REKAPITULASI

PROGRESS MINGGUAN

Pekerjaan : Repair dan Perkuatan Struktur SMPI Al-Azhar 28 Cibinong SERTIFIKAT MINGGU Ke-3 ( Ketiga )
No. Kontrak :- Bulan : Juli 2023
Nilai Kontrak : Rp. 2.850.000.000,- Tanggal : 29 Juni - 05 Juli 2023

PROGRESS MINGGUAN
No. URAIAN PROSENT. SAMPAI MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
Progress Persent. Progress Persent. Progress Persent.

A PEKERJAAN PERSIAPAN 4,631% 16,000% 0,741% 8,000% 0,370% 24,000% 1,111%

B PEKERJAAN INJEKSI EPOXY 22,043% 1,875% 0,413% 26,250% 5,786% 28,125% 6,200%

C PEKERJAAN PERKUATAN PLAT LANTAI 57,257% 7,598% 4,350% 22,501% 12,883% 30,099% 17,233%

D PEKERJAAN PERKUATAN BALOK 16,070% 0,707% 0,114% 24,411% 3,923% 25,118% 4,036%

TOTAL 100,00% 5,618% 22,963% 28,581%

PROGRESS S/D MINGGU INI 28,581%


TARGET SESUAI TIME SCHEDULE 15,199%
DEVIASI 13,382%

Jakarta, 05 Juli 2023


Mengetahui, Diperiksa oleh, Dibuat oleh,
PT. BERKAH GEMILANG KONSULTAN PENGAWAS

MOH. TAUFIKURROHMAN, ST.


PROGRESS MINGGUAN

Pekerjaan : Repair dan Perkuatan Struktur SMPI Al-Azhar 28 Cibinong SERTIFIKAT MINGGU Ke-3 ( Ketiga )
No. Kontrak :- Bulan : Juli 2023
Nilai Kontrak : Rp. 2.850.000.000,- Tanggal : 29 Juni - 05 Juli 2023

PROGRESS MINGGUAN
No. URAIAN PROSENT. SAMPAI MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
Progress Persent. Progress Persent. Progress Persent.

A PEKERJAAN PERSIAPAN
1 Mob Demob Alat dan Man Power 0,263% 16,000% 0,042% 8,000% 0,021% 24,000% 0,063%
2 Proteksi Area dan K3 0,421% 16,000% 0,067% 8,000% 0,034% 24,000% 0,101%
3 Air dan Listrik Kerja 0,000% - - - - - -
4 Pembersihan Lokasi Awal dan Akhir 0,000% 16,000% 0,000% 8,000% 0,000% 24,000% 0,000%
5 Site Management 2,631% 16,000% 0,421% 8,000% 0,210% 24,000% 0,631%
6 Sewa Tempat Tinggal Staff dan Pekerja 1,052% 16,000% 0,168% 8,000% 0,084% 24,000% 0,253%
7 Administrasi, Dokumentasi dan Pembuatan Laporan 0,263% 16,000% 0,042% 8,000% 0,021% 24,000% 0,063%
SUB JUMLAH - A 4,631% 16,000% 0,741% 8,000% 0,370% 24,000% 1,111%

B PEKERJAAN INJEKSI EPOXY


1 LANTAI DUA :
Injeksi Keretakan Plat Lantai dan Balok dengan Epoxy 5,511% - - - - - -
(termasuk Alat Bantu Perancah dan Peralatan Lain yang Digunakan)

2 LANTAI TIGA :
Injeksi Keretakan Plat Lantai dan Balok dengan Epoxy 8,266% - - - - - -
(termasuk Alat Bantu Perancah dan Peralatan Lain yang Digunakan)

3 LANTAI EMPAT :
Injeksi Keretakan Plat Lantai dan Balok dengan Epoxy 8,266% 5,000% 0,413% 70,000% 5,786% 75,000% 6,200%
(termasuk Alat Bantu Perancah dan Peralatan Lain yang Digunakan)
SUB JUMLAH - B 22,043% 1,875% 0,413% 26,250% 5,786% 28,125% 6,200%

