LAPORAN HARIAN KEMAJUAN PENGGALIAN

LUBANG BUKAAN PT TCM


Tanggal : Friday, 03 February 2023 Gilir: pagi, siang, malam (1,2,3)

ROAD HEADER EBZ 200


N0 URAIAN KETERANGAN
1 2 3
1 Lokasi Kegiatan Lubang Conv. & Suplai Material Lubang Udara Kotor Lubang Transport Mat.
3 Nama Pengawas
● Supervisor/Section Head Li Qin Fa TKA
● Leader Group 0 0 0
4 Waktu Operasi (menit) blm tercatat
5 Jumlah Tenaga Kerja (orang)
●TKA
- Operator RH & Helper 3 3 3
- ShotCrete 2 2 -
- Material Transport 1 1 1
- Extend Belt, Ducting & Pipe
4 4 4
(Water & Air)
- Survey 1 1 1
●TKI
- Operator RH & Helper - - -
- Shotcrete 3 3 -
- Material Transport 21 29 19
- Extend Belt, Ducting & Pipe
10 10 10
(Water & Air)
- Pengukuran 3 3 3
6 Kemajuan (meter) 7,400 7,500 1,400
Kumulatif (meter) 187,600 389,000 186,300 - bila terdapat struktur
7 Material geologi, ditambahkan
● Roof Bolt 56 56 8 cable bolt secukupnya
● Cable Bolt 21 21 5 (hingga 5 CB/1 meter
kemajuan)
- bila terdapat struktur
geologi, ditambahkan
cable bolt secukupnya
(hingga 5 CB/1 meter
●Wiremesh 42 42 6 kemajuan)
●Resin (dodol) 126 126 22
0 *note: Titik nol pengukuran kumulatif Junction diambil dari posisi Laser beam pada masing - masing CB use 2 resins, RB use
dst junction. 1,5 resin