No. DESCRIPTION SCOPE OF WORK Unit Qty Unit Price (IDR) Amount Price (IDR)
1 Preparation
a Mobilization & Demobilization Equipment, Personil ( Jakarta) ls 1.00 10,000,000.00 10,000,000.00
b Mess Pekerja ls 1.00 2,000,000.00 2,000,000.00
c Scaffolding ls 1.00 3,000,000.00 3,000,000.00
Sub Total 1 15,000,000.00
2 Flexural Beam Strengthening With FRP
a Perkuatan Balok dengan Carbon MapeWrap C UNI-AX m2 9.31 1,400,000.00 13,035,855.00
Sub Total 2 13,035,855.00
3 Shear Beam Strengthening With FRP
a Perkuatan Balok dengan Eglass MapeWrap G UNI-AX m2 42.20 1,200,000.00 50,645,250.00
Sub Total 3 50,645,250.00
4 Column Strengthening With FRP
a Perkuatan Kolom dengan Eglass MapeWrap G UNI-AX m2 50.69 1,400,000.00 70,963,200.00
Sub Total 4 70,963,200.00
5 Repair Beton
Non Shrink Cementious Grout Ex Sika, Fosroc,
a Perbaikan Balok dengan Patching m3 0.06 18,000,000.00 1,063,550.25
BASF
b Perbaikan Balok dengan Injeksi Epoxy Resin Titik 26 175,000.00 4,569,796.88
Non Shrink Cementious Grout Ex Sika, Fosroc,
c Perbaikan Kolom dengan Patching m3 0.03 18,000,000.00 479,001.60
BASF
d Perbaikan Kolom dengan Injeksi Epoxy Resin Titik 8 175,000.00 1,330,560.00
Sub Total 5 7,442,908.73
6 Perbaikan Dinding Retak Ringan
- Bongkar Plesteran m2 381.01 15,000.00 5,715,150.00
- Plesteran m2 381.01 55,000.00 20,955,550.00
- Wiremesh m2 381.01 33,000.00 12,573,330.00
Sub Total 6 39,244,030.00
7 Finishing
a Pekerjaan Bongkar Pasang Dinding
- Bongkar Dinding m2 20.00 85,000.00 1,700,000.00
- Pemasangan Hebel m2 20.00 250,000.00 5,000,000.00
- Plesteran Dinding m2 40.00 55,000.00 2,200,000.00
- Acian Dinding m2 40.00 40,000.00 1,600,000.00
- Pengecetan Dinding m2 40.00 40,000.00 1,600,000.00
- Pekerjaan Bongkar dan Pasang Pintu Existing - Bongkar & pasang include perbaikan pintu dan di unit 1.00 4,000,000.00 4,000,000.00

b Pekerjaan Bongkar Pasang Plafond


- Pekerjaan Bongkaran Plafond Existing m2 33.76 20,153.92 680,466.82
- Pemasangan Rangka Plafond m' 23.20 97,497.60 2,261,944.36
- Pekerjaan Pemasangan Plafond m2 33.76 62,509.26 2,110,531.40
- Pengecatan Plafond Gypsum m2 33.76 25,883.76 873,926.21
Sub Total 7 22,026,868.79
TOTAL 218,358,112.51
PPN 10% 21,835,811.25
GRAND TOTAL (TOTAL + PPN 10%) 240,193,923.76

Note:
Included PPN 10%
Project : Assessment, Testing dan Analisis Struktur Rumah Pribadi Ibu Meidy, Sukadamai - Kota Bogor
Subject : Beam Flexural Strengthening Using FRP

