LAPORAN HARIAN

Hari Ke : 1
Sisa Hari : 29

Tanggal : 16 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0000% 0.0054% 0.0054% 8.3333%
2 Medical check up 15.0 Org 2.7178% 1.07 0.0000% 0.1941% 0.1941% 7.1429%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 0.0000% 0.0000% 0.0000% 0.0000%
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.0000% 0.0812% 0.0812% 3.4483%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 0.0000% 0.4265% 0.4265% 8.3333%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.0000% 0.0791% 0.0791% 3.4483%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.0000% 0.0832% 0.0832% 3.4483%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.0000% 0.0832% 0.0832% 3.4483%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.0000% 0.0335% 0.0335% 3.4483%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.0000% 0.0294% 0.0294% 3.4483%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.0000% 0.0690% 0.0690% 3.4483%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.0000% 0.0669% 0.0669% 3.4483%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 0.0000% 0.1704% 0.1704% 3.4483%
2 Transportasi Peralatan dan matrial
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.0000% 0.0000% 0.0000% 0.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.0000% 0.0000% 0.0000% 0.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0000% 0.0000% 0.0000% 0.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.0000% 0.0000% 0.0000% 0.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0000% 0.0000% 0.0000% 0.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0000% 0.0000% 0.0000% 0.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.0000% 0.0000% 0.0000% 0.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 0.0000% 0.0000% 0.0000% 0.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 0.0000% 1.3219% 1.3219%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las
2 Admin 1.0 Org Mesin Potong
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil Org Alat Mekanik
6 Pekerja Mekanikal Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 4
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 32
4 Near Miss 4. Kumulatif s/d hari ini 32
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 2
Sisa Hari : 28

Tanggal : 17 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0054% 0.0054% 0.0109% 16.6667%
2 Medical check up 15.0 Org 2.7178% 1.07 0.1941% 0.1941% 0.3883% 14.2857%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 0.0000% 0.0000% 0.0000% 0.0000%
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.0812% 0.0812% 0.1625% 6.8966%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 0.4265% 0.4265% 0.8530% 16.6667%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.0791% 0.0791% 0.1582% 6.8966%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.0832% 0.0832% 0.1663% 6.8966%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.0832% 0.0832% 0.1663% 6.8966%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.0335% 0.0335% 0.0669% 6.8966%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.0294% 0.0294% 0.0588% 6.8966%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.0690% 0.0690% 0.1379% 6.8966%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.0669% 0.0669% 0.1339% 6.8966%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 0.1704% 0.1704% 0.3408% 6.8966%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.0000% 0.0000% 0.0000% 0.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.0000% 0.0000% 0.0000% 0.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0000% 0.0000% 0.0000% 0.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.0000% 0.0000% 0.0000% 0.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0000% 0.0000% 0.0000% 0.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0000% 0.0000% 0.0000% 0.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.0000% 0.0000% 0.0000% 0.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 0.0000% 0.0000% 0.0000% 0.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 1.3219% 1.3219% 2.6439%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las
2 Admin 1.0 Org Mesin Potong
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil Org Alat Mekanik
6 Pekerja Mekanikal Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 4
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 32
4 Near Miss 4. Kumulatif s/d hari ini 64
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 3
Sisa Hari : 27

Tanggal : 18 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0109% 0.0054% 0.0163% 25.0000%
2 Medical check up 15.0 Org 2.7178% 1.07 0.3883% 0.1941% 0.5824% 21.4286%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 0.0000% 0.0000% 0.0000% 0.0000%
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.1625% 0.0812% 0.2437% 10.3448%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 0.8530% 0.4265% 1.2795% 25.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.1582% 0.0791% 0.2373% 10.3448%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.1663% 0.0832% 0.2495% 10.3448%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.1663% 0.0832% 0.2495% 10.3448%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.0669% 0.0335% 0.1004% 10.3448%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.0588% 0.0294% 0.0882% 10.3448%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.1379% 0.0690% 0.2069% 10.3448%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.1339% 0.0669% 0.2008% 10.3448%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 0.3408% 0.1704% 0.5112% 10.3448%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.0000% 0.0000% 0.0000% 0.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.0000% 0.0000% 0.0000% 0.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0000% 0.0000% 0.0000% 0.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.0000% 0.0000% 0.0000% 0.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0000% 0.0000% 0.0000% 0.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0000% 0.0000% 0.0000% 0.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.0000% 0.0000% 0.0000% 0.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 0.0000% 0.0000% 0.0000% 0.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 2.6439% 1.3219% 3.9658%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las
2 Admin 1.0 Org Mesin Potong
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil Org Alat Mekanik
6 Pekerja Mekanikal Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 4
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 32
4 Near Miss 4. Kumulatif s/d hari ini 96
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 4
Sisa Hari : 26

Tanggal : 19 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0163% 0.0054% 0.0218% 33.3333%
2 Medical check up 15.0 Org 2.7178% 1.07 0.5824% 0.1941% 0.7765% 28.5714%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 0.0000% 0.0000% 0.0000% 0.0000%
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.2437% 0.0812% 0.3250% 13.7931%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 1.2795% 0.4265% 1.7060% 33.3333%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.2373% 0.0791% 0.3164% 13.7931%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.2495% 0.0832% 0.3327% 13.7931%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.2495% 0.0832% 0.3327% 13.7931%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.1004% 0.0335% 0.1339% 13.7931%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.0882% 0.0294% 0.1177% 13.7931%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.2069% 0.0690% 0.2759% 13.7931%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.2008% 0.0669% 0.2678% 13.7931%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 0.5112% 0.1704% 0.6816% 13.7931%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.0000% 0.0000% 0.0000% 0.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.0000% 0.0000% 0.0000% 0.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0000% 0.0000% 0.0000% 0.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.0000% 0.0000% 0.0000% 0.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0000% 0.0000% 0.0000% 0.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0000% 0.0000% 0.0000% 0.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.0000% 0.0000% 0.0000% 0.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 0.0000% 0.0000% 0.0000% 0.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 3.9658% 1.3219% 5.2878%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las
2 Admin 1.0 Org Mesin Potong
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil Org Alat Mekanik
6 Pekerja Mekanikal Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 4
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 32
4 Near Miss 4. Kumulatif s/d hari ini 128
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 5
Sisa Hari : 25

Tanggal : 20 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0218% 0.0054% 0.0272% 41.6667%
2 Medical check up 15.0 Org 2.7178% 1.07 0.7765% 0.1941% 0.9706% 35.7143%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 0.0000% 0.0000% 0.0000% 0.0000%
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.3250% 0.0812% 0.4062% 17.2414%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 1.7060% 0.4265% 2.1325% 41.6667%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.3164% 0.0791% 0.3956% 17.2414%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.3327% 0.0832% 0.4158% 17.2414%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.3327% 0.0832% 0.4158% 17.2414%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.1339% 0.0335% 0.1674% 17.2414%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.1177% 0.0294% 0.1471% 17.2414%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.2759% 0.0690% 0.3448% 17.2414%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.2678% 0.0669% 0.3347% 17.2414%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 0.6816% 0.1704% 0.8520% 17.2414%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.0000% 0.0000% 0.0000% 0.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.0000% 0.0000% 0.0000% 0.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0000% 0.0000% 0.0000% 0.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.0000% 0.0000% 0.0000% 0.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0000% 0.0000% 0.0000% 0.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0000% 0.0000% 0.0000% 0.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.0000% 0.0000% 0.0000% 0.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 0.0000% 0.0000% 0.0000% 0.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 5.2878% 1.3219% 6.6097%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las
2 Admin 1.0 Org Mesin Potong
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil Org Alat Mekanik
6 Pekerja Mekanikal Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 4
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 32
4 Near Miss 4. Kumulatif s/d hari ini 160
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 6
Sisa Hari : 24

