Anda di halaman 1dari 2

Proyek Relokasi PLTG Jakabaring 3x17 MW dan PLTG Batanghari 2x30 MW

Unit Pelaksana Proyek 2 Halmahera Timur (PT. ANTAM)


Title / Judul : DAILY REPORT / LAPORAN HARIAN
Date and Time / Hari-Tgl : Minggu, 04 Juni 2023
Place / Tempat : Site Halmahera Timur

NO TODAY'S WORK / PEKERJAAN HARI INI TARGET REALIZATION PIC CONDITION MANPOWER FOLLOW-UP INFORMATION
PT. REKADAYA ELEKTRIKA - RE
1 Area Monitoring & Standby On Site 100% - Kuswandi ±12 Orang
2 Berkoordinasi Pekerjaan Ke Under RE 100% - Kuswandi -
3 Pasang Batako Dinding ATS JKB 100% 76% Trido/Sigit P 2 Orang
4 Pulling Kabel di EDG 100% 100% Andi 4 Orang
5
6

PT. BANGUN KARYA PERKASA JAYA - BKPJ


1 Plesteran dan acian dinding, Administrasi Building 100% 98% Bagus Imanullah 7 Orang
2 Perapian kanopi, Administrasi Building 100% 98% Bagus Imanullah 8 Orang
3 Pemasangan rangka plafon, Administrasi Building 100% 55% Bagus Imanullah 2 Orang
4 Pengecetan dinding sisi dalam, Administrasi Buiiding 100% 60% Bagus Imanullah 2 Orang
5 Pemasangan keramik lantai, Administasi Building 100% 80% Bagus Imanullah 4 Orang
6 Pemasangan keramik lantai toilet, Administasi Building 100% 50% Bagus Imanullah 3 Orang
7 Pemasangan keramik dinding toilet, Administasi Building 100% 70% Bagus Imanullah 3 Orang
8 Bekisting lantai atap, Masjid 100% 78% Bagus Imanullah 7 Orang
9 Pembesian balok, Masjid 100% 50% Bagus Imanullah 3 Orang
10 Pemasangan pintu dan jendela, Adminstrasi Building 100% 65% Bagus Imanullah 2 Orang
11 Kupas tanah untuk badan jalan CCR Ke Barat ke Ruang Batery 100% - Bagus Imanullah -
12 Drainase keliling, WWL 100% 85% Bagus Imanullah 8 Orang
13 Pagar keliling sisi barat 100% 68% Bagus Imanullah 8 Orang
14 Pagar Keliling sisi timur 100% 68% Bagus Imanullah 7 Orang
15 Pengecoran landscaping GT Batanghari unit 2 100% 65% Bagus Imanullah 9 Orang
16 Perapian galian tanah, Landscaping GT Batanghari unit 1 100% 80% Bagus Imanullah 4 Orang
17 Pengecoran dinding saluran GT Batanghari unit 1, (sebelah selatan) 100% 100% Bagus Imanullah 8 Orang
18 Lantai kerja sloof pagar BRC 100% 50% Bagus Imanullah 6 Orang
19 Pemasangan keramik lantai teras, CCR 100% 60% Bagus Imanullah 3 Orang
20 Pemasangan keramik dinding meja pantry, CCR 100% 40% Bagus Imanullah 2 Orang
21 Fabrikasi pembesian 100% - 5 Orang

PT. INDOBARA - IBB


1 Setting auto on diesel pump 100% 70% Eka Agustira 2 Orang
2 Cek alignment diesel pump 100% 70% Eka Agustira 2 Orang
3 Pasang pipa gass suppression 100% 100% Eka Agustira 2 Orang
4 Pasang SRP foam system clean tank 100% 100% Eka Agustira 2 Orang
5
6

PT. TEKNO FLUIDA INDONESIA - TFI


1 Pembersihan tangki DWT setelah drain 100% 100% M. Ali Topan 3 Orang
2 Melanjutkan pemasangan grounding WTP ke Grit 100% 100% M. Ali Topan 3 Orang
3
4
5

PT. MITRATEK BANGUN GEMILANG - MBG


1 Libur 100% 100% Rahmat 5 Orang
2 100% 100% Rahmat 5 Orang
3 100% 100% Rahmat 5 Orang
4 100% 100% Rahmat 5 Orang

PT. NUTECH INTEGRASI


1 Libur 100% 100% Miskun 3 Orang
2 100% 75% Miskun 4 Orang
3 100% 85% Miskun 3 Orang
4 100% 60% Miskun 3 Orang
5 100% 60% Miskun 3 Orang

