DAFTAR HARGA UPAH

NO JENIS UPAH SPESIFIKASI harga real SATUAN

1 Pekerja / knek Rp 100,000.00 Oh


2 Tukang gali Rp 120,000.00 Oh
3 Kepala tukang batu Rp 80,000.00 Oh
4 Tukang batu Rp 55,000.00 Oh
5 Kepala tukang kayu Rp 80,000.00 Oh
6 Tukang kayu Rp 55,000.00 Oh
7 Kepala tukang besi Rp 80,000.00 Oh
8 Tukang besi Rp 55,000.00 Oh
9 Kepala tukang cat Rp 80,000.00 Oh
10 Tukang Cat Rp 55,000.00 Oh
11 Tukang aspalt Rp 55,000.00 Oh
12 Mandor/ pengawas Rp 150,000.00 Oh
13 Instalator Rp 80,000.00 Oh
14 Pembantu instalator Rp 120,000.00 Oh
15 Tukang babat rumput Rp 120,000.00 Oh
16 Tukang taman Rp 120,000.00 Oh
17 Kepala tukang pasang pipa Rp 80,000.00 Oh
18 Tukang pasang pipa Rp 120,000.00 Oh
19 Operator alat besar Rp 155,000.00 Oh
20 Pembantu operator alat besar Rp 100,000.00 Oh
21 Tukang las Rp 120,000.00 Oh
DAFTAR HARGA MATERIAL
NO JENIS UPAH SPESIFIKASI HARGA SATUAN SATUAN

PASIR DAN BATU


Pasir Urug 223.57 313,000 M3
Pasir Pasang 558.57 782,000 M3
Pasir Beton Hitam 107.14 150,000 M3
Pasir Putih Bangka - - M3
Batu Kali 400.00 560,000 M3
Batu Split 400.00 560,000 M3
Batu Pecah 3/5 560,000 M3
Sirtu - M3
Tanah 75,000 M3
Batu Bata Klas I 1,200 BH
Batu Bata Klas II 800 BH
Batako 10x20x40x0.5 cm - BH
Bata Ringan - - M3

SEMEN
Tiga Roda 40kg 1,775.00 71,000 ZAK
Tiga Roda 50kg 1,310.00 65,500 ZAK
Gresik 40kg - - ZAK
Gresik 50kg - - ZAK
Tonasa 40kg - - ZAK
Tonasa 50kg - - ZAK
Holcim 50kg - - ZAK
Holcim 40kg - - ZAK
Semen SCG 50kg - - ZAK
MU-300 Perekat bata - - ZAK
MU-380
Semen Warna 7,000 KG

KAYU
Dolken Kayu dia. 5 cm 22,500 BTG
Kayu Terentang (Durian) 1,850,000 M3
Papan Terlentang (Durian) 1,850,000 M3
Papan Kruing - M3
Papan Meranti - M3
Papan Borneo - M3
Kaso 5/7 Kruing - M3
Kaso 5/7 Kamper - M3
Kaso 5/7 Meranti - M3
Kaso 5/7 Borneo - BTG
Papan Bekisting (kayu Putih) - M3
Kau Buah (Steger) - M3
Steger (kayu Balok Campuran) - M3
Kayu Bakar - M3
Papan & Kayu Besi 5/10 - M3
Kayu Besi 10/10 - M3
Kayu Besi 6/12 - M3
Papan dan Kayu Matoa 5/10 - M3
Kayu Matoa 5/5 23,625 - M3
Bambu kecil - BTG
Bambu Sedang - BTG
Bambu Besar - BTG
Galam 10/12 6M - BTG
Galam 8/9 6M - BTG
Galam 6/10 7M - BTG
Plywood 3 mm 65,000 LBR
Plywood 4 mm 92,500 LBR
NO JENIS UPAH SPESIFIKASI HARGA SATUAN SATUAN

Plywood 6 mm 97,500 LBR


Plywood 9 mm 127,500 LBR
Plywood 12 mm 262,500 LBR

CAT TEMBOK PUTIH 25 KG


Vinilex 35,000 - PEIL
Catylac 45,000 KG
Dulux - PEIL
Metrolite - KG
Plamir 40,000 KG
Cat Dasar 72,000 KG

