I PEKERJAAN PRELIMINARIES
1 Pembongkaran Kondisi Existing 1.00 ls 0 0 sdh dilaksanakan
3
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN TOTAL (Rp) TOTAL (Rp)
(Rp)
1 2 3 4 5 6=(3x5) 7
12 Dewatering 1.00 ls 47,500,000 47,500,000.00
13 Keselamatan Kerja dan Kebersihan K3 12.00 bln 2,500,000 30,000,000.00
14 Biaya-biaya koordinasi, approval gambar, material, dll 1.00 ls 12,500,000 12,500,000.00
15 Sample material dan biaya-biaya pengetesan laboratorium 1.00 ls 10,000,000 10,000,000.00
4
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
IV PEKERJAAN STRUKTUR
IV.A. PEKERJAAN SUB STRUKTUR (BASEMENT)
1. Basement - 3
- Fix Bekisting Batako 330.78 m2 187,500 62,021,137.50
- Water Proofing membrand 330.78 m2 127,500 42,174,373.50
- Water Stop 110.26 m 67,125 7,401,189.08
- Dinding Beton Tebal 30 cm (termasuk tulangan dan 99.23 m3 3,750,000 372,126,825.00
bekisting)
- Kolom Beton ukuran 80 x 80 cm (termasuk tulangan dan 49.68 m3 4,500,000 223,579,872.00
bekisting)
- Balok 83.71 m3 4,250,000 355,756,620.00
- Plat Lantai 120.39 m3 3,750,000 451,446,375.00
- Struktur GWT 9.97 m3 4,250,000 42,365,640.50
- Struktur Tangga 6.08 m3 4,000,000 24,302,160.00
- Ramp 11.93 m3 4,000,000 47,704,240.00
2. Basement - 2
- Fix Bekisting Batako 330.78 m2 187,500 62,021,137.50
- Water Proofing membrand 330.78 m2 127,500 42,174,373.50
- Water Stop 110.26 m 67,125 7,401,189.08
- Dinding Beton Tebal 30 cm (termasuk tulangan dan 99.23 m3 3,750,000 372,126,825.00
bekisting)
- Kolom Beton ukuran 80 x 80 cm (termasuk tulangan dan 49.68 m3 4,500,000 223,579,872.00
bekisting)
- Balok 83.71 m3 4,250,000 355,756,620.00
- Plat Lantai 120.39 m2 3,750,000 451,446,375.00
- Struktur Tangga 6.08 m3 4,000,000 24,302,160.00
- R. Lift 5.40 m3 4,000,000 21,601,920.00
- Ramp 11.93 m3 4,000,000 47,704,240.00
5
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
3 Basement - 1
- Fix Bekisting Batako 396.94 m2 187,500 74,425,365.00
- Water Proofing membrand 396.94 m2 127,500 50,609,248.20
- Water Stop 110.26 m 67,125 7,401,189.08
- Dinding Beton Tebal 30 cm (termasuk tulangan dan 119.08 m3 3,750,000 446,552,190.00
bekisting)
- Kolom Beton ukuran 80 x 80 cm (termasuk tulangan dan 49.68 m3 4,500,000 223,579,872.00
bekisting)
- Balok 83.71 m3 4,250,000 355,756,620.00
- Plat Lantai 114.99 m2 3,750,000 431,194,575.00
- Struktur Tangga 6.55 m3 4,000,000 26,192,328.00
- R. Lift 5.60 m3 4,000,000 22,411,992.00
- Ramp 17.84 m3 4,000,000 71,376,344.00
Sub Jumlah IV.A. 4,946,492,867.93
1. LANTAI - 1
- Kolom Beton ukuran 80 x 80 cm (termasuk tulangan dan 61.97 m3 4,500,000 278,867,286.00
bekisting)
- Balok 76.96 m3 4,250,000 327,066,570.00
- Plat Lantai 96.76 m2 4,250,000 411,224,050.00
- Struktur Tangga 8.12 m3 4,000,000 32,492,888.00
- R. Lift 7.02 m3 4,000,000 28,082,496.00
2. LANTAI - 2
- Kolom Beton ukuran 80 x 80 cm (termasuk tulangan dan 49.57 m3 4,500,000 223,073,577.00