Flexural
No. of
No. of Wrap Width Concrete Area
Beam Width, Beam Depth, Beam Ave Slab Thk Wrap Length Layer(s) Wrap Area (m2)
Beams ID Remark Similar (mm) Middle (m2) Middle Material
b (mm) D (mm) Length (m) (mm) Bottom Middle Middle Bottom
Beams Bottom Bottom
Bottom
Lantai 2
Balok B1 150x300 As I/1'-2 1 150 300 1.500 120 1.28 150 1 0.19 0.19 Carbon
Balok B1 150x300 H/2-3 1 150 300 3.650 120 3.10 150 1 0.47 0.47 Carbon
Balok B1 150x300 F/3-4',H/3-4' 2 150 300 3.125 120 2.66 150 1 0.80 0.80 Carbon
Balok B1 150x300 A/4-5, C/4-5 2 150 300 3.450 120 2.93 150 1 0.88 0.88 Carbon
Balok B1 150x300 E/4'-5, F/4'-5, H/4'-5 3 150 300 2.650 120 2.25 150 1 1.01 1.01 Carbon
Balok B1 150x300 C/5-6 1 150 300 2.000 120 1.70 150 1 0.26 0.26 Carbon
Balok B1 150x300 D-E/1, D-E/4, D-E/6 3 150 300 2.630 120 2.24 150 1 1.01 1.01 Carbon
Balok B1 150x300 C-D/4, C-D/6 2 150 300 1.250 120 1.06 150 1 0.32 0.32 Carbon
Balok B1 150x300 B-E/3 1 150 300 4.535 120 3.85 150 1 0.58 0.58 Carbon
Balok B1 150x300 A-C/4, A-C/5, A-C/6 3 150 300 4.535 120 3.85 150 1 1.73 1.73 Carbon
Balok B1 150x300 E-F/3, E-F/7, E-F/5 3 150 300 1.550 120 1.32 150 1 0.59 0.59 Carbon
Balok B1 150x300 A-B/5-6 1 150 300 2.000 120 1.70 150 1 0.26 0.26 Carbon
Balok B1 150x300 C-D/7 1 150 300 1.500 120 1.28 150 1 0.19 0.19 Carbon
Balok B1 150x300 F-H/3, F-H/4, F-H/7 3 150 300 2.700 120 2.30 150 1 1.03 1.03 Carbon
Total 9.31 Carbon
Project: Assessment, Testing dan Analisis Struktur Rumah Pribadi Ibu Meidy, Sukadamai - Kota Bogor
Subject: Beam Shear Strengthening Using FRP

Shear left & Right (U-Wrapp)

Beam Wrap Length Wrap Length No. of No. of Concrete


No. of Similar Beam Depth, D Beam Length Ave Slab Thk Wrap Width Wrap Width Concrete Area Wrap Area Wrap Area
Beams ID Remark Width, b Bottom (m) Bottom (m) Layer(s) Layer(s) Area (m2) Material Material
Beams (mm) (m) (mm) (mm) Left (mm) Right (m2) Left (m2) Left (m2) Right
(mm) Left Right Left Right Right

Lantai 2
Balok B1 150x300 As D/1-2, I/1-2 2 150 300 3.000 120 0.8 0.8 750 750 1 1 1.13 1.13 1.13 Eglass 1.13 Eglass
Balok B1 150x300 E'/1-1',G/1-1' 2 150 300 2.150 120 0.5 0.5 750 750 1 1 0.81 0.81 0.81 Eglass 0.81 Eglass
Balok B1 150x300 E/2-3, H/2-3 2 150 300 3.650 120 0.9 0.9 750 750 1 1 1.37 1.37 1.37 Eglass 1.37 Eglass
Balok B1 150x300 B/3-4 1 150 300 2.250 120 0.6 0.6 750 750 1 1 0.42 0.42 0.42 Eglass 0.42 Eglass
Balok B1 150x300 E/3-4', F/3-4', G/3-4',H/3-4' 4 150 300 3.125 120 0.8 0.8 750 750 1 1 2.34 2.34 2.34 Eglass 2.34 Eglass
Balok B1 150x300 A/4-5, C/4-5 2 150 300 3.450 120 0.9 0.9 750 750 1 1 1.29 1.29 1.29 Eglass 1.29 Eglass
Balok B1 150x300 D/4-6 1 150 300 5.450 120 1.4 1.4 750 750 1 1 1.02 1.02 1.02 Eglass 1.02 Eglass
Balok B1 150x300 E/4'-5, H/4'-5 2 150 300 2.650 120 0.7 0.7 750 750 1 1 0.99 0.99 0.99 Eglass 0.99 Eglass
Balok B1 150x300 C/5-6 1 150 300 2.000 120 0.5 0.5 750 750 1 1 0.38 0.38 0.38 Eglass 0.38 Eglass
Balok B1 150x300 D/6-7,E/6-7 2 150 300 0.650 120 0.2 0.2 750 750 1 1 0.24 0.24 0.24 Eglass 0.24 Eglass
Balok B1 150x300 E/5-7,H/5-7 2 150 300 2.650 120 0.7 0.7 750 750 1 1 0.99 0.99 0.99 Eglass 0.99 Eglass
Balok B1 150x300 D-E/4, D-E/6,D-E/3 3 150 300 2.630 120 0.7 0.7 750 750 1 1 1.48 1.48 1.48 Eglass 1.48 Eglass
Balok B1 150x300 C-E/2 1 150 300 4.000 120 1.0 1.0 750 750 1 1 0.75 0.75 0.75 Eglass 0.75 Eglass
Balok B1 150x300 C-D/4, C-D/6 2 150 300 1.250 120 0.3 0.3 750 750 1 1 0.47 0.47 0.47 Eglass 0.47 Eglass
Balok B1 150x300 B-C/3, B-C/4 2 150 300 0.580 120 0.1 0.1 750 750 1 1 0.22 0.22 0.22 Eglass 0.22 Eglass
Balok B1 150x300 A-C/6 1 150 300 4.535 120 1.1 1.1 750 750 1 1 0.85 0.85 0.85 Eglass 0.85 Eglass
Balok B1 150x300 E-F/1, E-F/2, E-F/5 3 150 300 1.550 120 0.4 0.4 750 750 1 1 0.87 0.87 0.87 Eglass 0.87 Eglass
Balok B1 150x300 E-H/7 1 150 300 4.250 120 1.1 1.1 750 750 1 1 0.80 0.80 0.80 Eglass 0.80 Eglass
Balok B1 150x300 F-I/1, F-I/2 2 150 300 4.000 120 1.0 1.0 750 750 1 1 1.50 1.50 1.50 Eglass 1.50 Eglass
Balok B1 150x300 F-H/3, F-H/4, F-H/5, F-H/7 4 150 300 2.700 120 0.7 0.7 750 750 1 1 2.03 2.03 2.03 Eglass 2.03 Eglass
Balok B1 150x300 A-D/5-7 1 150 300 6.160 120 1.5 1.5 750 750 1 1 1.16 1.16 1.16 Eglass 1.16 Eglass
Total 21.10 Eglass 21.10 Eglass
Project : Assessment, Testing dan Analisis Struktur Rumah Pribadi Ibu Meidy, Sukadamai - Kota Bogor
Subject : BOQ Of Strengthening Column Using FRP

