI GALIAN TANAH FOOTPLAT 110 2 85 10
PASIR URUG FOOTPLAT 10 1 10
LANTAI KERJA FOOTPLAT K 100 20 1 20
PEMBESIAN PONDASI FOOTPLAT 110 2 70 40
BEKISTING PONDASI FOOTPLAT 20 2 10 10
BETON COR PONDASI FOOTPLAT K250 55 1 55
URUGAN TANAH KEMBALI FOOTPLAT 95 1 95
PASIR URUG BATU KALI 35 1 35
AANSTAMPING 50 1 50
PAS. BATU BELAH 85 2 10 75
URUGAN TANAH BATU KALI 70 2 5 65
III PEKERJAAN STRUKTUR SLOOF Pembesian 145 2 73 73
PEKERJAAN LANTAI 1 SLOOF Bekisting 55 2 27 28
SLOOF Beton Cor K-225 35 1 35
KOLOM Pembesian 195 3 65 115 2
KOLOM Bekisting 80 3 27 50 3
KOLOM Beton Cor K-250 30 2 25 5
BALOK Bekisting 125 2 45 80
BALOK Pembesian 255 2 180 75
BALOK Beton Cor K-225 55 1 55
TANGGA Bekisting 25 1 25
TANGGA Pembesian 60 1 60
TANGGA Beton Cor K-250 20 1 20
PLAT LT. II Bekisting 110 2 30 80
PLAT LT. II Pembesian 165 2 20 145
PLAT LT. II Beton Cor K-250 60 1 60
DAK + 3.17 Bekisting 40 1 40
DAK + 3.17 Pembesian 30 1 30
DAK + 3.17 Beton Cor K-225 20 1 20
PEKERJAAN LANTAI 2 KOLOM Pembesian 80 3 38 8 24
KOLOM Bekisting 55 3 28 8 19
KOLOM Beton Cor K-250 25 2 12 13
BALOK RING Pembesian 70 2 65 5
BALOK RING Bekisting 65 2 60 5
BALOK RING Beton Cor K-225 25 1 25
PLAT ATAP Bekisting 110 2 40 70
PLAT ATAP Pembesian 165 2 145 20
PLAT ATAP Beton Cor K-250 60 1 60
TOPI-TOPI +6.30 Bekisting 35 1 35
TOPI-TOPI +6.30 Pembesian 30 1 30
TOPI-TOPI +6.30 Beton Cor K-225 20 1 20
D. 1 PEK. PAS.BT. BATA & PLESTERAN PAS. BATA 45 7 6 6 6 11 2 6 6
2 PLESTERAN 1:3 55 5 11 20 2 11 11
E. 1 PEKERJAAN KUSEN KUSEN ALMUNIUM 30 2 25 5
2 DAUN KUSEN 105 2 105 10
3 KACA BURAM, T 5 MM, T 8 MM 25 1 25
GYSUM 20 2
MULTIPLEKS 20 2
4 AKSESORIES KUSEN 40 1 40
G. PEKERJAAN M & E PROPERTIES DAN INSTALASI M & E LT. 1 85 1 85
F. 1 PEKERJAAN SANITASI INSTALASI PIPA AIR KOTOR 20 1 20 20 20 20 20
2 SEPTICTANK 25 1 25
3 INSTALASI PIPA AIR BERSIH 30 1 30 30 30 30 30
4 PEMASANGAN PROPERTIES SANITASI 80 1 80
H. 1 PEKERJAAN FINISHING RANGKA HOLLOW 100 3 45 5 50
2 PLAFON TYPE A, B, DAN C (GYSUM BOARD) 50 2 25 25
3 LIST LANGIT-LANGIT KAYU PROFIL 50 1 50
4 URUGAN PASIR BAWAH ( T = 10 CM ) 20 1 20
5 LANTAI KERJA ( T = 5 CM ) BAWAH LANTAI 30 2 25 5
6 PLINT KERAMIK 10 X 20 CM 30 2 15 15
7 KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM 65 1 65
8 PEMASANGAN KERAMIK LANTAI RUANGAN DAN KM/WC 115 4 5 71 34 5
9 URUGAN PASIR BAWAH LANTAI RABAT BETON KORIDOR 10 1 10
10 LANTAI RABAT BETON KORIDOR ( T = 7 CM ) 20 1 20
11 CAT TEMBOK, PLAFON DAN KUSEN 50 4 12 12 19 7
JUMLAH 56 32 86 146 201 101 290 278 241 286 311 292 188 206 228 310 298 273 96 147 72 68 30 28
JUMLAH KUMULATIF 56 88 174 320 520 621 912 1190 1430 1716 2027 2319 2508 2714 2942 3251 3550 3823 3919 4066 4137 4205 4235 4263
GRAFIK MAN POWER PEMBANGUNAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

JUMLAH DURASI BULAN KE- 1 BULAN KE- 2 BULAN KE- 3 BULAN KE- 4 BULAN KE- 5 BULAN KE- 6
NO JENIS PEKERJAAN URAIAN PEKER JAAN
PEKERJA (MINGGU) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
I PEKERJAAN PERSIAPAN ADMINISTRASI 20 24 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
PEMBERSIHAN LAHAN 55 1 55
PENGUKURAN DAN BOWPLANG 30 1 30
II PEKERJAAN PONDASI GALIAN TANAH FOOTPLAT 110 2 55 55
PASIR URUG FOOTPLAT 10 1 10
LANTAI KERJA FOOTPLAT K 100 20 1 20
PEK.PONDASI FOOTPLAT 105 3 30 20 55
URUGAN TANAH KEMBALI FOOTPLAT 95 1 95
PASIR URUG BATU KALI 35 1 35
AANSTAMPING 50 1 50
PAS. BATU BELAH 85 2 45 40
URUGAN TANAH BATU KALI 70 2 40 30
III PEKERJAAN STRUKTUR PEK. SLOOF K-225 225 2 120 105
PEKERJAAN LANTAI I PEK KOLOM K-250 300 3 100 195 5
PEK. BALOK K-250 415 2 230 185
PEK.TANGGA K-250 80 2 30 50
PEK. PLAT LANTAI II K-250 220 3 10 200 10
PEK. TOPI - TOPI K-225 90 1 90
PEKERJAAN LANTAI 2 PEK. KOLOM K-250 155 3 80 70 5
PEK.BALOK RING K-250 155 2 30 130
PEK.PLAT ATAP K-250 180 4 171 3 3 3
PEK.TOPI-TOPI +630 K-225 65 2 30 35
V PEK. PAS.BT. BATA & PLESTERAN PAS. BATA 45 7 25 5 5 5 5
PLESTERAN 55 5 11 6 25 11 2
VI PEKERJAAN KUSEN KUSEN ALMUNIUM 30 2 25 5
DAUN KUSEN 105 2 95 10
KACA BURAM, T 5 MM, T 8 MM 25 1 25
GYSUM 20 2 15 5
MULTIPLEKS 20 2 15 5
AKSESORIES KUSEN 40 1 40
VII PEKERJAAN M & E PROPERTIES DAN INSTALASI M & E LT. 1 45 2 25 20
VIII PEKERJAAN SANITASI INSTALASI PIPA AIR KOTOR 20 1 20
INSTALASI PIPA AIR BERSIH 30 1 30
SEPTICTANK 25 1 25
PEMASANGAN PROPERTIES SANITASI 80 4 40 5 30 5
IX PEKERJAAN FINISHING RANGKA HOLLOW 100 3 15 45 40
PLAFON TYPE A, B, DAN C (GYSUM BOARD) 50 2 5 45
LIST LANGIT-LANGIT KAYU PROFIL 50 1 50
URUGAN PASIR BAWAH ( T = 10 CM ) 20 1 20
LANTAI KERJA ( T = 5 CM ) BAWAH LANTAI 30 2 10 20
PLINT KERAMIK 10 X 20 CM 30 2 15 15
KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM 65 1 65
PEMASANGAN KERAMIK LANTAI RUANGAN DAN KM/WC 115 4 5 55 50 5
URUGAN PASIR BAWAH LANTAI RABAT BETON KORIDOR 10 1 10
LANTAI RABAT BETON KORIDOR ( T = 7 CM ) 20 1 20
CAT TEMBOK, PLAFON DAN KUSEN 50 4 6 12 25 7
JUMLAH 56 31 86 131 151 171 191 206 221 241 287 297 231 207 183 172 164 149 134 116 102 68 36 28
JUMLAH KUMULATIF 56 87 173 304 454 625 816 1022 1243 1484 1770 2067 2298 2505 2688 2859 3023 3172 3306 3422 3524 3591 3627 3655
KETERANGAN GAMBAR

NO. JENIS PEKERJAAN NO. JENIS PEKERJAAN

A.1 ADMINISTRASI C.2.10 TOPI-TOPI +6.30 Bekisting


A.2 PEMBERSIHAN LAHAN C.2.11 TOPI-TOPI +6.30 Pembesian
A.3 PENGUKURAN DAN BOWPLANG C.2.12 TOPI-TOPI +6.30 Beton Cor K-225
B.1.1 GALIAN TANAH FOOTPLAT D.1 PAS. BATA
B.1.2 PASIR URUG FOOTPLAT D.2 PLESTERAN 1:3
B.1.3 LANTAI KERJA FOOTPLAT K 100 D.3 SPONENGAN
B.1.4 PEMBESIAN PONDASI FOOTPLAT E.1 KUSEN ALMUNIUM
B.1.5 BEKISTING PONDASI FOOTPLAT E.2 DAUN KUSEN
B.1.6 BETON COR PONDASI FOOTPLAT K250 E.3 KACA BURAM, T 5 MM, T 8 MM
B.1.7 URUGAN TANAH KEMBALI FOOTPLAT E.4 AKSESORIES KUSEN
B.2.1 GALIAN TANAH BATU KALI F.1 INSTALASI PIPA AIR KOTOR
B.2.2 PASIR URUG BATU KALI F.2 SEPTICTANK
B.2.3 AANSTAMPING F.3 INSTALASI PIPA AIR BERSIH
B.2.4 PAS. BATU BELAH F.4 PEMASANGAN PROPERTIES SANITASI
B.2.5 URUGAN TANAH BATU KALI G. PROPERTIES DAN INSTALASI M & E LT. 1
C.1.1 SLOOF Pembesian H.1 RANGKA HOLLOW
C.1.2 SLOOF Bekisting H.2 PLAFON TYPE A, B, DAN C (GYSUM BOARD)
C.1.3 SLOOF Beton Cor K-225 H.3 LIST LANGIT-LANGIT KAYU PROFIL
C.1.4 KOLOM Pembesian Lt. 1 H.4 URUGAN PASIR BAWAH ( T = 10 CM )
C.1.5 KOLOM Bekisting Lt. 1 H.5 LANTAI KERJA ( T = 5 CM ) BAWAH LANTAI
C.1.6 KOLOM Beton Cor K-250 Lt. 1 H.6 PLINT KERAMIK 10 X 20 CM
C.1.7 BALOK Bekisting Lt. 1 H.7 KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM
C.1.8 BALOK Pembesian Lt. 1 H.8 PEMASANGAN KERAMIK LANTAI RUANGAN DAN KM/WC
C.1.9 BALOK Beton Cor K-225 Lt. 1 H.9 URUGAN PASIR BAWAH LANTAI RABAT BETON KORIDOR
C.1.10 TANGGA Bekisting H.10 LANTAI RABAT BETON KORIDOR ( T = 7 CM )
C.1.11 TANGGA Pembesian H.11 CAT TEMBOK, PLAFON DAN KUSEN
C.1.12 TANGGA Beton Cor K-250
C.1.13 PLAT LT. II Bekisting
C.1.14 PLAT LT. II Pembesian
C.1.15 PLAT LT. II Beton Cor K-250
C.1.16 DAK + 3.17 Bekisting
C.1.17 DAK + 3.17 Pembesian
C.1.18 DAK + 3.17 Beton Cor K-225
C.2.1 KOLOM Pembesian Lt. 2
C.2.2 KOLOM Bekisting Lt. 2
C.2.3 KOLOM Beton Cor K-250 Lt. 2
C.2.4 BALOK RING Pembesian Lt. 2
C.2.5 BALOK RING Bekisting Lt. 2
C.2.6 BALOK RING Beton Cor K-225 Lt. 2
C.2.7 PLAT ATAP Bekisting
C.2.8 PLAT ATAP Pembesian
C.2.9 PLAT ATAP Beton Cor K-250
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

I PEKERJAAN PERSIAPAN
1.1 PEMBERSIHAN LAHAN
1 m2 Membersihkan Lapangan dan Perataan
A. Tenaga Rp 9,000.00
Pekerja 0.1 OH Rp 55,000.00 Rp 5,500.00
Mandor 0.05 OH Rp 70,000.00 Rp 3,500.00
B. Bahan
C. Peralatan
D. Jumlah ( A+B+C ) Rp 9,000.00
E. Overhead & Profit ( 10% ) Rp 900.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 9,900.00
1.2 PENGUKURAN DAN BOWPLANNK
1 m' Pengukuran dan Pemasangan Bouwplank
A. Tenaga Rp 14,150.00
Pekerja 0.1 OH Rp 55,000.00 Rp 5,500.00
Tukang Kayu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00

B. Bahan Rp 107,060.00
3
Kayu 5/7 x 4m Kayu Kruing 0.012 m Rp 5,400,000.00 Rp 64,800.00
Paku Biasa 2" - 5" 0.02 kg Rp 13,000.00 Rp 260.00
Kayu Papan 3/20 Kruing 0.007 m3 Rp 6,000,000.00 Rp 42,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 121,210.00
E. Overhead & Profit ( 10% ) Rp 12,121.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 133,331.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

