a. Pekerjaan : Titik
b. Lokasi : 0
c. Penyedia Jasa : 0
d. Alamat : Kaduhejo - Pandeglang
e. SPK
- Nomor : 0
- Tanggal : 0
f. Harga Borongan
- Nilai SPK : Rp. 290,329,000 ,-
- Terbilang : Tiga Ratus Empat Puluh Juta Rupiah
g. Waktu Pelaksanaan
- Masa Pelaksanaan : 60 (Enam Puluh) Hari Kalender
- Dimulai dari : 0
- Berakhir sampai : 15 September 2018
### Err:509
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
### Err:509
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
### Err:509
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
### Err:509
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
### Err:509
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
### Err:509
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
I II III IV V
### Err:509
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
### Err:509
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
### Err:509
Err:509 Err:509 100 100 100
Err:509 Err:509 100 100 100
### Err:509
Err:509 Err:509 100 100 100
Kemajuan laporan pekerjaan telah mencapai prosentase sebesar 100% (Seratus Persen)
Demikian laporan pekerjaan ini dibuat dengan sebenarnya untuk digunakan seperlunya.
Diperiksa/Setuju Dibuat Oleh
Kontraktor Pelaksana #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Mengetahui / Setuju :
#REF!
#REF!
#REF!
#REF!
4.8
B. Terhadap satuan kegiatan/pekerjaan, volume, bobot, spesifikasi teknis, lokasi dan waktu :
1. Lokasi : 0
2. Waktu Pelaksanaan : 60 (Enam Puluh) Hari Kalender
3. Satuan kegiatan/pekerjaan, volume, bobot dan spesifikasi teknis/dimensi
Spesifikasi
Bobot
No URAIAN PEKERJAAN Volume
(%)
Teknis/Dimensi Keterangan
Dimensi
(1) (2) (3) (4) (5) (6)
### Err:509
Err:509 Err:509 102.00 m2 #REF!
Err:509 Err:509 102.00 m2 #REF!
Err:509 Err:509 51.00 Unit #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
### Err:509
Err:509 Err:509 51.00 m1 #REF!
Err:509 Err:509 51.00 bh #REF!
Err:509 Err:509 51.00 bh #REF!
### Err:509
Err:509 Err:509 - - #REF!
Err:509 Err:509 306.00 M1 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
### Err:509
Err:509 Err:509 51.00 Unit #REF!
Err:509 Err:509 51.00 Unit #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
### Err:509
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
### Err:509
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
(1) (2) (3) (4) (5) (6)
### Err:509
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
### Err:509
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
### Err:509
Err:509 Err:509 Err:509 Err:509 #REF!
Err:509 Err:509 Err:509 Err:509 #REF!
### Err:509
Err:509 Err:509 Err:509 Err:509 #REF!
Ket :
√ = Sesuai
x = Tidak sesuai
Apabila tidak sesuai beri penjelasan pada kolom keterangan
C. Pengetesan / Pengujian
### Err:509
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
### Err:509
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
