NAMA PEKERJAAAN :PENGGANTIAN DAN CLEANING LINE PIPA CWBP DAN HE C3W
NOMOR KONTRAK /SPK/SPJ/PO : 0268.SPK/DAN.01.02/PLNIP150000/2023
LOKASI PEKERJAAN : TURBIN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Durasi
Bobot Keterang
No Uraian Kegiatan Pekerjaa
% Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari Hari an
n ( day)
Ke-1 Ke-2 Ke-3 Ke-4 Ke-5 Ke-6 Ke-7 Ke-8 Ke-9 Ke-10 Ke-11 Ke-12 Ke-13 Ke-14 Ke-15 Ke-16 Ke-17 Ke-18 Ke-19 Ke-20
5 Pelepasan Baut dan Pembongkaran Elbow 4 20,0% 5,00% 5,00% 5,00% 5,00%
6 Cleaning Flang dan Pemasangan Elbow Bar dan Baud Pres 4 20,0% 5,00% 5,00% 5,00% 5,00%
Total 20 100,0%
Rencana Pekerjaan 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00% 5,00%
Rencana Kumulatif 5,00% 10,00% 15,00% 20,00% 25,00% 30,00% 35,00% 40,00% 45,00% 50,00% 55,00% 60,00% 65,00% 70,00% 75,00% 80,00% 85,00% 90,00% 95,00% 100,00%
Realisasi Progress 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Realisai kumulatif progress 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%