REKAPITULASI

RENCANA ANGGARAN BIAYA


PEMBANGUNAN GEDUNG APARTEMEN, HOTEL & FASILITASNYA
PURI PAKUAN, SADANG - PURWAKARTA

NO URAIAN PEKERJAAN JUMLAH (RP.)

I PEKERJAAN PRELIMINARIES Rp 402,405,920,000.00


I.1 OVERHEAD DAN MANAGEMENT Rp. 109,036,140,000
I.2 PEKERJAAN PERSIAPAN DAN PENDUKUNG Rp. 150,604,920,000
I.3 BIAYA TANAH, KONSULTAN DAN PERIJINAN Rp. 142,764,860,000

II PEKERJAAN STRUKTUR Rp 330,273,330,275.46


II.1 PEKERJAAN STRUKTUR BLOK A & B Rp. 188,720,143,867.93
II.2 PEKERJAAN STRUKTUR BLOK C Rp. 65,577,272,752.84
II.3 PEKERJAAN STRUKTUR BLOK D Rp. 64,309,815,835.75
II.4 PEKERJAAN STRUKTUR HOTEL Rp. 11,666,097,818.95

III PEKERJAAN ARSITEKTUR Rp 330,835,764,747.39


III.1 PEKERJAAN ARSITEKTUR BLOK A & B Rp. 183,035,162,019.20
III.2 PEKERJAAN ARSITEKTUR BLOK C Rp. 63,893,254,659.95
III.3 PEKERJAAN ARSITEKTUR BLOK D Rp. 67,937,880,962.34
III.4 PEKERJAAN ARSITEKTUR HOTEL Rp. 15,969,467,105.90

IV PEKERJAAN MEKANIKAL & ELEKTRIKAL Rp 183,234,066,808.38


IV.1 PEKERJAAN M & E BLOK A & B Rp. 100,417,624,247.10
IV.2 PEKERJAAN M & E BLOK C Rp. 37,208,331,287.68
IV.3 PEKERJAAN M & E BLOK D Rp. 34,714,269,314.86
IV.4 PEKERJAAN M & E HOTEL Rp. 10,893,841,958.74

Jumlah Total Rp. 1,246,749,081,831.22


PPn (10%) Rp. 124,674,908,183.12

Jumlah Total + PPn Rp. 1,371,423,990,014.35


Dibulatkan Rp. 1,371,423,990,000.00

Terbilang :
#Satu trilyun tiga ratus tujuh puluh satu milyar empat ratus dua puluh tiga juta sembilan ratus sembilan puluh ribu#

Purwakarta, Maret 2016

PT. ALUMAS JAYA MANDIRI

Sidik Setiyadi
Direktur