### Err:509
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
### Err:509
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
### Err:509
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
### Err:509
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
### Err:509
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
(1) (2) (3) (4)
### Err:509
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
### Err:509
Err:509 Err:509 Sesuai
Err:509 Err:509 Sesuai
### Err:509
Err:509 Err:509 Sesuai
Ket : Pilih salah satu pada kolom (3) (Sesuai/Tidak Sesuai atau Memenuhi/Tidak Memenuhi)
Apabila Tidak Sesuai/Tidak Sesuai/Tidak Memenuhi beri keterangan pada kolom (4)
D. Penilaian terhadap hasil pekerjaan
Ket :
√ = Sesuai
x = Terdapat kekurangan atau Cacat Cacat
Apabila terdapat Kekurangan/Cacat cacat maka pada kolom keterangan diberi penjelasan tentang perbaikan yang harus dilakukan
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Domestik Setempat (SPALD-S) - Tematik Penanggulangan Kemiskinan
Pekerjaan : Pembangunan Tangki Septik Skala Individual Perdesaan Minimal 50 KK - Tematik Penanggulangan Kemiskinan
Volume : 51 Titik
Lokasi : Desa Sukajadi
Kec / Kab : Kec. Carita / Kab. Pandeglang
Pelaksana : KSM Sukajadi Bersih
Tahun Anggaran : 2021
TIME SCHEDULE
JUMLAH RENCANA BOBOT 0.25 1.50 5.00 10.00 12.00 20.00 20.00 12.25 10.00 5.00 2.50 1.50
JUMLAH RENCANA BOBOT KOMULATIF 0.25 1.75 6.75 16.75 28.75 48.75 68.75 81.00 91.00 96.00 98.50 100.00
JUMLAH REALISASI BOBOT 7.44 9.44 9.44 9.44 9.85 9.91 16.27 18.54
JUMLAH REALISASI BOBOT KOMULATIF 7.44 16.88 26.31 35.75 45.60 55.50 71.78 90.32
HENDI RAHMAN, ST
LAPORAN BULANAN BULAN KE - I
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Domestik Setempat (SPALD-S) - Tematik Penanggulangan Kemiskinan
Pekerjaan : Pembangunan Tangki Septik Skala Individual Perdesaan Minimal 50 KK - Tematik Penanggulangan Kemiskinan BULAN KE : 1 (SATU)
Volume : 51 Titik MINGGU AWAL KE : I (SATU)
Lokasi : Desa Sukajadi MINGGU AKHIR KE : IV (EMPAT)
Kec / Kab : Kec. Carita / Kab. Pandeglang PELAKSANA : KSM Sukajadi Bersih
Pelaksana : KSM Sukajadi Bersih KEC/KAB : Kec. Carita / Kab. Pandeglang
Tahun Anggaran : 2021 TAHUN : 2021
JUMLAH HARGA Bobot BULAN LALU BULAN INI REALISASI S/D BULAN INI
NO URAIAN PEKERJAAN VOLUME/SAT. ( Rp ) Pekerjaan Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai
(%) (%) (%) (%) (%) (%) (%) ( Rp )
A B C D E F G G H I J K
- - - - - - -
- - - - - - -
- - - - - - -
- - -
- - - - - - -
35.00 0.47 55.00 0.74 90.00 1.22 4,143,645.00
35.00 0.16 50.00 0.22 85.00 0.38 1,286,347.50
0.97 1.60 5,429,992.50
KETERANGAN :
1. Bobot Prestasi Pekerjaan Sampai Dengan Bulan Ini ( % )
2. Rencana Prestasi Pekerjaan Menurut Time Schedule ( % )
3. Selisih Bobot Prestasi Pekerjaan Dari Rencana Time Schedule ( - / + )
4. Sisa Waktu Pelaksanaan ( Hari Kalender )
Pandeglang 1 Agustus 2021
