BILL OF QUANTITY & PRICE
I PEKERJAAN PERSIAPAN
1 Pekerjaan Persiapan
1,1 Mobilisasi & Demobilisasi Ls 1,00 - 7.459.510 - 7.459.510 7.459.510
1,2 Alat Keselamatan Kerja & APD Ls 1,00 - 1.015.000 - 1.015.000 1.015.000
IV PEKERJAAN PASANGAN
1 Pemasangan Dinding Batako
1,1 Pasangan Dinding Batako 1 Pc : 4 Ps M² 136,50 31.250 15.080 4.265.625 2.058.420 6.324.045
1,2 Plesteran Dinding 1 Pc : 4 Ps + Aci M² 273,00 24.897 10.556 6.796.990 2.881.788 9.678.778
1,3 Keramik Dinding Toilet / WC 20 x 25 cm M² 12,00 75.000 37.700 900.000 452.400 1.352.400
V PEKERJAAN LANTAI
1 Lantai Beton K-200
1,1 Urugan Tanah & Pemadatan M³ 3,60 - 37.700 - 135.720 135.720
1,2 Urugan Pasir, t = 50 mm M³ 3,60 120.000 15.080 432.000 54.288 486.288
1,3 Pengecoran Lantai T = 100 mm, K-200 M³ 7,20 1.079.400 211.120 7.771.680 1.520.064 9.291.744
1,4 Pem. Keramik Lantai 40 x 40 cm, Merek Roman/Setara M² 72,00 37.951 33.176 2.732.500 2.388.672 5.121.172
1,5 Pem. Keramik Lantai Kmr Mandi 20 x 20 cm, Merek Roman/Setara M² 2,23 78.000 3.468 173.745 7.726 181.471
VI PEKERJAAN ATAP
1 Kuda-Kuda Atap
1,1 Kuda-Kuda Atap Baja Ringan Kanal C 0.75 mm Merk Kaso Btg 158,00 135.000 12.064 21.330.000 1.906.112 23.236.112
1,2 Reng Baja Ringan, Tebal 0.45 mm Btg 45,00 68.000 8.294 3.060.000 373.230 3.433.230
2 Penutup Atap
2,1 Atap Spandek Warna Merah Maroon M² 137,26 103.000 7.842 14.137.404 1.076.309 15.213.714
3 List Plank
3,1 Pasang lisplank GRC, lebar 20 cm M' 42,40 22.917 7.540 971.667 319.696 1.291.363
PRICE / UNIT TOTAL PRICE TOTAL COST
ESTIMATED
NO. JOB DESCRIPTION / SPESIFICATION UNIT
VOLUME Material Wage Material Wage Rp.
Rp. Rp. Rp. Rp.
VII PEKERJAAN PLAFOND
1 Rangka Plafond
1,1 Pasang Rangka Plafond Hollow Zincalume 40x40x0,3 mm Btg 72,00 40.000 4.072 2.880.000 293.155 3.173.155
2 Plafond
2,1 Pasang Plafond Triplek 3 mm M² 103,68 20.000 8.294 2.073.600 859.922 2.933.522
3 List Plafond
3,1 Pasang List Plafond Gypsum M' 42,00 68.000 7.540 2.856.000 316.680 3.172.680
3 Bouvenlight
3,1 Bouvenlight Uk. 60x40 cm Unit 1,00 350.000 25.636 350.000 25.636 375.636
3 Septic Tank
Bilangan Septic Tank
3,1 Pekerjaan Septictank (Gorong" Beton Ø1Mtr ) Pcs 2,00 1.000.000 120.640 2.000.000 241.280 2.241.280
4 Sanitair Fixture
4,1 Pasang Kloset Jongkok Unit 1,00 139.200 67.860 139.200 67.860 207.060
4,2 Floor Drain PVC Pcs 1,00 1.563 70.876 1.563 70.876 72.439
4,3 Kran Air PVC 1/2'' Pcs 1,00 5.000 54.288 5.000 54.288 59.288
4,4 Bak Fibre PVC Unit 1,00 4.375 - 4.375 - 4.375
XI PEKERJAAN PENGECATAN
1 Pengecatan Dinding
1,1 Cat Dasar Merk Vinilex Wall Sealer (Alkali-Resisting) (1 Lapis) M² 273,00 1.563 3.016 426.563 823.368 1.249.931
1,2 Cat Finishing Exterior Merk Nippon Vinilex - Glory Yellow (2 Lapis) M² 126,00 10.000 3.016 1.260.000 380.016 1.640.016
1,3 Cat Finishing Interior Merk Nippon Vinilex - Extra White (2 Lapis) M² 147,00 8.750 3.016 1.286.250 443.352 1.729.602
2 Pengecatan Plafond
2,1 Cat Dasar Merk Vinilex /Setara Wall Sealer (Alkali-Resisting) (1 Lapis) M² 103,68 1.563 3.468 162.000 359.604 521.604
2,2 Cat Finishing Interior Merk Nippon Vinilex - Extra White (2 Lapis) M² 103,68 8.750 3.468 907.200 359.604 1.266.804
Terbilang : Seratus Tiga Puluh Lima Juta Lima Ratus Dua Puluh Tiga Ribu Rupiah