NO TODAY'S WORK / PEKERJAAN HARI INI TARGET REALIZATION PIC CONDITION MANPOWER FOLLOW-UP INFORMATION
PT. REKADAYA ELEKTRIKA - RE
1 Area Monitoring & Standby On Site 100% - Kuswandi ±12 Orang
2 Berkoordinasi Pekerjaan Ke Under RE 100% - Kuswandi -
3 Pasang Batako Dinding ATS JKB 100% 76% Trido/Sigit P 2 Orang
4 Pulling Kabel di EDG 100% 100% Andi 4 Orang
5
6
PT. NUTECH
1 Pasang Public Access Speaker 10 buah di Admin Building 100% 75% Miskun 4 Orang
2 Instal patch cord UTP cat pada equipment rack di CCR 100% 85% Miskun 3 Orang
3 Pasang CCTV di Admin Building 100% 60% Miskun 3 Orang
4 Pasang JB dan kabel clock di Admin building 100% 60% Miskun 3 Orang