Column Column Wrap


No. of Similar Column Wrap No. of Concrete Wrap Area
Column ID Remark Width, b Depth, D Width Material
Column Height (m) Height (m) Layer(s) Area (m2) (m2)
(mm) (mm) (mm)
Lantai 1
Kolom K1 150x150 Semua Kolom 16 150 150 3.96 3.96 0.80 1 50.7 50.7 Eglass
Total 50.69 Eglass
Project : Assessment, Testing dan Analisis Struktur Rumah Pribadi Ibu Meidy, Sukadamai - Kota Bogor
Subject : Estimasi Volume Perbaikan Balok Beton

PATCHING
No. of Thickness
Beam Width, b Beam Depth, Beam Concrete Area Presentase Total
Beams ID Remark Similar Patching
(mm) D (mm) Length (m) (m2) Patching (%) Patching (m3)
Beams (mm)
Lantai 2
Balok B1 150x300 As D/1-2, I/1-2 2 150 300 3.000 4.50 70 1 0.003
Balok B1 150x300 E'/1-1',G/1-1' 2 150 300 2.150 3.22 70 1 0.002
Balok B1 150x300 E/2-3, H/2-3 2 150 300 3.650 5.48 70 1 0.004
Balok B1 150x300 B/3-4 1 150 300 2.250 1.69 70 1 0.001
Balok B1 150x300 E/3-4', F/3-4', G/3-4',H/3-4' 4 150 300 3.125 9.38 70 1 0.007
Balok B1 150x300 A/4-5, C/4-5 2 150 300 3.450 5.18 70 1 0.004
Balok B1 150x300 D/4-6 1 150 300 5.450 4.09 70 1 0.003
Balok B1 150x300 E/4'-5, H/4'-5 2 150 300 2.650 3.97 70 1 0.003
Balok B1 150x300 C/5-6 1 150 300 2.000 1.50 70 1 0.001
Balok B1 150x300 D/6-7,E/6-7 2 150 300 0.650 0.98 70 1 0.001
Balok B1 150x300 E/5-7,H/5-7 2 150 300 2.650 3.97 70 1 0.003
Balok B1 150x300 D-E/4, D-E/6,D-E/3 3 150 300 2.630 5.92 70 1 0.004
Balok B1 150x300 C-E/2 1 150 300 4.000 3.00 70 1 0.002
Balok B1 150x300 C-D/4, C-D/6 2 150 300 1.250 1.88 70 1 0.001
Balok B1 150x300 B-C/3, B-C/4 2 150 300 0.580 0.87 70 1 0.001
Balok B1 150x300 A-C/6 1 150 300 4.535 3.40 70 1 0.002
Balok B1 150x300 E-F/1, E-F/2, E-F/5 3 150 300 1.550 3.49 70 1 0.002
Balok B1 150x300 E-H/7 1 150 300 4.250 3.19 70 1 0.002
Balok B1 150x300 F-I/1, F-I/2 2 150 300 4.000 6.00 70 1 0.004
Balok B1 150x300 F-H/3, F-H/4, F-H/5, F-H/7 4 150 300 2.700 8.10 70 1 0.006
Balok B1 150x300 A-D/5-7 1 150 300 6.160 4.62 70 1 0.003
TOTAL PATCHING GRANDTOTAL 0.059