Tanggal : 21 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0272% 0.0054% 0.0326% 50.0000%
2 Medical check up 15.0 Org 2.7178% 1.07 0.9706% 0.1941% 1.1648% 42.8571%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 0.0000% 0.0000% 0.0000% 0.0000%
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.4062% 0.0812% 0.4874% 20.6897%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 2.1325% 0.4265% 2.5590% 50.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.3956% 0.0791% 0.4747% 20.6897%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.4158% 0.0832% 0.4990% 20.6897%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.4158% 0.0832% 0.4990% 20.6897%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.1674% 0.0335% 0.2008% 20.6897%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.1471% 0.0294% 0.1765% 20.6897%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.3448% 0.0690% 0.4138% 20.6897%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.3347% 0.0669% 0.4016% 20.6897%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 0.8520% 0.1704% 1.0224% 20.6897%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.0000% 0.0000% 0.0000% 0.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.0000% 0.0000% 0.0000% 0.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0000% 0.0000% 0.0000% 0.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.0000% 0.0000% 0.0000% 0.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0000% 0.0000% 0.0000% 0.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0000% 0.0000% 0.0000% 0.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.0000% 0.0000% 0.0000% 0.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 0.0000% 0.0000% 0.0000% 0.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 6.6097% 1.3219% 7.9316%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las
2 Admin 1.0 Org Mesin Potong
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil Org Alat Mekanik
6 Pekerja Mekanikal Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 4
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 32
4 Near Miss 4. Kumulatif s/d hari ini 192
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 7
Sisa Hari : 23

Tanggal : 22 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0326% 0.0054% 0.0381% 58.3333%
2 Medical check up 15.0 Org 2.7178% 1.07 1.1648% 0.1941% 1.3589% 50.0000%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 0.0000% 0.0000% 0.0000% 0.0000%
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.4874% 0.0812% 0.5687% 24.1379%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 2.5590% 0.4265% 2.9854% 58.3333%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.4747% 0.0791% 0.5538% 24.1379%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.4990% 0.0832% 0.5822% 24.1379%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.4990% 0.0832% 0.5822% 24.1379%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.2008% 0.0335% 0.2343% 24.1379%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.1765% 0.0294% 0.2059% 24.1379%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.4138% 0.0690% 0.4828% 24.1379%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.4016% 0.0669% 0.4686% 24.1379%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 1.0224% 0.1704% 1.1928% 24.1379%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.0000% 0.0000% 0.0000% 0.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.0000% 0.0000% 0.0000% 0.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0000% 0.0000% 0.0000% 0.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.0000% 0.0000% 0.0000% 0.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0000% 0.0000% 0.0000% 0.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0000% 0.0000% 0.0000% 0.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.0000% 0.0000% 0.0000% 0.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 0.0000% 0.0000% 0.0000% 0.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 7.9316% 1.3219% 9.2536%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las
2 Admin 1.0 Org Mesin Potong
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil Org Alat Mekanik
6 Pekerja Mekanikal Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 4
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 32
4 Near Miss 4. Kumulatif s/d hari ini 224
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 8
Sisa Hari : 22

Tanggal : 23 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0381% 0.0054% 0.0435% 66.6667%
2 Medical check up 15.0 Org 2.7178% 1.07 1.3589% 0.1941% 1.5530% 57.1429%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 0.0000% 0.0000% 0.0000% 0.0000%
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.5687% 0.0812% 0.6499% 27.5862%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 2.9854% 0.4265% 3.4119% 66.6667%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.5538% 0.0791% 0.6329% 27.5862%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.5822% 0.0832% 0.6653% 27.5862%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.5822% 0.0832% 0.6653% 27.5862%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.2343% 0.0335% 0.2678% 27.5862%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.2059% 0.0294% 0.2353% 27.5862%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.4828% 0.0690% 0.5518% 27.5862%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.4686% 0.0669% 0.5355% 27.5862%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 1.1928% 0.1704% 1.3632% 27.5862%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.0000% 0.0000% 0.0000% 0.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.0000% 0.0000% 0.0000% 0.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0000% 0.0000% 0.0000% 0.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.0000% 0.0000% 0.0000% 0.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0000% 0.0000% 0.0000% 0.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0000% 0.0000% 0.0000% 0.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.0000% 0.0000% 0.0000% 0.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 0.0000% 0.0000% 0.0000% 0.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 9.2536% 1.3219% 10.5755%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las
2 Admin 1.0 Org Mesin Potong
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil Org Alat Mekanik
6 Pekerja Mekanikal Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 4
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 32
4 Near Miss 4. Kumulatif s/d hari ini 256
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 9
Sisa Hari : 21

Tanggal : 24 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0435% 0.0054% 0.0490% 75.0000%
2 Medical check up 15.0 Org 2.7178% 1.07 1.5530% 0.1941% 1.7471% 64.2857%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 6.00 0.0000% 0.8012% 0.8012% 50.0000%
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.6499% 0.0812% 0.7312% 31.0345%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 3.4119% 0.4265% 3.8384% 75.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.6329% 0.0791% 0.7120% 31.0345%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.6653% 0.0832% 0.7485% 31.0345%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.6653% 0.0832% 0.7485% 31.0345%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.2678% 0.0335% 0.3012% 31.0345%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.2353% 0.0294% 0.2647% 31.0345%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.5518% 0.0690% 0.6207% 31.0345%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.5355% 0.0669% 0.6025% 31.0345%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 1.3632% 0.1704% 1.5335% 31.0345%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.0000% 0.1103% 0.1103% 5.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 0.0000% 0.3530% 0.3530% 5.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0000% 0.0027% 0.0027% 6.2500%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.0000% 0.0213% 0.0213% 6.2500%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0000% 0.0008% 0.0008% 6.2500%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0000% 0.0042% 0.0042% 6.2500%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0000% 0.0044% 0.0044% 6.2500%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.0000% 0.0358% 0.0358% 6.2500%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.0000% 0.0232% 0.0232% 6.2500%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 0.0000% 0.1438% 0.1438% 6.2500%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 10.5755% 2.8227% 13.3982%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 408
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 10
Sisa Hari : 20

Tanggal : 25 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0490% 0.0054% 0.0544% 83.3333%
2 Medical check up 15.0 Org 2.7178% 1.07 1.7471% 0.1941% 1.9413% 71.4286%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 6.00 0.8012% 0.8012% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.7312% 0.0812% 0.8124% 34.4828%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 3.8384% 0.4265% 4.2649% 83.3333%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.7120% 0.0791% 0.7911% 34.4828%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.7485% 0.0832% 0.8317% 34.4828%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.7485% 0.0832% 0.8317% 34.4828%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.3012% 0.0335% 0.3347% 34.4828%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.2647% 0.0294% 0.2941% 34.4828%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.6207% 0.0690% 0.6897% 34.4828%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.6025% 0.0669% 0.6694% 34.4828%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 1.5335% 0.1704% 1.7039% 34.4828%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.1103% 0.1103% 0.2206% 10.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 0.3530% 0.3530% 0.7059% 10.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0027% 0.0027% 0.0053% 12.5000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.0213% 0.0213% 0.0426% 12.5000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0008% 0.0008% 0.0016% 12.5000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0042% 0.0042% 0.0085% 12.5000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0044% 0.0044% 0.0089% 12.5000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.0358% 0.0358% 0.0717% 12.5000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.0232% 0.0232% 0.0464% 12.5000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 0.1438% 0.1438% 0.2877% 12.5000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 13.3982% 2.8227% 16.2209%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 560
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 11
Sisa Hari : 19

Tanggal : 26 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0544% 0.0054% 0.0599% 91.6667%
2 Medical check up 15.0 Org 2.7178% 1.07 1.9413% 0.1941% 2.1354% 78.5714%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.8124% 0.0812% 0.8937% 37.9310%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 4.2649% 0.4265% 4.6914% 91.6667%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.7911% 0.0791% 0.8702% 37.9310%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.8317% 0.0832% 0.9149% 37.9310%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.8317% 0.0832% 0.9149% 37.9310%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.3347% 0.0335% 0.3682% 37.9310%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.2941% 0.0294% 0.3235% 37.9310%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.6897% 0.0690% 0.7587% 37.9310%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.6694% 0.0669% 0.7363% 37.9310%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 1.7039% 0.1704% 1.8743% 37.9310%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.2206% 0.1103% 0.3309% 15.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 0.7059% 0.3530% 1.0589% 15.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0053% 0.0027% 0.0080% 18.7500%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.0426% 0.0213% 0.0640% 18.7500%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0016% 0.0008% 0.0024% 18.7500%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0085% 0.0042% 0.0127% 18.7500%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0089% 0.0044% 0.0133% 18.7500%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.0717% 0.0358% 0.1075% 18.7500%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.0464% 0.0232% 0.0696% 18.7500%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 0.2877% 0.1438% 0.4315% 18.7500%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 16.2209% 2.0215% 18.2425%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 712
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 15
Sisa Hari : 15