bekisting)
- Balok 76.96 m3 4,250,000 327,066,570.00
- Plat Lantai 96.76 m2 4,250,000 411,224,050.00
6
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
- Struktur Tangga 6.50 m3 4,000,000 26,012,312.00
- R. Lift 5.61 m3 4,000,000 22,456,996.00
- Struktur Kolam Renang 12.15 m3 4,250,000 51,642,090.00
3. LANTAI - 3
- Kolom Beton ukuran 80 x 80 cm (termasuk tulangan dan 49.57 m3 4,500,000 223,073,577.00
bekisting)
- Balok 76.96 m3 4,250,000 327,066,570.00
- Plat Lantai 96.76 m3 4,250,000 411,224,050.00
- Struktur Tangga 6.50 m3 4,000,000 26,012,312.00
- R. Lift 5.61 m3 4,000,000 22,456,996.00
4 LANTAI - 4 s.d. 15
- Kolom Beton ukuran 80 x 80 cm (termasuk tulangan dan 818.00 m3 5,500,000 4,499,021,752.50
bekisting)
- Balok 1269.79 m3 4,250,000 5,396,598,405.00
- Plat Lantai 1596.52 m2 4,250,000 6,785,196,825.00
- Struktur Tangga 107.23 m3 4,000,000 428,933,124.00
- R. Lift 92.67 m3 4,000,000 370,675,446.00
5 LANTAI - ATAP
- Kolom Beton dan sirip Beton (termasuk tulangan dan 159.76 m3 5,500,000 878,703,100.00
bekisting)
- Balok 3.67 m3 4,250,000 15,588,260.50
- Plat Lantai 6.91 m2 4,250,000 29,359,484.50
- Struktur Tangga 6.50 m3 4,000,000 26,012,312.00
- R. Lift 5.61 m3 4,000,000 22,456,996.00
Sub Jumlah IV.A. 21,601,588,095.50
7
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
V. PEKERJAAN ARSITEKTUR/FINISHING
2. LANTAI - 1
- Pester/Acian Beton Ekspose (Dinding/Kolom) 220.80 m2 57,500 12,696,000.00
- Pasangan Bata Ringan Tebal 12 cm 1,050.00 m2 187,500 196,875,000.00
- Plester dan Acian 2,100.00 m2 64,750 135,975,000.00
- Pengecatan Dinding 2,320.80 m2 37,500 87,030,000.00
3. LANTAI - 2
- Pester/Acian Beton Ekspose (Dinding/Kolom) 220.80 m2 57,500 12,696,000.00
- Pasangan Bata Ringan Tebal 12 cm 752.00 m2 187,500 141,000,000.00
- Plester dan Acian 1,504.00 m2 64,750 97,384,000.00
- Pengecatan Dinding 1,724.80 m2 37,500 64,680,000.00
4. LANTAI - 3
- Pester/Acian Beton Ekspose (Dinding/Kolom) 220.80 m2 57,500 12,696,000.00
- Pasangan Bata Ringan Tebal 12 cm 784.00 m2 187,500 147,000,000.00
- Plester dan Acian 1,568.00 m2 64,750 101,528,000.00
- Pengecatan Dinding 1,788.80 m2 37,500 67,080,000.00
8
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
5. LANTAI - 4 s.d. 15
- Pester/Acian Beton Ekspose (Dinding/Kolom) 2,649.60 m2 57,500 152,352,000.00
- Pasangan Bata Ringan Tebal 12 cm 11,270.00 m2 187,500 2,113,124,062.50
- Plester dan Acian 22,540.01 m2 64,750 1,459,465,323.75
- Pengecatan Dinding 25,189.61 m2 37,500 944,610,187.50
6. LANTAI - ATAP
- Pester/Acian Beton Ekspose (Dinding/Kolom) 248.00 m2 57,500 14,260,000.00
- Pasangan Bata Ringan Tebal 12 cm 324.00 m2 187,500 60,750,000.00
- Plester dan Acian 648.00 m2 64,750 41,958,000.00
- Pengecatan Dinding 896.00 m2 37,500 33,600,000.00
Sub Jumlah V.A. 6,119,837,973.75
V.B PEKERJAAN PLAFOND
2. LANTAI - 1
- Plafond Gypsum termasuk rangka 430.00 m2 124,000 53,320,000.00