Dibuat Oleh
TFL TEKNIK
HENDI RAHMAN, ST
BULAN KE - II
JUMLAH HARGA Bobot MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN PEKERJAAN VOLUME/SAT. ( Rp ) Pek Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai
(%) (%) (%) (%) (%) (%) (%) ( Rp )
A B C D E F G G H I J K
MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D M
Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi
(%) (%) (%) (%) (%) (%) ( Rp ) (%) (%) (%) (%) (%) (%) ( Rp ) (%) (%) (%) (%) (%)
G G H I J K G G H I J K G G H I
10.00 0.33 10.00 0.33 20.00 0.67 2,264,916.38 20.00 0.67 10.00 0.33 30.00 1.00 3,397,374.56 30.00 1.00 10.00 0.33 40.00
10.00 0.04 10.00 0.04 20.00 0.08 275,098.71 20.00 0.08 10.00 0.04 30.00 0.12 412,648.07 30.00 0.12 10.00 0.04 40.00
10.00 0.16 10.00 0.16 20.00 0.31 1,057,144.79 20.00 0.31 10.00 0.16 30.00 0.47 1,585,717.19 30.00 0.47 10.00 0.16 40.00
10.00 0.03 10.00 0.03 20.00 0.06 201,086.37 20.00 0.06 10.00 0.03 30.00 0.09 301,629.56 30.00 0.09 10.00 0.03 40.00
0.56 1.12 3,798,246.25 0.56 1.68 5,697,369.38 0.56
- - 10.00 0.12 10.00 0.12 393,609.02 10.00 0.12 10.00 0.12 20.00 0.23 787,218.05 20.00 0.23 10.00 0.12 30.00
- - 10.00 0.23 10.00 0.23 797,058.27 10.00 0.23 10.00 0.23 20.00 0.47 1,594,116.55 20.00 0.47 10.00 0.23 30.00
- - 10.00 0.49 10.00 0.49 1,650,189.86 10.00 0.49 10.00 0.49 20.00 0.97 3,300,379.73 20.00 0.97 10.00 0.49 30.00
0.84 0.84 2,840,857.16 0.84 1.67 5,681,714.32 0.84
10.00 0.39 10.00 0.39 20.00 0.78 2,651,347.20 20.00 0.78 10.00 0.39 30.00 1.17 3,977,020.80 30.00 1.17 10.00 0.39 40.00
10.00 0.21 10.00 0.21 20.00 0.43 1,446,482.40 20.00 0.43 10.00 0.21 30.00 0.64 2,169,723.60 30.00 0.64 10.00 0.21 40.00
10.00 5.12 10.00 5.12 20.00 10.24 34,807,500.00 20.00 10.24 10.00 5.12 30.00 15.36 52,211,250.00 30.00 15.36 10.00 5.12 40.00
5.72 11.44 38,905,329.60 5.72 17.16 58,357,994.40 5.72
5.00 0.02 10.00 0.05 15.00 0.07 232,078.05 15.00 0.07 10.00 0.05 25.00 0.11 386,796.75 25.00 0.11 10.00 0.05 35.00
5.00 0.00 10.00 0.01 15.00 0.01 26,775.00 15.00 0.01 10.00 0.01 25.00 0.01 44,625.00 25.00 0.01 10.00 0.01 35.00
5.00 0.07 10.00 0.15 15.00 0.22 765,000.00 15.00 0.22 10.00 0.15 25.00 0.37 1,275,000.00 25.00 0.37 10.00 0.15 35.00
0.20 0.30 1,023,853.05 0.20 0.50 1,706,421.75 0.20
5.00 0.37 10.00 0.74 15.00 1.11 3,790,054.80 15.00 1.11 10.00 0.74 25.00 1.86 6,316,758.00 25.00 1.86 10.00 0.74 35.00
0.74 1.11 3,790,054.80 0.74 1.86 6,316,758.00 0.74
5.00 0.26 10.00 0.53 15.00 0.79 2,691,989.10 15.00 0.79 10.00 0.53 25.00 1.32 4,486,648.50 25.00 1.32 10.00 0.53 35.00
5.00 0.33 10.00 0.67 15.00 1.00 3,415,082.40 15.00 1.00 10.00 0.67 25.00 1.67 5,691,804.00 25.00 1.67 10.00 0.67 35.00
1.20 1.80 6,107,071.50 1.20 2.99 10,178,452.50 1.20
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - -
SI PEKERJAAN PRESTASI PEKERJAAN PRESTASI PEKERJAAN PRESTASI
REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI
Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi
(%) ( Rp ) (%) (%) (%) (%) (%) (%) ( Rp ) (%) (%) (%) (%) (%) (%) ( Rp ) (%) (%) (%)
J K G G H I J K G G H I J K G G H
1.33 4,529,832.75 40.00 1.33 10.00 0.33 50.00 1.67 5,662,290.94 50.00 1.67 10.00 0.33 60.00 2.00 6,794,749.13 60.00 2.00 20.00
0.16 550,197.42 40.00 0.16 10.00 0.04 50.00 0.20 687,746.78 50.00 0.20 10.00 0.04 60.00 0.24 825,296.14 60.00 0.24 20.00
0.62 2,114,289.59 40.00 0.62 10.00 0.16 50.00 0.78 2,642,861.99 50.00 0.78 10.00 0.16 60.00 0.93 3,171,434.38 60.00 0.93 20.00
0.12 402,172.74 40.00 0.12 10.00 0.03 50.00 0.15 502,715.93 50.00 0.15 10.00 0.03 60.00 0.18 603,259.11 60.00 0.18 20.00
2.23 7,596,492.50 0.56 2.79 9,495,615.63 0.56 3.35 11,394,738.76
0.35 1,180,827.07 30.00 0.35 10.00 0.12 40.00 0.46 1,574,436.10 40.00 0.46 10.00 0.12 50.00 0.58 1,968,045.12 50.00 0.58 20.00
0.70 2,391,174.82 30.00 0.70 10.00 0.23 40.00 0.94 3,188,233.09 40.00 0.94 10.00 0.23 50.00 1.17 3,985,291.37 50.00 1.17 20.00
1.46 4,950,569.59 30.00 1.46 10.00 0.49 40.00 1.94 6,600,759.46 40.00 1.94 10.00 0.49 50.00 2.43 8,250,949.32 50.00 2.43 20.00
2.51 8,522,571.48 0.84 3.34 11,363,428.65 0.84 4.18 14,204,285.81
1.56 5,302,694.40 40.00 1.56 10.00 0.39 50.00 1.95 6,628,368.00 50.00 1.95 10.00 0.39 60.00 2.34 7,954,041.60 60.00 2.34 15.00
0.85 2,892,964.80 40.00 0.85 10.00 0.21 50.00 1.06 3,616,206.00 50.00 1.06 10.00 0.21 60.00 1.28 4,339,447.20 60.00 1.28 15.00
20.47 69,615,000.00 40.00 20.47 10.00 5.12 50.00 25.59 87,018,750.00 50.00 25.59 10.00 5.12 60.00 30.71 104,422,500.00 60.00 30.71 15.00
22.89 77,810,659.20 5.72 28.61 97,263,324.00 5.72 34.33 116,715,988.80
0.16 541,515.45 35.00 0.16 10.00 0.05 45.00 0.20 696,234.15 45.00 0.20 10.00 0.05 55.00 0.25 850,952.85 55.00 0.25 15.00
0.02 62,475.00 35.00 0.02 10.00 0.01 45.00 0.02 80,325.00 45.00 0.02 10.00 0.01 55.00 0.03 98,175.00 55.00 0.03 15.00
0.52 1,785,000.00 35.00 0.52 10.00 0.15 45.00 0.67 2,295,000.00 45.00 0.67 10.00 0.15 55.00 0.82 2,805,000.00 55.00 0.82 15.00
0.70 2,388,990.45 0.20 0.90 3,071,559.15 0.20 1.10 3,754,127.85
2.60 8,843,461.20 35.00 2.60 10.00 0.74 45.00 3.34 11,370,164.40 45.00 3.34 10.00 0.74 55.00 4.09 13,896,867.60 55.00 4.09 20.00
2.60 8,843,461.20 0.74 3.34 11,370,164.40 0.74 4.09 13,896,867.60
1.85 6,281,307.90 35.00 1.85 10.00 0.53 45.00 2.38 8,075,967.30 45.00 2.38 10.00 0.53 55.00 2.90 9,870,626.70 55.00 2.90 20.00
2.34 7,968,525.60 35.00 2.34 10.00 0.67 45.00 3.01 10,245,247.20 45.00 3.01 10.00 0.67 55.00 3.68 12,521,968.80 55.00 3.68 20.00
4.19 14,249,833.50 1.20 5.39 18,321,214.50 1.20 6.59 22,392,595.50
MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI
Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai
(%) (%) (%) ( Rp ) (%) (%) (%) (%) (%) (%) ( Rp )
I J K G G H I J K
0.67 80.00 2.66 9,059,665.50 80.00 2.66 15.00 0.50 95.00 3.16 10,758,352.78