II. PEKERJAAN PONDASI


2.1 PONDASI FOOTPLAT
2.1.1 GALIAN TANAH FOOTPLAT
1 m3 Menggali Tanah Biasa Sedalam 3 m
A. Tenaga Rp 62,440.00
Pekerja 1.05 OH Rp 55,000.00 Rp 57,750.00
Mandor 0.067 OH Rp 70,000.00 Rp 4,690.00
B. Bahan
C. Peralatan
D. Jumlah ( A+B+C ) Rp 62,440.00
E. Overhead & Profit ( 10% ) Rp 6,244.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 68,684.00
2.1.2 URUGAN TANAH KEMBALI FOOTPLAT
1 m3 Pengurugan Kembali
A. Tenaga Rp 31,000.00
Pekerja 0.5 OH Rp 55,000.00 Rp 27,500.00
Mandor 0.05 OH Rp 70,000.00 Rp 3,500.00
B. Bahan
C. Peralatan
D. Jumlah ( A+B+C ) Rp 31,000.00
E. Overhead & Profit ( 10% ) Rp 3,100.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 34,100.00
2.1.3 PASIR URUG FOOTPLAT
1 m3 Urugan Pasir
A. Tenaga Rp 17,200.00
Pekerja 0.3 OH Rp 55,000.00 Rp 16,500.00
Mandor 0.01 OH Rp 70,000.00 Rp 700.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 144,000.00
Pasir Urug 1.2 m3 Rp 120,000.00 Rp 144,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 161,200.00
E. Overhead & Profit ( 10% ) Rp 16,120.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 177,320.00
2.1.4 LANTAI KERJA FOOTPLAT K100
1 m3 Membuat Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K100), slum (3-6)cm, w/c = 0.87
A. Tenaga Rp 83,020.00
Pekerja 1.2 OH Rp 55,000.00 Rp 66,000.00
Tukang Batu 0.2 OH Rp 75,000.00 Rp 15,000.00
Kepala Tukang 0.02 OH Rp 80,000.00 Rp 1,600.00
Mandor 0.006 OH Rp 70,000.00 Rp 420.00
B. Bahan Rp 672,013.91
Portland Semen 230 kg Rp 1,300.00 Rp 299,000.00
Pasir Beton 893 kg Rp 192.86 Rp 172,223.98
Kerikil (Maksimum 30mm) 1027 kg Rp 192.59 Rp 197,789.93
Air 200 ltr Rp 15.00 Rp 3,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 755,033.91
E. Overhead & Profit ( 10% ) Rp 75,503.39
F. Harga Satuan Pekerjaan ( D+E ) Rp 830,537.30
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH
2.1.5 BETON COR PONDASI FOOTPLAT K250
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 835,985.13
Portland Semen 384 kg Rp 1,300.00 Rp 499,200.00
Pasir Beton 692 kg Rp 192.86 Rp 133,459.12
Kerikil (Maksimum 30mm) 1039 kg Rp 192.59 Rp 200,101.01
Air 215 ltr Rp 15.00 Rp 3,225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 955,410.13
E. Overhead & Profit ( 10% ) Rp 95,541.01
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,050,951.14
2.1.6 PEMBESIAN PONDASI FOOTPLAT
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

E. Overhead & Profit ( 10% ) Rp 14,336.50


F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
2.1.7 BEKISTING PONDASI FOOTPLAT
1 m2 Memasang Bekisting untuk Pondasi
A. Tenaga Rp 52,000.00
Pekerja 0.52 OH Rp 55,000.00 Rp 28,600.00
Tukang Kayu 0.26 OH Rp 75,000.00 Rp 19,500.00
Kepala Tukang 0.026 OH Rp 80,000.00 Rp 2,080.00
Mandor 0.026 OH Rp 70,000.00 Rp 1,820.00
B. Bahan Rp 84,800.00
Kayu Klas III (Terentang) 0.04 m3 Rp 2,000,000.00 Rp 80,000.00
Paku Biasa 2" - 5" 0.3 kg Rp 13,000.00 Rp 3,900.00
Minyak Bekisting 0.1 ltr Rp 9,000.00 Rp 900.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 136,800.00
E. Overhead & Profit ( 10% ) Rp 13,680.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 150,480.00
2.2 PONDASI BATU BELAH
2.2.1 PASANGAN BATU BELAH
1 m3 Pemasangan Pondasi Batu Belah 1SP : 5PP
A. Tenaga Rp 150,000.00
Pekerja 1.5 OH Rp 55,000.00 Rp 82,500.00
Tukang Batu 0.75 OH Rp 75,000.00 Rp 56,250.00
Kepala Tukang 0.075 OH Rp 80,000.00 Rp 6,000.00
Mandor 0.075 OH Rp 70,000.00 Rp 5,250.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 513,600.00
Batu Belah 15/20 1.2 m3 Rp 190,000.00 Rp 228,000.00
Portland Cement 136 kg Rp 1,300.00 Rp 176,800.00
Pasir Pasang 0.544 m3 Rp 200,000.00 Rp 108,800.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 663,600.00
E. Overhead & Profit ( 10% ) Rp 66,360.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 729,960.00
2.2.2 AANSTAMPING
1 m3 Pemasangan Batu Kosong / Anstamping
A. Tenaga Rp 78,000.00
Pekerja 0.78 OH Rp 55,000.00 Rp 42,900.00
Tukang Batu 0.39 OH Rp 75,000.00 Rp 29,250.00
Kepala Tukang 0.039 OH Rp 80,000.00 Rp 3,120.00
Mandor 0.039 OH Rp 70,000.00 Rp 2,730.00
B. Bahan Rp 279,840.00
Batu Belah 15/20 1.2 m3 Rp 190,000.00 Rp 228,000.00
3
Pasir Urug 0.432 m Rp 120,000.00 Rp 51,840.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 357,840.00
E. Overhead & Profit ( 10% ) Rp 35,784.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 393,624.00
2.2.3 PASIR URUG BATU KALI
1 m3 Urugan Pasir
A. Tenaga Rp 17,200.00
Pekerja 0.3 OH Rp 55,000.00 Rp 16,500.00
Mandor 0.01 OH Rp 70,000.00 Rp 700.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 144,000.00
3
Pasir Urug 1.2 m Rp 120,000.00 Rp 144,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 161,200.00
E. Overhead & Profit ( 10% ) Rp 16,120.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 177,320.00
2.2.4 URUGAN TANAH KEMBALI BATU KALI
1 m3 Pengurugan Kembali
A. Tenaga Rp 31,000.00
Pekerja 0.5 OH Rp 55,000.00 Rp 27,500.00
Mandor 0.05 OH Rp 70,000.00 Rp 3,500.00
B. Bahan
C. Peralatan
D. Jumlah ( A+B+C ) Rp 31,000.00
E. Overhead & Profit ( 10% ) Rp 3,100.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 34,100.00
PEKERJAAN LANTAI 1
III.A PEKERJAAN STRUKTUR
3.1 PEKERJAAN SLOOF BETON BERTULANG K225
PEMBESIAN SLOOF
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
BEKISTING SLOOF
1 m2 Memasang Bekisting untuk Sloof
A. Tenaga Rp 52,000.00
Pekerja 0.52 OH Rp 55,000.00 Rp 28,600.00
Tukang Kayu 0.26 OH Rp 75,000.00 Rp 19,500.00
Kepala Tukang 0.026 OH Rp 80,000.00 Rp 2,080.00
Mandor 0.026 OH Rp 70,000.00 Rp 1,820.00
B. Bahan Rp 94,800.00
Kayu Klas III (Terentang) 0.045 m3 Rp 2,000,000.00 Rp 90,000.00
Paku Biasa 2" - 5" 0.3 kg Rp 13,000.00 Rp 3,900.00
Minyak Bekisting 0.1 ltr Rp 9,000.00 Rp 900.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 1,820.00
E. Overhead & Profit ( 10% ) Rp 182.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 2,002.00
BETON COR K225
1 m3 Membuat Beton Mutu f'c = 19.3 Mpa (K225), slum (12±2)cm, w/c = 0.58
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00


Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 821,783.01
Portland Semen 371 kg Rp 1,300.00 Rp 482,300.00
Pasir Beton 698 kg Rp 192.86 Rp 134,616.28
Kerikil (Maksimum 30mm) 1047 kg Rp 192.59 Rp 201,641.73
Air 215 ltr Rp 15.00 Rp 3,225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 821,783.01
E. Overhead & Profit ( 10% ) Rp 82,178.30
F. Harga Satuan Pekerjaan ( D+E ) Rp 903,961.31
3.2 PEKERJAAN KOLOM BETON BERTULANG K250
PEMBESIAN KOLOM
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

BEKISTING KOLOM
1 m2 Memasang Bekisting untuk Kolom
A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00
B. Bahan Rp 242,500.00
Kayu Klas III (Terentang) 0.04 m3 Rp 2,000,000.00 Rp 80,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00
Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00
Balok Kayu Klas II 0.015 m3 Rp 5,400,000.00 Rp 81,000.00
Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 2 btg Rp 18,000.00 Rp 36,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 308,500.00
E. Overhead & Profit ( 10% ) Rp 30,850.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 339,350.00
BETON COR K250
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 835,985.13
Portland Semen 384 kg Rp 1,300.00 Rp 499,200.00
Pasir Beton 692 kg Rp 192.86 Rp 133,459.12
Kerikil (Maksimum 30mm) 1039 kg Rp 192.59 Rp 200,101.01
Air 215 ltr Rp 15.00 Rp 3,225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 955,410.13
E. Overhead & Profit ( 10% ) Rp 95,541.01
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,050,951.14
3.3 PEKERJAAN BALOK BETON BERTULANG K250
PEMBESIAN BALOK
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
BEKISTING BALOK
1 m2 Memasang Bekisting untuk Balok
A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00


Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00
B. Bahan Rp 258,700.00
Kayu Klas III (Terentang) 0.04 m3 Rp 2,000,000.00 Rp 80,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00
Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00
Balok Kayu Klas II 0.018 m3 Rp 5,400,000.00 Rp 97,200.00
Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 2 btg Rp 18,000.00 Rp 36,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 324,700.00
E. Overhead & Profit ( 10% ) Rp 32,470.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 357,170.00
BETON COR K250
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 835,985.13
Portland Semen 384 kg Rp 1,300.00 Rp 499,200.00
Pasir Beton 692 kg Rp 192.86 Rp 133,459.12
Kerikil (Maksimum 30mm) 1039 kg Rp 192.59 Rp 200,101.01
Air 215 ltr Rp 15.00 Rp 3,225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 955,410.13

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

E. Overhead & Profit ( 10% ) Rp 95,541.01


F. Harga Satuan Pekerjaan ( D+E ) Rp 1,050,951.14
3.5 PEKERJAAN TANGGA
PEMBESIAN TANGGA
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
BEKISTING TANGGA
1 m2 Memasang Bekisting untuk Tangga
A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00
B. Bahan Rp 222,050.00
Kayu Klas III (Terentang) 0.03 m3 Rp 2,000,000.00 Rp 60,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Minyak Bekisting 0.15 ltr Rp 9,000.00 Rp 1,350.00


3
Balok Kayu Klas II 0.015 m Rp 5,400,000.00 Rp 81,000.00
Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 2 btg Rp 18,000.00 Rp 36,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 288,050.00
E. Overhead & Profit ( 10% ) Rp 28,805.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 316,855.00
BETON COR K250
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 835,985.13
Portland Semen 384 kg Rp 1,300.00 Rp 499,200.00
Pasir Beton 692 kg Rp 192.86 Rp 133,459.12
Kerikil (Maksimum 30mm) 1039 kg Rp 192.59 Rp 200,101.01
Air 215 ltr Rp 15.00 Rp 3,225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 955,410.13
E. Overhead & Profit ( 10% ) Rp 95,541.01
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,050,951.14

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

3.6 PEKERJAAN PLAT LANTAI DAN ATAP


3.6.1 PLAT LANTAI II K250
PEMBESIAN PLAT LANTAI
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
BEKISTING PLAT LANTAI
1 m2 Memasang Bekisting untuk Lantai
A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00

B. Bahan Rp 314,500.00
3
Kayu Klas III (Terentang) 0.04 m Rp 2,000,000.00 Rp 80,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00


3
Balok Kayu Klas II (Borneo) 0.015 m Rp 5,400,000.00 Rp 81,000.00
Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 6 btg Rp 18,000.00 Rp 108,000.00

C. Peralatan
D. Jumlah ( A+B+C ) Rp 380,500.00
E. Overhead & Profit ( 10% ) Rp 38,050.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 418,550.00
BETON COR K250
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 835,985.13
Portland Semen 384 kg Rp 1,300.00 Rp 499,200.00
Pasir Beton 692 kg Rp 192.86 Rp 133,459.12
Kerikil (Maksimum 30mm) 1039 kg Rp 192.59 Rp 200,101.01
Air 215 ltr Rp 15.00 Rp 3,225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 955,410.13
E. Overhead & Profit ( 10% ) Rp 95,541.01
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,050,951.14

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

3.6.2 TOPI - TOPI +3.17


PEMBESIAN TOPI - TOPI +3.17
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
BETON COR K225
1 m3 Membuat Beton Mutu f'c = 19.3 Mpa (K225), slum (12±2)cm, w/c = 0.58
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 821,783.01
Portland Semen 371 kg Rp 1,300.00 Rp 482,300.00
Pasir Beton 698 kg Rp 192.86 Rp 134,616.28
Kerikil (Maksimum 30mm) 1047 kg Rp 192.59 Rp 201,641.73
Air 215 ltr Rp 15.00 Rp 3,225.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