CAT TEMBOK WARNA 5 KG


Avian - GLN
Vinilex 41000 - GLN

CAT MINYAK 1 KG
Glotex - KLG
Avian - KLG
nippe 2000 - KLG

PIPA PVC
PVC Uk. 1/2" - BTG
PVC Uk. 3/4" - BTG
PVC Uk. 1" - BTG
PVC Uk. 1 1/2" - BTG
PVC Uk. 2" - BTG
PVC Uk. 2 1/2" - BTG
PVC Uk. 3" - BTG
PVC Uk. 4" - BTG
PVC Uk. 6" - BTG

PVC Uk. 1/2" 24,360 BTG


PVC Uk. 3/4" 25,375 BTG
PVC Uk. 1" 34,800 BTG
PVC Uk. 1 1/2" 40,600 BTG
PVC Uk. 2" 49,300 BTG
PVC Uk. 2 1/2" - BTG
PVC Uk. 3" 65,250 BTG
PVC Uk. 4" 118,900 BTG
PVC Uk. 6" - BTG

BESI
Besi Polos 6 mm - BTG
Besi Polos 8 mm - BTG
Besi Polos 10 mm - BTG
Besi Polos 12 mm - BTG
Besi Polos 16 mm - BTG
Besi Ulir 10 mm - BTG
Besi Ulir 13 mm - BTG
Besi Ulir 16 mm - BTG
Besi Ulir 19 mm - BTG
Besi Ulir 25 mm - BTG
Besi Siku 20x20x3 - BTG
Besi Siku 30x30x3 - BTG
Besi Siku 40x40x3 - BTG
Besi Siku 30x30x4 - BTG
Besi Siku 40x40x4 - BTG
Besi Siku 50x50x4 - BTG
Seng Gelombang 0.02x90 cm - LBR
Seng Gelombang 0.03x90 cm 115,000 LBR
Kawat Bendrat 22,500 KG
NO JENIS UPAH SPESIFIKASI HARGA SATUAN SATUAN

Wiremess m4 2,1X5,4 - - LBR


Wiremess m6 2,1X5,4 66,137.57 750,000 LBR
Wiremess m8 2,1X5,4 74,955.91 850,000 LBR
Wiremess m10 2,1X5,4 - - LBR
Besi Polos 22,500 KG
Besi Ulir 27,500 KG
Bondex - M2
Spandex - M2

PAKU
Paku Biasa 9,000 KG
Paku Beton 5 cm 22,000 KG
Paku Beton 7 cm 22,000 KG
Paku Tripleks 25,000 KG

GENTENG
Genteng Metal SAKURA T.0.3MM 95,000 LBR
Genteng Metal MULTIROOF T.0.3MM 52,500 LBR
Genteng Metal Serbuk - LBR
Bubung / Nok Metal - BH
Rangka Atap Baja Ringan 185,000 M2

KERAMIK
Keramik Roman - M2
Keramik Asia Tile 75,000 M2
Keramik KIA - M2
Keramik Mulia - M2

PLAFOND
Gypsum 9 mm 110,000 LBR

Air 250 LTR


ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

I PEKERJAAN PERSIAPAN
ANALISA 001 1 m' Pagar Sementara dari Seng Gelombang tinggi 2 m 498,320.00 68,600.00 566,920.00
JUMLAH (A+B+C) 566,920.00
OVERHEAD & PROFIT (Max 15%) -
HARGA SATUAN PEKERJAAN (D+E) 566,920.00

ANALISA 002 1 m' Pek. Pengukuran kembali (site) & Pemasangan Bowplank 56,680.00 23,550.00 80,230.00
JUMLAH (A+B+C) 80,230.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 80,230.00

ANALISA 003 1 m² Pek. Kantor Direksi Keet , dengan lantai plesteran 821,522.50 591,500.00 1,413,022.50
JUMLAH (A+B+C) 1,413,022.50
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,413,022.50
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 004 1 m² Pembuatan Gudang Semen dan Alat - alat 653,087.50 363,500.00 1,016,587.50
JUMLAH (A+B+C) 1,016,587.50
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,016,587.50

ANALISA 005 1 m² Pembuatan Bedeng Buruh 622,412.50 363,500.00 985,912.50


JUMLAH (A+B+C) 985,912.50
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 985,912.50

II PEKERJAAN TANAH
ANALISA 006 1 m3 Pek. Galian Tanah Biasa Max Kedalaman 1 m' 0.00 109,000.00 109,000.00
JUMLAH (A+B+C) 109,000.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 109,000.00