0.08 80.00 0.32 1,100,394.85 80.00 0.32 15.00 0.06 95.00 0.38 1,306,718.88
0.31 80.00 1.24 4,228,579.18 80.00 1.24 15.00 0.23 95.00 1.48 5,021,437.77
0.06 80.00 0.24 804,345.48 80.00 0.24 15.00 0.04 95.00 0.28 955,160.26
1.12 4.47 15,192,985.01 0.84 5.31 18,041,669.70
0.23 70.00 0.81 2,755,263.17 70.00 0.81 20.00 0.23 90.00 1.04 3,542,481.22
0.47 70.00 1.64 5,579,407.92 70.00 1.64 20.00 0.47 90.00 2.11 7,173,524.46
0.97 70.00 3.40 11,551,329.05 70.00 3.40 20.00 0.97 90.00 4.37 14,851,708.78
1.67 5.85 19,886,000.13 1.67 7.52 25,567,714.45
0.58 75.00 2.92 9,942,552.00 75.00 2.92 15.00 0.58 90.00 3.51 11,931,062.40
0.32 75.00 1.60 5,424,309.00 75.00 1.60 15.00 0.32 90.00 1.91 6,509,170.80
7.68 75.00 38.39 130,528,125.00 75.00 38.39 20.00 10.24 95.00 48.63 165,335,625.00
8.58 42.91 145,894,986.00 11.14 54.05 183,775,858.20
0.07 70.00 0.32 1,083,030.90 70.00 0.32 20.00 0.09 90.00 0.41 1,392,468.30
0.01 70.00 0.04 124,950.00 70.00 0.04 20.00 0.01 90.00 0.05 160,650.00
0.22 70.00 1.05 3,570,000.00 70.00 1.05 20.00 0.30 90.00 1.35 4,590,000.00
0.30 1.41 4,777,980.90 0.40 1.81 6,143,118.30
1.49 75.00 5.57 18,950,274.00 75.00 5.57 20.00 1.49 95.00 7.06 24,003,680.40
1.49 5.57 18,950,274.00 1.49 7.06 24,003,680.40
1.06 75.00 3.96 13,459,945.50 75.00 3.96 15.00 0.79 90.00 4.75 16,151,934.60
1.34 75.00 5.02 17,075,412.00 75.00 5.02 15.00 1.00 90.00 6.03 20,490,494.40
2.39 8.98 30,535,357.50 1.80 10.78 36,642,429.00
0.03 30.00 0.04 133,230.38 30.00 0.04 65.00 0.08 95.00 0.12 421,896.19
0.00 30.00 0.00 16,182.28 30.00 0.00 65.00 0.01 95.00 0.02 51,243.88
0.01 30.00 0.02 62,184.99 30.00 0.02 65.00 0.04 95.00 0.06 196,919.13
0.00 30.00 0.00 11,828.61 30.00 0.00 65.00 0.01 95.00 0.01 37,457.27
0.04 0.07 223,426.25 0.14 0.21 707,516.46
II. PEKERJAAN BETON
1 Pek Beton Lantai Kerja ad. 1:3:5 0.14 M3 154,356.48 0.05 - - - - - -
2 Pek. Beton diatas IPAL T = 0.8 cm camp 1 : 3 : 5 0.29 M3 312,571.87 0.09 - - - - - -
3 Pek. Beton Penutup T = 5 cm (Resapan) 0.16 M3 647,133.28 0.19 - - - - - -
Jumlah 1,114,061.63 0.33 - - - -
III. PEKERJAAN TANGKI SEPTIK DAN RESAPAN
1 Pek. Pasangan Dinding bata Merah 1/2 Bata ad 1 : 3 4.00 m2 519,872.00 0.15 - - - - - -
2 Pek. Plesteran berikut acian 1 : 4 2.00 m2 141,812.00 0.04 - - - - - -
3 Pek. Tangki septik pabrikasi 2.00 Unit 6,825,000.00 2.01 - - - - - -
Jumlah 7,486,684.00 2.20 - - -
IV. PEK. PENGADAAN DAN PEMASANGAN PIPA & ACCESSORIES
1 Pek. Pasang Pipa PVC dia. 1" (Pipa Sirkulasi) 2.00 m1 60,674.00 0.02 - - - - - -
2 Pek. Pasang Tee PVC dia. 1" (Pipa Sirkulasi) 2.00 bh 7,000.00 0.00 - - - - - -
3 Pek. Kloset Jongkok 2.00 bh 200,000.00 0.06 - - - - - -
Jumlah 267,674.00 0.08 - - -
B. PEKERJAAN JARINGAN PIPA (DISTRIBUSI DAN SAMBUNGAN RUMAH)
I. PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA
1 Pek. Pemasangan Pipa SDR-41 dia. 3 " 12.00 M1 990,864.00 0.29 - - - - - -
