PERHITUNGAN VOLUME GALIAN GEDUNG PARKIR

ITEM PEKERJAAN Sat URAIAN PERHITUNGAN

Type Luas Tinggi Vol Jumlah Total Vol Sat


Galian Pile Cap & Sumpit m3 PC2 20.00 1.3 26 153 3,978 m3
PC2 22.12 3.05 67.47 5 337 m3
PC3 30.77 1.3 40.00 4 160 m3
4,475
Sumpit A 9.77 2.615 25.55 2 51 m3
Sumpit B 8.00 1.815 14.52 5 73
124 m3
Total 4,599 m3

Galian Tie Beam m3 921.40 m3

Type Luas Tinggi


Galian Semi Basement & Pit Lift m3 Plat 9,119.81 1.1 10,031.79
Lift 44.20 1.88 82.87
10,114.66
TOTAL m3 15,635.09

2 Buang tanah hasil galian m3 Volume Beton Plat Bsm = 1,741.26 m3


Vol Beton Pile Cap = 2,153.28 m3
Vol Beton Bored Pile = 2,979.86 m3
Vol Beton Fit Lift = 37.74 m3
Vol Beton Tie Beam = 429.91 m3
Vol Beton Sumpit = 26.45 m3
Vol Lantai Kerja = 435.31 m3
Vol Urugan Pasir = 609.44 m3
8,413.25 m3

3 Urugan Tanah dari luar lokasi terma m3 7,221.83 m3

Type Luas Tebal Vol


4 Urugan pasir dibawah lantai tebal 7 c m3 Plat 8,735 0.07 611.44 m3

611.44 m3

Type Luas Tebal Vol


5 Lantai kerja beton K.175, tebal 5 cm m3 Plat 8,735 0.05 436.74 m3
m3 Pile Cap 0.05 m3
m3 Tie Beam 417.28 0.05 m3
Sumpit 39.96 0.05 2.00 m3
436.74 m3

6 Potong Kepala pancang Dia. 100 cm 328 pcs


7 Buang sisa potong pancang 328 pcs

Di Buat Oleh :

Muhammad Alimin
ANTI RAYAP

Luas Plat 8,734.79 m2

Luas Dinding Pile Cap P2 22.36 158 3532.88


P3 25.9376 4 103.75
3,636.6 m2
Luas Dinding Tie Beam 2,576.78 m2

TOTAL 14,948.20 m2
PEKERJAAN WATERSTOP

NO LOKASI VOLUME SAT


1 E-I3/5-6 52.4 m'
2 A'-E/4-5 38 m'
3 A'-E/5-6 40 m'
4 E-F/9-11 23 m'

E1-H/9-9', G-H/9-11,
5 28.7 m'
E1-F/10-11, E1-F/11

6 A"-D2/6-7 33.3 m'


7 I6/6-7, D1-D2/6-9 60 m'

8 I6-A2/8'-9, D2-A2/8'-9 96.05 m'

9 E/8'-9 10.2 m'


10 I6-B1/10-11 55 m'
11 13/14, 12/13 105.45 ml ml2
12 C3-I2/I5-14 68.1 m2
13 17/16 33.85 m2
14 15-14 42.15 m2
Volume Pekerjaan Expantion Joint Dilatasi

Volume Sat
Lantai 1 71.728 m'
Lantai 2 69.866 m'
Lantai 3 67.032 m'
Lantai 4 62.011 m'