ANALISA 007 1 m3 Pek. Galian Tanah Biasa Max Kedalaman 2 m' 0.00 123,300.00 123,300.00
JUMLAH (A+B+C) 123,300.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 123,300.00

ANALISA 008 1 m3 Pek. Galian Tanah Keras Max Kedalaman 1 m' 0.00 134,800.00 134,800.00
JUMLAH (A+B+C) 134,800.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 134,800.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 009 1 m³ Pembuangan Tanah sejauh 150 m 0.00 26,700.00 26,700.00


JUMLAH (A+B+C) 26,700.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 26,700.00

ANALISA 010 1 m3 Pek. Urugan Pasir 375,600.00 31,500.00 407,100.00


JUMLAH (A+B+C) 407,100.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 407,100.00

IV PEKERJAAN DINDING
ANALISA 011 1 m2 Pasangan Bata Merah 1Pc : 3Ps 1/2 Bata 112,786.75 45,050.00 157,836.75
JUMLAH (A+B+C) 157,836.75
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 157,836.75

V PEKERJAAN PELESTERAN
ANALISA 012 1 m2 Plesteran Dinding 1Pc : 3Ps 42,645.20 53,550.00 96,195.20
JUMLAH (A+B+C) 96,195.20
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 96,195.20
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 013 1 m2 Plesteran Dinding 1 : 3 + ACIAN 34,532.00 42,800.00 77,332.00


JUMLAH (A+B+C) 77,332.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 77,332.00

PEKERJAAN BETON
ANALISA 014 1 m³ Membuat Beton Tumbuk 1 Pc : 3 Ps : 5 Kr 952,150.00 209,000.00 1,161,150.00
JUMLAH (A+B+C) 1,161,150.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,161,150.00

ANALISA 015 1 m³ Membuat Beton Tumbuk 1 Pc : 4 Ps : 6 Kr 879,775.00 209,000.00 1,088,775.00


JUMLAH (A+B+C) 1,088,775.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,088,775.00

ANALISA 016 1 m³ Membuat Beton Bertulang 1 Pc : 2 Ps : 4 Kr 1,068,500.00 209,000.00 1,277,500.00


JUMLAH (A+B+C) 1,277,500.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,277,500.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 017 1 m³ Membuat Beton Bertulang 1 Pc : 1 Ps : 2Kr 1,320,125.00 209,000.00 1,529,125.00


JUMLAH (A+B+C) 1,529,125.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,529,125.00

ANALISA 018 1 m³ Membuat Beton Bertulang 1 Pc : 2Ps : 3 Splt 1,131,000.00 394,800.00 1,525,800.00
JUMLAH (A+B+C) 1,525,800.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,525,800.00

ANALISA 019 1 m³ Membuat Beton Kedap Air dengan Strorox - 100 1,240,395.00 394,800.00 1,635,195.00
JUMLAH (A+B+C) 1,635,195.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,635,195.00

ANALISA 020 1 Kg Pembesian dengan Besi Polos atau Besi Ulir 23,962.50 1,641.00 25,603.50
JUMLAH (A+B+C) 25,603.50
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 25,603.50
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 021 1 m2 Pasang Bekisting Uuntuk Lantai 157,103.00 73,140.00 230,243.00


JUMLAH (A+B+C) 230,243.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 230,243.00

ANALISA 022 1 m2 Pasang Bekisting untuk Sloof 76,889.00 64,030.00 140,919.00


JUMLAH (A+B+C) 140,919.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 140,919.00

ANALISA 023 1 m2 Pasang Bekisting untuk Kolom 184,853.00 73,140.00 257,993.00


JUMLAH (A+B+C) 257,993.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 257,993.00

ANALISA 024 1 m2 Pasang Bekisting untuk Balok 190,403.00 75,140.00 265,543.00


JUMLAH (A+B+C) 265,543.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 265,543.00

ANALISA 025 1 m2 Pasang Bekisting untuk Dinding 274,875.00 75,140.00 350,015.00


Bahan
JUMLAH (A+B+C) 350,015.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 350,015.00

ANALISA 026 1 m³ Membuat Sloof Beton Bertulang ( 200 Kg + bekisting ) 4,824,259.00 934,180.00 5,758,439.00
JUMLAH (A+B+C) 5,758,439.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 5,758,439.00