2 Pek. Elbow 90 dia. 3" 110.00 bh 4,604,050.00 1.35 - 5.00 0.07 5.00 0.07 230,202.50
3 Pek. Elbow 45 dia. 3" 38.00 bh 1,513,350.00 0.45 - 5.00 0.02 5.00 0.02 75,667.50
Jumlah 7,108,264.00 2.09 0.09 0.09 305,870.00
II. PEKERJAAN BAK KONTROL DAN GREASETRAP
1 Pek. Bak Kontrol 2.00 Unit 703,788.00 0.21 - - - - - -
2 Pek. Greasetrap 2.00 Unit 892,832.00 0.26 - - - - - -
Jumlah 1,596,620.00 0.47 - - -
III. PEKERJAAN FINISHING DAN LAIN LAIN
I. Cat tembok 2x 132.64 m2 6,949,579.09 2.04 - - - - - -
Jumlah 6,949,579.09 2.04 - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - -
- - - - - - - - - - - - - - - - - - -
5.00 0.07 10.00 0.14 15.00 0.20 690,607.50 15.00 0.20 10.00 0.14 25.00 0.34 1,151,012.50 25.00 0.34 10.00 0.14 35.00
5.00 0.02 10.00 0.04 15.00 0.07 227,002.50 15.00 0.07 10.00 0.04 25.00 0.11 378,337.50 25.00 0.11 10.00 0.04 35.00
0.18 0.27 917,610.00 0.18 0.45 1,529,350.00 0.18
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
- - - - - - - -
- - - - - - - - - - - - - - - - - - -
0.47 1,611,417.50 35.00 0.47 10.00 0.14 45.00 0.61 2,071,822.50 45.00 0.61 10.00 0.14 55.00 0.74 2,532,227.50 55.00 0.74 10.00
0.16 529,672.50 35.00 0.16 10.00 0.04 45.00 0.20 681,007.50 45.00 0.20 10.00 0.04 55.00 0.24 832,342.50 55.00 0.24 10.00
0.63 2,141,090.00 0.18 0.81 2,752,830.00 0.18 0.99 3,364,570.00
- - - - 20.00 0.41 20.00 0.41 1,389,915.82 20.00 0.41 20.00 0.41 40.00 0.82 2,779,831.64 40.00 0.82 20.00
- - 0.41 0.41 1,389,915.82 0.41 0.82 2,779,831.64
0.03 30.00 0.05 155,961.60 30.00 0.05 35.00 0.05 65.00 0.10 337,916.80
0.01 20.00 0.01 28,362.40 20.00 0.01 40.00 0.02 60.00 0.03 85,087.20
- - - - - - - - - - -
0.04 0.05 184,324.00 0.07 0.12 423,004.00
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - -
- - - - - - - - - - -
0.14 65.00 0.88 2,992,632.50 65.00 0.88 25.00 0.34 90.00 1.22 4,143,645.00
0.04 65.00 0.29 983,677.50 65.00 0.29 20.00 0.09 85.00 0.38 1,286,347.50
0.18 1.17 3,976,310.00 0.43 1.60 5,429,992.50
0.04 30.00 0.06 211,136.40 30.00 0.06 17.00 0.04 47.00 0.10 330,780.36
- - - - - - - - - - -
0.04 0.06 211,136.40 0.04 0.10 330,780.36
0.41 60.00 1.23 4,169,747.45 60.00 1.23 25.00 0.51 85.00 1.74 5,907,142.23
0.41 1.23 4,169,747.45 0.51 1.74 5,907,142.23
KETERANGAN :
1. Bobot Prestasi Pekerjaan Sampai Dengan Minggu Ini ( % )
2. Rencana Prestasi Pekerjaan Menurut Time Schedule ( % )
3. Selisih Bobot Prestasi Pekerjaan Dari Rencana Time Schedule ( - / + )
4. Sisa Waktu Pelaksanaan ( Hari Kalender )
Pandeglang 11 Juli 2021
Dibuat Oleh
TFL TEKNIK
HENDI RAHMAN, ST
PRESTASI PEKERJAAN PRESTASI PEKERJAAN PRESTASI PEKERJAAN
MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D M
Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi
(%) (%) (%) (%) (%) (%) ( Rp ) (%) (%) (%) (%) (%) (%) ( Rp ) (%) (%) (%) (%) (%)
G H I J K L M G H I J K L M G H I J K
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI
Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi
(%) ( Rp ) (%) (%) (%) (%) (%) (%) ( Rp ) (%) (%) (%) (%) (%) (%) ( Rp ) (%) (%) (%)
L M G H I J K L M G H I J K L M G H I
MINGGU INI REALISASI S/D MINGGU INI MINGGU LALU MINGGU INI REALISASI S/D MINGGU INI
Bobot Prestasi Bobot Nilai Prestasi Bobot Prestasi Bobot Prestasi Bobot Nilai
(%) (%) (%) ( Rp ) (%) (%) (%) (%) (%) (%) ( Rp )
J K L M G H I J K L M
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Domestik Setempat (SPALD-S) - Tematik Penanggulangan Kemiskinan
Pekerjaan : Pembangunan Tangki Septik Skala Individual Perdesaan Minimal 50 KK - Tematik Penanggulangan Kemiskinan
Volume : 51 Titik
Lokasi : Desa Sukajadi
Kec / Kab : Kec. Carita / Kab. Pandeglang
Tahun Anggaran : 2021
Menurut Tambah
Menurut MC-100%
Kurang
No. URAIAN PEKERJAAN
Jumlah Harga Jumlah Harga Keterangan :
(Rp) (Rp)
(1) (2) (3) (4) (5)
Dibuat Oleh
TFL TEKNIK
HENDI RAHMAN, ST
Lampiran II
Berita Acara Pemeriksaan Bersama Akhir (Mutual Check 100%)
Nomor : .....................................
Tanggal : .....................................
================================================================
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Domestik Setempat (SPALD-S) - Tematik Penanggulangan Kemiskinan
Pekerjaan : Pembangunan Tangki Septik Skala Individual Perdesaan Minimal 50 KK - Tematik Penanggulangan Kemiskinan
Volume : 51 Titik
Lokasi : Desa Sukajadi
Kec / Kab : Kec. Carita / Kab. Pandeglang
Tahun Anggaran : 2021
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Domestik Setempat (SPALD-S) - Tematik Penanggulangan Kemiskinan
Pekerjaan : Pembangunan Tangki Septik Skala Individual Perdesaan Minimal 50 KK - Tematik Penanggulangan Kemiskinan
Volume : 51 Titik
Lokasi : Desa Sukajadi
Kec / Kab : Kec. Carita / Kab. Pandeglang
Tahun Anggaran : 2021
Dibuat Oleh
TFL TEKNIK
HENDI RAHMAN, ST
Lampiran II
Berita Acara Pemeriksaan Bersama Tambah Kurang
Nomor : ……………………………….
Tanggal :
……………………………….
================================================================
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Domestik Setempat (SPALD-S) - Tematik Penanggulangan Kemiskinan
Pekerjaan : Pembangunan Tangki Septik Skala Individual Perdesaan Minimal 50 KK - Tematik Penanggulangan Kemiskinan
Volume : 51 Titik
Lokasi : Desa Sukajadi
Kec / Kab : Kec. Carita / Kab. Pandeglang
Tahun Anggaran : 2021
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Domestik Setempat (SPALD-S) - Tematik Penanggulangan Kemiskinan
Pekerjaan : Pembangunan Tangki Septik Skala Individual Perdesaan Minimal 50 KK - Tematik Penanggulangan Kemiskinan
Volume : 51 Titik
Lokasi : Desa Sukajadi
Kec / Kab : Kec. Carita / Kab. Pandeglang
Tahun Anggaran : 2021
Dibuat Oleh
TFL TEKNIK
HENDI RAHMAN, ST
Lampiran II
Berita Acara Pemeriksaan Bersama Awal (Mutual Check 0%)
Nomor : ………………………………………….