D. Jumlah ( A+B+C ) Rp 821,783.01


E. Overhead & Profit ( 10% ) Rp 82,178.30
F. Harga Satuan Pekerjaan ( D+E ) Rp 903,961.31
V.A PEKERJAAN PAS.BATU BATA DAN PLSTERAN
5.1 PEKERJAAN PASANGAN BATU BATA
PASANGAN BATU BATA 1 : 3
1 m2 Pemasangan Dinding Bata Merah Ukuran(5x11x22)cm Tebal 1/2 Bata Camp. 1PS : 3PP
A. Tenaga Rp 25,850.00
Pekerja 0.3 OH Rp 55,000.00 Rp 16,500.00
Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.015 OH Rp 70,000.00 Rp 1,050.00
B. Bahan Rp 61,681.00
Bata Merah 5 x 11 x 22 70 Buah Rp 500.00 Rp 35,000.00
Portland Semen 14.37 kg Rp 1,300.00 Rp 18,681.00
Pasir Pasang 0.04 m3 Rp 200,000.00 Rp 8,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 87,531.00
E. Overhead & Profit ( 10% ) Rp 8,753.10
F. Harga Satuan Pekerjaan ( D+E ) Rp 96,284.10
PASANGAN BATU BATA 1 : 5
1 m2 Pemasangan Dinding Bata Merah Ukuran(5x11x22)cm Tebal 1/2 Bata Camp. 1PS : 5PP
A. Tenaga Rp 25,850.00
Pekerja 0.3 OH Rp 55,000.00 Rp 16,500.00
Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Mandor 0.015 OH Rp 70,000.00 Rp 1,050.00


B. Bahan Rp 56,584.00
Bata Merah 5 x 11 x 22 70 Buah Rp 500.00 Rp 35,000.00
Portland Semen 9.68 kg Rp 1,300.00 Rp 12,584.00
Pasir Pasang 0.045 m3 Rp 200,000.00 Rp 9,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 82,434.00
E. Overhead & Profit ( 10% ) Rp 8,243.40
F. Harga Satuan Pekerjaan ( D+E ) Rp 90,677.40
5.2 PEKERJAAN PLESTERAN
PEKERJAAN PLESTERAN 1 : 3
1 m2 Pemasangan Plesteran 1PC : 3PP Tebal 20 mm
A. Tenaga Rp 31,810.00
Pekerja 0.26 OH Rp 55,000.00 Rp 14,300.00
Tukang Batu 0.2 OH Rp 75,000.00 Rp 15,000.00
Kepala Tukang 0.02 OH Rp 80,000.00 Rp 1,600.00
Mandor 0.013 OH Rp 70,000.00 Rp 910.00
B. Bahan Rp 19,678.40
Portland Semen 10.368 kg Rp 1,300.00 Rp 13,478.40
Pasir Pasang 0.031 m3 Rp 200,000.00 Rp 6,200.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 51,488.40
E. Overhead & Profit ( 10% ) Rp 5,148.84
F. Harga Satuan Pekerjaan ( D+E ) Rp 56,637.24

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

PEKERJAAN PLESTERAN 1 : 5
1 m2 Pemasangan Plesteran 1PC : 5PP Tebal 20 mm
A. Tenaga Rp 40,140.00
Pekerja 0.4 OH Rp 55,000.00 Rp 22,000.00
Tukang Batu 0.2 OH Rp 75,000.00 Rp 15,000.00
Kepala Tukang 0.02 OH Rp 80,000.00 Rp 1,600.00
Mandor 0.022 OH Rp 70,000.00 Rp 1,540.00
B. Bahan Rp 15,985.60
Portland Semen 6.912 kg Rp 1,300.00 Rp 8,985.60
3
Pasir Pasang 0.035 m Rp 200,000.00 Rp 7,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 56,125.60
E. Overhead & Profit ( 10% ) Rp 5,612.56
F. Harga Satuan Pekerjaan ( D+E ) Rp 61,738.16
VI.A PEKERJAAN KUSEN
PINTU DAN JENDELA
KUSEN PINTU ALUMUNIUM
1m' Pemasangan Kusen Pintu Allumunium
A. Tenaga Rp 6,081.00
Pekerja 0.043 OH Rp 55,000.00 Rp 2,365.00
Tukang Besi 0.043 OH Rp 75,000.00 Rp 3,225.00
Kepala Tukang 0.0043 OH Rp 80,000.00 Rp 344.00
Mandor 0.0021 OH Rp 70,000.00 Rp 147.00
B. Bahan Rp 92,500.00
Profil Allumunium 1.1 m' Rp 80,000.00 Rp 88,000.00
Skrup Fixer 2 bh Rp 750.00 Rp 1,500.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Seatant 0.06 tube Rp 50,000.00 Rp 3,000.00


C. Peralatan
D. Jumlah ( A+B+C ) Rp 98,581.00
E. Overhead & Profit ( 10% ) Rp 9,858.10
F. Harga Satuan Pekerjaan ( D+E ) Rp 108,439.10
DAUN PINTU
1 m2 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III
A. Tenaga Rp 107,660.00
Pekerja 0.35 OH Rp 55,000.00 Rp 19,250.00
Tukang Kayu 1.05 OH Rp 75,000.00 Rp 78,750.00
Kepala Tukang 0.105 OH Rp 80,000.00 Rp 8,400.00
Mandor 0.018 OH Rp 70,000.00 Rp 1,260.00
B. Bahan Rp 304,650.00
Kayu Klas II (Kamfer) papan 0.04 m3 Rp 7,600,000.00 Rp 304,000.00
Paku Biasa 2" - 5" 0.05 kg Rp 13,000.00 Rp 650.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 412,310.00
E. Overhead & Profit ( 10% ) Rp 41,231.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 453,541.00
KACA T = 8 mm
1 m2 Pemasangan Kaca tebal 8 mm
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 154,000.00
Kaca Tebal 8 mm 1.1 m2 Rp 140,000.00 Rp 154,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 167,327.50
E. Overhead & Profit ( 10% ) Rp 16,732.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 184,060.25
KACA T = 5 mm
1 m2 Pemasangan Kaca tebal 5 mm
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50
B. Bahan Rp 77,000.00
Kaca Tebal 5 mm 1.1 m2 Rp 70,000.00 Rp 77,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 90,327.50
E. Overhead & Profit ( 10% ) Rp 9,032.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 99,360.25
HANDEL
1 Buah Pemasangan Handle Pintu HINGE ES SL 9″ SN
A. Tenaga Rp 13,800.00
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.0075 OH Rp 70,000.00 Rp 525.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 50,000.00
Handle Pintu 1 bh Rp 50,000.00 Rp 50,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 63,800.00
E. Overhead & Profit ( 10% ) Rp 6,380.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 70,180.00
KACA BURAM
1 m2 Pemasangan Kaca Buram T = 5 mm
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50
B. Bahan Rp 68,750.00
Kaca Buram T = 5 mm 1.1 m2 Rp 62,500.00 Rp 68,750.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 82,077.50
E. Overhead & Profit ( 10% ) Rp 8,207.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 90,285.25
ENGSEL
1 Buah Pemasangan Engsel Pintu
A. Tenaga Rp 13,800.00
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.0075 OH Rp 70,000.00 Rp 525.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH


B. Bahan Rp 6,000.00
Engsel Pintu 1 bh Rp 6,000.00 Rp 6,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 19,800.00
E. Overhead & Profit ( 10% ) Rp 1,980.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 21,780.00
MULTIPLEKS
1 m2 Pembuatan & Pemasangan Pintu Kayu Lapis ( Plywood ) Rangkap Rangka Kayu Klass II ( lbr s/d 90 cm )
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50
B. Bahan Rp 297,390.00
Kayu Klas II (Kamfer) papan 0.025 m3 Rp 7,600,000.00 Rp 190,000.00
Paku Biasa 1/2" - 1" 0.03 kg Rp 13,000.00 Rp 390.00
Lem Kayu 0.5 lbr Rp 18,000.00 Rp 9,000.00
Multipleks ( 9 mm ) 1 lbr Rp 98,000.00 Rp 98,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 310,717.50
E. Overhead & Profit ( 10% ) Rp 31,071.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 341,789.25
PINTU KACA RANGKA ALUMUNIUM
1 m2 Pemasangan Pintu Kaca Rangka Allumunium
A. Tenaga Rp 12,120.00
Pekerja 0.085 OH Rp 55,000.00 Rp 4,675.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Tukang Besi 0.085 OH Rp 75,000.00 Rp 6,375.00


Kepala Tukang 0.009 OH Rp 80,000.00 Rp 720.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00
B. Bahan Rp 388,000.00
Pintu Allumunium 4.4 m' Rp 80,000.00 Rp 352,000.00
Profil Kaca 4.5 bh Rp 5,000.00 Rp 22,500.00
Seatant 0.27 tube Rp 50,000.00 Rp 13,500.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 400,120.00
E. Overhead & Profit ( 10% ) Rp 40,012.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 440,132.00
VII.A PEKERJAAN MECHANICAL DAN ELECTRICAL
VIII.A PEKERJAAN SANITASI
CLOSET JONGKOK
1 Unit Memasang Closet Jongkok Porselen
A. Tenaga Rp 298,700.00
Pekerja 1 OH Rp 55,000.00 Rp 55,000.00
Tukang Batu 1.5 OH Rp 75,000.00 Rp 112,500.00
Kepala Tukang 1.5 OH Rp 80,000.00 Rp 120,000.00
Mandor 0.16 OH Rp 70,000.00 Rp 11,200.00
B. Bahan Rp 149,800.00
Kloset Jongkok 1 bh Rp 140,000.00 Rp 140,000.00
Portland Semen 6 kg Rp 1,300.00 Rp 7,800.00
Pasir Pasang 0.01 m3 Rp 200,000.00 Rp 2,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 448,500.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

E. Overhead & Profit ( 10% ) Rp 44,850.00


F. Harga Satuan Pekerjaan ( D+E ) Rp 493,350.00
WASHTAFEL
1 Unit Memasang Wastafel
A. Tenaga Rp 95,875.00
Pekerja 1.2 OH Rp 55,000.00 Rp 66,000.00
Tukang Batu 0.145 OH Rp 75,000.00 Rp 10,875.00
Kepala Tukang 0.15 OH Rp 80,000.00 Rp 12,000.00
Mandor 0.1 OH Rp 70,000.00 Rp 7,000.00
B. Bahan Rp 367,300.00
Wastafel 1 bh Rp 275,000.00 Rp 275,000.00
Perlengkapan 30% Harga Wastafel 0.3 Rp 275,000.00 Rp 82,500.00
Portland Semen 6 kg Rp 1,300.00 Rp 7,800.00
Pasir Pasang 0.01 m3 Rp 200,000.00 Rp 2,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 463,175.00
E. Overhead & Profit ( 10% ) Rp 46,317.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 509,492.50
BAK MANDI
1 Unit Memasang Bak Mandi Batu Bata Vol. 0.30 m3
A. Tenaga Rp 581,100.00
Pekerja 6 OH Rp 55,000.00 Rp 330,000.00
Tukang Batu 3 OH Rp 75,000.00 Rp 225,000.00
Kepala Tukang 0.3 OH Rp 80,000.00 Rp 24,000.00
Mandor 0.03 OH Rp 70,000.00 Rp 2,100.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 529,392.00
Batu Bata 150 bh Rp 500.00 Rp 75,000.00
Portland Semen 120 kg Rp 1,300.00 Rp 156,000.00
Pasir Pasang 0.3 m3 Rp 200,000.00 Rp 60,000.00
Porselen 11 x 11 cm 360 bh Rp 512.20 Rp 184,392.00
Semen Nat 6 kg Rp 9,000.00 Rp 54,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 1,110,492.00
E. Overhead & Profit ( 10% ) Rp 111,049.20
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,221,541.20
FLOOR DRAIN
1 Buah Pemasangan Floor Drain
A. Tenaga Rp 9,200.00
Pekerja 0.01 OH Rp 55,000.00 Rp 550.00
Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00
B. Bahan Rp 15,000.00
Floor Drain 1 bh Rp 15,000.00 Rp 15,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 24,200.00
E. Overhead & Profit ( 10% ) Rp 2,420.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 26,620.00
KRAN AIR
1 Buah Pemasangan Kran diameter 1/2" atau 3/4"
A. Tenaga Rp 34,100.00
Pekerja 0.01 OH Rp 55,000.00 Rp 550.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Tukang Batu 0.4 OH Rp 75,000.00 Rp 30,000.00


Kepala Tukang 0.04 OH Rp 80,000.00 Rp 3,200.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00

B. Bahan Rp 15,009.75
Kran Air 1 bh Rp 15,000.00 Rp 15,000.00
Sealtape 0.0025 kg Rp 3,900.00 Rp 9.75

C. Peralatan
D. Jumlah ( A+B+C ) Rp 49,109.75
E. Overhead & Profit ( 10% ) Rp 4,910.98
F. Harga Satuan Pekerjaan ( D+E ) Rp 54,020.73
PIPA PVC DIAMETER 2.5"
1 m' Pemasangan Pipa PVC tipe AW diameter 2.5"
A. Tenaga Rp 15,940.00
Pekerja 0.081 OH Rp 55,000.00 Rp 4,455.00
Tukang Batu 0.135 OH Rp 75,000.00 Rp 10,125.00
Kepala Tukang 0.0135 OH Rp 80,000.00 Rp 1,080.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 51,666.66
Pipa PVC diameter 2.5" 1.2 m' Rp 33,333.33 Rp 40,000.00
Perlengkapan 35% x pipa 0.35 Ls Rp 33,333.33 Rp 11,666.67
C. Peralatan
D. Jumlah ( A+B+C ) Rp 67,606.66
E. Overhead & Profit ( 10% ) Rp 6,760.67
F. Harga Satuan Pekerjaan ( D+E ) Rp 74,367.33
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

PIPA PVC DIAMETER 4"