ANALISA 027 1 m³ Membuat Kolom Beton Bertulang ( 300 Kg + bekisting ) 7,762,905.00 1,503,100.00 9,266,005.00
JUMLAH (A+B+C) 9,266,005.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 9,266,005.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 028 1 m³ Membuat Balok Beton Bertulang ( 150 Kg + bekisting ) 5,340,074.00 1,145,350.00 6,485,424.00
JUMLAH (A+B+C) 6,485,424.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 6,485,424.00

ANALISA 029 1 m³ Membuat Dinding Beton Bertulang ( 150 Kg + bekisting ) 5,086,074.00 1,105,750.00 6,191,824.00
JUMLAH (A+B+C) 6,191,824.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 6,191,824.00

ANALISA 030 1 m1 Membuat Ring Balok Beton Bertulang (10 x 15) cm 84,687.50 44,630.00 129,317.50
JUMLAH (A+B+C) 129,317.50
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 129,317.50

V PEKERJAAN PENTUP ATAP


ANALISA 031 1m² Pasang Atap Genteng Metal 98,700.00 32,950.00 131,650.00
JUMLAH (A+B+C) 131,650.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 131,650.00

ANALISA 032 1m' Pasang Nok Genteng Metal 204,750.00 46,150.00 250,900.00
JUMLAH (A+B+C) 250,900.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 250,900.00

VII PEKERJAAN LANGIT - LANGIT


ANALISA 033 1 m² Langit - langit Gypsum 39,870.00 20,325.00 60,195.00
JUMLAH (A+B+C) 60,195.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 60,195.00

ANALISA 034 Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50cm 321,735.00 213,170.00 534,905.00
JUMLAH (A+B+C) 534,905.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 534,905.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 035 Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (60 x 60 )cm, t = 65cm 492,139.80 336,360.00 828,499.80
JUMLAH (A+B+C) 828,499.80
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 828,499.80

ANALISA 036 Memasang 1 m' Pipa PVC tipe AW Ø ½" 26,040.00 11,550.00 37,590.00
JUMLAH (A+B+C) 37,590.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 37,590.00

ANALISA 037 Memasang 1 m' Pipa PVC tipe AW Ø ¾" 27,125.00 11,550.00 38,675.00
JUMLAH (A+B+C) 38,675.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 38,675.00

ANALISA 038 Memasang 1 m' Pipa PVC tipe AW Ø 1" 37,200.00 11,550.00 48,750.00
JUMLAH (A+B+C) 48,750.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 48,750.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 039 Memasang 1 m' Pipa PVC tipe AW Ø 1½" 62,930.00 11,550.00 74,480.00
JUMLAH (A+B+C) 74,480.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 74,480.00

ANALISA 040 Memasang 1 m' Pipa PVC tipe AW Ø 2" 52,700.00 17,325.00 70,025.00
JUMLAH (A+B+C) 70,025.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 70,025.00

ANALISA 041 Memasang 1 m' Pipa PVC tipe AW Ø 2½" 0.00 11,550.00 11,550.00
JUMLAH (A+B+C) 11,550.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 11,550.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 042 Memasang 1 m' Pipa PVC tipe AW Ø 3" 69,750.00 25,995.00 95,745.00
JUMLAH (A+B+C) 95,745.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 95,745.00

ANALISA 043 Memasang 1 m' Pipa PVC tipe AW Ø 4" 127,100.00 25,995.00 153,095.00
JUMLAH (A+B+C) 153,095.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 153,095.00

VII PEKERJAAN BESI DAN ALLUMINIUM


ANALISA 044 1 Kg Pasang Rangka Atap Baja 23,376.00 8,325.00 31,701.00
JUMLAH (A+B+C) 31,701.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 31,701.00

ANALISA 045 1 m² Pasang Pintu Besi Baja 650,000.00 153,000.00 803,000.00


JUMLAH (A+B+C) 803,000.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 803,000.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 046 1 m² Pasang Jendela Besi 265,000.00 240,187.50 505,187.50


JUMLAH (A+B+C) 505,187.50
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 505,187.50

ANALISA 047 1 m² Pasang Terali Besi 202,400.00 241,050.00 443,450.00


JUMLAH (A+B+C) 443,450.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 443,450.00

ANALISA 048 1 m² Pasang Kawat Harmonika 212,055.00 22,875.00 234,930.00


JUMLAH (A+B+C) 234,930.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 234,930.00

