Anda di halaman 1dari 3

Proyek Relokasi PLTDG Jakabaring 3x17 MW dan PLTDG

Batanghari 2x30 MW ke Halmahera Timur (PT. ANTAM)


Unit Pelaksana Proyek 2
Judul : LAPORAN DAILY PROGRESS
Hari / Tanggal : Senin, 03 April 2023
Tempat : Site Halmahera

NO PEKERJAAN TARGET REALISASI PIC KONDISI MANPOWER TINDAK LANJUT KETERANGAN


PEKERJAAN HARI INI
PT. PJBS JAKABARING (HALTIM)
1 - Runout shaft cooler lube oil fan 50% 50% Arief 43 Orang
2 - Filling hydraulic tank unit 1& 2 100% 100% Arief
3 - Penormala heater panel unit 1 jkb onprogress onprogress Wachid
4 - Penormalan control mcc unit 2 jkb onprogress onprogress Wachid
5 - Pemasangan Greeting Cooler Generator #1 onprogress onprogress Wachid
6 - Pemasangan & Charging Battery #1 onprogress onprogress Wachid
7 - Pemasangan & Charging Battery #2 100% 100% Wachid
8 - Dummy Load Battery #2 onprogress onprogress Wachid
9 - Pengechekan Tempearture Switch #1 onprogress onprogress Robi

PT. PJBS BATANGHARI (HALTIM)


10 - Waiting permit Onprogress Onprogress all Bidang 29 Orang
11 - Safety induction Onprogress Onprogress all Bidang
12 - Pemindahan truck tools dr dirkit ke area unit 2 100% 100% Andrianto
13 - Diassembly line piping atomizing 100% 100% Andrianto
14 - Disassembly line fleksibel gas dan hsd 100% 100% Andrianto
15 - Diassembly check valve hsd 100% 100% Andrianto
16 - Diassembly nozel 100% 100% Andrianto
17 - Disaasembly flange piping area engine 50% 50% Andrianto
18 - Disassembly baut pengikat exhaust blower 50% 50% Andrianto

PT. OMEGA SOLUSINDO BERSAMA


19 - Fit Up Pipa Underground untuk Tanki 5000 kL diarea Tanki onprogress onprogress Rifai 8 Orang
20 - Pengelasan Pipa Undrground untuk Tanki 5000 kL di area tankionprogress onprogress
21 - Pengecetan Pipa HSD onprogress onprogress

PT MIRLINDO
22 - Stringging Pipa Compressor 25% 25% Fauzan 7 Orang
23 - Stringging Support Compressor 28% 28%
24 - Fitt up pipa & Fitting Compressor 44% 44%
25 - Cutting rubber support Compressor 47% 47%
26 - Welding Pipa Compressor 16% 16%

TEMUAN PIC KONDISI TINDAK LANJUT


Proyek Relokasi PLTDG Jakabaring 3x17 MW dan PLTDG
Batanghari 2x30 MW ke Halmahera Timur (PT. ANTAM)
Unit Pelaksana Proyek 2
Judul : LAPORAN DAILY PROGRESS
Hari / Tanggal : Senin, 03 April 2023
Tempat : Site Halmahera

NO PEKERJAAN TARGET REALISASI PIC KONDISI MANPOWER TINDAK LANJUT KETERANGAN


PEKERJAAN
RENCANA HARI INI BESOK
PEKERJAAN
PT. PJBS JAKABARING (HALTIM)
1 - Runout shaft cooler lube oil fan onprogress 43 Orang
2 - Penormalan control mcc unit 1 jkb onprogress Wachid
3 - Penormala heater panel unit 1 jkb onprogress Wachid
4 - Penormalan control mcc unit 2 jkb onprogress Wachid
5 - Pengechekan Tempearture Switch #1

PT. PJBS BATANGHARI (HALTIM)


6 - Waiting permit Onprogress all Bidang 29 Orang
7 - Safety induction Onprogress all Bidang
8 - Disaasembly flange piping area engine 100% Andrianto
9 - Disassembly baut pengikat exhaust blower 100% Andrianto

PT. OMEGA SOLUSINDO BERSAMA


5 - Fit Up Pipa Underground untuk Tanki 5000 kL diarea Tanki onprogress Rifai 8 Orang
6 - Pengelasan Pipa Undrground untuk Tanki 5000 kL di area tankionprogress
7 - Pengecetan Pipa HSD onprogress 3 Oang

PT MIRLINDO
10 - Stringging Pipa Compressor 25% Fauzan 7 Orang
11 - Stringging Support Compressor 28%
12 - Fitt up pipa & Fitting Compressor 44%
13 - Cutting rubber support Compressor 47%
14 - Welding Pipa Compressor 16%

RENDAL

DERRY FERDIANSYAH
Proyek Relokasi PLTDG Jakabaring 3x17 MW dan PLTDG
Batanghari 2x30 MW ke Halmahera Timur (PT. ANTAM)
Unit Pelaksana Proyek 2

Anda mungkin juga menyukai