1 m' Pemasangan Pipa PVC tipe AW diameter 4"
A. Tenaga Rp 7,100.00
Pekerja 0.036 OH Rp 55,000.00 Rp 1,980.00
Tukang Batu 0.06 OH Rp 75,000.00 Rp 4,500.00
Kepala Tukang 0.006 OH Rp 80,000.00 Rp 480.00
Mandor 0.002 OH Rp 70,000.00 Rp 140.00
B. Bahan Rp 77,500.00
Pipa PVC diameter 4" 1.2 m' Rp 50,000.00 Rp 60,000.00
Perlengkapan 35% x pipa 0.35 Ls Rp 50,000.00 Rp 17,500.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 84,600.00
E. Overhead & Profit ( 10% ) Rp 8,460.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 93,060.00
BAK KONTROL
1 Buah Pemasangan Bak Kontrol Pas. Batu Bata 45 x 45 tinggi 50 cm
A. Tenaga Rp 264,250.00
Pekerja 3.2 OH Rp 55,000.00 Rp 176,000.00
Tukang Batu 1.15 OH Rp 75,000.00 Rp 86,250.00
Kepala Tukang 0.011 OH Rp 80,000.00 Rp 880.00
Mandor 0.016 OH Rp 70,000.00 Rp 1,120.00
B. Bahan Rp 203,100.00
Batu Bata 70 bh Rp 500.00 Rp 35,000.00
Portland Semen 77 kg Rp 1,300.00 Rp 100,100.00
Pasir Pasang 0.13 m3 Rp 200,000.00 Rp 26,000.00
Pasir Beton 0.09 m3 Rp 270,000.00 Rp 24,300.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Kerikil 0.02 m3 Rp 125,000.00 Rp 2,500.00


Baja Tulangan 1.6 kg Rp 9,500.00 Rp 15,200.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 467,350.00
E. Overhead & Profit ( 10% ) Rp 46,735.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 514,085.00
IX.A PEKERJAAN FINISHING
9.1 PEKERJAAN PEMASANGAN PLAFOND
GYSUM BOARD
1 m2 Memasang Langit-Langit Gypsum Board, Uk (120x240) tebal 9 mm
A. Tenaga Rp 10,070.00
Pekerja 0.1 OH Rp 55,000.00 Rp 5,500.00
Tukang Kayu 0.05 OH Rp 75,000.00 Rp 3,750.00
Kepala Tukang 0.005 OH Rp 80,000.00 Rp 400.00
Mandor 0.006 OH Rp 70,000.00 Rp 420.00
B. Bahan Rp 25,310.00
Gypsum Board 0.364 lbr Rp 65,000.00 Rp 23,660.00
Paku Sekrup 0.11 kg Rp 15,000.00 Rp 1,650.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 35,380.00
E. Overhead & Profit ( 10% ) Rp 3,538.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 38,918.00
RANGKA HOLLOW
1 m2 Pemasangan Rangka Besi Hollow 1 x 40.40.2 mm; Modul 60x60 cm dinding plafond
A. Tenaga Rp 49,560.00
Pekerja 0.35 OH Rp 55,000.00 Rp 19,250.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Tukang Besi 0.35 OH Rp 75,000.00 Rp 26,250.00


Kepala Tukang 0.035 OH Rp 80,000.00 Rp 2,800.00
Mandor 0.018 OH Rp 70,000.00 Rp 1,260.00
B. Bahan Rp 120,000.00
Rangka Metal Hollow 40.40.2 mm 4 m Rp 15,000.00 Rp 60,000.00
Aksessoris (perkuatan, las, dll ) 1 Rp 60,000.00 Rp 60,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 169,560.00
E. Overhead & Profit ( 10% ) Rp 16,956.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 186,516.00
LIST LANGIT - LANGIT KAYU PROFIL
1 m List Langit-Langit Kayu Profil
A. Tenaga Rp 7,110.00
Pekerja 0.05 OH Rp 55,000.00 Rp 2,750.00
Tukang Kayu 0.05 OH Rp 75,000.00 Rp 3,750.00
Kepala Tukang 0.005 OH Rp 80,000.00 Rp 400.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 5,170.00
List Kayu Profil 1.05 m Rp 4,800.00 Rp 5,040.00
Paku 0.01 kg Rp 13,000.00 Rp 130.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 12,280.00
E. Overhead & Profit ( 10% ) Rp 1,228.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 13,508.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

9.2 PEKERJAAN PASANGAN KERAMIK LANTA DAN DINDING


KERAMIK 20 X 20
1 m2 Pemasangan Lantai Keramik 20 x 20 cm
A. Tenaga Rp 70,000.00
Pekerja 0.7 OH Rp 55,000.00 Rp 38,500.00
Tukang Batu 0.35 OH Rp 75,000.00 Rp 26,250.00
Kepala Tukang 0.035 OH Rp 80,000.00 Rp 2,800.00
Mandor 0.035 OH Rp 70,000.00 Rp 2,450.00
B. Bahan Rp 94,340.00
Ubin Keramik 20 x 20 cm 26.5 bh Rp 2,160.00 Rp 57,240.00
Portland Semen 10.4 kg Rp 1,300.00 Rp 13,520.00
Semen Warna 1.62 kg Rp 9,000.00 Rp 14,580.00
Pasir Pasang 0.045 m3 Rp 200,000.00 Rp 9,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 164,340.00
E. Overhead & Profit ( 10% ) Rp 16,434.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 180,774.00
KERAMIK 30 X 30
1 m2 Pemasangan Lantai Keramik 30 x 30 cm
A. Tenaga Rp 70,000.00
Pekerja 0.7 OH Rp 55,000.00 Rp 38,500.00
Tukang Batu 0.35 OH Rp 75,000.00 Rp 26,250.00
Kepala Tukang 0.035 OH Rp 80,000.00 Rp 2,800.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Mandor 0.035 OH Rp 70,000.00 Rp 2,450.00


B. Bahan Rp 91,612.69
Keramik 30 x 30 cm 11.87 bh Rp 4,727.27 Rp 56,112.69
Portland Semen 10 kg Rp 1,300.00 Rp 13,000.00
Semen Warna 1.5 kg Rp 9,000.00 Rp 13,500.00
Pasir Pasang 0.045 m3 Rp 200,000.00 Rp 9,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 161,612.69
E. Overhead & Profit ( 10% ) Rp 16,161.27
F. Harga Satuan Pekerjaan ( D+E ) Rp 177,773.96
PLINT KERAMIK 10 X 20
1 m' Pemasangan Plint Keramik Ukuran 10 x 20 cm
A. Tenaga Rp 12,770.00
Pekerja 0.09 OH Rp 55,000.00 Rp 4,950.00
Tukang Batu 0.09 OH Rp 75,000.00 Rp 6,750.00
Kepala Tukang 0.009 OH Rp 80,000.00 Rp 720.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00
B. Bahan Rp 15,557.00
Ubin Keramik 5.3 bh Rp 2,500.00 Rp 13,250.00
Portland Semen 1.14 kg Rp 1,300.00 Rp 1,482.00
Pasir Pasang 0.003 m3 Rp 200,000.00 Rp 600.00
Semen Warna 0.025 kg Rp 9,000.00 Rp 225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 28,327.00
E. Overhead & Profit ( 10% ) Rp 2,832.70
F. Harga Satuan Pekerjaan ( D+E ) Rp 31,159.70

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

DINDING KERAMIK 20 X 20
1 m2 Pemasangan Dinding Keramik 20 x 20 cm
A. Tenaga Rp 90,000.00
Pekerja 0.9 OH Rp 55,000.00 Rp 49,500.00
Tukang Batu 0.45 OH Rp 75,000.00 Rp 33,750.00
Kepala Tukang 0.045 OH Rp 80,000.00 Rp 3,600.00
Mandor 0.045 OH Rp 70,000.00 Rp 3,150.00
B. Bahan Rp 83,070.00
Keramik 20 x 20 26 bh Rp 1,920.00 Rp 49,920.00
Portland Semen 9.3 kg Rp 1,300.00 Rp 12,090.00
Pasir Pasang 0.018 m3 Rp 200,000.00 Rp 3,600.00
Semen Warna 1.94 kg Rp 9,000.00 Rp 17,460.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 173,070.00
E. Overhead & Profit ( 10% ) Rp 17,307.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 190,377.00
9.3 PEKERJAAN PENGECETAN
CAT TEMBOK EXERIOR
1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Eksterior )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 89,500.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00


Cat Penutup 2 Kali ( Dulux Weather Shield 2.5 lit 1 ltr Rp 86,000.00 Rp 86,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 96,039.00
E. Overhead & Profit ( 10% ) Rp 9,603.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 105,642.90
CAT TEMBOK INTERIOR
1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Interior )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 58,300.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00
Cat Penutup 2 Kali ( Dulux 2.5 liter ) 1 ltr Rp 54,800.00 Rp 54,800.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 64,839.00
E. Overhead & Profit ( 10% ) Rp 6,483.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 71,322.90
CAT PLAFON
1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Plafond )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00


Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 58,300.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00
Cat Penutup 2 Kali ( Dulux 2.5 liter ) 1 ltr Rp 54,800.00 Rp 54,800.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 64,839.00
E. Overhead & Profit ( 10% ) Rp 6,483.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 71,322.90
CAT KUSEN
1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Kusen )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 43,500.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00
Cat Penutup 2 Kali ( Dulux 1 liter ) 1 kg Rp 40,000.00 Rp 40,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 50,039.00
E. Overhead & Profit ( 10% ) Rp 5,003.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 55,042.90

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

PEKERJAAN LANTAI 2
III.B PEKERJAAN STRUKTUR
3.2 PEKERJAAN KOLOM BETON BERTULANG K250
PEMBESIAN KOLOM
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
BEKISTING KOLOM
1 m2 Memasang Bekisting untuk Kolom
A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00
B. Bahan Rp 242,500.00
Kayu Klas III (Terentang) 0.04 m3 Rp 2,000,000.00 Rp 80,000.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00


Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00
Balok Kayu Klas II 0.015 m3 Rp 5,400,000.00 Rp 81,000.00
Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 2 btg Rp 18,000.00 Rp 36,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 308,500.00
E. Overhead & Profit ( 10% ) Rp 30,850.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 339,350.00
BETON COR K250
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 835,985.13
Portland Semen 384 kg Rp 1,300.00 Rp 499,200.00
Pasir Beton 692 kg Rp 192.86 Rp 133,459.12
Kerikil (Maksimum 30mm) 1039 kg Rp 192.59 Rp 200,101.01
Air 215 ltr Rp 15.00 Rp 3,225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 955,410.13
E. Overhead & Profit ( 10% ) Rp 95,541.01
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,050,951.14

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

3.4 PEKERJAAN BALOK RING BETON BERTULANG K250


PEMBESIAN BALOK
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
BEKISTING BALOK
1 m2 Memasang Bekisting untuk Balok
A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00
B. Bahan Rp 258,700.00
Kayu Klas III (Terentang) 0.04 m3 Rp 2,000,000.00 Rp 80,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00
Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Balok Kayu Klas II 0.018 m3 Rp 5,400,000.00 Rp 97,200.00


Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 2 btg Rp 18,000.00 Rp 36,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 324,700.00
E. Overhead & Profit ( 10% ) Rp 32,470.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 357,170.00
BETON COR K250
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 835,985.13
Portland Semen 384 kg Rp 1,300.00 Rp 499,200.00
Pasir Beton 692 kg Rp 192.86 Rp 133,459.12
Kerikil (Maksimum 30mm) 1039 kg Rp 192.59 Rp 200,101.01
Air 215 ltr Rp 15.00 Rp 3,225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 955,410.13
E. Overhead & Profit ( 10% ) Rp 95,541.01
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,050,951.14

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

3.6 PEKERJAAN PLAT LANTAI DAN ATAP


3.6.1 DAK K250
PEMBESIAN DAK
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
BEKISTING DAK
1 m2 Memasang Bekisting untuk Atap
A. Tenaga Rp 66,000.00
Pekerja 0.66 OH Rp 55,000.00 Rp 36,300.00
Tukang Kayu 0.33 OH Rp 75,000.00 Rp 24,750.00
Kepala Tukang 0.033 OH Rp 80,000.00 Rp 2,640.00
Mandor 0.033 OH Rp 70,000.00 Rp 2,310.00
B. Bahan Rp 314,500.00
Kayu Klas III (Terentang) 0.04 m3 Rp 2,000,000.00 Rp 80,000.00
Paku Biasa 2" - 5" 0.4 kg Rp 13,000.00 Rp 5,200.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Minyak Bekisting 0.2 ltr Rp 9,000.00 Rp 1,800.00


Balok Kayu Klas II (Borneo) 0.015 m3 Rp 5,400,000.00 Rp 81,000.00
Plywood tebal 9mm 0.35 lbr Rp 110,000.00 Rp 38,500.00
Dolken Kayu Galam diameter 8-10 cm / 4 m 6 btg Rp 18,000.00 Rp 108,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 380,500.00
E. Overhead & Profit ( 10% ) Rp 38,050.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 418,550.00
BETON COR K250
1 m3 Membuat Beton Mutu f'c = 21,7 Mpa (K250), slum (12±2)cm, w/c = 0.56
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 835,985.13
Portland Semen 384 kg Rp 1,300.00 Rp 499,200.00
Pasir Beton 692 kg Rp 192.86 Rp 133,459.12
Kerikil (Maksimum 30mm) 1039 kg Rp 192.59 Rp 200,101.01
Air 215 ltr Rp 15.00 Rp 3,225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 955,410.13
E. Overhead & Profit ( 10% ) Rp 95,541.01
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,050,951.14

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

3.6.3 TOPI - TOPI +6.30


PEMBESIAN TOPI - TOPI +6.30
10 Kg Pembesian dg Besi Polos atau Besi Ulir
A. Tenaga Rp 9,940.00
Pekerja 0.07 OH Rp 55,000.00 Rp 3,850.00
Tukang Besi 0.07 OH Rp 75,000.00 Rp 5,250.00
Kepala Tukang 0.007 OH Rp 80,000.00 Rp 560.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 133,425.00
Besi Beton (polos/ulir) 10.5 kg Rp 12,500.00 Rp 131,250.00
Kawat Beton 0.15 ltr Rp 14,500.00 Rp 2,175.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 143,365.00
E. Overhead & Profit ( 10% ) Rp 14,336.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 157,701.50
BETON COR K225
1 m3 Membuat Beton Mutu f'c = 19.3 Mpa (K225), slum (12±2)cm, w/c = 0.58
A. Tenaga Rp 119,425.00
Pekerja 1.65 OH Rp 55,000.00 Rp 90,750.00
Tukang Batu 0.275 OH Rp 75,000.00 Rp 20,625.00
Kepala Tukang 0.028 OH Rp 80,000.00 Rp 2,240.00
Mandor 0.083 OH Rp 70,000.00 Rp 5,810.00
B. Bahan Rp 821,783.01
Portland Semen 371 kg Rp 1,300.00 Rp 482,300.00
Pasir Beton 698 kg Rp 192.86 Rp 134,616.28
Kerikil (Maksimum 30mm) 1047 kg Rp 192.59 Rp 201,641.73
Air 215 ltr Rp 15.00 Rp 3,225.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