- plafond Gypsum Pola (area lobby lift, lounge, main lobby 80.00 m2 167,500 13,400,000.00
3. LANTAI - 2
9
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
- Pester/Acian Beton Ekspose 84.00 m2 57,500 4,830,000.00
- Plafond Gypsum termasuk rangka 164.00 m2 124,000 20,336,000.00
- Plafond Calciboard termasuk rangka 187.00 m2 142,000 26,554,000.00
- plafond Gypsum Pola - m2 167,500
- Drop Plafond 120.00 m 124,000 14,880,000.00
- Profil Gypsum 220.00 m 17,500 3,850,000.00
- Pengecatan Plafond 435.00 m2 37,500 16,312,500.00
4. LANTAI - 3
- Plafond Gypsum termasuk rangka 434.00 m2 124,000 53,816,000.00
- plafond Gypsum Pola 8.00 m2 167,500 1,340,000.00
- Drop Plafond 320.00 m 124,000 39,680,000.00
- Profil Gypsum 580.00 m 17,500 10,150,000.00
- Pengecatan Plafond 442.00 m2 37,500 16,575,000.00
5. LANTAI - 4 s.d. 15
- Plafond Gypsum termasuk rangka 4,848.00 m2 124,000 601,152,000.00
- plafond Gypsum Pola 72.00 m2 167,500 12,060,000.00
- Plafond Gypsum Wet Area 528.00 m2 135,000 71,280,000.00
- Drop Plafond 2,940.00 m 124,000 364,560,000.00
- Profil Gypsum 4,104.00 m 17,500 71,820,000.00
- Pengecatan Plafond 5,448.00 m2 37,500 204,300,000.00
6. LANTAI - ATAP
- Pester/Acian Beton Ekspose 32.00 m2 57,500 1,840,000.00
- Pengecatan Dinding 32.00 m2 37,500 1,200,000.00
Sub Jumlah V.B. 1,815,287,100.00
10
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
V.C. PEKERJAAN LANTAI dan KERAMIK DINDING
2. LANTAI - 1
- Lantai Marble Ujung Pandang Cutting 60 x 120 258.00 m2 975,000 251,550,000.00
- Lantai Marble Pola di area lobby lift dan main Lobby 42.00 m2 1,200,000 50,400,000.00
- Granite Tile 172.00 m2 475,000 81,700,000.00
- Granit Tile untuk dinding dan lantai toilet/R. Wudlu 112.00 m2 425,000 47,600,000.00
- Keramik Tangga Darurat 32.40 m2 110,000 3,564,000.00
- Plint Lantai Marble 110.00 m 37,500 4,125,000.00
- Plint lantai Granit tile 198.00 m 22,500 4,455,000.00
- Mrble Dinding Lobby Lift 1.00 ls 88,975,000 88,975,000.00
3. LANTAI - 2
- Lantai Granite 60 x 60 cm 128.00 m2 475,000 60,800,000.00
- Granite Tile Pola Area Lobby Lift 12.00 m2 675,000 8,100,000.00
- Granite Tile Un Polish/Texture/Rocky 219.00 m2 525,000 114,975,000.00
- Keramik dindidng dan lantai Toilet dan R. Bilas 145.00 m2 425,000 61,625,000.00
- Pol Deck Kolam Renang/Artificial Wood 48.00 m2 425,000 20,400,000.00
- Keramik Tangga Darurat 30.28 m2 97,500 2,952,300.00
- Plint lantai Granit tile 142.00 m 22,500 3,195,000.00
- Mrble Dinding Lobby Lift 1.00 ls 88,975,000 88,975,000.00
11
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
4. LANTAI - 3
- Lantai Granite 60 x 60 cm 284.72 m2 475,000 135,242,000.00
- Lantai Karpet Meeting Room / Ball Room Lantai 3 175.80 m2 500,000 87,900,000.00
- Granite Tile Pola Area Lobby Lift dan Pre Fuction 48.00 m2 675,000 32,400,000.00
- Keramik dindidng dan lantai Toilet dan Pantry 145.00 m2 425,000 61,625,000.00