Tanggal : ………………………………………….
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Domestik Setempat (SPALD-S) - Tematik Penanggulangan Kemiskinan Nomor Kontrak : ………………………………………
Pekerjaan : Pembangunan Tangki Septik Skala Individual Perdesaan Minimal 50 KK - Tematik Penanggulangan Kemiskinan Tanggal Kontrak :
Volume : 51 Titik Pelaksana : KSM Sukajadi Bersih
Lokasi : Desa Sukajadi
Kec / Kab : Kec. Carita / Kab. Pandeglang
Tahun Anggaran : 2021
REKAPITULASI
Penawaran
Jumlah
No. Uraian Pekerjaan
Harga
( Rp.)
A B C
I. PEKERJAAN PERSIAPAN 1,421,155.00
II. PEK. GALIAN DAN URUGAN 995,256.96
III. PEKERJAAN DINDING, PONDASI DAN BETON 30,193,885.00
IV. PEKERJAAN KUDA KUDA DAN ATAP 31,565,184.00
V. PEKERJAAN PLAFOND DAN LANTAI 18,177,532.00
VI. PEKERJAAN LISTRIK 2,132,752.00
VII. PEKERJAAN PENGECATAN 3,805,655.00
VIII. PEKERJAAN LAIN LAIN 500,000.00
Jumlah Fisik 88,791,419.96
Ppn 10% 8,879,142.00
Jumlah Total 97,670,561.96
Dibulatkan 97,670,000.00
Terbilang : #NAME?
Pandeglang, ###
248,400.00
222,755.00
300,000.00
300,000.00
1,071,155.00
650,160.00
156,240.00
188,856.96
995,256.96
1,104,614.80
7,226,100.00
4,216,800.00
4,762,800.00
3,534,678.00
3,231,297.00
3,058,797.60
3,058,797.60
30,193,885.00
16,641,372.00
11,062,128.00
1,850,724.00
2,010,960.00
31,565,184.00
2,829,125.00
5,205,590.00
715,500.00
9,427,317.00
18,177,532.00
1,456,452.00
95,000.00
75,000.00
122,000.00
122,000.00
15,000.00
11,700.00
25,600.00
210,000.00
2,132,752.00
1,995,000.00
1,523,375.00
287,280.00
3,805,655.00
200,000.00
200,000.00
88,141,419.96
8,814,142.00
96,955,561.96
96,955,000.00
Negosiasi
Jumlah
Harga
( Rp.)
C
1,071,155.00
995,256.96
30,193,885.00
31,565,184.00
18,177,532.00
2,132,752.00
3,805,655.00
200,000.00
88,141,419.96
8,814,142.00
96,955,561.96
96,955,000.00
PANDEGLANG BERKAH
REKAPITULASI RENCANA ANGGARAN BIAYA
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Domestik Setempat (SPALD-S) - Tematik Penanggulangan Kemiskinan
Pekerjaan : Pembangunan Tangki Septik Skala Individual Perdesaan Minimal 50 KK - Tematik Penanggulangan Kemiskinan
Volume 51 Titik
Lokasi : Desa Sukajadi
: Kecamatan Carita Kabupaten Pandeglang
Tahun Anggaran : 2021
( …………………./……………….) 0
Ketua
Menyetujui,
Pejabat Pelaksana Teknis Kegiatan
DAK BIDANG SANITASI T.A 2021
Dinas PKPP KAB. PANDEGLANG
JUMLAH
VOLUME HARGA SATUAN
NO. URAIAN PEKERJAAN SAT 51 TITIK BOBOT 51
51 TITIK (Rp.)
(Rp.)
Tanggal
:
:
HARI KE
s/d
Kegiatan : Pembangunan Sistem Pengelolaan Air Limbah Pelaksana : KSM Sukajadi Bersih
Domestik Setempat (SPALD-S) - Tematik Desa : Sukajadi
Penanggulangan Kemiskinan Kec/Kab : Kec. Carita / Kab. Pandeglang
Pekerjaan Pembangunan Tangki Septik Skala Individual Tahun : 2021
Kemiskinan
JUMLAH
_____________________________
Mandor Lapangan