INJECTION
No. of
Beam Width, b Beam Depth, Beam Length Concrete Area Jlh Presentase Total Injeksi
Beams ID Remark Similar
(mm) D (mm) (m) (m2) Injeksi/m2 Injeksi(%) (Titik)
Beams
Lantai 2
Balok B1 150x300 As D/1-2, I/1-2 2 150 300 3.000 4.5 10 3 1
Balok B1 150x300 E'/1-1',G/1-1' 2 150 300 2.150 3.225 10 3 1
Balok B1 150x300 E/2-3, H/2-3 2 150 300 3.650 5.475 10 3 2
Balok B1 150x300 B/3-4 1 150 300 2.250 1.6875 10 3 1
Balok B1 150x300 E/3-4', F/3-4', G/3-4',H/3-4' 4 150 300 3.125 9.375 10 3 3
Balok B1 150x300 A/4-5, C/4-5 2 150 300 3.450 5.175 10 3 2
Balok B1 150x300 D/4-6 1 150 300 5.450 4.0875 10 3 1
Balok B1 150x300 E/4'-5, H/4'-5 2 150 300 2.650 3.975 10 3 1
Balok B1 150x300 C/5-6 1 150 300 2.000 1.5 10 4 1
Balok B1 150x300 D/6-7,E/6-7 2 150 300 0.650 0.975 10 6 1
Balok B1 150x300 E/5-7,H/5-7 2 150 300 2.650 3.975 10 3 1
Balok B1 150x300 D-E/4, D-E/6,D-E/3 3 150 300 2.630 5.9175 10 3 2
Balok B1 150x300 C-E/2 1 150 300 4.000 3 10 3 1
Balok B1 150x300 C-D/4, C-D/6 2 150 300 1.250 1.875 10 3 1
Balok B1 150x300 B-C/3, B-C/4 2 150 300 0.580 0.87 10 7 1
Balok B1 150x300 A-C/6 1 150 300 4.535 3.40125 10 3 1
Balok B1 150x300 E-F/1, E-F/2, E-F/5 3 150 300 1.550 3.4875 10 3 1
Balok B1 150x300 E-H/7 1 150 300 4.250 3.1875 10 3 1
Balok B1 150x300 F-I/1, F-I/2 2 150 300 4.000 6 10 3 2
Balok B1 150x300 F-H/3, F-H/4, F-H/5, F-H/7 4 150 300 2.700 8.1 10 3 2
Balok B1 150x300 A-D/5-7 1 150 300 6.160 4.62 10 3 1
TOTAL INJECTION GRANDTOTAL 26
Project : Assessment, Testing dan Analisis Struktur Rumah Pribadi Ibu Meidy, Sukadamai - Kota Bogor
Subject : Estimasi Volume Perbaikan Kolom Beton

PATCHING
Column Thickness
No. of Similar Column Column Concrete Area Presentase Total Patching
Column ID Remark Depth, D Patching
Column Width, b (mm) Length (m) (m2) Patching (%) (m3)
(mm) (mm)
Lantai 1
Kolom K1 150x150 Semua Kolom 16 150 150 3.96 38.0 70 1 0.027
TOTAL PATCHING GRANDTOTAL 0.027

INJECTION
Column
No. of Similar Column Column Concrete Area Jlh Presentase Total Injeksi
Column ID Remark Depth, D
Column Width, b (mm) Length (m) (m2) Injeksi/m2 Injeksi(%) (Titik)
(mm)
Lantai 1
Kolom K1 150x150 Semua Kolom 16 150 150 3.96 38.0 10 2 7.603
TOTAL INJECTION GRANDTOTAL 8
Project : Assessment, Testing dan Analisis Struktur Rumah Pribadi Ibu Meidy, Sukadamai - Kota Bogor
Subject : Estimasi Volume Bongkar Pasang

No. of
Beam Length Bongkaran Bongkaran
Beams ID Remark Similar Jenis Plafon Jenis Dinding
(m) Plafon (m2) Dinding (m2)
Beams