- Lantai Keramik Storage 24.00 m2 425,000 10,200,000.00
- Keramik Tangga Darurat 30.28 m2 97,500 2,952,300.00
- Plint lantai Granit tile 178.00 m 22,500 4,005,000.00
- Mrble Dinding Lobby Lift 1.00 ls 88,975,000 88,975,000.00
5. LANTAI - 4 s.d. 15
- Lantai Karpet Korridor Lantai 4-15 957.60 m2 500,000 478,800,000.00
- Granite Tile Pola Area Lobby Lift 144.00 m2 675,000 97,200,000.00
- Lantai Parquet Kamar Lantai 4-15 3771.36 m2 450,000 1,697,112,000.00
- Granite Tile lantai dan dinding Kamar mandi 1108.80 m 475,000 526,680,000.00
- Keramik Tangga Darurat 42.72 m2 97,500 4,165,200.00
- Mrble Dinding Lobby Lift 1.00 ls 978,725,000 978,725,000.00
6. LANTAI - ATAP
- Lantai Keramik Ruang Mesin Lift dan Tangga 48.00 m2 97,500 4,680,000.00
Sub Jumlah V.C. 5,314,350,300.00
12
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
- Pintu Kaca double lengkap dengan accessories (lobby lift) 1.00 set 8,750,000 8,750,000.00
2. LANTAI - 1
- Kusen Alumunium 458.00 m2 135,000 61,830,000.00
- Kaca Mati 188.00 m2 375,000 70,500,000.00
- Daun Jendela lengkap dengan Accessories 16.00 unit 1,125,000 18,000,000.00
- Pintu Kayu Double lengkap dengan kusen dan 2.00 set 4,275,000 8,550,000.00
Accessories
(solid engineering door)
- Pintu Kayu Single lengkap dengan kusen dan Accessories 7.00 set 2,465,000 17,255,000.00
.3. LANTAI - 2
- Kusen Alumunium 224.00 m2 135,000 30,240,000.00
- Kaca Mati 98.00 m2 375,000 36,750,000.00
- Daun Jendela lengkap dengan Accessories 10.00 unit 1,125,000 11,250,000.00
- Pintu Kayu Double lengkap dengan kusen dan 1.00 set 4,275,000 4,275,000.00
Accessories
(solid engineering door)
- Pintu Kayu Single lengkap dengan kusen dan Accessories 5.00 set 2,465,000 12,325,000.00
13
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
exit panic bar.
- Pintu Smoking room fire rated dan pintu evakuasi 1.00 unit 3,175,000 3,175,000.00
4. LANTAI - 3
- Kusen Alumunium 324.00 m2 135,000 43,740,000.00
- Kaca Mati 133.00 m2 375,000 49,875,000.00
- Daun Jendela lengkap dengan Accessories 12.00 unit 1,125,000 13,500,000.00
- Pintu Kayu Double lengkap dengan kusen dan 4.00 set 4,275,000 17,100,000.00
Accessories
(solid engineering door)
- Pintu Kayu Single lengkap dengan kusen dan Accessories 6.00 set 2,465,000 14,790,000.00
5. LANTAI - 4 s.d. 15
- Kusen Alumunium 3,225.60 m2 135,000 435,456,000.00
- Kaca Mati 1,123.20 m2 375,000 421,200,000.00
- Daun Jendela/Pintu Kaca lengkap dengan Accessories 168.00 unit 1,450,000 243,600,000.00
- Pintu Kayu Single 90 X 210 lengkap dengan kusen dan 144.00 set 2,465,000 354,960,000.00
Accesso-
ris solid engineering door (Pintu Unit)
- Pintu Kayu Single 70 X 210 lengkap dengan kusen dan 132.00 set 1,875,000 247,500,000.00
Accessoris solid engineering door (Pintu Unit)
- Pintu Tangga kebakaran Fire Rated lengkap dengan 12.00 unit 4,275,000 51,300,000.00
Emergency
exit panic bar.
