Anda di halaman 1dari 1

RENCANA ANGGARAN BIAYA (RAB)

KELURAHAN : GUNUNG STELENG No. RAB :


KECAMATAN : PENAJAM S. DANA : SWADAYA MASYARAKAT
KABUPATEN : PENAJAM PASER UTARA
PROPINSI : KALIMANTAN TMUR KEGIATAN : Pembangunan Dudukan Kubah
Mesjid ........................... (Pak Ion)

HRG SATUAN JUMLAH


URAIAN VOLUME SAT TOTAL
(Rp.) (Rp.)
a b c d e=b xd
1 BAHAN
1 Semen portland @ 40 kg 54.91 zak 54,000.00 2,965,373.44
2 Pasir Pasang Putih 4.56 m³ 212,500.00 969,937.98
3 Batu split 3.11 m³ 400,000.00 1,242,117.33
4 Air 1167.88 ltr 91.66 107,051.38
5 Besi beton (polos/ulir)
Besi Ø12 31.00 btg 135,000.00 4,185,000.00
Besi Ø8 19.00 btg 56,000.00 1,064,000.00
Besi Ø10 38.00 btg 98,000.00 3,724,000.00
Besi Ø6 24.00 btg 42,000.00 1,008,000.00
6 Bendrat 11.40 kg 30,000.00 342,009.54
7 Paku 5 - 12 cm 12.52 kg 25,000.00 313,056.00
8 Minyak begisting 6.26 ltr 11,000.00 68,872.32
9 Balok kayu kelas II 0.58 m³ 2,530,000.00 1,475,708.52
10 Plywood tebal 9 mm 10.96 lbr 137,500.00 1,506,582.00
11 Kayu Sungkai Ø8-12 171.75 btg 11,000.00 1,889,289.60
12 Bata merah 1065.24 bh 900.00 958,716.00
13 Krawangan Tempel GRC 10.00 m² 625,000.00 6,250,000.00
SUB TOTAL 1 21,819,714.11
2 ALAT / PERLENGKAPAN

SUB TOTAL 2 -
3 UPAH / BIAYA
1 Upah Borongan Tukang (35% x Sub Total 1) 35.00 % 21,819,714.11 7,636,899.94
2 Pemasangan Krawangan tempel 10.00 m² 250,000.00 2,500,000.00
SUB TOTAL 3 10,136,899.94
4 BIAYA PERENCANAAN

SUB TOTAL 4 -
JUMLAH 31,956,614.05
PEMBULATAN 31,956,000.00

Terbilang : Tiga Puluh Satu Juta Sembilan Ratus Lima Puluh Enam Ribu Rupiah,-