D. Jumlah ( A+B+C ) Rp 821,783.01


E. Overhead & Profit ( 10% ) Rp 82,178.30
F. Harga Satuan Pekerjaan ( D+E ) Rp 903,961.31
V.B PEKERJAAN PAS.BATU BATA DAN PLSTERAN
5.1 PEKERJAAN PASANGAN BATU BATA
PASANGAN BATU BATA 1 : 3
1 m2 Pemasangan Dinding Bata Merah Ukuran(5x11x22)cm Tebal 1/2 Bata Camp. 1PS : 3PP
A. Tenaga Rp 25,850.00
Pekerja 0.3 OH Rp 55,000.00 Rp 16,500.00
Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.015 OH Rp 70,000.00 Rp 1,050.00
B. Bahan Rp 61,681.00
Bata Merah 5 x 11 x 22 70 Buah Rp 500.00 Rp 35,000.00
Portland Semen 14.37 kg Rp 1,300.00 Rp 18,681.00
Pasir Pasang 0.04 m3 Rp 200,000.00 Rp 8,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 87,531.00
E. Overhead & Profit ( 10% ) Rp 8,753.10
F. Harga Satuan Pekerjaan ( D+E ) Rp 96,284.10
PASANGAN BATU BATA 1 : 5
1 m2 Pemasangan Dinding Bata Merah Ukuran(5x11x22)cm Tebal 1/2 Bata Camp. 1PS : 5PP
A. Tenaga Rp 25,850.00
Pekerja 0.3 OH Rp 55,000.00 Rp 16,500.00
Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Mandor 0.015 OH Rp 70,000.00 Rp 1,050.00


B. Bahan Rp 56,584.00
Bata Merah 5 x 11 x 22 70 Buah Rp 500.00 Rp 35,000.00
Portland Semen 9.68 kg Rp 1,300.00 Rp 12,584.00
Pasir Pasang 0.045 m3 Rp 200,000.00 Rp 9,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 82,434.00
E. Overhead & Profit ( 10% ) Rp 8,243.40
F. Harga Satuan Pekerjaan ( D+E ) Rp 90,677.40
5.2 PEKERJAAN PLESTERAN
PEKERJAAN PLESTERAN 1 : 3
1 m2 Pemasangan Plesteran 1PC : 3PP Tebal 20 mm
A. Tenaga Rp 31,810.00
Pekerja 0.26 OH Rp 55,000.00 Rp 14,300.00
Tukang Batu 0.2 OH Rp 75,000.00 Rp 15,000.00
Kepala Tukang 0.02 OH Rp 80,000.00 Rp 1,600.00
Mandor 0.013 OH Rp 70,000.00 Rp 910.00
B. Bahan Rp 19,678.40
Portland Semen 10.368 kg Rp 1,300.00 Rp 13,478.40
3
Pasir Pasang 0.031 m Rp 200,000.00 Rp 6,200.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 51,488.40
E. Overhead & Profit ( 10% ) Rp 5,148.84
F. Harga Satuan Pekerjaan ( D+E ) Rp 56,637.24

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

PEKERJAAN PLESTERAN 1 : 5
1 m2 Pemasangan Plesteran 1PC : 5PP Tebal 20 mm
A. Tenaga Rp 40,140.00
Pekerja 0.4 OH Rp 55,000.00 Rp 22,000.00
Tukang Batu 0.2 OH Rp 75,000.00 Rp 15,000.00
Kepala Tukang 0.02 OH Rp 80,000.00 Rp 1,600.00
Mandor 0.022 OH Rp 70,000.00 Rp 1,540.00
B. Bahan Rp 15,985.60
Portland Semen 6.912 kg Rp 1,300.00 Rp 8,985.60
3
Pasir Pasang 0.035 m Rp 200,000.00 Rp 7,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 56,125.60
E. Overhead & Profit ( 10% ) Rp 5,612.56
F. Harga Satuan Pekerjaan ( D+E ) Rp 61,738.16
VI.B PEKERJAAN KUSEN
PINTU DAN JENDELA
KUSEN PINTU ALUMUNIUM
1m' Pemasangan Kusen Pintu Allumunium
A. Tenaga Rp 6,081.00
Pekerja 0.043 OH Rp 55,000.00 Rp 2,365.00
Tukang Besi 0.043 OH Rp 75,000.00 Rp 3,225.00
Kepala Tukang 0.0043 OH Rp 80,000.00 Rp 344.00
Mandor 0.0021 OH Rp 70,000.00 Rp 147.00
B. Bahan Rp 92,500.00
Profil Allumunium 1.1 m' Rp 80,000.00 Rp 88,000.00
Skrup Fixer 2 bh Rp 750.00 Rp 1,500.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Seatant 0.06 tube Rp 50,000.00 Rp 3,000.00


C. Peralatan
D. Jumlah ( A+B+C ) Rp 98,581.00
E. Overhead & Profit ( 10% ) Rp 9,858.10
F. Harga Satuan Pekerjaan ( D+E ) Rp 108,439.10
DAUN PINTU
1 m2 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III
A. Tenaga Rp 107,660.00
Pekerja 0.35 OH Rp 55,000.00 Rp 19,250.00
Tukang Kayu 1.05 OH Rp 75,000.00 Rp 78,750.00
Kepala Tukang 0.105 OH Rp 80,000.00 Rp 8,400.00
Mandor 0.018 OH Rp 70,000.00 Rp 1,260.00
B. Bahan Rp 304,650.00
Kayu Klas II (Kamfer) papan 0.04 m3 Rp 7,600,000.00 Rp 304,000.00
Paku Biasa 2" - 5" 0.05 kg Rp 13,000.00 Rp 650.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 412,310.00
E. Overhead & Profit ( 10% ) Rp 41,231.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 453,541.00
KACA T = 8 mm
1 m2 Pemasangan Kaca tebal 8 mm
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 154,000.00
Kaca Tebal 8 mm 1.1 m2 Rp 140,000.00 Rp 154,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 167,327.50
E. Overhead & Profit ( 10% ) Rp 16,732.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 184,060.25
KACA T = 5 mm
1 m2 Pemasangan Kaca tebal 5 mm
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50
B. Bahan Rp 77,000.00
Kaca Tebal 5 mm 1.1 m2 Rp 70,000.00 Rp 77,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 90,327.50
E. Overhead & Profit ( 10% ) Rp 9,032.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 99,360.25
HANDEL
1 Buah Pemasangan Handle Pintu HINGE ES SL 9″ SN
A. Tenaga Rp 13,800.00
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.0075 OH Rp 70,000.00 Rp 525.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 50,000.00
Handle Pintu 1 bh Rp 50,000.00 Rp 50,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 63,800.00
E. Overhead & Profit ( 10% ) Rp 6,380.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 70,180.00
KACA BURAM
1 m2 Pemasangan Kaca Buram T = 5 mm
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50
B. Bahan Rp 68,750.00
Kaca Buram T = 5 mm 1.1 m2 Rp 62,500.00 Rp 68,750.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 82,077.50
E. Overhead & Profit ( 10% ) Rp 8,207.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 90,285.25
ENGSEL
1 Buah Pemasangan Engsel Pintu
A. Tenaga Rp 13,800.00
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.0075 OH Rp 70,000.00 Rp 525.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 6,000.00
Engsel Pintu 1 bh Rp 6,000.00 Rp 6,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 19,800.00
E. Overhead & Profit ( 10% ) Rp 1,980.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 21,780.00
MULTIPLEKS
1 m2 Pembuatan & Pemasangan Pintu Kayu Lapis ( Plywood ) Rangkap Rangka Kayu Klass II ( lbr s/d 90 cm )
A. Tenaga Rp 13,327.50
Pekerja 0.015 OH Rp 55,000.00 Rp 825.00
Tukang Kayu 0.15 OH Rp 75,000.00 Rp 11,250.00
Kepala Tukang 0.015 OH Rp 80,000.00 Rp 1,200.00
Mandor 0.00075 OH Rp 70,000.00 Rp 52.50
B. Bahan Rp 297,390.00
Kayu Klas II (Kamfer) papan 0.025 m3 Rp 7,600,000.00 Rp 190,000.00
Paku Biasa 1/2" - 1" 0.03 kg Rp 13,000.00 Rp 390.00
Lem Kayu 0.5 lbr Rp 18,000.00 Rp 9,000.00
Multipleks ( 9 mm ) 1 lbr Rp 98,000.00 Rp 98,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 310,717.50
E. Overhead & Profit ( 10% ) Rp 31,071.75
F. Harga Satuan Pekerjaan ( D+E ) Rp 341,789.25
PINTU KACA RANGKA ALUMUNIUM
1 m2 Pemasangan Pintu Kaca Rangka Allumunium
A. Tenaga Rp 12,120.00
Pekerja 0.085 OH Rp 55,000.00 Rp 4,675.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Tukang Besi 0.085 OH Rp 75,000.00 Rp 6,375.00


Kepala Tukang 0.009 OH Rp 80,000.00 Rp 720.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00
B. Bahan Rp 388,000.00
Pintu Allumunium 4.4 m' Rp 80,000.00 Rp 352,000.00
Profil Kaca 4.5 bh Rp 5,000.00 Rp 22,500.00
Seatant 0.27 tube Rp 50,000.00 Rp 13,500.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 400,120.00
E. Overhead & Profit ( 10% ) Rp 40,012.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 440,132.00
VII.B PEKERJAAN MECHANICAL DAN ELECTRICAL
VIII.B PEKERJAAN SANITASI
CLOSET JONGKOK
1 Unit Memasang Closet Jongkok Porselen
A. Tenaga Rp 298,700.00
Pekerja 1 OH Rp 55,000.00 Rp 55,000.00
Tukang Batu 1.5 OH Rp 75,000.00 Rp 112,500.00
Kepala Tukang 1.5 OH Rp 80,000.00 Rp 120,000.00
Mandor 0.16 OH Rp 70,000.00 Rp 11,200.00
B. Bahan Rp 149,800.00
Kloset Jongkok 1 bh Rp 140,000.00 Rp 140,000.00
Portland Semen 6 kg Rp 1,300.00 Rp 7,800.00
Pasir Pasang 0.01 m3 Rp 200,000.00 Rp 2,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 448,500.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

E. Overhead & Profit ( 10% ) Rp 44,850.00


F. Harga Satuan Pekerjaan ( D+E ) Rp 493,350.00
WASHTAFEL
1 Unit Memasang Wastafel
A. Tenaga Rp 95,875.00
Pekerja 1.2 OH Rp 55,000.00 Rp 66,000.00
Tukang Batu 0.145 OH Rp 75,000.00 Rp 10,875.00
Kepala Tukang 0.15 OH Rp 80,000.00 Rp 12,000.00
Mandor 0.1 OH Rp 70,000.00 Rp 7,000.00
B. Bahan Rp 367,300.00
Wastafel 1 bh Rp 275,000.00 Rp 275,000.00
Perlengkapan 30% Harga Wastafel 0.3 Rp 275,000.00 Rp 82,500.00
Portland Semen 6 kg Rp 1,300.00 Rp 7,800.00
Pasir Pasang 0.01 m3 Rp 200,000.00 Rp 2,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 463,175.00
E. Overhead & Profit ( 10% ) Rp 46,317.50
F. Harga Satuan Pekerjaan ( D+E ) Rp 509,492.50
BAK MANDI
1 Unit Memasang Bak Mandi Batu Bata Vol. 0.30 m3
A. Tenaga Rp 581,100.00
Pekerja 6 OH Rp 55,000.00 Rp 330,000.00
Tukang Batu 3 OH Rp 75,000.00 Rp 225,000.00
Kepala Tukang 0.3 OH Rp 80,000.00 Rp 24,000.00
Mandor 0.03 OH Rp 70,000.00 Rp 2,100.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

B. Bahan Rp 529,392.00
Batu Bata 150 bh Rp 500.00 Rp 75,000.00
Portland Semen 120 kg Rp 1,300.00 Rp 156,000.00
Pasir Pasang 0.3 m3 Rp 200,000.00 Rp 60,000.00
Porselen 11 x 11 cm 360 bh Rp 512.20 Rp 184,392.00
Semen Nat 6 kg Rp 9,000.00 Rp 54,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 1,110,492.00
E. Overhead & Profit ( 10% ) Rp 111,049.20
F. Harga Satuan Pekerjaan ( D+E ) Rp 1,221,541.20
FLOOR DRAIN
1 Buah Pemasangan Floor Drain
A. Tenaga Rp 9,200.00
Pekerja 0.01 OH Rp 55,000.00 Rp 550.00
Tukang Batu 0.1 OH Rp 75,000.00 Rp 7,500.00
Kepala Tukang 0.01 OH Rp 80,000.00 Rp 800.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00
B. Bahan Rp 15,000.00
Floor Drain 1 bh Rp 15,000.00 Rp 15,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 24,200.00
E. Overhead & Profit ( 10% ) Rp 2,420.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 26,620.00
KRAN AIR
1 Buah Pemasangan Kran diameter 1/2" atau 3/4"
A. Tenaga Rp 34,100.00
Pekerja 0.01 OH Rp 55,000.00 Rp 550.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Tukang Batu 0.4 OH Rp 75,000.00 Rp 30,000.00