Tanggal : 30 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.1374% 0.0812% 1.2186% 51.7241%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.1076% 0.0791% 1.1867% 51.7241%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.1644% 0.0832% 1.2475% 51.7241%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.1644% 0.0832% 1.2475% 51.7241%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.4686% 0.0335% 0.5021% 51.7241%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.4118% 0.0294% 0.4412% 51.7241%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.9656% 0.0690% 1.0345% 51.7241%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.9372% 0.0669% 1.0041% 51.7241%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 2.3855% 0.1704% 2.5559% 51.7241%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.6618% 0.1103% 0.7721% 35.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 2.1178% 0.3530% 2.4707% 35.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0160% 0.0027% 0.0187% 43.7500%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.1279% 0.0213% 0.1493% 43.7500%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0047% 0.0008% 0.0055% 43.7500%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0254% 0.0042% 0.0296% 43.7500%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0266% 0.0044% 0.0310% 43.7500%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.2150% 0.0358% 0.2508% 43.7500%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.1393% 0.0232% 0.1625% 43.7500%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 0.8630% 0.1438% 1.0068% 43.7500%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 55.50 0.0000% 0.4406% 0.4406% 50.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 55.50 0.0000% 0.5041% 0.5041% 50.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 23.4431% 2.3401% 25.7832%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 1320
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 12
Sisa Hari : 18

Tanggal : 27 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.08 0.0599% 0.0054% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 1.07 2.1354% 0.1941% 2.3295% 85.7143%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.8937% 0.0812% 0.9749% 41.3793%
4 Pengadaan APD 15.0 Lot/org 5.1179% 1.25 4.6914% 0.4265% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.8702% 0.0791% 0.9493% 41.3793%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.9149% 0.0832% 0.9980% 41.3793%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.9149% 0.0832% 0.9980% 41.3793%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.3682% 0.0335% 0.4016% 41.3793%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.3235% 0.0294% 0.3530% 41.3793%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.7587% 0.0690% 0.8276% 41.3793%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.7363% 0.0669% 0.8033% 41.3793%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 1.8743% 0.1704% 2.0447% 41.3793%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.3309% 0.1103% 0.4412% 20.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 1.0589% 0.3530% 1.4118% 20.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0080% 0.0027% 0.0107% 25.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.0640% 0.0213% 0.0853% 25.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0024% 0.0008% 0.0031% 25.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0127% 0.0042% 0.0169% 25.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0133% 0.0044% 0.0177% 25.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.1075% 0.0358% 0.1433% 25.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.0696% 0.0232% 0.0929% 25.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 0.4315% 0.1438% 0.5753% 25.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 18.2425% 2.0215% 20.2640%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 864
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 13
Sisa Hari : 17

Tanggal : 28 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 1.07 2.3295% 0.1941% 2.5237% 92.8571%
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 0.9749% 0.0812% 1.0561% 44.8276%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 0.9493% 0.0791% 1.0284% 44.8276%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 0.9980% 0.0832% 1.0812% 44.8276%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 0.9980% 0.0832% 1.0812% 44.8276%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.4016% 0.0335% 0.4351% 44.8276%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.3530% 0.0294% 0.3824% 44.8276%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.8276% 0.0690% 0.8966% 44.8276%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.8033% 0.0669% 0.8702% 44.8276%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 2.0447% 0.1704% 2.2151% 44.8276%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.4412% 0.1103% 0.5515% 25.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 1.4118% 0.3530% 1.7648% 25.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0107% 0.0027% 0.0133% 31.2500%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.0853% 0.0213% 0.1066% 31.2500%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0031% 0.0008% 0.0039% 31.2500%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0169% 0.0042% 0.0211% 31.2500%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0177% 0.0044% 0.0222% 31.2500%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.1433% 0.0358% 0.1791% 31.2500%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.0929% 0.0232% 0.1161% 31.2500%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 0.5753% 0.1438% 0.7192% 31.2500%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 20.2640% 1.5896% 21.8535%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 1016
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 14
Sisa Hari : 16

Tanggal : 29 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 1.07 2.5237% 0.1941% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.0561% 0.0812% 1.1374% 48.2759%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.0284% 0.0791% 1.1076% 48.2759%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.0812% 0.0832% 1.1644% 48.2759%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.0812% 0.0832% 1.1644% 48.2759%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.4351% 0.0335% 0.4686% 48.2759%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.3824% 0.0294% 0.4118% 48.2759%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 0.8966% 0.0690% 0.9656% 48.2759%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 0.8702% 0.0669% 0.9372% 48.2759%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 2.2151% 0.1704% 2.3855% 48.2759%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.5515% 0.1103% 0.6618% 30.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 1.7648% 0.3530% 2.1178% 30.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0133% 0.0027% 0.0160% 37.5000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.1066% 0.0213% 0.1279% 37.5000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0039% 0.0008% 0.0047% 37.5000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0211% 0.0042% 0.0254% 37.5000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0222% 0.0044% 0.0266% 37.5000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.1791% 0.0358% 0.2150% 37.5000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.1161% 0.0232% 0.1393% 37.5000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 0.7192% 0.1438% 0.8630% 37.5000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 0.0000% 0.0000% 0.0000% 0.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 21.8535% 1.5896% 23.4431%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 1168
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 16
Sisa Hari : 14

Tanggal : 31 Maret 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.20 0.0000% 1.7091% 1.7091% 20.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.2186% 0.0812% 1.2999% 55.1724%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.1867% 0.0791% 1.2658% 55.1724%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.2475% 0.0832% 1.3307% 55.1724%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.2475% 0.0832% 1.3307% 55.1724%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.5021% 0.0335% 0.5355% 55.1724%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.4412% 0.0294% 0.4706% 55.1724%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.0345% 0.0690% 1.1035% 55.1724%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.0041% 0.0669% 1.0710% 55.1724%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 2.5559% 0.1704% 2.7263% 55.1724%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.7721% 0.1103% 0.8824% 40.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 2.4707% 0.3530% 2.8237% 40.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0187% 0.0027% 0.0214% 50.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.1493% 0.0213% 0.1706% 50.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0055% 0.0008% 0.0063% 50.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0296% 0.0042% 0.0338% 50.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0310% 0.0044% 0.0354% 50.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.2508% 0.0358% 0.2866% 50.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.1625% 0.0232% 0.1857% 50.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 1.0068% 0.1438% 1.1506% 50.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 55.50 0.4406% 0.4406% 0.8812% 100.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 55.50 0.5041% 0.5041% 1.0082% 100.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 25.7832% 4.0493% 29.8325%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 1472
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 17
Sisa Hari : 13

Tanggal : 01 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.20 1.7091% 1.7091% 3.4182% 40.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.2999% 0.0812% 1.3811% 58.6207%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.2658% 0.0791% 1.3449% 58.6207%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.3307% 0.0832% 1.4139% 58.6207%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.3307% 0.0832% 1.4139% 58.6207%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.5355% 0.0335% 0.5690% 58.6207%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.4706% 0.0294% 0.5000% 58.6207%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.1035% 0.0690% 1.1725% 58.6207%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.0710% 0.0669% 1.1380% 58.6207%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 2.7263% 0.1704% 2.8967% 58.6207%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.8824% 0.1103% 0.9927% 45.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 2.8237% 0.3530% 3.1766% 45.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0214% 0.0027% 0.0240% 56.2500%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.1706% 0.0213% 0.1919% 56.2500%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0063% 0.0008% 0.0071% 56.2500%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0338% 0.0042% 0.0381% 56.2500%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0354% 0.0044% 0.0399% 56.2500%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.2866% 0.0358% 0.3224% 56.2500%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.1857% 0.0232% 0.2089% 56.2500%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 1.1506% 0.1438% 1.2945% 56.2500%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 0.0000% 0.0000% 0.0000% 0.0000%
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 0.0000% 0.0000% 0.0000% 0.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 0.0000% 0.0000% 0.0000% 0.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 29.8325% 3.1046% 32.9371%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 1624
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 18
Sisa Hari : 12