14
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
- Pintu Smoking room fire rated dan pintu evakuasi 12.00 unit 3,175,000 38,100,000.00
6. LANTAI - ATAP
- Pintu Ruang Mesin Lift dan tangga Metal Door 3.00 unit 2,275,000 6,825,000.00
Sub Jumlah V.D. 2,274,395,000.00
2 LANTAI 2
- Closet Duduk 2.00 unit 3,275,000 6,550,000.00
- Urinoir 1.00 unit 4,175,000 4,175,000.00
- Wastafel 6.00 unit 3,245,000 19,470,000.00
- Shower Lengkap Dengan MIXING VALVE 2.00 unit 3,750,000 7,500,000.00
- Floor Drain 5.00 unit 325,000 1,625,000.00
- Kran Washtafel 6.00 unit 675,000 4,050,000.00
- Kran Washtafel Panas Dingin - unit -
- Jet Washer 2.00 unit 515,000 1,030,000.00
- Kran dinding 3.00 unit 275,000 825,000.00
- Meja Granit 2.00 unit 1,675,000 3,350,000.00
15
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
3 LANTAI-3
- Closet Duduk 2.00 unit 3,275,000 6,550,000.00
- Urinoir 1.00 unit 4,175,000 4,175,000.00
- Wastafel 6.00 unit 3,245,000 19,470,000.00
- Floor Drain 5.00 unit 325,000 1,625,000.00
- Kran Washtafel 6.00 unit 675,000 4,050,000.00
- Kran Washtafel Panas Dingin - unit -
- Jet Washer 2.00 unit 515,000 1,030,000.00
- Kran dinding 3.00 unit 275,000 825,000.00
- Meja Granit 2.00 unit 1,675,000 3,350,000.00
4 LANTAI-4-15
- Closet Duduk 136.00 unit 4,165,000 566,440,000.00
- Urinoir - unit - -
- Wastafel 136.00 unit 3,245,000 441,320,000.00
- Floor Drain 272.00 unit 325,000 88,400,000.00
- Kran Washtafel - unit -
- Kran Washtafel Panas Dingin 136.00 unit 967,500 131,580,000.00
- Jet Washer 136.00 unit 515,000 70,040,000.00
- Kran dinding - unit 275,000
- Meja Granit 136.00 unit 1,100,000 149,600,000.00
- Bath Tube 136.00 unit 6,000,000 816,000,000.00
- Shower Set Panas Dingin 136.00 unit 5,000,000 680,000,000.00
Sub Jumlah V.E. 3,073,730,000.00
5 PEKERJAAN RAILLING 1.00 ls 515,872,672 515,872,671.88
6 PEKERJAAN FASADE 1.00 ls 2,704,865,625 2,704,865,625.00
Sub Jumlah V. 21,818,338,670.63
16
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
VI PEKERJAAN INTERIOR
1 Meubelair terpasang di area recepsionis 1.00 ls 89,375,000 89,375,000.00
Back Drop, Counter lengkap dengan kabinet bawah, ceiling
dan
luminasi
2 Meubeulair Unit Kamar 136.00 set 40,000,000 5,440,000,000.00 5,529,375,000.00
Tidak termasuk sofa/kursi
17
HARGA SUB HARGA
No. URAIAN PEKERJAAN VOL. SAT. SATUAN (Rp) TOTAL (Rp) TOTAL (Rp)
1 2 3 4 5 6=(3x5) 7
18
F, F & E HOTEL THE RAYYAN
7 Perpanjangan Rekomendasi Tata Letak dan Jenis Tanaman serta Design 125,000,000
8 Perpanjangan Rekomendasi Teknis Pencegahan dan Penanggulangan Bahaya 125,000,000
Kebakaran
9 Perpanjangan Rekomendasi Pengelolaan Persampahan (PD Kebersihan) 125,000,000
10 Perpanjangan Rekomendasi Pengelolaan Air Limbah (PDAM Tirta Wening) 125,000,000