ANALISA 049 1 Buah Pasang Rel Pintu Dorong 275,000.00 83,250.00 358,250.00
JUMLAH (A+B+C) 358,250.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 358,250.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

VI PEKERJAAN PENUTUP LANTAI DAN DINDING


ANALISA 050 1 m² Pasang Lantai Keramik 33 x 33 cm 146,043.50 111,300.00 257,343.50
JUMLAH (A+B+C) 257,343.50
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 257,343.50

ANALISA 051 1 m² Pasang Lantai Keramik 33 x 33 cm anti slip 63,543.50 111,300.00 174,843.50
JUMLAH (A+B+C) 174,843.50
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 174,843.50

VI PEKERJAAN PENGECATAN
ANALISA 052 1 m² Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 41,308.00 10,439.00 51,747.00
JUMLAH (A+B+C) 51,747.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 51,747.00

ANALISA 053 1 m² Pengecatan Permukaan Baja dengan Meni Besi 2,072.00 29,100.00 31,172.00
JUMLAH (A+B+C) 31,172.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 31,172.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 054 1m3 Pengurugan Kembali Tanah bekas galian 0.00 57,500.00 57,500.00
JUMLAH (A+B+C) 57,500.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 57,500.00

ANALISA 055 Memasang 1 m' Pipa PVC tipe AW Ø 4" 127,100.00 17,205.00 144,305.00
JUMLAH (A+B+C) 144,305.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 144,305.00

ANALISA 056 Memasang 1 m' Pipa PVC tipe AW Ø 10" 0.00 17,205.00 17,205.00
JUMLAH (A+B+C) 17,205.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 17,205.00

ANALISA 057 1m3 Pasangan Pondasi Batu Belah Campuran 1 sp : 5pp 1,338,808.00 208,500.00 1,547,308.00
JUMLAH (A+B+C) 1,547,308.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,547,308.00
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 058 1m3 Pasangan Batu Aanstamping 807,216.00 108,420.00 915,636.00


JUMLAH (A+B+C) 915,636.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 915,636.00

ANALISA 059 1m3 Pasangan Lantai Kerja beton mutu f'c = 7,4 Mpa (K100) 964,728.57 141,600.00 1,106,328.57
JUMLAH (A+B+C) 1,106,328.57
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,106,328.57

ANALISA 060 1m3 beton mutu f'c = 21.7 Mpa (K250) 1,004,305.36 194,815.00 1,199,120.36
JUMLAH (A+B+C) 1,199,120.36
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,199,120.36

ANALISA 061 1m3 beton mutu f'c = 26.4 Mpa (K300) 1,051,226.79 194,815.00 1,246,041.79
JUMLAH (A+B+C) 1,246,041.79
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,246,041.79
ANALISA HARGA SATUAN S.N.I
NO. URAIAN KOEF SAT HARGA SAT matrial HARGA SAT upah JUMLAH matrial JUMLAH upah TOTAL harga

A B C D E F G=(CXE) H = (C X F ) I = ( G+H )

ANALISA 062 1 m³ Membuat Dinding Beton Bertulang ( 200 Kg + bekisting ) 5,752,568.00 1,016,490.00 6,769,058.00
JUMLAH (A+B+C) 6,769,058.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 6,769,058.00

ANALISA 063 1 m2 Pasang Bekisting untuk Lantai 274,853.00 113,190.00 388,043.00


JUMLAH (A+B+C) 388,043.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 388,043.00

ANALISA 064 1 m2 Pemasangan Acian 5,768.75 34,300.00 40,068.75


JUMLAH (A+B+C) 40,068.75
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 40,068.75

ANALISA 065 1 m2 Pembesian dengan WIREMESS M8 82,789.00 1,641.00 84,430.00


JUMLAH (A+B+C) 84,430.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 84,430.00

ANALISA 066 1 m2 Pembesian dengan WIREMESS M6 73,088.82 1,641.00 74,729.82


Bahan
Wiremess M6 1.10 m2 66,137.57 72,751.32
Kawat Beton 0.02 Kg 22,500.00 337.50
Tenaga
Perkerja 0.01 Oh Rp 100,000.00 700
Tukang Besi 0.01 Oh Rp 120,000.00 Rp 840.00
Kepala Tukang 0.00 Oh Rp 80,000.00 Rp 56.00
Mandor 0.00 Oh Rp 150,000.00 45
C PERALATAN
-
-