Tanggal : 02 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.20 3.4182% 1.7091% 5.1274% 60.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.3811% 0.0812% 1.4623% 62.0690%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.3449% 0.0791% 1.4240% 62.0690%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.4139% 0.0832% 1.4970% 62.0690%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.4139% 0.0832% 1.4970% 62.0690%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.5690% 0.0335% 0.6025% 62.0690%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.5000% 0.0294% 0.5294% 62.0690%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.1725% 0.0690% 1.2414% 62.0690%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.1380% 0.0669% 1.2049% 62.0690%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 2.8967% 0.1704% 3.0671% 62.0690%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 0.9927% 0.1103% 1.1030% 50.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 3.1766% 0.3530% 3.5296% 50.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0240% 0.0027% 0.0267% 62.5000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.1919% 0.0213% 0.2132% 62.5000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0071% 0.0008% 0.0078% 62.5000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0381% 0.0042% 0.0423% 62.5000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0399% 0.0044% 0.0443% 62.5000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.3224% 0.0358% 0.3583% 62.5000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.2089% 0.0232% 0.2321% 62.5000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 1.2945% 0.1438% 1.4383% 62.5000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.0000% 0.0000% 0.0000% 0.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.0000% 0.0000% 0.0000% 0.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.0000% 0.0000% 0.0000% 0.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0000% 0.0000% 0.0000% 0.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0000% 0.0000% 0.0000% 0.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.0000% 0.0000% 0.0000% 0.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 55.50 0.0000% 1.5018% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 11.50 0.0000% 0.3194% 0.3194% 25.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 17.13 0.0000% 0.5265% 0.5265% 12.5000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 111.00 0.0000% 1.5280% 1.5280% 100.0000%
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 32.9371% 6.9802% 39.9173%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 1776
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 19
Sisa Hari : 11

Tanggal : 03 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.20 5.1274% 1.7091% 6.8365% 80.0000%
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.4623% 0.0812% 1.5436% 65.5172%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.4240% 0.0791% 1.5031% 65.5172%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.4970% 0.0832% 1.5802% 65.5172%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.4970% 0.0832% 1.5802% 65.5172%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.6025% 0.0335% 0.6359% 65.5172%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.5294% 0.0294% 0.5589% 65.5172%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.2414% 0.0690% 1.3104% 65.5172%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.2049% 0.0669% 1.2719% 65.5172%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 3.0671% 0.1704% 3.2375% 65.5172%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 1.1030% 0.1103% 1.2133% 55.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 3.5296% 0.3530% 3.8825% 55.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0267% 0.0027% 0.0294% 68.7500%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.2132% 0.0213% 0.2346% 68.7500%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0078% 0.0008% 0.0086% 68.7500%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0423% 0.0042% 0.0465% 68.7500%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0443% 0.0044% 0.0487% 68.7500%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.3583% 0.0358% 0.3941% 68.7500%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.2321% 0.0232% 0.2554% 68.7500%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 1.4383% 0.1438% 1.5821% 68.7500%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 3.67 0.0000% 0.0427% 0.0427% 33.3333%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 5.67 0.0000% 0.0913% 0.0913% 33.3333%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 3.33 0.0000% 0.0601% 0.0601% 33.3333%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 7.00 0.0000% 0.1747% 0.1747% 33.3333%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.33 0.0000% 0.0080% 0.0080% 33.3333%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.33 0.0000% 0.0123% 0.0123% 33.3333%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000%
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000%
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 18.50 0.0000% 0.0424% 0.0424% 33.3333%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 18.50 0.0000% 0.0468% 0.0468% 33.3333%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 11.50 0.3194% 0.3194% 0.6388% 50.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 17.13 0.5265% 0.5265% 1.0529% 25.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.0000% 0.0000% 0.0000% 0.0000%
100.0000% 39.9173% 4.4287% 44.3460%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 1928
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 20
Sisa Hari : 10

Tanggal : 04 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 0.20 6.8365% 1.7091% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.5436% 0.0812% 1.6248% 68.9655%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.5031% 0.0791% 1.5822% 68.9655%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.5802% 0.0832% 1.6634% 68.9655%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.5802% 0.0832% 1.6634% 68.9655%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.6359% 0.0335% 0.6694% 68.9655%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.5589% 0.0294% 0.5883% 68.9655%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.3104% 0.0690% 1.3794% 68.9655%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.2719% 0.0669% 1.3388% 68.9655%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 3.2375% 0.1704% 3.4079% 68.9655%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 1.2133% 0.1103% 1.3236% 60.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 3.8825% 0.3530% 4.2355% 60.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0294% 0.0027% 0.0320% 75.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.2346% 0.0213% 0.2559% 75.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0086% 0.0008% 0.0094% 75.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0465% 0.0042% 0.0507% 75.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0487% 0.0044% 0.0532% 75.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.3941% 0.0358% 0.4299% 75.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.2554% 0.0232% 0.2786% 75.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 1.5821% 0.1438% 1.7260% 75.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 3.67 0.0427% 0.0427% 0.0854% 66.6667%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 5.67 0.0913% 0.0913% 0.1825% 66.6667%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 3.33 0.0601% 0.0601% 0.1202% 66.6667%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 7.00 0.1747% 0.1747% 0.3494% 66.6667%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.33 0.0080% 0.0080% 0.0160% 66.6667%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.33 0.0123% 0.0123% 0.0246% 66.6667%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 18.50 0.0424% 0.0424% 0.0849% 66.6667%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 18.50 0.0468% 0.0468% 0.0936% 66.6667%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 11.50 0.6388% 0.3194% 0.9581% 75.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 17.13 1.0529% 0.5265% 1.5794% 37.5000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.13 0.0000% 0.1250% 0.1250% 12.5000%
100.0000% 44.3460% 4.5537% 48.8997%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 2080
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 21
Sisa Hari : 9

Tanggal : 05 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.6248% 0.0812% 1.7061% 72.4138%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000%
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.5822% 0.0791% 1.6613% 72.4138%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.6634% 0.0832% 1.7465% 72.4138%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.6634% 0.0832% 1.7465% 72.4138%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.6694% 0.0335% 0.7029% 72.4138%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.5883% 0.0294% 0.6177% 72.4138%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.3794% 0.0690% 1.4483% 72.4138%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.3388% 0.0669% 1.4058% 72.4138%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 3.4079% 0.1704% 3.5783% 72.4138%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 1.3236% 0.1103% 1.4339% 65.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 4.2355% 0.3530% 4.5885% 65.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0320% 0.0027% 0.0347% 81.2500%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.2559% 0.0213% 0.2772% 81.2500%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0094% 0.0008% 0.0102% 81.2500%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0507% 0.0042% 0.0550% 81.2500%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0532% 0.0044% 0.0576% 81.2500%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.4299% 0.0358% 0.4658% 81.2500%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.2786% 0.0232% 0.3018% 81.2500%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 1.7260% 0.1438% 1.8698% 81.2500%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 3.67 0.0854% 0.0427% 0.1281% 100.0000%
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 5.67 0.1825% 0.0913% 0.2738% 100.0000%
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 3.33 0.1202% 0.0601% 0.1802% 100.0000%
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 7.00 0.3494% 0.1747% 0.5241% 100.0000%
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.33 0.0160% 0.0080% 0.0240% 100.0000%
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.33 0.0246% 0.0123% 0.0370% 100.0000%
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.0000% 0.0000% 0.0000% 0.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 0.0000% 0.0000% 0.0000% 0.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0000% 0.0000% 0.0000% 0.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 18.50 0.0849% 0.0424% 0.1273% 100.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 18.50 0.0936% 0.0468% 0.1404% 100.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 11.50 0.9581% 0.3194% 1.2775% 100.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 17.13 1.5794% 0.5265% 2.1059% 50.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.13 0.1250% 0.1250% 0.2500% 25.0000%
100.0000% 48.8997% 2.8446% 51.7444%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 2232
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 22
Sisa Hari : 8