Kepala Tukang 0.04 OH Rp 80,000.00 Rp 3,200.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00
B. Bahan Rp 15,009.75
Kran Air 1 bh Rp 15,000.00 Rp 15,000.00
Sealtape 0.0025 kg Rp 3,900.00 Rp 9.75

C. Peralatan
D. Jumlah ( A+B+C ) Rp 49,109.75
E. Overhead & Profit ( 10% ) Rp 4,910.98
F. Harga Satuan Pekerjaan ( D+E ) Rp 54,020.73
PIPA PVC DIAMETER 2.5"
1 m' Pemasangan Pipa PVC tipe AW diameter 2.5"
A. Tenaga Rp 15,940.00
Pekerja 0.081 OH Rp 55,000.00 Rp 4,455.00
Tukang Batu 0.135 OH Rp 75,000.00 Rp 10,125.00
Kepala Tukang 0.0135 OH Rp 80,000.00 Rp 1,080.00
Mandor 0.004 OH Rp 70,000.00 Rp 280.00
B. Bahan Rp 51,666.66
Pipa PVC diameter 2.5" 1.2 m' Rp 33,333.33 Rp 40,000.00
Perlengkapan 35% x pipa 0.35 Ls Rp 33,333.33 Rp 11,666.67
C. Peralatan
D. Jumlah ( A+B+C ) Rp 67,606.66
E. Overhead & Profit ( 10% ) Rp 6,760.67
F. Harga Satuan Pekerjaan ( D+E ) Rp 74,367.33

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

PIPA PVC DIAMETER 4"


1 m' Pemasangan Pipa PVC tipe AW diameter 4"
A. Tenaga Rp 7,100.00
Pekerja 0.036 OH Rp 55,000.00 Rp 1,980.00
Tukang Batu 0.06 OH Rp 75,000.00 Rp 4,500.00
Kepala Tukang 0.006 OH Rp 80,000.00 Rp 480.00
Mandor 0.002 OH Rp 70,000.00 Rp 140.00
B. Bahan Rp 77,500.00
Pipa PVC diameter 4" 1.2 m' Rp 50,000.00 Rp 60,000.00
Perlengkapan 35% x pipa 0.35 Ls Rp 50,000.00 Rp 17,500.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 84,600.00
E. Overhead & Profit ( 10% ) Rp 8,460.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 93,060.00
BAK KONTROL
1 Buah Pemasangan Bak Kontrol Pas. Batu Bata 45 x 45 tinggi 50 cm
A. Tenaga Rp 264,250.00
Pekerja 3.2 OH Rp 55,000.00 Rp 176,000.00
Tukang Batu 1.15 OH Rp 75,000.00 Rp 86,250.00
Kepala Tukang 0.011 OH Rp 80,000.00 Rp 880.00
Mandor 0.016 OH Rp 70,000.00 Rp 1,120.00
B. Bahan Rp 203,100.00
Batu Bata 70 bh Rp 500.00 Rp 35,000.00
Portland Semen 77 kg Rp 1,300.00 Rp 100,100.00
Pasir Pasang 0.13 m3 Rp 200,000.00 Rp 26,000.00
Pasir Beton 0.09 m3 Rp 270,000.00 Rp 24,300.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Kerikil 0.02 m3 Rp 125,000.00 Rp 2,500.00


Baja Tulangan 1.6 kg Rp 9,500.00 Rp 15,200.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 467,350.00
E. Overhead & Profit ( 10% ) Rp 46,735.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 514,085.00
IX.A PEKERJAAN FINISHING
9.1 PEKERJAAN PEMASANGAN PLAFOND
GYSUM BOARD
1 m2 Memasang Langit-Langit Gypsum Board, Uk (120x240) tebal 9 mm
A. Tenaga Rp 10,070.00
Pekerja 0.1 OH Rp 55,000.00 Rp 5,500.00
Tukang Kayu 0.05 OH Rp 75,000.00 Rp 3,750.00
Kepala Tukang 0.005 OH Rp 80,000.00 Rp 400.00
Mandor 0.006 OH Rp 70,000.00 Rp 420.00
B. Bahan Rp 25,310.00
Gypsum Board 0.364 lbr Rp 65,000.00 Rp 23,660.00
Paku Sekrup 0.11 kg Rp 15,000.00 Rp 1,650.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 35,380.00
E. Overhead & Profit ( 10% ) Rp 3,538.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 38,918.00
RANGKA HOLLOW
1 m2 Pemasangan Rangka Besi Hollow 1 x 40.40.2 mm; Modul 60x60 cm dinding plafond
A. Tenaga Rp 49,560.00
Pekerja 0.35 OH Rp 55,000.00 Rp 19,250.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH
Tukang Besi 0.35 OH Rp 75,000.00 Rp 26,250.00
Kepala Tukang 0.035 OH Rp 80,000.00 Rp 2,800.00
Mandor 0.018 OH Rp 70,000.00 Rp 1,260.00
B. Bahan Rp 120,000.00
Rangka Metal Hollow 40.40.2 mm 4 m Rp 15,000.00 Rp 60,000.00
Aksessoris (perkuatan, las, dll ) 1 Rp 60,000.00 Rp 60,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 169,560.00
E. Overhead & Profit ( 10% ) Rp 16,956.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 186,516.00
LIST LANGIT - LANGIT KAYU PROFIL
1 m List Langit-Langit Kayu Profil
A. Tenaga Rp 7,110.00
Pekerja 0.05 OH Rp 55,000.00 Rp 2,750.00
Tukang Kayu 0.05 OH Rp 75,000.00 Rp 3,750.00
Kepala Tukang 0.005 OH Rp 80,000.00 Rp 400.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 5,170.00
List Kayu Profil 1.05 m Rp 4,800.00 Rp 5,040.00
Paku 0.01 kg Rp 13,000.00 Rp 130.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 12,280.00
E. Overhead & Profit ( 10% ) Rp 1,228.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 13,508.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG

NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH


NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

9.2 PEKERJAAN PASANGAN KERAMIK LANTA DAN DINDING


KERAMIK 20 X 20
1 m2 Pemasangan Lantai Keramik 20 x 20 cm
A. Tenaga Rp 70,000.00
Pekerja 0.7 OH Rp 55,000.00 Rp 38,500.00
Tukang Batu 0.35 OH Rp 75,000.00 Rp 26,250.00
Kepala Tukang 0.035 OH Rp 80,000.00 Rp 2,800.00
Mandor 0.035 OH Rp 70,000.00 Rp 2,450.00
B. Bahan Rp 94,340.00
Ubin Keramik 20 x 20 cm 26.5 bh Rp 2,160.00 Rp 57,240.00
Portland Semen 10.4 kg Rp 1,300.00 Rp 13,520.00
Semen Warna 1.62 kg Rp 9,000.00 Rp 14,580.00
Pasir Pasang 0.045 m3 Rp 200,000.00 Rp 9,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 164,340.00
E. Overhead & Profit ( 10% ) Rp 16,434.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 180,774.00
KERAMIK 30 X 30
1 m2 Pemasangan Lantai Keramik 30 x 30 cm
A. Tenaga Rp 70,000.00
Pekerja 0.7 OH Rp 55,000.00 Rp 38,500.00
Tukang Batu 0.35 OH Rp 75,000.00 Rp 26,250.00
Kepala Tukang 0.035 OH Rp 80,000.00 Rp 2,800.00

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Mandor 0.035 OH Rp 70,000.00 Rp 2,450.00


B. Bahan Rp 91,612.69
Keramik 30 x 30 cm 11.87 bh Rp 4,727.27 Rp 56,112.69
Portland Semen 10 kg Rp 1,300.00 Rp 13,000.00
Semen Warna 1.5 kg Rp 9,000.00 Rp 13,500.00
Pasir Pasang 0.045 m3 Rp 200,000.00 Rp 9,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 161,612.69
E. Overhead & Profit ( 10% ) Rp 16,161.27
F. Harga Satuan Pekerjaan ( D+E ) Rp 177,773.96
PLINT KERAMIK 10 X 20
1 m' Pemasangan Plint Keramik Ukuran 10 x 20 cm
A. Tenaga Rp 12,770.00
Pekerja 0.09 OH Rp 55,000.00 Rp 4,950.00
Tukang Batu 0.09 OH Rp 75,000.00 Rp 6,750.00
Kepala Tukang 0.009 OH Rp 80,000.00 Rp 720.00
Mandor 0.005 OH Rp 70,000.00 Rp 350.00
B. Bahan Rp 15,557.00
Ubin Keramik 5.3 bh Rp 2,500.00 Rp 13,250.00
Portland Semen 1.14 kg Rp 1,300.00 Rp 1,482.00
Pasir Pasang 0.003 m3 Rp 200,000.00 Rp 600.00
Semen Warna 0.025 kg Rp 9,000.00 Rp 225.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 28,327.00
E. Overhead & Profit ( 10% ) Rp 2,832.70
F. Harga Satuan Pekerjaan ( D+E ) Rp 31,159.70

DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI


EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

DINDING KERAMIK 20 X 20
1 m2 Pemasangan Dinding Keramik 20 x 20 cm
A. Tenaga Rp 90,000.00
Pekerja 0.9 OH Rp 55,000.00 Rp 49,500.00
Tukang Batu 0.45 OH Rp 75,000.00 Rp 33,750.00
Kepala Tukang 0.045 OH Rp 80,000.00 Rp 3,600.00
Mandor 0.045 OH Rp 70,000.00 Rp 3,150.00
B. Bahan Rp 83,070.00
Keramik 20 x 20 26 bh Rp 1,920.00 Rp 49,920.00
Portland Semen 9.3 kg Rp 1,300.00 Rp 12,090.00
Pasir Pasang 0.018 m3 Rp 200,000.00 Rp 3,600.00
Semen Warna 1.94 kg Rp 9,000.00 Rp 17,460.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 173,070.00
E. Overhead & Profit ( 10% ) Rp 17,307.00
F. Harga Satuan Pekerjaan ( D+E ) Rp 190,377.00
9.3 PEKERJAAN PENGECETAN
CAT TEMBOK EXERIOR
1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Eksterior )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 89,500.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00


Cat Penutup 2 Kali ( Dulux Weather Shield 2.5 lit 1 ltr Rp 86,000.00 Rp 86,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 96,039.00
E. Overhead & Profit ( 10% ) Rp 9,603.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 105,642.90
CAT TEMBOK INTERIOR
1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Interior )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 58,300.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00
Cat Penutup 2 Kali ( Dulux 2.5 liter ) 1 ltr Rp 54,800.00 Rp 54,800.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 64,839.00
E. Overhead & Profit ( 10% ) Rp 6,483.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 71,322.90
CAT PLAFON
1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Plafond )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
DAFTAR ANALISA PEKERJAAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI
EDISI SEPTEMBER 2015 SEMARANG
NO URAIAN PEKERJAAN KOEF SAT HARGA BAHAN / UPAH (Rp) JUMLAH

Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00


Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 58,300.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00
Cat Penutup 2 Kali ( Dulux 2.5 liter ) 1 ltr Rp 54,800.00 Rp 54,800.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 64,839.00
E. Overhead & Profit ( 10% ) Rp 6,483.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 71,322.90
CAT KUSEN
1 m2 Pengecat Tembok Baru ( 1 Lap. Plamir, 1 Lap. Cat Dasar, 2 Lap. Cat Penutup ( Kusen )
A. Tenaga Rp 6,539.00
Pekerja 0.02 OH Rp 55,000.00 Rp 1,100.00
Tukang Batu 0.063 OH Rp 75,000.00 Rp 4,725.00
Kepala Tukang 0.0063 OH Rp 80,000.00 Rp 504.00
Mandor 0.003 OH Rp 70,000.00 Rp 210.00
B. Bahan Rp 43,500.00
Plamir 0.1 kg Rp 20,000.00 Rp 2,000.00
Cat Dasar 0.1 kg Rp 15,000.00 Rp 1,500.00
Cat Penutup 2 Kali ( Dulux 1 liter ) 1 kg Rp 40,000.00 Rp 40,000.00
C. Peralatan
D. Jumlah ( A+B+C ) Rp 50,039.00
E. Overhead & Profit ( 10% ) Rp 5,003.90
F. Harga Satuan Pekerjaan ( D+E ) Rp 55,042.90
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA
HARI ( OH ) ( OH ) ( ORANG ) PEK.
I PEKERJAAN PERSIAPAN
PEMBERSIHAN LAHAN 451.500 m2 7 Pekerja 0.1 45.150 6.450 7 11
Mandor 0.05 22.575 3.225 4

PENGUKURAN DAN BOWPLANG 97.500 m 7 Pekerja 0.1 9.750 1.393 2 6


Tukang Kayu 0.1 9.750 1.393 2
Kepala Tukang 0.01 0.975 0.139 1
Mandor 0.005 0.488 0.070 1

II PEKERJAAN PONDASI
GALIAN TANAH FOOTPLAT 259.000 m3 14 Pekerja 1.05 271.950 19.425 20 22
Mandor 0.067 17.353 1.240 2

PASIR URUG FOOTPLAT 7.390 m3 7 Pekerja 0.3 2.217 0.317 1 2


Mandor 0.01 0.074 0.011 1

LANTAI KERJA FOOTPLAT K 100 3.680 m3 7 Pekerja 1.200 4.416 0.631 1 4


Tukang Batu 0.200 0.736 0.105 1
Kepala Tukang 0.020 0.074 0.011 1
Mandor 0.006 0.022 0.003 1
PEK. PONDASI FOOTPLAT 14
PEMBESIAN PONDASI FOOTPLAT 1843.721 kg Pekerja 0.070 129.060 9.219 10 22
Tukang Besi 0.070 129.060 9.219 10
Kepala Tukang 0.007 12.906 0.922 1
Mandor 0.004 7.375 0.527 1

BEKISTING PONDASI FOOTPLAT 22.920 m2 Pekerja 0.520 11.918 0.851 1 4


Tukang Kayu 0.260 5.959 0.426 1
Kepala Tukang 0.026 0.596 0.043 1
Mandor 0.026 0.596 0.043 1