PT. AGUNG JAYA ENGINNERING - AJE


1 Libur 100% - Hendra 3 Orang
2

PT. TRAFINDO - TPP


1 Comissioning Trafo 1 & 2 100% 50% Ahmad 3 Orang

PIC KONDISI TINDAK LANJUT

TOMORROW'S WORK PLAN / RENCANA KERJA BESOK

PT. REKADAYA ELEKTRIKA - RE


1 Area Monitoring & Standby On Site 100% - Kuswandi ±12 Orang
2 Berkoordinasi Pekerjaan Ke Under RE 100% - Kuswandi -
3 Pasang Batako Dinding ATS di Jakabaring 100% 76% Trido/Sigit P 2 Orang
4 Pembersihan Lumpur Cable Trench JKB Unit 2 100% - Trido/Sigit P 3 Orang
5 Pengecoran Bottom Cable Trench JKB Unit 2 100% - Trido/Sigit P 5 Orang
6
7

PT. BANGUN KARYA PERKASA JAYA - BKPJ


1 Plesteran dan acian dinding, Administrasi Building 100% 98% Bagus Imanullah 7 Orang
2 Perapian kanopi, Administrasi Building 100% 98% Bagus Imanullah 8 Orang
3 Pemasangan rangka plafon, Administrasi Building 100% 55% Bagus Imanullah 2 Orang
4 Pengecetan dinding sisi dalam, Administrasi Buiiding 100% 60% Bagus Imanullah 2 Orang
5 Pemasangan keramik lantai, Administasi Building 100% 80% Bagus Imanullah 4 Orang
6 Pemasangan keramik lantai toilet, Administasi Building 100% 50% Bagus Imanullah 3 Orang
7 Pemasangan keramik dinding toilet, Administasi Building 100% 70% Bagus Imanullah 3 Orang
8 Bekisting lantai atap, Masjid 100% 78% Bagus Imanullah 7 Orang
9 Pembesian balok, Masjid 100% 50% Bagus Imanullah 3 Orang
10 Pemasangan pintu dan jendela, Adminstrasi Building 100% 65% Bagus Imanullah 2 Orang
11 Kupas tanah untuk badan jalan CCR Ke Barat ke Ruang Batery 100% - Bagus Imanullah -
12 Drainase keliling, WWL 100% 85% Bagus Imanullah 8 Orang
13 Pagar keliling sisi barat 100% 68% Bagus Imanullah 8 Orang
14 Pagar Keliling sisi timur 100% 68% Bagus Imanullah 7 Orang
15 Pengecoran landscaping GT Batanghari unit 2 100% 65% Bagus Imanullah 9 Orang
16 Perapian galian tanah, Landscaping GT Batanghari unit 1 100% 80% Bagus Imanullah 4 Orang
17 Lantai kerja sloof pagar BRC 100% 50% Bagus Imanullah 6 Orang
18 Pemasangan keramik lantai teras, CCR 100% 60% Bagus Imanullah 3 Orang
19 Pemasangan keramik dinding meja pantry, CCR 100% 40% Bagus Imanullah 2 Orang
20 Fabrikasi pembesian 100% - 5 Orang

PT. INDOBARA - IBB


1 Setting auto on diesel pump 100% 70% Eka Agustira 2 Orang
2 Cek alignment diesel pump 100% 70% Eka Agustira 2 Orang
3
4
PT. TEKNO FLUIDA INDONESIA - TFI
1 Pengisian tangki NaOH HCl untuk regenerasi 100% - M. Ali Topan 3 Orang
2 Melanjutkan Filling water RWT 100% - M. Ali Topan 3 Orang
3 Melanjutkan trial anion cation A 100% - M. Ali Topan 3 Orang
4
5

PT. MITRATEK BANGUN GEMILANG - MBG


1 Membuat 2 Buat Galian area FF & WTP Untuk Check Visual Grounding 100% - Rahmat 5 Orang
2 Melanjutkan Moving Kabel & Pulling 1c-500 dari Generator 3 ke GSUT 100% - Rahmat 5 Orang
3

PT. NUTECH
1 Pasang Public Access Speaker 10 buah di Admin Building 100% 75% Miskun 4 Orang
2 Instal patch cord UTP cat pada equipment rack di CCR 100% 85% Miskun 3 Orang
3 Pasang CCTV di Admin Building 100% 60% Miskun 3 Orang
4 Pasang JB dan kabel clock di Admin building 100% 60% Miskun 3 Orang

PT. AGUNG JAYA ENGINERING - AJE


1 Dewatering Cable Trench JKB Unit 1 100% - Hendra 3 Orang
2 Pengelasan Cable Tray di Cable Trench JKB Unit 1 100% - Hendra 3 Orang
-

PT. TRAFINDO - TPP


1 Melanjutkan Comissioning Trafo 1 & 2 100% - Risal 3 Orang

Mengetahui, Dibuat Oleh

KUSWANDI EFLEN BATAWI


SITE MANAGER ADMIN PROJECT
Proyek Relokasi PLTG Jakabaring 3x17 MW dan PLTG Batanghari 2x30 MW
Halmahera Timur (PT. ANTAM)
Unit Pelaksana Proyek 2

Lampiran Dokumentasi