Tanggal : 06 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.7061% 0.0812% 1.7873% 75.8621%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000% SELESAI
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.6613% 0.0791% 1.7405% 75.8621%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.7465% 0.0832% 1.8297% 75.8621%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.7465% 0.0832% 1.8297% 75.8621%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.7029% 0.0335% 0.7363% 75.8621%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.6177% 0.0294% 0.6471% 75.8621%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.4483% 0.0690% 1.5173% 75.8621%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.4058% 0.0669% 1.4727% 75.8621%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 3.5783% 0.1704% 3.7487% 75.8621%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 1.4339% 0.1103% 1.5442% 70.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 4.5885% 0.3530% 4.9414% 70.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0347% 0.0027% 0.0374% 87.5000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.2772% 0.0213% 0.2985% 87.5000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0102% 0.0008% 0.0110% 87.5000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0550% 0.0042% 0.0592% 87.5000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0576% 0.0044% 0.0620% 87.5000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.4658% 0.0358% 0.5016% 87.5000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.3018% 0.0232% 0.3250% 87.5000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 1.8698% 0.1438% 2.0136% 87.5000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.1281% 0.0000% 0.1281% 100.0000% SELESAI
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.2738% 0.0000% 0.2738% 100.0000% SELESAI
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.1802% 0.0000% 0.1802% 100.0000% SELESAI
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.5241% 0.0000% 0.5241% 100.0000% SELESAI
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0240% 0.0000% 0.0240% 100.0000% SELESAI
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0370% 0.0000% 0.0370% 100.0000% SELESAI
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 26.06 0.0000% 0.0215% 0.0215% 12.5000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 142.00 0.0000% 0.2063% 0.2063% 12.5000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 1.50 0.0000% 0.0060% 0.0060% 12.5000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.1273% 0.0000% 0.1273% 100.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.1404% 0.0000% 0.1404% 100.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 0.0000% 0.0000% 0.0000% 0.0000%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 1.2775% 0.0000% 1.2775% 100.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 17.13 2.1059% 0.5265% 2.6323% 62.5000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.13 0.2500% 0.1250% 0.3750% 37.5000%
100.0000% 51.7444% 2.2807% 54.0250%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 2384
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 23
Sisa Hari : 7

Tanggal : 07 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.7873% 0.0812% 1.8686% 79.3103%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000% SELESAI
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.7405% 0.0791% 1.8196% 79.3103%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.8297% 0.0832% 1.9129% 79.3103%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.8297% 0.0832% 1.9129% 79.3103%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.7363% 0.0335% 0.7698% 79.3103%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.6471% 0.0294% 0.6765% 79.3103%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.5173% 0.0690% 1.5863% 79.3103%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.4727% 0.0669% 1.5396% 79.3103%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 3.7487% 0.1704% 3.9191% 79.3103%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 1.5442% 0.1103% 1.6545% 75.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 4.9414% 0.3530% 5.2944% 75.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0374% 0.0027% 0.0400% 93.7500%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.2985% 0.0213% 0.3199% 93.7500%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0110% 0.0008% 0.0118% 93.7500%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0592% 0.0042% 0.0634% 93.7500%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0620% 0.0044% 0.0665% 93.7500%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.5016% 0.0358% 0.5374% 93.7500%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.3250% 0.0232% 0.3482% 93.7500%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 2.0136% 0.1438% 2.1575% 93.7500%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.1281% 0.0000% 0.1281% 100.0000% SELESAI
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.2738% 0.0000% 0.2738% 100.0000% SELESAI
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.1802% 0.0000% 0.1802% 100.0000% SELESAI
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.5241% 0.0000% 0.5241% 100.0000% SELESAI
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0240% 0.0000% 0.0240% 100.0000% SELESAI
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0370% 0.0000% 0.0370% 100.0000% SELESAI
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 26.06 0.0215% 0.0215% 0.0429% 25.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 142.00 0.2063% 0.2063% 0.4127% 25.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 1.50 0.0060% 0.0060% 0.0119% 25.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.1273% 0.0000% 0.1273% 100.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.1404% 0.0000% 0.1404% 100.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 29.79 0.0000% 0.2260% 0.2260% 14.2857%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 162.29 0.0000% 1.3155% 1.3155% 14.2857%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 0.0000% 0.0000% 0.0000% 0.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 1.2775% 0.0000% 1.2775% 100.0000%
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 17.13 2.6323% 0.5265% 3.1588% 75.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.13 0.3750% 0.1250% 0.5000% 50.0000%
100.0000% 54.0250% 3.8222% 57.8473%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 2536
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 24
Sisa Hari : 6

Tanggal : 08 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.8686% 0.0812% 1.9498% 82.7586%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000% SELESAI
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.8196% 0.0791% 1.8987% 82.7586%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.9129% 0.0832% 1.9960% 82.7586%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.9129% 0.0832% 1.9960% 82.7586%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.7698% 0.0335% 0.8033% 82.7586%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.6765% 0.0294% 0.7059% 82.7586%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.5863% 0.0690% 1.6553% 82.7586%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.5396% 0.0669% 1.6066% 82.7586%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 3.9191% 0.1704% 4.0895% 82.7586%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 1.6545% 0.1103% 1.7648% 80.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 5.2944% 0.3530% 5.6473% 80.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 1.38 0.0400% 0.0027% 0.0427% 100.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 6.25 0.3199% 0.0213% 0.3412% 100.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 1.38 0.0118% 0.0008% 0.0126% 100.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 6.25 0.0634% 0.0042% 0.0677% 100.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 1.44 0.0665% 0.0044% 0.0709% 100.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 6.81 0.5374% 0.0358% 0.5732% 100.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 1.38 0.3482% 0.0232% 0.3714% 100.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 6.25 2.1575% 0.1438% 2.3013% 100.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.1281% 0.0000% 0.1281% 100.0000% SELESAI
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.2738% 0.0000% 0.2738% 100.0000% SELESAI
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.1802% 0.0000% 0.1802% 100.0000% SELESAI
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.5241% 0.0000% 0.5241% 100.0000% SELESAI
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0240% 0.0000% 0.0240% 100.0000% SELESAI
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0370% 0.0000% 0.0370% 100.0000% SELESAI
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 26.06 0.0429% 0.0215% 0.0644% 37.5000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 142.00 0.4127% 0.2063% 0.6190% 37.5000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 1.50 0.0119% 0.0060% 0.0179% 37.5000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.1273% 0.0000% 0.1273% 100.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.1404% 0.0000% 0.1404% 100.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 29.79 0.2260% 0.2260% 0.4521% 28.5714%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 162.29 1.3155% 1.3155% 2.6311% 28.5714%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 30.83 0.0000% 1.2527% 1.2527% 16.6667%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 1.2775% 0.0000% 1.2775% 100.0000% SELESAI
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 17.13 3.1588% 0.5265% 3.6853% 87.5000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.13 0.5000% 0.1250% 0.6250% 62.5000%
100.0000% 57.8473% 5.0749% 62.9222%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 2688
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 25
Sisa Hari : 5

Tanggal : 09 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 1.9498% 0.0812% 2.0310% 86.2069%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000% SELESAI
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.8987% 0.0791% 1.9778% 86.2069%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 1.9960% 0.0832% 2.0792% 86.2069%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 1.9960% 0.0832% 2.0792% 86.2069%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.8033% 0.0335% 0.8368% 86.2069%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.7059% 0.0294% 0.7353% 86.2069%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.6553% 0.0690% 1.7242% 86.2069%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.6066% 0.0669% 1.6735% 86.2069%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 4.0895% 0.1704% 4.2598% 86.2069%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 1.7648% 0.1103% 1.8751% 85.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 5.6473% 0.3530% 6.0003% 85.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0427% 0.0000% 0.0427% 100.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.3412% 0.0000% 0.3412% 100.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0126% 0.0000% 0.0126% 100.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0677% 0.0000% 0.0677% 100.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0709% 0.0000% 0.0709% 100.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.5732% 0.0000% 0.5732% 100.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.3714% 0.0000% 0.3714% 100.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 2.3013% 0.0000% 2.3013% 100.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.1281% 0.0000% 0.1281% 100.0000% SELESAI
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.2738% 0.0000% 0.2738% 100.0000% SELESAI
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.1802% 0.0000% 0.1802% 100.0000% SELESAI
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.5241% 0.0000% 0.5241% 100.0000% SELESAI
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0240% 0.0000% 0.0240% 100.0000% SELESAI
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0370% 0.0000% 0.0370% 100.0000% SELESAI
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 26.06 0.0644% 0.0215% 0.0859% 50.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 142.00 0.6190% 0.2063% 0.8253% 50.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 1.50 0.0179% 0.0060% 0.0239% 50.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.1273% 0.0000% 0.1273% 100.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.1404% 0.0000% 0.1404% 100.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 29.79 0.4521% 0.2260% 0.6781% 42.8571%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 162.29 2.6311% 1.3155% 3.9466% 42.8571%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 30.83 1.2527% 1.2527% 2.5054% 33.3333%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 1.2775% 0.0000% 1.2775% 100.0000% SELESAI
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 17.13 3.6853% 0.5265% 4.2118% 100.0000%
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.13 0.6250% 0.1250% 0.7500% 75.0000%
100.0000% 62.9222% 4.8386% 67.7608%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 2840
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 26
Sisa Hari : 4

