HARGA JUMLAH
NO. ITEM PEKERJAAN VOLUME SAT. SATUAN HARGA
( Rp ) ( Rp )
a b c d e f=cxe

IV PEKERJAAN PONDASI
1 Pas. Batu Kosong 2.49 M3 397,881.00 990,723.69
2 Pas. Pondasi Batu Kali 1Pc : 6Ps 18.24 M3 769,510.50 14,035,871.52
Jumlah 15,026,595.21
V PEKERJAAN BETON
1 Pek. Rabat Lantai Beton 7,4 Mpa (K100) 1.91 M3 719,247.13 1,373,762.02
2 Pek. Beton Pondasi Telapak 90x90x20 cm
- Pek. Beton Cor Mutu 14,5 Mpa ( K175) 0.16 M3 926,388.17 148,222.11
- Pek. Pembesian 19.44 Kg 14,488.10 281,648.66
3 Pek. Beton Sloof 12/20 cm
- Pek. Beton Cor Mutu 14,5 Mpa ( K175) 0.50 M3 926,388.17 463,194.09
- Pek. Pembesian 97.76 Kg 14,488.10 1,416,356.66
4 Pek. Beton Kolom 20/20 cm
- Pek. Beton Cor Mutu 14,5 Mpa ( K175) 0.19 M3 926,388.17 176,013.75
- Pek. Pembesian 37.88 Kg 14,488.10 548,809.23
5 Pek. Beton Kolom 12/12 cm
- Pek. Beton Cor Mutu 14,5 Mpa ( K175) 0.08 M3 926,388.17 74,111.05
- Pek. Pembesian 25.31 Kg 14,488.10 366,693.81
6 Pek. Beton Ring 12/15 cm
- Pek. Beton Cor Mutu 14,5 Mpa ( K175) 0.38 M3 926,388.17 352,027.50
- Pek. Pembesian 67.48 Kg 14,488.10 977,656.99
7 Pas. Beton Pengeresek (pagar) 1.79 M3 606,508.10 1,085,649.50
8 Pek. Beton Pengeresek (padma) 0.81 M3 606,508.10 491,271.56
Jumlah 7,755,416.93
VI PEKERJAAN PASANGAN DAN PESTERAN
1 Pek. Padma Batu Tabas 1.00 Unit 49,250,000.00 49,250,000.00
2 Pek. Pasangan Pagar Batu Candi 41.16 M2 674,850.00 27,776,826.00
3 Pek. Pasangan Paduraksa Batu Candi 7.00 Unit 1,450,000.00 10,150,000.00
4 Pek. Plesteran Pondasi 27.62 M2 65,142.00 1,799,222.04
5 Pek. Plesteran Lantai 30.75 M2 65,142.00 2,003,116.50
6 Pek. Cat Hitam Anti Air Pondasi 27.62 M2 34,938.20 964,993.08
7 Pek. Pasangan Dinding Batu Candi (Bataran Padma) 4.20 M2 674,850.00 2,834,370.00
8 Pek. Pasangan Lantai Batu Sikat (Bataran Padma) 9.63 M2 239,035.50 2,301,911.87
Jumlah 97,080,439.49
Jumlah Total 119,862,451.63