Lantai 2
Balok B1 150x300 As D/1-2, I/1-2 2 3.000 6.00 Gypsum 1.20 Bata
Balok B1 150x300 E'/1-1',G/1-1' 2 2.150 4.30 Gypsum 0.86 Bata
Balok B1 150x300 E/2-3, H/2-3 2 3.650 7.30 Gypsum 1.46 Bata
Balok B1 150x300 B/3-4 1 2.250 2.25 Gypsum 0.45 Bata
Balok B1 150x300 E/3-4', F/3-4', G/3-4',H/3-4' 4 3.125 12.50 Gypsum 2.50 Bata
Balok B1 150x300 A/4-5, C/4-5 2 3.450 6.90 Gypsum 1.38 Bata
Balok B1 150x300 D/4-6 1 5.450 5.45 Gypsum 1.09 Bata
Balok B1 150x300 E/4'-5, H/4'-5 2 2.650 5.30 Gypsum 1.06 Bata
Balok B1 150x300 C/5-6 1 2.000 2.00 Gypsum 0.40 Bata
Balok B1 150x300 D/6-7,E/6-7 2 0.650 1.30 Gypsum 0.26 Bata
Balok B1 150x300 E/5-7,H/5-7 2 2.650 5.30 Gypsum 1.06 Bata
Balok B1 150x300 D-E/4, D-E/6,D-E/3 3 2.630 7.89 Gypsum 1.58 Bata
Balok B1 150x300 C-E/2 1 4.000 4.00 Gypsum 0.80 Bata
Balok B1 150x300 C-D/4, C-D/6 2 1.250 2.50 Gypsum 0.50 Bata
Balok B1 150x300 B-C/3, B-C/4 2 0.580 1.16 Gypsum 0.23 Bata
Balok B1 150x300 A-C/6 1 4.535 4.54 Gypsum 0.91 Bata
Balok B1 150x300 E-F/1, E-F/2, E-F/5 3 1.550 4.65 Gypsum 0.93 Bata
Balok B1 150x300 E-H/7 1 4.250 4.25 Gypsum 0.85 Bata
Balok B1 150x300 F-I/1, F-I/2 2 4.000 8.00 Gypsum 1.60 Bata
Balok B1 150x300 F-H/3, F-H/4, F-H/5, F-H/7 4 2.700 10.80 Gypsum 2.16 Bata
Balok B1 150x300 A-D/5-7 1 6.160 6.16 Gypsum 1.23 Bata
TOTAL 112.54 Gypsum 14.60 Bata
33.76 Asumsi dibongka 2.92 Asumsi dibongkar 50 %

No. of
Column Bongkaran Jenis
Column ID Remark Similar
Hight (m) Dinding (m2) Dinding
Column
Lantai 1
Kolom K1 150x150 Semua Kolom 16 3.96 25.344 Bata
TOTAL 12.67 Bata
Asumsi dibongkar 50 %
Project: Assessment, Testing dan Analisis Struktur Rumah Pribadi Ibu Meidy, Sukadamai - Kota Bogor
Subject: Estimasi Volume Perbaikan Dinding Beton (Retak Ringan)