Tanggal : 10 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 2.0310% 0.0812% 2.1123% 89.6552%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000% SELESAI
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 1.9778% 0.0791% 2.0569% 89.6552%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 2.0792% 0.0832% 2.1624% 89.6552%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 2.0792% 0.0832% 2.1624% 89.6552%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.8368% 0.0335% 0.8702% 89.6552%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.7353% 0.0294% 0.7647% 89.6552%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.7242% 0.0690% 1.7932% 89.6552%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.6735% 0.0669% 1.7405% 89.6552%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 4.2598% 0.1704% 4.4302% 89.6552%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 1.8751% 0.1103% 1.9854% 90.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 6.0003% 0.3530% 6.3533% 90.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0427% 0.0000% 0.0427% 100.0000%
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.3412% 0.0000% 0.3412% 100.0000%
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0000% 0.0000% 0.0000% 0.0000%
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0126% 0.0000% 0.0126% 100.0000%
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0677% 0.0000% 0.0677% 100.0000%
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0709% 0.0000% 0.0709% 100.0000%
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.5732% 0.0000% 0.5732% 100.0000%
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.3714% 0.0000% 0.3714% 100.0000%
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 2.3013% 0.0000% 2.3013% 100.0000%
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.1281% 0.0000% 0.1281% 100.0000% SELESAI
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.2738% 0.0000% 0.2738% 100.0000% SELESAI
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.1802% 0.0000% 0.1802% 100.0000% SELESAI
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.5241% 0.0000% 0.5241% 100.0000% SELESAI
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0240% 0.0000% 0.0240% 100.0000% SELESAI
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0370% 0.0000% 0.0370% 100.0000% SELESAI
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 26.06 0.0859% 0.0215% 0.1073% 62.5000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 142.00 0.8253% 0.2063% 1.0316% 62.5000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 1.50 0.0239% 0.0060% 0.0298% 62.5000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.1273% 0.0000% 0.1273% 100.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.1404% 0.0000% 0.1404% 100.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 29.79 0.6781% 0.2260% 0.9041% 57.1429%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 162.29 3.9466% 1.3155% 5.2621% 57.1429%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 30.83 2.5054% 1.2527% 3.7581% 50.0000%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 1.2775% 0.0000% 1.2775% 100.0000% SELESAI
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 4.2118% 0.0000% 4.2118% 100.0000% SELESAI
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.13 0.7500% 0.1250% 0.8750% 87.5000%
100.0000% 67.7608% 4.3122% 72.0730%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 2992
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 27
Sisa Hari : 3

Tanggal : 11 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 2.1123% 0.0812% 2.1935% 93.1034%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000% SELESAI
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 2.0569% 0.0791% 2.1360% 93.1034%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 2.1624% 0.0832% 2.2455% 93.1034%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 2.1624% 0.0832% 2.2455% 93.1034%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.8702% 0.0335% 0.9037% 93.1034%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.7647% 0.0294% 0.7942% 93.1034%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.7932% 0.0690% 1.8622% 93.1034%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.7405% 0.0669% 1.8074% 93.1034%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 4.4302% 0.1704% 4.6006% 93.1034%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 1.9854% 0.1103% 2.0957% 95.0000%
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 6.3533% 0.3530% 6.7062% 95.0000%
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0427% 0.0000% 0.0427% 100.0000% SELESAI
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.3412% 0.0000% 0.3412% 100.0000% SELESAI
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 1.00 0.0000% 0.0125% 0.0125% 100.0000% SELESAI
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0126% 0.0000% 0.0126% 100.0000% SELESAI
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0677% 0.0000% 0.0677% 100.0000% SELESAI
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0709% 0.0000% 0.0709% 100.0000% SELESAI
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.5732% 0.0000% 0.5732% 100.0000% SELESAI
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.3714% 0.0000% 0.3714% 100.0000% SELESAI
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 2.3013% 0.0000% 2.3013% 100.0000% SELESAI
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.1281% 0.0000% 0.1281% 100.0000% SELESAI
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.2738% 0.0000% 0.2738% 100.0000% SELESAI
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.1802% 0.0000% 0.1802% 100.0000% SELESAI
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.5241% 0.0000% 0.5241% 100.0000% SELESAI
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0240% 0.0000% 0.0240% 100.0000% SELESAI
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0370% 0.0000% 0.0370% 100.0000% SELESAI
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 26.06 0.1073% 0.0215% 0.1288% 75.0000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 142.00 1.0316% 0.2063% 1.2380% 75.0000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 1.50 0.0298% 0.0060% 0.0358% 75.0000%
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.1273% 0.0000% 0.1273% 100.0000%
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.1404% 0.0000% 0.1404% 100.0000%
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 29.79 0.9041% 0.2260% 1.1302% 71.4286%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 162.29 5.2621% 1.3155% 6.5777% 71.4286%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0000% 0.0000% 0.0000% 0.0000%
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 30.83 3.7581% 1.2527% 5.0108% 66.6667%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 1.2775% 0.0000% 1.2775% 100.0000% SELESAI
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 4.2118% 0.0000% 4.2118% 100.0000% SELESAI
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.0000% 0.0000% 0.0000% 0.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 0.0000% 0.0000% 0.0000% 0.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.0000% 0.0000% 0.0000% 0.0000%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 0.13 0.8750% 0.1250% 1.0001% 100.0000% SELESAI
100.0000% 72.0730% 4.3246% 76.3976%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 3144
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 28
Sisa Hari : 2

Tanggal : 12 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 2.1935% 0.0812% 2.2748% 96.5517%
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000% SELESAI
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 2.1360% 0.0791% 2.2151% 96.5517%
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 2.2455% 0.0832% 2.3287% 96.5517%
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 2.2455% 0.0832% 2.3287% 96.5517%
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.9037% 0.0335% 0.9372% 96.5517%
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.7942% 0.0294% 0.8236% 96.5517%
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.8622% 0.0690% 1.9311% 96.5517%
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.8074% 0.0669% 1.8743% 96.5517%
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 4.6006% 0.1704% 4.7710% 96.5517%
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 0.75 2.0957% 0.1103% 2.2060% 100.0000% SELESAI
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 0.75 6.7062% 0.3530% 7.0592% 100.0000% SELESAI
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0427% 0.0000% 0.0427% 100.0000% SELESAI
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.3412% 0.0000% 0.3412% 100.0000% SELESAI
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0125% 0.0000% 0.0125% 100.0000% SELESAI
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0126% 0.0000% 0.0126% 100.0000% SELESAI
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0677% 0.0000% 0.0677% 100.0000% SELESAI
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0709% 0.0000% 0.0709% 100.0000% SELESAI
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.5732% 0.0000% 0.5732% 100.0000% SELESAI
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.3714% 0.0000% 0.3714% 100.0000% SELESAI
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 2.3013% 0.0000% 2.3013% 100.0000% SELESAI
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.1281% 0.0000% 0.1281% 100.0000% SELESAI
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.2738% 0.0000% 0.2738% 100.0000% SELESAI
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.1802% 0.0000% 0.1802% 100.0000% SELESAI
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.5241% 0.0000% 0.5241% 100.0000% SELESAI
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0240% 0.0000% 0.0240% 100.0000% SELESAI
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0370% 0.0000% 0.0370% 100.0000% SELESAI
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 26.06 0.1288% 0.0215% 0.1503% 87.5000%
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 142.00 1.2380% 0.2063% 1.4443% 87.5000%
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 1.50 0.0358% 0.0060% 0.0417% 87.5000% SELESAI
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.1273% 0.0000% 0.1273% 100.0000% SELESAI
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.1404% 0.0000% 0.1404% 100.0000% SELESAI
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 29.79 1.1302% 0.2260% 1.3562% 85.7143%
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 162.29 6.5777% 1.3155% 7.8932% 85.7143%
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 4.00 0.0000% 0.0407% 0.0407% 100.0000% SELESAI
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 3.00 0.0000% 0.0348% 0.0348% 100.0000% SELESAI
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 30.83 5.0108% 1.2527% 6.2634% 83.3333%
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 1.2775% 0.0000% 1.2775% 100.0000% SELESAI
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 4.2118% 0.0000% 4.2118% 100.0000% SELESAI
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 1.00 0.0000% 1.4236% 1.4236% 33.3333%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.65 0.0000% 1.2311% 1.2311% 50.0000%
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 1.50 0.0000% 1.5883% 1.5883% 50.0000%
3 Witness Hydrotest 1.0 lot 3.4119% 0.33 0.0000% 1.1373% 1.1373% 33.3333%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.33 0.0000% 0.2157% 0.2157% 33.3333%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 1.0001% 0.0000% 1.0001% 100.0000% SELESAI
100.0000% 76.3976% 9.8587% 86.2563%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 3296
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 29
Sisa Hari : 1