JUMLAH (A+B+C) 74,729.82


OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 74,729.82

ANALISA 066 1 m2 Pembesian dengan WIREMESS M10 337.50 1,641.00 1,978.50


JUMLAH (A+B+C) 1,978.50
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 1,978.50

ANALISA 067 1 m3 Pek. Pengurugan Kembali Tanah Bekas Galian 0.00 57,500.00 57,500.00
JUMLAH (A+B+C) 57,500.00
OVERHEAD & PROFIT (Max 15%) 0% -
HARGA SATUAN PEKERJAAN (D+E) 57,500.00
KODE SATUAN PEKERJAAN

PEKERJAAN PERSIAPAN
ANALISA 001 1 m' Pagar Sementara dari Seng Gelombang tinggi 2 m
ANALISA 002 1 m' Pek. Pengukuran kembali (site) & Pemasangan Bowplank
ANALISA 003 1 m² Pek. Kantor Direksi Keet , dengan lantai plesteran
ANALISA 004 1 m² Pembuatan Gudang Semen dan Alat - alat
ANALISA 005 1 m² Pembuatan Bedeng Buruh

PEKERJAAN TANAH
ANALISA 006 1 m3 Pek. Galian Tanah Biasa Max Kedalaman 1 m'
ANALISA 007 1 m3 Pek. Galian Tanah Biasa Max Kedalaman 2 m'
ANALISA 008 1 m3 Pek. Galian Tanah Keras Max Kedalaman 1 m'
ANALISA 009 1 m³ Pembuangan Tanah sejauh 150 m
ANALISA 010 1 m3 Pek. Pengurugan Kembali Tanah Bekas Galian
ANALISA 011 1 m3 Pek. Urugan Pasir
ANALISA 012 1m3 Pasangan Pondasi Batu Belah Campuran 1 sp : 5pp
ANALISA 013 1m3 Pasangan Batu Aanstamping

PEKERJAAN DINDING
ANALISA 014 1 m2 Pasangan Bata Merah 1Pc : 3Ps 1/2 Bata
ANALISA 015 1 m2 Plesteran Dinding 1Pc : 3Ps
ANALISA 016 1 m2 Plesteran Dinding 1 : 3 + ACIAN
ANALISA 017 1 m2 Pemasangan Acian

PEKERJAAN BETON
ANALISA 018 1 m³ Membuat Beton Tumbuk 1 Pc : 3 Ps : 5 Kr
ANALISA 019 1 m³ Membuat Beton Tumbuk 1 Pc : 4 Ps : 6 Kr
ANALISA 020 1 m³ Membuat Beton Bertulang 1 Pc : 2 Ps : 4 Kr
ANALISA 021 1 m³ Membuat Beton Bertulang 1 Pc : 1 Ps : 2Kr
ANALISA 022 1 m³ Membuat Beton Bertulang 1 Pc : 2Ps : 3 Splt
ANALISA 023 1 m³ Membuat Beton Kedap Air dengan Strorox - 100
ANALISA 024 1 m2 Pasang Bekisting Uuntuk Lantai
ANALISA 025 1 m2 Pasang Bekisting untuk Sloof
ANALISA 026 1 m2 Pasang Bekisting untuk Kolom
ANALISA 027 1 m2 Pasang Bekisting untuk Balok
ANALISA 028 1 m2 Pasang Bekisting untuk Dinding
ANALISA 029 1 m³ Membuat Sloof Beton Bertulang ( 200 Kg + bekisting )
ANALISA 030 1 m³ Membuat Kolom Beton Bertulang ( 300 Kg + bekisting )
ANALISA 031 1 m³ Membuat Balok Beton Bertulang ( 150 Kg + bekisting )
ANALISA 032 1 m2 Pasang Bekisting untuk Lantai
ANALISA 033 1 m³ Membuat Dinding Beton Bertulang ( 150 Kg + bekisting )
ANALISA 034 1 m³ Membuat Dinding Beton Bertulang ( 200 Kg + bekisting )
ANALISA 035 1 m1 Membuat Ring Balok Beton Bertulang (10 x 15) cm
ANALISA 036 1m3 Pasangan Lantai Kerja beton mutu f'c = 7,4 Mpa (K100)
ANALISA 037 1m3 beton mutu f'c = 21.7 Mpa (K250)
ANALISA 038 1m3 beton mutu f'c = 26.4 Mpa (K300)
ANALISA 039 1 Kg Pembesian dengan Besi Polos atau Besi Ulir
ANALISA 040 1 m2 Pembesian dengan WIREMESS M8
ANALISA 041 1 m2 Pembesian dengan WIREMESS M6
ANALISA 042 1 m2 Pembesian dengan WIREMESS M10