PLESTERAN
Wall Total
No. of Wall Hight Repair Concrete
Wall ID Remark Direction Width, b Plesteran
Similar Wall (m) Area (m) Area (m2)
(m) (m2)
Lantai 1
Dinding 3-4/B Vertikal 2 2.25 3.000 0.5 3.00 6.000
Dinding 3-4/B Horizontal 1 2.25 3.000 0.5 1.13 2.250
Dinding 7/C-D Vertikal 3.000 0.5 0.00 0.000
Dinding 7/C-D Horizontal 3 0.3 3.000 0.5 0.45 0.900
Dinding 4/C-D Vertikal 2 1.25 3.000 0.5 3.00 6.000
Dinding 4/C-D Horizontal 3 1.25 3.000 0.5 1.88 3.750
Dinding 5/A-C Vertikal 1 1.88 3.000 0.5 1.50 3.000
Dinding 5/A-C Horizontal 1 1.88 3.000 0.5 0.94 1.880
Dinding 5-6/A-C Vertikal 2 2 3.000 0.5 3.00 6.000
Dinding 5-6/A-C Horizontal 3 2 3.000 0.5 3.00 6.000
Dinding 5-7/E Vertikal 1 2.65 3.000 0.5 1.50 3.000
Dinding 5-7/E Horizontal 1 2.65 3.000 0.5 1.33 2.650
Dinding 4-5/H Vertikal 1 3.45 3.000 0.5 1.50 3.000
Dinding 4-5/H Horizontal 1 3.45 3.000 0.5 1.73 3.450
Dinding 4'/F-H Vertikal 1 2.7 3.000 0.5 1.50 3.000
Dinding 4'/F-H Horizontal 1 2.7 3.000 0.5 1.35 2.700
Dinding 4-4'/E Vertikal 1 0.85 3.000 0.5 1.50 3.000
Dinding 4-4'/E Horizontal 2 0.85 3.000 0.5 0.85 1.700
Dinding 3-4/H Vertikal 1 2.25 3.000 0.5 1.50 3.000
Dinding 3-4/H Horizontal 2 2.25 3.000 0.5 2.25 4.500
Dinding 3/G-H Vertikal 3.000 0.5 0.00 0.000
Dinding 3/G-H Horizontal 3 0.9 3.000 0.5 1.35 2.700
Dinding 2-3/H Vertikal 1 3.65 3.000 0.5 1.50 3.000
Dinding 2-3/H Horizontal 2 3.65 3.000 0.5 3.65 7.300
Dinding 2/F-H Vertikal 2 2.7 3.000 0.5 3.00 6.000
Dinding 2/F-H Horizontal 3 2.7 3.000 0.5 4.05 8.100
Dinding 2-3/E Vertikal 2 3.65 3.000 0.5 3.00 6.000
Dinding 2-3/E Horizontal 2 3.65 3.000 0.5 3.65 7.300
Dinding 3/D-E Vertikal 3 2.63 3.000 0.5 4.50 9.000
Dinding 3/D-E Horizontal 2 2.63 3.000 0.5 2.63 5.260
Dinding 2/D-E Vertikal 2 2.63 3.000 0.5 3.00 6.000
Dinding 2/D-E Horizontal 3 2.63 3.000 0.5 3.95 7.890
Dinding 1-2/I Vertikal 2 3 3.000 0.5 3.00 6.000
Dinding 1-2/I Horizontal 1 3 3.000 0.5 1.50 3.000
Dinding E'/1-2 Vertikal 1 3 3.000 0.5 1.50 3.000
Dinding E'/1-2 Horizontal 2 3 3.000 0.5 3.00 6.000
Dinding 1'/E1-G Vertikal 1 3.35 3.000 0.5 1.50 3.000
Dinding 1'/E1-G Horizontal 1 3.35 3.000 0.5 1.68 3.350
Dinding E-G/1 Vertikal 1 3.35 3.000 0.5 1.50 3.000
Dinding E-G/1 Horizontal 2 3.35 3.000 0.5 3.35 6.700
Lantai 2
Dinding 4/D-E Vertikal 1 2.63 3.000 0.5 1.50 3.000
Dinding 4/D-E Horizontal 2 2.63 3.000 0.5 2.63 5.260
Dinding 2-3/E Vertikal 1 3.65 3.000 0.5 1.50 3.000
Dinding 2-3/E Horizontal 1 3.65 3.000 0.5 1.83 3.650
Dinding 1/D-E Vertikal 3 2.63 3.000 0.5 4.50 9.000
Dinding 1/D-E Horizontal 1 2.63 3.000 0.5 1.32 2.630
Dinding D/1-2 Vertikal 3 3 3.000 0.5 4.50 9.000
Dinding D/1-2 Horizontal 3 3 3.000 0.5 4.50 9.000
Dinding 2/D-E Vertikal 3 2.63 3.000 0.5 4.50 9.000
Dinding 2/D-E Horizontal 4 2.63 3.000 0.5 5.26 10.520
Dinding G/1-1 Vertikal 3.000 0.5 0.00 0.000
Dinding G/1-1 Horizontal 3 2.5 3.000 0.5 3.75 7.500
Dinding 1/E'-G Vertikal 1 2.55 3.000 0.5 1.50 3.000
Dinding 1/E'-G Horizontal 3 2.55 3.000 0.5 3.82 7.650
Dinding 2/F-H Vertikal 2 2.7 3.000 0.5 3.00 6.000
Dinding 2/F-H Horizontal 3 2.7 3.000 0.5 4.05 8.100
Dinding 1'/G-H Vertikal 1 0.9 3.000 0.5 1.50 3.000
Dinding 1'/G-H Horizontal 3.000 0.5 0.00 0.000
Dinding 1-2/I Vertikal 3.000 0.5 0.00 0.000
Dinding 1-2/I Horizontal 3 3 3.000 0.5 4.50 9.000
Dinding 2-3/F Vertikal 2 3.65 3.000 0.5 3.00 6.000
Dinding 2-3/F Horizontal 3 3.65 3.000 0.5 5.48 10.950
Dinding 3/F-H Vertikal 3.000 0.5 0.00 0.000
Dinding 3/F-H Horizontal 2 2.7 3.000 0.5 2.70 5.400
Dinding 2-3/H Vertikal 2 3.65 3.000 0.5 3.00 6.000
Dinding 2-3/H Horizontal 1 3.65 3.000 0.5 1.83 3.650
Dinding 4/F-H Vertikal 3.000 0.5 0.00 0.000
Dinding 4/F-H Horizontal 3 2.7 3.000 0.5 4.05 8.100
Dinding 5/F-H Vertikal 2 2.7 3.000 0.5 3.00 6.000
Dinding 5/F-H Horizontal 2 2.7 3.000 0.5 2.70 5.400
Dinding E/5-6 Vertikal 1 2 3.000 0.5 1.50 3.000
Dinding E/5-6 Horizontal 2 2 3.000 0.5 2.00 4.000
Dinding H/5-6 Vertikal 2 2 3.000 0.5 3.00 6.000
Dinding H/5-6 Horizontal 1 2 3.000 0.5 1.00 2.000
Dinding E-H/7 Vertikal 3.000 0.5 0.00 0.000
Dinding E-H/7 Horizontal 2 2.7 3.000 0.5 2.70 5.400
Dinding 6/D-E Vertikal 3.000 0.5 0.00 0.000
Dinding 6/D-E Horizontal 2 2.63 3.000 0.5 2.63 5.260
Dinding A-B/7 Vertikal 1 3 3.000 0.5 1.50 3.000
Dinding A-B/7 Horizontal 2 3 3.000 0.5 3.00 6.000
Dinding 4-5/A Vertikal 1 3.45 3.000 0.5 1.50 3.000
Dinding 4-5/A Horizontal 2 3.45 3.000 0.5 3.45 6.900
Dinding 4/D-E Vertikal 1 2.63 3.000 0.5 1.50 3.000
Dinding 4/D-E Horizontal 2 2.63 3.000 0.5 2.63 5.260
TOTAL PLESTERAN GRANDTOTAL 381.010