Tanggal : 13 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP - FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 1.03 2.2748% 0.0812% 2.3560% 100.0000% SELESAI
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000% SELESAI
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 0.03 2.2151% 0.0791% 2.2942% 100.0000% SELESAI
2 Site Manager 1.0 Bln/Org 2.4119% 0.03 2.3287% 0.0832% 2.4119% 100.0000% SELESAI
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 0.03 2.3287% 0.0832% 2.4119% 100.0000% SELESAI
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.03 0.9372% 0.0335% 0.9706% 100.0000% SELESAI
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.03 0.8236% 0.0294% 0.8530% 100.0000% SELESAI
3 Construction Report 1.0 Lot/spk 2.0001% 0.03 1.9311% 0.0690% 2.0001% 100.0000% SELESAI
4 Project Procedure 1.0 Lot/spk 1.9413% 0.03 1.8743% 0.0669% 1.9413% 100.0000% SELESAI
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 1.03 4.7710% 0.1704% 4.9414% 100.0000% SELESAI
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 2.2060% 0.0000% 2.2060% 100.0000% SELESAI
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 7.0592% 0.0000% 7.0592% 100.0000% SELESAI
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0427% 0.0000% 0.0427% 100.0000% SELESAI
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.3412% 0.0000% 0.3412% 100.0000% SELESAI
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0125% 0.0000% 0.0125% 100.0000% SELESAI
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0126% 0.0000% 0.0126% 100.0000% SELESAI
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0677% 0.0000% 0.0677% 100.0000% SELESAI
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0709% 0.0000% 0.0709% 100.0000% SELESAI
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.5732% 0.0000% 0.5732% 100.0000% SELESAI
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.3714% 0.0000% 0.3714% 100.0000% SELESAI
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 2.3013% 0.0000% 2.3013% 100.0000% SELESAI
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.1281% 0.0000% 0.1281% 100.0000% SELESAI
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.2738% 0.0000% 0.2738% 100.0000% SELESAI
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.1802% 0.0000% 0.1802% 100.0000% SELESAI
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.5241% 0.0000% 0.5241% 100.0000% SELESAI
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0240% 0.0000% 0.0240% 100.0000% SELESAI
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0370% 0.0000% 0.0370% 100.0000% SELESAI
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 26.06 0.1503% 0.0215% 0.1717% 100.0000% SELESAI
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 142.00 1.4443% 0.2063% 1.6506% 100.0000% SELESAI
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 1.50 0.0417% 0.0060% 0.0477% 100.0000% SELESAI
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.1273% 0.0000% 0.1273% 100.0000% SELESAI
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.1404% 0.0000% 0.1404% 100.0000% SELESAI
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 29.79 1.3562% 0.2260% 1.5822% 100.0000% SELESAI
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 162.29 7.8932% 1.3155% 9.2087% 100.0000% SELESAI
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0407% 0.0000% 0.0407% 100.0000% SELESAI
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0348% 0.0000% 0.0348% 100.0000% SELESAI
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 30.83 6.2634% 1.2527% 7.5161% 100.0000% SELESAI
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 1.2775% 0.0000% 1.2775% 100.0000% SELESAI
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 4.2118% 0.0000% 4.2118% 100.0000% SELESAI
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 1.00 1.4236% 1.4236% 2.8472% 66.6667%
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 0.0000% 0.0000% 0.0000% 0.0000%
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 0.65 1.2311% 1.2311% 2.4622% 100.0000% SELESAI
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 1.50 1.5883% 1.5883% 3.1766% 100.0000% SELESAI
3 Witness Hydrotest 1.0 lot 3.4119% 0.33 1.1373% 1.1373% 2.2746% 66.6667%
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.33 0.2157% 0.2157% 0.4314% 66.6667%
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 1.0001% 0.0000% 1.0001% 100.0000% SELESAI
100.0000% 86.2563% 9.3199% 95.5762%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 3296
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1
LAPORAN HARIAN
Hari Ke : 30
Sisa Hari : 0

Tanggal : 14 April 2021


Judul Pekerjaan : Pemasangan Pipa Flowline Sumur Bor Baru RNT-SZ22 PT. Pertamina EP Asset 1 Field Rantau
Lokasi Pekerjaan : PT.PERTAMINA EP FIELD RANTAU
Kontraktor : PT SINAR ABADI KENCANA
SPB/SP3MP No. : 001/SPK/FL/21-014/RTU/2021
T.M.T Pekerjaan : 16/03/2021 s/d 14/04/2021
Jangka Waktu Pelaksanaan : 30 Hari Kalender

Hujan Berawan /
Mendung Cerah / Terang
Keadaan Cuaca Deras Sedang

Waktu s/d s/d s/d 08.00 s/d 17.00

Realisasi Bobot Realisasi Bobot


Realisasi Vol hari Realisasi Bobot Hari Progres
Vol Sat Bobot SPB (%) Kumulatif kemarin Komulatif
No URAIAN PEKERJAAN ini Ini (%) Pekerjaan (%) KETERANGAN
(%) (%)

