Anda di halaman 1dari 2

TIMES SCHEDULE

BULAN KE
NO URAIAN PEKERJAAN BOBOT PERSEN
1 2 3 4 5 6 7 8 9 10 11 12
1. PEK. PENDAHULUAN 1.597 1.597 100

2.861 2.861 2.861


2. PEK. TANAH / PONDASI 8.583

4.190 4.190 4.190 4.190 4.190 4.190 4.190 4.190


3. PEK. BETON 33.517
80
2.578 2.578 2.578 2.578 2.578 2.578
4. PEK. DINDING 15.468
2.384 2.384 2.384 2.384
5. PEK. KAYU,ATAP,PLAFON 9.537
2.7152 2.7152 2.7152 2.7152 2.7152 60
6. PEK. LANTAI 13.576

2.905 2.905
7. PEK. PINTU DAN JENDELA 5.810

0.707 0.707 0.707 0.707 0.707 40


8. PEK. PENGECETAN 3.535

0.2486 0.2486 0.2486 0.249 0.249 0.249 0.249 0.249 0.249


9. PEK. INSTALASI LISTRIK 2.237

1.101 1.101 1.101 1.101 1.101 20


10. PEK. SANITASI 5.503

0.319 0.319
11. PEK. FINISHING 0.637
0
Jumlah bobot rencana 100 4.458 7.051 9.629 7.016 9.731 9.731 10.438 11.539 14.250 7.345 4.759 4.052
Kumulatif bobot rencana 0 4.458 11.509 21.137 28.153 37.885 47.616 58.055 69.594 83.844 91.189 95.948 100.000
jumlah bobotrealisasi
kumulatif bobot realisasi
selisih