BETON COR PONDASI FOOTPLAT K250 26.585 m3 Pekerja 1.650 43.865 3.133 4 7
Tukang Batu 0.275 7.311 0.522 1
Kepala Tukang 0.028 0.744 0.053 1
Mandor 0.083 2.207 0.158 1

URUGAN TANAH KEMBALI FOOTPLAT 225.800 m3 21 Pekerja 0.500 112.900 5.376 6 7


Mandor 0.050 11.290 0.538 1
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA
HARI ( OH ) ( OH ) ( ORANG ) PEK.
PASIR URUG BATU KALI 19.860 7 Pekerja 0.300 5.958 0.851 1 7
Mandor 0.010 0.199 0.028 1

AANSTAMPING 39.720 7 Pekerja 0.78 30.982 4.426 5 10


Tukang Batu 0.39 15.491 2.213 3
Kepala Tukang 0.039 1.549 0.221 1
Mandor 0.039 1.549 0.221 1

PAS. BATU BELAH 87.384 14 Pekerja 1.500 131.076 9.363 10 17


Tukang Batu 0.750 65.538 4.681 5
Kepala Tukang 0.075 6.554 0.468 1
Mandor 0.075 6.554 0.468 1

URUGAN TANAH BATU KALI 317.264 14 Pekerja 0.500 158.632 11.331 12 14


Mandor 0.050 15.863 1.133 2

III PEKERJAAN STRUKTUR


PEKERJAAN LANTAI 1
PEKERJAAN SLOOF 21
SLOOF Pembesian 2402.367 kg Pekerja 0.070 168.166 8.008 9 20
Tukang Besi 0.070 168.166 8.008 9
Kepala Tukang 0.007 16.817 0.801 1
Mandor 0.004 9.609 0.458 1

SLOOF Bekisting 157.900 m2 Pekerja 0.520 82.108 3.910 4 8


Tukang Kayu 0.260 41.054 1.955 2
Kepala Tukang 0.026 4.105 0.195 1
Mandor 0.026 4.105 0.195 1

SLOOF Beton Cor K-225 15.693 m3 Pekerja 1.650 25.893 1.233 2 5


Tukang Batu 0.275 4.316 0.206 1
Kepala Tukang 0.028 0.439 0.021 1
Mandor 0.083 1.303 0.062 1
PEKERJAAN KOLOM 21
KOLOM Pembesian 5217.761 kg Pekerja 0.070 365.243 17.393 18 39
Tukang Besi 0.070 365.243 17.393 18
Kepala Tukang 0.007 36.524 1.739 2
Mandor 0.004 20.871 0.994 1

KOLOM Bekisting 280.350 m2 Pekerja 0.660 185.031 8.811 9 16


Tukang Kayu 0.330 92.516 4.406 5
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Kepala Tukang 0.033 9.252 0.441 1


Mandor 0.033 9.252 0.441 1
WKT KOEF. JUMLAH MAN POWER TTL
NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
KOLOM Beton Cor K-250 19.339 m3 Pekerja 1.650 31.909 1.519 2 5
Tukang Batu 0.275 5.318 0.253 1
Kepala Tukang 0.028 0.541 0.026 1
Mandor 0.083 1.605 0.076 1
PEKERJAAN BALOK 14
2
BALOK Bekisting 305.481 m Pekerja 0.660 201.617 14.401 15 25
Tukang Kayu 0.330 100.809 7.201 8
Kepala Tukang 0.033 10.081 0.720 1
Mandor 0.033 10.081 0.720 1

BALOK Pembesian 4497.642 kg Pekerja 0.070 314.835 22.488 23 51


Tukang Besi 0.070 314.835 22.488 23
Kepala Tukang 0.007 31.483 2.249 3
Mandor 0.004 17.991 1.285 2

BALOK Beton Cor K-225 26.263 m3 Pekerja 1.650 43.334 3.095 4 7


Tukang Batu 0.275 7.222 0.516 1
Kepala Tukang 0.028 0.735 0.053 1
Mandor 0.083 2.180 0.156 1
PEKERJAAN TANGGA 14
2
TANGGA Bekisting 15.262 m Pekerja 0.660 10.073 0.719 1 4
Tukang Kayu 0.330 5.036 0.360 1
Kepala Tukang 0.033 0.504 0.036 1
Mandor 0.033 0.504 0.036 1

TANGGA Pembesian 407.504 kg Pekerja 0.070 28.525 2.038 3 8


Tukang Besi 0.070 28.525 2.038 3
Kepala Tukang 0.007 2.853 0.204 1
Mandor 0.004 1.630 0.116 1

TANGGA Beton Cor K-250 2.865 m3 Pekerja 1.650 4.727 0.338 1 4


Tukang Batu 0.275 0.788 0.056 1
Kepala Tukang 0.028 0.080 0.006 1
Mandor 0.083 0.238 0.017 1
PEK.PLAT LANTAI II 21
PLAT LT. II Bekisting 268.993 m2 Pekerja 0.660 177.535 8.454 9 16
Tukang Kayu 0.330 88.768 4.227 5
Kepala Tukang 0.033 8.877 0.423 1
Mandor 0.033 8.877 0.423 1
PLAT LT. II Pembesian 2821.872 kg Pekerja 0.070 197.531 9.406 10 22
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Tukang Besi 0.070 197.531 9.406 10


Kepala Tukang 0.007 19.753 0.941 1
Mandor 0.004 11.287 0.537 1
WKT KOEF. JUMLAH MAN POWER TTL
NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
PLAT LT. II Beton Cor K-250 31.344 m3 Pekerja 1.650 51.718 2.463 3 6
Tukang Batu 0.275 8.620 0.410 1
Kepala Tukang 0.028 0.878 0.042 1
Mandor 0.083 2.602 0.124 1
PEK.TOPI-TOPI +3.17 7
2
TOPI - TOPI + 3.17 Bekisting 32.160 m Pekerja 0.660 21.226 3.032 4 8
Tukang Kayu 0.330 10.613 1.516 2
Kepala Tukang 0.033 1.061 0.152 1
Mandor 0.033 1.061 0.152 1

TOPI - TOPI + 3.17 Pembesian 168.127 kg Pekerja 0.070 11.769 1.681 2 6


Tukang Besi 0.070 11.769 1.681 2
Kepala Tukang 0.007 1.177 0.168 1
Mandor 0.004 0.673 0.096 1

TOPI - TOPI + 3.17 Beton Cor K-225 2.898 m3 Pekerja 1.650 4.782 0.683 1 4
Tukang Batu 0.275 0.797 0.114 1
Kepala Tukang 0.028 0.081 0.012 1
Mandor 0.083 0.241 0.034 1

PEKERJAAN LANTAI II
PEKERJAAN KOLOM 21
KOLOM Pembesian 2089.834 kg Pekerja 0.07 146.288 6.966 7 16
Tukang Besi 0.07 146.288 6.966 7
Kepala Tukang 0.007 14.629 0.697 1
Mandor 0.004 8.359 0.398 1

KOLOM Bekisting 162.450 m2 Pekerja 0.660 107.217 5.106 6 11


Tukang Kayu 0.330 53.609 2.553 3
Kepala Tukang 0.033 5.361 0.255 1
Mandor 0.033 5.361 0.255 1

KOLOM Beton Cor K-250 10.248 m3 Pekerja 1.650 16.909 0.805 1 4


Tukang Batu 0.275 2.818 0.134 1
Kepala Tukang 0.028 0.287 0.014 1
Mandor 0.083 0.851 0.041 1
PEKERJAAN BALOK 14
BALOK RING Pembesian 1135.722 kg Pekerja 0.07 79.501 5.679 6 14
Tukang Besi 0.07 79.501 5.679 6
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Kepala Tukang 0.007 7.950 0.568 1


Mandor 0.004 4.543 0.324 1

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
BALOK RING Bekisting 136.600 m2 Pekerja 0.660 90.156 6.440 7 13
Tukang Kayu 0.330 45.078 3.220 4
Kepala Tukang 0.033 4.508 0.322 1
Mandor 0.033 4.508 0.322 1

BALOK RING Beton Cor K-225 8.069 m3 Pekerja 1.650 13.314 0.951 1 4
Tukang Batu 0.275 2.219 0.158 1
Kepala Tukang 0.028 0.226 0.016 1
Mandor 0.083 0.670 0.048 1
PEKERJAAN PLAT ATAP 28
PLAT ATAP Bekisting 273.620 m2 Pekerja 0.660 180.589 6.450 7 13
Tukang Kayu 0.330 90.295 3.225 4
Kepala Tukang 0.033 9.029 0.322 1
Mandor 0.033 9.029 0.322 1

PLAT ATAP Pembesian 2821.872 kg Pekerja 0.070 197.531 7.055 8 18


Tukang Besi 0.070 197.531 7.055 8
Kepala Tukang 0.007 19.753 0.705 1
Mandor 0.004 11.287 0.403 1

PLAT ATAP Beton Cor K-250 31.344 m3 Pekerja 1.650 51.718 1.847 2 5
Tukang Batu 0.275 8.620 0.308 1
Kepala Tukang 0.028 0.878 0.031 1
Mandor 0.083 2.602 0.093 1
PEK.TOPI-TOPI +6.30 14
2
TOPI-TOPI +6.30 Bekisting 26.460 m 7 Pekerja 0.660 17.464 1.247 2 5
Tukang Kayu 0.330 8.732 0.624 1
Kepala Tukang 0.033 0.873 0.062 1
Mandor 0.033 0.873 0.062 1

TOPI-TOPI +6.30 Pembesian 134.370 kg 7 Pekerja 0.070 9.406 0.672 1 4


Tukang Besi 0.070 9.406 0.672 1
Kepala Tukang 0.007 0.941 0.067 1
Mandor 0.004 0.537 0.038 1

TOPI-TOPI +6.30 Beton Cor K-225 2.356 m3 7 Pekerja 1.650 3.887 0.278 1 4
Tukang Batu 0.275 0.648 0.046 1
Kepala Tukang 0.028 0.066 0.005 1
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Mandor 0.083 0.196 0.014 1

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
V PEKERJAAN PASANGAN BATU BATA DAN PLESTERAN
PAS. BATA 658.548 m2 35 Pekerja 0.300 197.564 5.645 6 10
Tukang Batu 0.100 65.855 1.882 2
Kepala Tukang 0.010 6.585 0.188 1
Mandor 0.015 9.878 0.282 1

PLESTERAN 658.548 m2 21 Pekerja 0.260 171.222 8.153 9 18


Tukang Batu 0.200 131.710 6.272 7
Kepala Tukang 0.020 13.171 0.627 1
Mandor 0.013 8.561 0.408 1

VI PEKERJAAN KUSEN
KUSEN ALMUNIUM 410.420 m 14 Pekerja 0.043 17.648 1.261 2 6
Tukang Besi 0.043 17.648 1.261 2
Kepala Tukang 0.004 1.765 0.126 1
Mandor 0.002 0.862 0.062 1

DAUN KUSEN 171.825 m2 14 Pekerja 0.350 60.139 4.296 5 21


Tukang Kayu 1.050 180.416 12.887 13
Kepala Tukang 0.105 18.042 1.289 2
Mandor 0.018 3.093 0.221 1

KACA BURAM, T 5 MM, T 8 MM 63.871 m2 7 Pekerja 0.015 0.958 0.137 1 5


Tukang Kayu 0.150 9.581 1.369 2
Kepala Tukang 0.015 0.958 0.137 1
Mandor 0.001 0.048 0.007 1

GYSUM 3.956 m2 14 Pekerja 0.100 0.396 0.028 1 4


Tukang Kayu 0.050 0.198 0.014 1
Kepala Tukang 0.005 0.020 0.001 1
Mandor 0.006 0.024 0.002 1

MULTIPLEKS 18.540 m2 14 Pekerja 0.015 0.278 0.020 1 4


Tukang Kayu 0.150 2.781 0.199 1
Kepala Tukang 0.015 0.278 0.020 1
Mandor 0.00075 0.014 0.001 1
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

AKSESORIES KUSEN 208.000 bh 7 Pekerja 0.015 3.120 0.446 1 8


Tukang Kayu 0.150 31.200 4.457 5
Kepala Tukang 0.015 3.120 0.446 1
Mandor 0.008 1.560 0.223 1

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA ( OH ) ( ORANG ) PEK.
HARI ( OH )
VII PEKERJAAN MECHANICAL AND ELECTRICAL
PROPERTIES DAN INSTALASI M & E LT. 1 184 ttk 14 Pekerja 0.48 88.320 6.309 7 9
Tukang Listrik 0.048 8.832 0.631 1
Kepala Tukang 0.048 8.832 0.631 1

VIII PEKERJAAN SANITASI


INSTALASI PIPA AIR KOTOR 75.000 m 14 Pekerja 0.036 2.700 0.193 1 4
Tukang Batu 0.06 4.500 0.321 1
Kepala Tukang 0.006 0.450 0.032 1
Mandor 0.002 0.150 0.011 1

SEPTICTANK 7.795 m3 7 Pekerja 1.65 12.862 1.837 2 5


Tukang Batu 0.275 2.144 0.306 1
Kepala Tukang 0.028 0.218 0.031 1
Mandor 0.083 0.647 0.092 1

INSTALASI PIPA AIR BERSIH 95.000 m 14 Pekerja 0.081 7.695 0.550 1 4


Tukang Batu 0.135 12.825 0.916 1
Kepala Tukang 0.0135 1.283 0.092 1
Mandor 0.004 0.380 0.027 1

PEMASANGAN PROPERTIES SANITASI 38 bh 28 Pekerja 6 228.000 8.143 9 16


Tukang Batu 3 114.000 4.071 5
Kepala Tukang 0.3 11.400 0.407 1
Mandor 0.03 1.140 0.041 1

