Anda di halaman 1dari 1

PT PEMBANGKITAN JAWA BALI SERVICES

SIAP INTEGRATED MANAGEMENT SYSTEM


RECOVERY TURBINE PLTG PLN-ANTAM HALTIM UNIT 2
TAHUN 2023
LAPORAN PROGRESS PEKERJAAN HARI KE 15 TANGGAL 14 APRIL 2023
Bobot Bobot Total Prog.
Item Pekerjaan Keterangan
Rencana Realisasi / Pekerjaan KURVA S
GE Frame VI 100.00%
DISASSEMBLY 33.00% 33.00% 100.00% Closed
INSPECTION AND REPAIR 15.53% 15.98% 63.91% On Progress
ASESMENT STATIC
0.67% 1.00% 25.00% On Progress 90.00%
BALANCING
ASSEMBLY 0.00% 0.00% 0.00% On Progress
FSNL & SIAP SINKRON 0.00% 0.00% 0.00% On Progress
TOTAL PROGRESS 49.20% 49.98% 80.00%

INFORMASI PROGRESS
RENCANA 49.20% 70.00%
REALISASI 49.98%
LEADING 0.78%

60.00%
PROGRESS

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%
1 4 7 10 13 16 19 22 25 28 31 34 37
HARI KE-

Rencana Realisasi

Mengetahui Yang Membuat


Site Manager Rendal Project

Hafidz Purwa Kusuma Angga Pramana

Anda mungkin juga menyukai