<a> <b> <c> <d> < e=(c/a)xb > <f=d+e > <g=f/b>
A MATERIAL
1 Pengadaan Material Utama 1.0 Lot/spk 8.5456% 8.5456% 0.0000% 8.5456% 100.0000% SELESAI
B PEKERJAAN PERSIAPAN
1 Pengurusan Izin Kerja
1 Pengurusan Izin Kerja 1.0 Lot/spk 0.0653% 0.0653% 0.0000% 0.0653% 100.0000% SELESAI
2 Medical check up 15.0 Org 2.7178% 2.7178% 0.0000% 2.7178% 100.0000% SELESAI
2 Pembuatan Gudang sementara
1 Pembuatan Gudang sementara / m2 12.0 m2 1.6024% 1.6024% 0.0000% 1.6024% 100.0000% SELESAI
3 Tenaga Keamanan
1 Tenaga Keamanan 30.0 hari/org 2.3560% 2.3560% 0.0000% 2.3560% 100.0000% SELESAI
4 Pengadaan APD 15.0 Lot/org 5.1179% 5.1179% 0.0000% 5.1179% 100.0000% SELESAI
C Project Management dan Dokumen
1 Management
1 HSE Officer 1.0 Bln/Org 2.2942% 2.2942% 0.0000% 2.2942% 100.0000% SELESAI
2 Site Manager 1.0 Bln/Org 2.4119% 2.4119% 0.0000% 2.4119% 100.0000% SELESAI
3 QA/QC Engineer 1.0 Bln/Org 2.4119% 2.4119% 0.0000% 2.4119% 100.0000% SELESAI
2 Survey & Engineering
1 Survey 1.0 Lot/spk 0.9706% 0.9706% 0.0000% 0.9706% 100.0000% SELESAI
2 Drawing for Construction 1.0 Lot/spk 0.8530% 0.8530% 0.0000% 0.8530% 100.0000% SELESAI
3 Construction Report 1.0 Lot/spk 2.0001% 2.0001% 0.0000% 2.0001% 100.0000% SELESAI
4 Project Procedure 1.0 Lot/spk 1.9413% 1.9413% 0.0000% 1.9413% 100.0000% SELESAI
D Transportasi Kerja
1 Transportasi Kerja
1 Sewa Mobil 4WD Double Cabin 30.0 Hari 4.9414% 4.9414% 0.0000% 4.9414% 100.0000% SELESAI
2 Transportasi Peralatan dan matrial 0.0000%
1 Sewa Mobil Transport Material 15.0 Hari 2.2060% 2.2060% 0.0000% 2.2060% 100.0000% SELESAI
1 Sewa Picker Truck 6 x 4 Kap. c/w Winch 8 Ton 15.0 Hari 7.0592% 7.0592% 0.0000% 7.0592% 100.0000% SELESAI
E Pekerjaan Pemipaan
1 Pengeceran Pipa Sch.40
1 Ecer pipa ø2'' Sch 40 @ 12 M / Jts 22.0 jts 0.0427% 0.0427% 0.0000% 0.0427% 100.0000% SELESAI
2 Ecer pipa ø3'' Sch 40 @ 12 M / Jts 100.0 jts 0.3412% 0.3412% 0.0000% 0.3412% 100.0000% SELESAI
3 Ecer pipa ø8'' Sch 40 @ 12 M / Jts 1.0 jts 0.0125% 0.0125% 0.0000% 0.0125% 100.0000% SELESAI
2 Menyablon Pipa @ 12 M
1 Menyablon pipa ø2'' @12 M / Jts 22.0 jts 0.0126% 0.0126% 0.0000% 0.0126% 100.0000% SELESAI
2 Menyablon pipa ø3'' @12 M / Jts 100.0 jts 0.0677% 0.0677% 0.0000% 0.0677% 100.0000% SELESAI
3 Potong Dan Bevel Pipa Sch.40
1 Memotong & Bevel pipa ø2'' Sch 40 / Ttk 23.0 Ttk 0.0709% 0.0709% 0.0000% 0.0709% 100.0000% SELESAI
2 Memotong & Bevel pipa ø3'' Sch 40 / Ttk 109.0 Ttk 0.5732% 0.5732% 0.0000% 0.5732% 100.0000% SELESAI
4 Pengelasan Pipa Sch.40
1 Las pipa ø2'' Sch.40 @ 12 M / Jts 22.0 jts 0.3714% 0.3714% 0.0000% 0.3714% 100.0000% SELESAI
2 Las pipa ø3'' Sch.40 @ 12 M / Jts 100.0 jts 2.3013% 2.3013% 0.0000% 2.3013% 100.0000% SELESAI
5 Stel & las Flange sch.40
1 Stel & las flange ø2'' Sch.40 / Pcs 11.0 pcs 0.1281% 0.1281% 0.0000% 0.1281% 100.0000% SELESAI
2 Stel & las flange ø3'' Sch.40 / Pcs 17.0 pcs 0.2738% 0.2738% 0.0000% 0.2738% 100.0000% SELESAI
6 Elbow Sch.40
1 Stel & las Elbow ø2'' Sch.40 / Pcs 10.0 pcs 0.1802% 0.1802% 0.0000% 0.1802% 100.0000% SELESAI
2 Stel & las Elbow ø3'' Sch.40 / Pcs 21.0 pcs 0.5241% 0.5241% 0.0000% 0.5241% 100.0000% SELESAI
7 Tee Sch. 40
1 Stel & las Tee ø 2'' Sch.40 / Pcs 1.0 pcs 0.0240% 0.0240% 0.0000% 0.0240% 100.0000% SELESAI
8 Tee Reducer Sch. 40
1 Stel & las TeeReducer ø3 x 2'' Sch.40 / Pcs 1.0 pcs 0.0370% 0.0370% 0.0000% 0.0370% 100.0000% SELESAI
9 Mendudukkan Pipa Sch.40
1 Mendudukkan Pipa ø2'' Sch.40 / Mtr 208.5 mtr 0.1717% 0.1717% 0.0000% 0.1717% 100.0000% SELESAI
2 Mendudukkan Pipa ø3'' Sch.40 / Mtr 1,136.0 mtr 1.6506% 1.6506% 0.0000% 1.6506% 100.0000% SELESAI
3 Mendudukkan Pipa ø8'' Sch.40 / Mtr 12.0 mtr 0.0477% 0.0477% 0.0000% 0.0477% 100.0000% SELESAI
10 Wrapping Pipa
1 Pembalutan/ Wrapping pipa ø2"/Mtr 111.0 Mtr 0.8812% 0.8812% 0.0000% 0.8812% 100.0000% SELESAI
2 Pembalutan/ Wrapping pipa ø3"/Mtr 111.0 Mtr 1.0082% 1.0082% 0.0000% 1.0082% 100.0000% SELESAI
11 Lowering In Pipa Sch.40
2 Pipa ø2" Sch 40 /Mtr 55.5 Mtr 0.1273% 0.1273% 0.0000% 0.1273% 100.0000% SELESAI
2 Pipa ø3" Sch 40 /Mtr 55.5 Mtr 0.1404% 0.1404% 0.0000% 0.1404% 100.0000% SELESAI
12 Mengecat Pipa dengan, Cat menie & Cat Enamel
1 Pipa ø2'' Dengan Cat Enamel / Mtr 208.5 mtr 1.5822% 1.5822% 0.0000% 1.5822% 100.0000% SELESAI
2 Pipa ø3'' Dengan Cat Enamel / Mtr 1,136.0 mtr 9.2087% 9.2087% 0.0000% 9.2087% 100.0000% SELESAI
13 Pasang Ball Valve 150#
1 Pasang Valve 2'' - 150# / Pcs 4.0 pcs 0.0407% 0.0407% 0.0000% 0.0407% 100.0000% SELESAI
2 Pasang Valve 3'' - 150# / Pcs 3.0 pcs 0.0348% 0.0348% 0.0000% 0.0348% 100.0000% SELESAI
14 Pembuatan Support
1 Pembuatan Support dengan Pipa 3" 185.0 Set 7.5161% 7.5161% 0.0000% 7.5161% 100.0000% SELESAI
F Pekerjaan Sipil
1 Pekerjaan Galian
1 Galian Tanah Biasa 55.5 M3 1.5018% 1.5018% 0.0000% 1.5018% 100.0000% SELESAI
G Pekerjaan Pengujian
1 Pemeriksaan Radiography
1 Radiography Pipa Dia ø2" / Jts 46.0 jts 1.2775% 1.2775% 0.0000% 1.2775% 100.0000% SELESAI
2 Radiography Pipa Dia ø3" / Jts 137.0 jts 4.2118% 4.2118% 0.0000% 4.2118% 100.0000% SELESAI
2 Holidaytest
1 Holiday Test Pipa 2"-6" 111.0 Mtr 1.5280% 1.5280% 0.0000% 1.5280% 100.0000% SELESAI
3 Pengujian Hydrostatic Test
1 Pengujian Hydrostatic Tes 3.0 hari 4.2708% 1.00 2.8472% 1.4236% 4.2708% 100.0000% SELESAI
4 Pekerjaan Commisioning
1 Commissioning 1.0 Lot/Spk 1.6471% 1.00 0.0000% 1.6471% 1.6471% 100.0000% SELESAI
H Pekerjaan Sertifikasi
1 Sertifikasi Pipa
1 Biaya Sertifikasi Pipa 1.3 Km 2.4622% 2.4622% 0.0000% 2.4622% 100.0000% SELESAI
2 Transportasi Inspector & Team 3.0 Visit 3.1766% 3.1766% 0.0000% 3.1766% 100.0000% SELESAI
3 Witness Hydrotest 1.0 lot 3.4119% 0.33 2.2746% 1.1373% 3.4119% 100.0000% SELESAI
I Pekerjaan Penyelesaian
1 Pekerjaan Pembersihan
1 Pembersihan 1.0 Lot/Spk 0.6471% 0.33 0.4314% 0.2157% 0.6471% 100.0000% SELESAI
2 Pekerjaan As Built Drawing
1 As Built Drawing 1.0 Lot/Spk 1.0001% 1.0001% 0.0000% 1.0001% 100.0000% SELESAI
100.0000% 95.5762% 4.4238% 100.0000%

Tenaga Kerja Peralatan Kerja Disiapkan Dipakai Keterangan


1 Site Manager 1.0 Org Mesin Las 1 Unit
2 Admin 1.0 Org Mesin Potong 1 Unit
3 HSE Officer 1.0 Org Alat Instrumen
4 QA/QC Engineer 1.0 Org Alat Sipil
5 Pekerja Sipil 3.0 Org Alat Mekanik 1 Lot
6 Pekerja Mekanikal 12.0 Org Alat Berat

Kinerja HSE
Jenis Kecelakaan Hari ini Kumulatif Jam Kerja Selamat
1 Fatal 1. Jumlah Pekerja 19
2 Lost Time Incident (LTI) 2. Jam Kerja hari ini 8
3 Non Lost Time Incident (NLTI) 3. Jam Kerja Selamat 152
4 Near Miss 4. Kumulatif s/d hari ini 3448
5 Unsafe Act
6 Unsafe Condition Keterangan :
7 Medical Treatment Jam Kerja Selamat = Jam Kerja x Jumlah Pekerja
8 First Aid
Catatan
: On Progres
: Pekerjaan Telah Selesai

Dibuat Oleh : Disetujui Oleh :


Pelaksana Pekerjaan Pengawas Pekerjaan
PT. Sinar Abadi Kencana PT. PERTAMINA EP

Ahmad Fauzan Fahrul Muharram


Site Manager PMC Project Zona 1