IX PEKERJAAN FINISHING
PEKERJAAN PEMASANGAN PLAFON
RANGKA HOLLOW 505.800 m2 21 Pekerja 0.350 177.030 8.430 9 20
Tukang Besi 0.350 177.030 8.430 9
Kepala Tukang 0.035 17.703 0.843 1
Mandor 0.018 9.104 0.434 1

PLAFON TYPE A, B, DAN C (GYSUM BOA 597.063 m2 14 Pekerja 0.1 59.706 4.265 5 10
Tukang Kayu 0.05 29.853 2.132 3
Kepala Tukang 0.005 2.985 0.213 1
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Mandor 0.006 3.582 0.256 1

LIST LANGIT-LANGIT KAYU PROFIL 428.000 m 7 Pekerja 0.050 21.400 3.057 4 10


Tukang Kayu 0.050 21.400 3.057 4
Kepala Tukang 0.005 2.140 0.306 1
Mandor 0.003 1.284 0.183 1

WKT KOEF. JUMLAH MAN POWER TTL


NO JENIS PEKERJAAN VOLUME JENIS PEKERJA
HARI ( OH ) ( OH ) ( ORANG ) PEK.
PEKERJAAN PASANGAN KERAMIK LANTAI DAN DINDING
H.4 URUGAN PASIR BAWAH ( T = 10 CM 50.580 m3 7 Pekerja 0.300 15.174 2.168 3 4
Mandor 0.010 0.506 0.072 1

H.5 LANTAI KERJA ( T = 5 CM ) BAWAH 25.291 m3 14 Pekerja 1.200 30.349 2.168 3 6


Tukang Batu 0.200 5.058 0.361 1
Kepala Tukang 0.020 0.506 0.036 1
Mandor 0.006 0.152 0.011 1
H.6 PLINT KERAMIK 10 X 20 CM 261.430 m 14 Pekerja 0.090 23.529 1.681 2 6
Tukang Batu 0.090 23.529 1.681 2
Kepala Tukang 0.009 2.353 0.168 1
Mandor 0.005 1.307 0.093 1

H.7 KERAMIK DINDING KM/WC&LAB. UK 20 52.440 m2 14 Pekerja 0.900 47.196 3.371 4 8


Tukang Batu 0.450 23.598 1.686 2
Kepala Tukang 0.045 2.360 0.169 1
Mandor 0.045 2.360 0.169 1

H.8 P.KERAMIK LANTAI RUANGAN DAN KM/WC 546.540 m2 28 Pekerja 0.700 382.578 13.664 14 23
Tukang Batu 0.350 191.289 6.832 7
Kepala Tukang 0.035 19.129 0.683 1
Mandor 0.035 19.129 0.683 1

H.9 URUGAN PASIR BAWAH LANTAI RABAT BETON 1.858 m3 7 Pekerja 0.300 0.557 0.080 1 2
Mandor 0.010 0.019 0.003 1

H.10 LANTAI RABAT BETON KORIDOR ( T = 7 CM ) 1.300 m3 7 Pekerja 1.200 1.560 0.223 1 4
Tukang Batu 0.200 0.260 0.037 1
Kepala Tukang 0.020 0.026 0.004 1
Mandor 0.006 0.008 0.001 1

PEKERJAAN PENGECATAN
H.11 CAT TEMBOK, PLAFON DAN KUSEN 2404.060 m2 14 Pekerja 0.020 48.081 3.434 4 18
Tukang Batu 0.063 151.456 10.818 11
Kepala Tukang 0.006 15.146 1.082 2
ANALISA KEBUTUHAN TENAGA KERJA PEMBANGUNAN GED. PMI BOYOLALI

Mandor 0.003 7.212 0.515 1


TIME SCHEDULE (KURVA S) PEMBANGUNAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

DURASI BULAN KE- 1 BULAN KE- 2 BULAN KE- 3 BULAN KE- 4 BULAN KE- 5 BULAN KE- 6
NO JENIS PEKERJAAN URAIAN PEKER JAAN BOBOT
(MINGGU) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
I 1.1 PEKERJAAN PERSIAPAN ADMINISTRASI 0.379% 24 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016% 0.016%
1.2 PEMBERSIHAN LAHAN 0.212% 1 0.212%
1.3 PENGUKURAN DAN BOWPLANG 0.616% 1 0.616%
II 2.1 PEKERJAAN PONDASI GALIAN TANAH FOOTPLAT 0.842% 2 0.459% 0.383%
2.2 PASIR URUG FOOTPLAT 0.062% 1 0.062%
2.3 LANTAI KERJA FOOTPLAT K 100 0.145% 1 0.145%
2.4 PEK.PONDASI FOOTPLAT 2.863% 2 1.301% 1.562%
2.5 URUGAN TANAH KEMBALI FOOTPLAT 0.365% 3 0.156% 0.156% 0.052%
2.6 PASIR URUG BATU KALI 0.167% 1 0.167%
2.7 AANSTAMPING 0.740% 1 0.740%
2.8 PAS. BATU BELAH 3.021% 2 0.711% 2.310%
2.9 URUGAN TANAH BATU KALI 0.512% 2 0.220% 0.293%
III 3.1 PEKERJAAN STRUKTUR PEKERJAAN SLOOF K-225 3.770% 3 0.343% 0.914% 2.513%
3.2 PEKERJAAN LANTAI 1 PEKERJAAN KOLOM K-250 9.364% 3 6.867% 2.341% 0.156%
3.3 PEKERJAAN BALOK K-250 9.833% 2 3.910% 5.923%
3.4 PEKERJAAN TANGGA K-250 0.676% 2 0.423% 0.254%
3.5 PEK.PLAT LANTAI II K-250 8.999% 3 6.136% 2.454% 0.409%
3.6 PEK.TOPI-TOPI +3.17 K-225 0.905% 1 0.905%
3.7 PEKERJAAN LANTAI 2 PEKERJAAN KOLOM K-250 4.682% 3 4.229% 0.302% 0.151%
3.8 PEKERJAAN BALOK RING K-250 3.560% 2 1.952% 1.608%
3.9 PEK.PLAT ATAP K-250 9.090% 4 0.253% 3.030% 2.778% 3.030%
3.10 PEK.TOPI-TOPI+6.30 K-225 0.740% 2 0.398% 0.342%
V 5.1 PEK. PAS.BT. BATA & PLESTERAN PAS. BATA 2.835% 5 1.134% 0.284% 0.284% 0.567% 0.567%
5.2 PLESTERAN 1.919% 3 1.188% 0.457% 0.274%
VI 6.1 PEKERJAAN KUSEN KUSEN ALMUNIUM 2.108% 2 1.756% 0.351%
6.2 DAUN KUSEN 3.690% 2 1.757% 1.933%
6.3 KACA BURAM, T 5 MM, T 8 MM 0.428% 1 0.428%
6.4 GYSUM 0.007% 2 0.002% 0.005%
6.5 MULTIPLEK 0.300% 2 0.150% 0.150%
6.6 AKSESORIES KUSEN 0.338% 1 0.338%
VII 7.1 PEKERJAAN M & E PROPERTIES DAN INSTALASI M & E 3.086% 2 2.057% 1.029%
VIII 8.1 PEKERJAAN SANITASI INSTALASI PIPA AIR BERSIH 0.335% 2 0.167% 0.167%
8.2 INSTALASI PIPA AIR KOTOR 0.331% 2 0.165% 0.165%
8.3 SEPTICTANK 0.061% 1 0.061%
8.4 PEMASANGAN PROPERTIES SANITASI 0.941% 4 0.529% 0.118% 0.235% 0.059%
IX 9.1 PEKERJAAN FINISHING RANGKA HOLLOW 4.468% 3 2.010% 1.787% 0.670%
9.2 PLAFON TYPE A, B, DAN C (GYSUM BOARD) 1.100% 2 0.110% 0.990%
9.3 LIST LANGIT-LANGIT KAYU PROFIL 0.274% 1 0.274%
9.4 URUGAN PASIR BAWAH ( T = 10 CM ) 0.425% 1 0.425%
9.5 LANTAI KERJA ( T = 5 CM ) BAWAH LANTAI 0.995% 2 0.332% 0.663%
9.6 PLINT KERAMIK 10 X 20 CM 0.386% 2 0.193% 0.193%
9.7 KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM 0.601% 2 0.301% 0.301%
9.8 PEMASANGAN KERAMIK LANTAI RUANGAN DAN KM/WC 4.475% 4 0.195% 2.140% 1.946% 0.195%
9.9 URUGAN PASIR BAWAH LANTAI RABAT BETON KORIDO 0.016% 1
9.10 LANTAI RABAT BETON KORIDOR ( T = 7 CM ) 0.051% 1
9.11 CAT TEMBOK, PLAFON DAN KUSEN 9.287% 2
JUMLAH 100.00% 0.227% 0.631% 0.475% 0.606% 1.473% 1.734% 2.029% 3.792% 3.215% 6.883% 6.266% 6.095% 10.799% 6.648% 3.090% 5.636% 5.979% 5.809% 4.133% 5.848% 5.729% 3.514%
JUMLAH KUMULATIF 0.227% 0.859% 1.334% 1.939% 3.413% 5.146% 7.175% 10.967% 14.182% 21.064% 27.331% 33.426% 44.225% 50.874% 53.963% 59.599% 65.578% 71.387% 75.519% 81.368% 87.097% 90.611%
MBANGUNAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

BULAN KE- 6
23 24
0.016% 0.016%

0.016%
0.051%
7.223% 2.064%
7.255% 2.131%
97.866% 100.00%
GRAFIK MAN POWER PEMBANGUNAN GEDUNG PMI CAB. BOYOLALI : KABUPATEN BOYOLALI

JUMLAH DURASI BULAN KE- 1 BULAN KE- 2 BULAN KE- 3 BULAN KE- 4 BULAN KE- 5 BULAN KE- 6
NO JENIS PEKERJAAN URAIAN PEKER JAAN
PEKERJA (MINGGU) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
I 1.1 PEKERJAAN PERSIAPAN ADMINISTRASI 20 24 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1.2 PEMBERSIHAN LAHAN 55 1 55
1.3 PENGUKURAN DAN BOWPLANG 30 1 30
II 2.1 PEKERJAAN PONDASI GALIAN TANAH FOOTPLAT 110 2 60 50
2.2 PASIR URUG FOOTPLAT 10 1 10
2.3 LANTAI KERJA FOOTPLAT K 100 20 1 20
2.4 PEK.PONDASI FOOTPLAT 165 2 75 90
2.5 URUGAN TANAH KEMBALI FOOTPLAT 35 3 15 15 5
2.6 PASIR URUG BATU KALI 35 1 35
2.7 AANSTAMPING 50 1 50
2.8 PAS. BATU BELAH 85 2 20 65
2.9 URUGAN TANAH BATU KALI 70 2 30 40
III 3.1 PEKERJAAN STRUKTUR PEK. SLOOF K-225 165 3 15 40 110
3.2 PEKERJAAN LANTAI I PEK KOLOM K-250 300 3 220 75 5
3.3 PEK. BALOK K-250 415 2 165 250
3.4 PEK.TANGGA K-250 80 2 50 30
3.5 PEK. PLAT LANTAI II K-250 220 3 150 60 10
3.6 PEK. TOPI - TOPI K-225 90 1 90
3.7 PEKERJAAN LANTAI 2 PEK. KOLOM K-250 155 3 140 10 5
3.8 PEK.BALOK RING K-250 155 2 85 70
3.9 PEK.PLAT ATAP K-250 180 4 5 60 55 60
3.10 PEK.TOPI-TOPI +630 K-225 65 2 35 30
V 5.1 PEK. PAS.BT. BATA & PLESTERAN PAS. BATA 50 5 20 5 5 10 10
5.2 PLESTERAN 105 3 65 25 15
VI 6.1 PEKERJAAN KUSEN KUSEN ALMUNIUM 30 2 25 5
6.2 DAUN KUSEN 105 2 50 55
6.3 KACA BURAM, T 5 MM, T 8 MM 25 1 25
6.4 GYSUM 20 2 5 15
6.5 MULTIPLEKS 20 2 10 10
6.6 AKSESORIES KUSEN 40 1 40
VII 7.1 PEKERJAAN M & E PROPERTIES DAN INSTALASI M & E LT. 1 45 2 30 15
VIII 8.1 PEKERJAAN SANITASI INSTALASI PIPA AIR KOTOR 20 2 10 10
8.2 INSTALASI PIPA AIR BERSIH 20 2 10 10
8.3 SEPTICTANK 25 1 25
8.4 PEMASANGAN PROPERTIES SANITASI 80 4 45 10 20 5
IX 9.1 PEKERJAAN FINISHING RANGKA HOLLOW 100 3 45 40 15
9.2 PLAFON TYPE A, B, DAN C (GYSUM BOARD) 50 2 5 45
9.3 LIST LANGIT-LANGIT KAYU PROFIL 50 1 50
9.4 URUGAN PASIR BAWAH ( T = 10 CM ) 20 1 20
9.5 LANTAI KERJA ( T = 5 CM ) BAWAH LANTAI 30 2 10 20
9.6 PLINT KERAMIK 10 X 20 CM 30 2 15 15
9.7 KERAMIK DINDING KM/WC DAN LAB. UK 20 X 20 CM 40 2 20 20
9.8 PEMASANGAN KERAMIK LANTAI RUANGAN DAN KM/WC 115 4 5 55 50 5
9.9 URUGAN PASIR BAWAH LANTAI RABAT BETON KORIDOR 10 1 10
9.10 LANTAI RABAT BETON KORIDOR ( T = 7 CM ) 20 1 20
9.11 CAT TEMBOK, PLAFON DAN KUSEN 90 2 70 20
JUMLAH 56 31 61 81 91 106 126 156 196 221 241 256 246 241 226 216 196 186 171 161 151 116 81 41
JUMLAH KUMULATIF 56 87 148 229 319 425 551 707 903 1124 1364 1620 1866 2107 2333 2549 2744 2930 3101 3262 3413 3528 3609 3650