C PEKERJAAN PERKUATAN PLAT LANTAI


1 LANTAI DUA :
PEKERJAAN DARI SISI ATAS :
a. Bongkar Keramik dan Screed 2,297% - - - - - -
(termasuk Peralatan dan Pembuangan Puing Keluar Lokasi)
b. Bongkar Dinding Sisi Bawah 0,124% - - - - - -
c. Shear Connector f10 - 500 6,391% - - - - - -
d. Bonding Agent SBR (Styrene Butadiene Rubber)
(lem beton perekat antara beton lama dan beton baru) 0,919% - - - - - -
e. Wiremesh M8 2,680% - - - - - -
f. Beton Screening NFA, fc' 29 MPa + Super Plasticizer 2,220% - - - - - -

PEKERJAAN DARI SISI BAWAH :


a. Grinding Permukaan Beton 0,295% - - - - - -
b. Pemasangan Carbon Wrap 4,160% - - - - - -

2 LANTAI TIGA :
PEKERJAAN DARI SISI ATAS :
a. Bongkar Keramik dan Screed 2,297% 50,000% 1,149% 0,000% 0,000% 50,000% 1,149%
(termasuk Peralatan dan Pembuangan Puing Keluar Lokasi)
b. Bongkar Dinding Sisi Bawah 0,124% - - 50,000% 0,062% 50,000% 0,062%
c. Shear Connector f10 - 500 6,391% 5,000% 0,320% 5,000% 0,320% 10,000% 0,639%
d. Bonding Agent SBR (Styrene Butadiene Rubber)
(lem beton perekat antara beton lama dan beton baru) 0,919% - - - - - -
e. Wiremesh M8 2,680% - - 35,000% 0,938% 35,000% 0,938%
f. Beton Screening NFA, fc' 29 MPa + Super Plasticizer 2,220% - - - - - -

PEKERJAAN DARI SISI BAWAH :


a. Grinding Permukaan Beton 0,295% - - 5,000% 0,015% 5,000% 0,015%
b. Pemasangan Carbon Wrap 4,160% - - - - - -

3 LANTAI EMPAT :
PEKERJAAN DARI SISI ATAS :
a. Bongkar Keramik dan Screed 2,297% 95,000% 2,182% 5,000% 0,115% 100,000% 2,297%
(termasuk Peralatan dan Pembuangan Puing Keluar Lokasi)
b. Bongkar Dinding Sisi Bawah 0,124% 7,500% 0,009% 92,500% 0,114% 100,000% 0,124%
c. Shear Connector f10 - 500 6,391% 5,000% 0,320% 95,000% 6,071% 100,000% 6,391%
d. Bonding Agent SBR (Styrene Butadiene Rubber)
(lem beton perekat antara beton lama dan beton baru) 0,919% - - 0,000% 0,000% 0,000% 0,000%
e. Wiremesh M8 2,680% 10,000% 0,268% 90,000% 2,412% 100,000% 2,680%
f. Beton Screening NFA, fc' 29 MPa + Super Plasticizer 2,220% - - 0,000% 0,000% 0,000% 0,000%

PEKERJAAN DARI SISI BAWAH :


a. Grinding Permukaan Beton 0,295% 35,000% 0,103% 45,000% 0,133% 80,000% 0,236%
b. Pemasangan Carbon Wrap 4,160% - - 65,000% 2,704% 65,000% 2,704%
SUB JUMLAH - C 57,257% 7,598% 4,350% 22,501% 12,883% 30,099% 17,233%
PROGRESS MINGGUAN
No. URAIAN PROSENT. SAMPAI MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
Progress Persent. Progress Persent. Progress Persent.

D PEKERJAAN PERKUATAN BALOK


A LANTAI DUA :
1 BALOK P10A (300x650)
PEKERJAAN DARI SISI BAWAH :
a. Grinding Permukaan Beton 0,189% - - - - - -
b. Pemasangan Carbon Wrap 5,167% - - - - - -

2 LANTAI TIGA :
BALOK P10A (300x650)
PEKERJAAN DARI SISI BAWAH :
a. Grinding Permukaan Beton 0,189% - - - - - -
b. Pemasangan Carbon Wrap 5,167% - - - - - -

3 LANTAI EMPAT :
BALOK P10A (300x650)
PEKERJAAN DARI SISI BAWAH :
a. Grinding Permukaan Beton 0,189% 60,000% 0,114% 25,000% 0,047% 85,000% 0,161%
b. Pemasangan Carbon Wrap 5,167% - - 75,000% 3,875% 75,000% 3,875%
SUB JUMLAH - D 16,070% 0,707% 0,114% 24,411% 3,923% 25,118% 4,036%