WIREMESH
Wall Total
No. of Wall Hight Repair Concrete
Wall ID Remark Direction Width, b Wiremesh
Similar Wall (m) Area (m) Area (m2)
(m) (m2)
Lantai 1
Dinding 3-4/B Vertikal 2 2.25 3.000 0.5 3.00 6.000
Dinding 3-4/B Horizontal 1 2.25 3.000 0.5 1.13 2.250
Dinding 7/C-D Vertikal 0 3.000 0.5 0.00 0.000
Dinding 7/C-D Horizontal 3 0.3 3.000 0.5 0.45 0.900
Dinding 4/C-D Vertikal 2 1.25 3.000 0.5 3.00 6.000
Dinding 4/C-D Horizontal 3 1.25 3.000 0.5 1.88 3.750
Dinding 5/A-C Vertikal 1 1.88 3.000 0.5 1.50 3.000
Dinding 5/A-C Horizontal 1 1.88 3.000 0.5 0.94 1.880
Dinding 5-6/A-C Vertikal 2 2 3.000 0.5 3.00 6.000
Dinding 5-6/A-C Horizontal 3 2 3.000 0.5 3.00 6.000
Dinding 5-7/E Vertikal 1 2.65 3.000 0.5 1.50 3.000
Dinding 5-7/E Horizontal 1 2.65 3.000 0.5 1.33 2.650
Dinding 4-5/H Vertikal 1 3.45 3.000 0.5 1.50 3.000
Dinding 4-5/H Horizontal 1 3.45 3.000 0.5 1.73 3.450
Dinding 4'/F-H Vertikal 1 2.7 3.000 0.5 1.50 3.000
Dinding 4'/F-H Horizontal 1 2.7 3.000 0.5 1.35 2.700
Dinding 4-4'/E Vertikal 1 0.85 3.000 0.5 1.50 3.000
Dinding 4-4'/E Horizontal 2 0.85 3.000 0.5 0.85 1.700
Dinding 3-4/H Vertikal 1 2.25 3.000 0.5 1.50 3.000
Dinding 3-4/H Horizontal 2 2.25 3.000 0.5 2.25 4.500
Dinding 3/G-H Vertikal 0 3.000 0.5 0.00 0.000
Dinding 3/G-H Horizontal 3 0.9 3.000 0.5 1.35 2.700
Dinding 2-3/H Vertikal 1 3.65 3.000 0.5 1.50 3.000
Dinding 2-3/H Horizontal 2 3.65 3.000 0.5 3.65 7.300
Dinding 2/F-H Vertikal 2 2.7 3.000 0.5 3.00 6.000
Dinding 2/F-H Horizontal 3 2.7 3.000 0.5 4.05 8.100
Dinding 2-3/E Vertikal 2 3.65 3.000 0.5 3.00 6.000
Dinding 2-3/E Horizontal 2 3.65 3.000 0.5 3.65 7.300
Dinding 3/D-E Vertikal 3 2.63 3.000 0.5 4.50 9.000
Dinding 3/D-E Horizontal 2 2.63 3.000 0.5 2.63 5.260
Dinding 2/D-E Vertikal 2 2.63 3.000 0.5 3.00 6.000
Dinding 2/D-E Horizontal 3 2.63 3.000 0.5 3.95 7.890
Dinding 1-2/I Vertikal 2 3 3.000 0.5 3.00 6.000
Dinding 1-2/I Horizontal 1 3 3.000 0.5 1.50 3.000
Dinding E'/1-2 Vertikal 1 3 3.000 0.5 1.50 3.000
Dinding E'/1-2 Horizontal 2 3 3.000 0.5 3.00 6.000
Dinding 1'/E1-G Vertikal 1 3.35 3.000 0.5 1.50 3.000
Dinding 1'/E1-G Horizontal 1 3.35 3.000 0.5 1.68 3.350
Dinding E-G/1 Vertikal 1 3.35 3.000 0.5 1.50 3.000
Dinding E-G/1 Horizontal 2 3.35 3.000 0.5 3.35 6.700
Lantai 2