PEKERJAAN PENTUP ATAP


ANALISA 043 1m² Pasang Atap Genteng Metal
ANALISA 044 1m' Pasang Nok Genteng Metal

PEKERJAAN LANGIT - LANGIT


ANALISA 044 1 m² Langit - langit Gypsum
ANALISA 045 Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50cm
ANALISA 046 Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (60 x 60 )cm, t = 65cm

PEKERJAAN PEMIPAAN
ANALISA 047 Memasang 1 m' Pipa PVC tipe AW Ø ½"
ANALISA 048 Memasang 1 m' Pipa PVC tipe AW Ø ¾"
ANALISA 049 Memasang 1 m' Pipa PVC tipe AW Ø 1"
ANALISA 050 Memasang 1 m' Pipa PVC tipe AW Ø 1½"
ANALISA 051 Memasang 1 m' Pipa PVC tipe AW Ø 2"
ANALISA 052 Memasang 1 m' Pipa PVC tipe AW Ø 2½"
ANALISA 053 Memasang 1 m' Pipa PVC tipe AW Ø 3"
ANALISA 054 Memasang 1 m' Pipa PVC tipe AW Ø 4"
ANALISA 055 Memasang 1 m' Pipa PVC tipe AW Ø 10"

PEKERJAAN BESI DAN ALLUMINIUM


ANALISA 053 1 Kg Pasang Rangka Atap Baja
ANALISA 054 1 m² Pasang Pintu Besi Baja
ANALISA 055 1 m² Pasang Jendela Besi
ANALISA 056 1 m² Pasang Terali Besi
ANALISA 057 1 m² Pasang Kawat Harmonika
ANALISA 058 1 Buah Pasang Rel Pintu Dorong

PEKERJAAN PENUTUP LANTAI DAN DINDING


ANALISA 059 1 m² Pasang Lantai Keramik 33 x 33 cm
ANALISA 060 1 m² Pasang Lantai Keramik 33 x 33 cm anti slip

PEKERJAAN PENGECATAN
ANALISA 061 1 m² Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
ANALISA 062 1 m² Pengecatan Permukaan Baja dengan Meni Besi
ANALISA 063 1m3 Pengurugan Kembali Tanah bekas galian
PEKERJAAN LAIN-LAIN
1 unit Tutup Chamber Besi Siku + Plat Besi
HARGA SATUAN

Rp 566,920.00
Rp 80,230.00
Rp 1,413,022.50
Rp 1,016,587.50
Rp 985,912.50

Rp 109,000.00
Rp 123,300.00
Rp 134,800.00
Rp 26,700.00
Rp 57,500.00
Rp 407,100.00
Rp 1,547,308.00
Rp 915,636.00

Rp 157,836.75
Rp 96,195.20
Rp 77,332.00
Rp 40,068.75

Rp 1,161,150.00
Rp 1,088,775.00
Rp 1,277,500.00
Rp 1,529,125.00
Rp 1,525,800.00
Rp 1,635,195.00
Rp 230,243.00
Rp 140,919.00
Rp 257,993.00
Rp 265,543.00
Rp 350,015.00
Rp 5,758,439.00
Rp 9,266,005.00
Rp 6,485,424.00
Rp 388,043.00
Rp 6,191,824.00
Rp 6,769,058.00
Rp 129,317.50
Rp 1,106,328.57
Rp 1,199,120.36
Rp 1,246,041.79
Rp 25,603.50
Rp 84,430.00
Rp 74,729.82
Rp 1,978.50

Rp 131,650.00
Rp 250,900.00

Rp 60,195.00
Rp 534,905.00
Rp 828,499.80

Rp 37,590.00
Rp 38,675.00
Rp 48,750.00
Rp 74,480.00
Rp 70,025.00
Rp 11,550.00
Rp 95,745.00
Rp 153,095.00
Rp 17,205.00

Rp 31,701.00
Rp 803,000.00
Rp 505,187.50
Rp 443,450.00
Rp 234,930.00
Rp 358,250.00

Rp 257,343.50
Rp 174,843.50

Rp 51,747.00
Rp 31,172.00
Rp 57,500.00