Anda di halaman 1dari 2

NO URAIAN SAT VOLUME HARGA SATUAN TOTAL HARGA

KEBUTUHAN MATERIAL CANOPY ( 7.4 m X 5 m ) m2 34 Rp 212,752 Rp 7,233,580

1 Hollow 40x40x1.2 mm panjang 6m btg 9.01 125,000 1,126,250


2 Hollow 40x20x1 mm panjang 6m btg 6.02 85,000 511,530
3 Polycarbonat ex Solarlite ( 2.1 m x 11.80 m ) roll 1.53 1,400,000 2,142,000
4 Omega panjang 6m btg 3.03 35,000 105,910
5 Zinchromate kg 2.14 40,000 85,680
6 Thinner kg 5.10 15,000 76,500
7 Cat minyak warna hitam metalik kg 3.40 55,000 187,000
8 Batu gerinda tangan pcs 4.01 10,000 40,120
9 Betu gerinda cutting wheel pcs 1.02 45,000 45,900
10 Amplas halus disc susun pcs 4.01 15,000 60,180
11 Amplas halus disc single pcs 7.00 7,000 49,028
12 Kawat las Oerlikon 2.6 dus 0.51 98,000 49,980
13 Dempul Sanpolac klg 0.31 60,000 18,360
14 Dempul Isamu klg 0.31 50,000 15,300
15 Dynabolt - M10 pcs 30.02 1,000 30,022
16 Listrik hari 10.00 20,000 199,920
17 Sewa alat hari 10.00 15,000 149,940
18 Operational hari 10.00 10,000 99,960
19 Sewa mobil untuk angkut barang hari 1.00 200,000 200,000
20 Upah tukang m2 34.00 60,000 2,040,000

Sub Total Rp 7,233,580


NO URAIAN SAT VOLUME HARGA SATUAN TOTAL HARGA

KEBUTUHAN MATERIAL CANOPY ( 7.4 m X 5 m ) m2 37 Rp 207,411 Rp 7,674,190

1 Hollow 40x40x1.2 mm panjang 6m btg 9.81 125,000 1,225,625


2 Hollow 40x20x1 mm panjang 6m btg 6.55 85,000 556,665
3 Polycarbonat ex Solarlite ( 2.1 m x 11.80 m ) roll 1.67 1,400,000 2,331,000
4 Omega panjang 6m btg 3.29 35,000 115,255
5 Zinchromate kg 2.33 40,000 93,240
6 Thinner kg 5.55 15,000 83,250
7 Cat minyak warna hitam metalik kg 3.70 55,000 203,500
8 Batu gerinda tangan pcs 4.37 10,000 43,660
9 Betu gerinda cutting wheel pcs 1.11 45,000 49,950
10 Amplas halus disc susun pcs 4.37 15,000 65,490
11 Amplas halus disc single pcs 7.62 7,000 53,354
12 Kawat las Oerlikon 2.6 dus 0.56 98,000 54,390
13 Dempul Sanpolac klg 0.33 60,000 19,980
14 Dempul Isamu klg 0.33 50,000 16,650
15 Dynabolt - M10 pcs 32.67 1,000 32,671
16 Listrik hari 10.88 20,000 217,560
17 Sewa alat hari 10.88 15,000 163,170
18 Operational hari 10.88 10,000 108,780
19 Sewa mobil untuk angkut barang hari 1.00 200,000 200,000
20 Upah tukang m2 34.00 60,000 2,040,000

Sub Total Rp 7,674,190

Anda mungkin juga menyukai