Dinding 4/D-E Vertikal 1 2.63 3.000 0.5 1.50 3.000
Dinding 4/D-E Horizontal 2 2.63 3.000 0.5 2.63 5.260
Dinding 2-3/E Vertikal 1 3.65 3.000 0.5 1.50 3.000
Dinding 2-3/E Horizontal 1 3.65 3.000 0.5 1.83 3.650
Dinding 1/D-E Vertikal 3 2.63 3.000 0.5 4.50 9.000
Dinding 1/D-E Horizontal 1 2.63 3.000 0.5 1.32 2.630
Dinding D/1-2 Vertikal 3 3 3.000 0.5 4.50 9.000
Dinding D/1-2 Horizontal 3 3 3.000 0.5 4.50 9.000
Dinding 2/D-E Vertikal 3 2.63 3.000 0.5 4.50 9.000
Dinding 2/D-E Horizontal 4 2.63 3.000 0.5 5.26 10.520
Dinding G/1-1 Vertikal 0 3.000 0.5 0.00 0.000
Dinding G/1-1 Horizontal 3 2.5 3.000 0.5 3.75 7.500
Dinding 1/E'-G Vertikal 1 2.55 3.000 0.5 1.50 3.000
Dinding 1/E'-G Horizontal 3 2.55 3.000 0.5 3.82 7.650
Dinding 2/F-H Vertikal 2 2.7 3.000 0.5 3.00 6.000
Dinding 2/F-H Horizontal 3 2.7 3.000 0.5 4.05 8.100
Dinding 1'/G-H Vertikal 1 0.9 3.000 0.5 1.50 3.000
Dinding 1'/G-H Horizontal 0 3.000 0.5 0.00 0.000
Dinding 1-2/I Vertikal 0 3 3.000 0.5 0.00 0.000
Dinding 1-2/I Horizontal 3 3 3.000 0.5 4.50 9.000
Dinding 2-3/F Vertikal 2 3.65 3.000 0.5 3.00 6.000
Dinding 2-3/F Horizontal 3 3.65 3.000 0.5 5.48 10.950
Dinding 3/F-H Vertikal 0 3.000 0.5 0.00 0.000
Dinding 3/F-H Horizontal 2 2.7 3.000 0.5 2.70 5.400
Dinding 2-3/H Vertikal 2 3.65 3.000 0.5 3.00 6.000
Dinding 2-3/H Horizontal 1 3.65 3.000 0.5 1.83 3.650
Dinding 4/F-H Vertikal 0 0 3.000 0.5 0.00 0.000
Dinding 4/F-H Horizontal 3 2.7 3.000 0.5 4.05 8.100
Dinding 5/F-H Vertikal 2 2.7 3.000 0.5 3.00 6.000
Dinding 5/F-H Horizontal 2 2.7 3.000 0.5 2.70 5.400
Dinding E/5-6 Vertikal 1 2 3.000 0.5 1.50 3.000
Dinding E/5-6 Horizontal 2 2 3.000 0.5 2.00 4.000
Dinding H/5-6 Vertikal 2 2 3.000 0.5 3.00 6.000
Dinding H/5-6 Horizontal 1 2 3.000 0.5 1.00 2.000
Dinding E-H/7 Vertikal 0 3.000 0.5 0.00 0.000
Dinding E-H/7 Horizontal 2 2.7 3.000 0.5 2.70 5.400
Dinding 6/D-E Vertikal 0 3.000 0.5 0.00 0.000
Dinding 6/D-E Horizontal 2 2.63 3.000 0.5 2.63 5.260
Dinding A-B/7 Vertikal 1 3 3.000 0.5 1.50 3.000
Dinding A-B/7 Horizontal 2 3 3.000 0.5 3.00 6.000
Dinding 4-5/A Vertikal 1 3.45 3.000 0.5 1.50 3.000
Dinding 4-5/A Horizontal 2 3.45 3.000 0.5 3.45 6.900
Dinding 4/D-E Vertikal 1 2.63 3.000 0.5 1.50 3.000
Dinding 4/D-E Horizontal 2 2.63 3.000 0.5 2.63 5.260
TOTAL WIREMESH GRANDTOTAL 381.010