BILL OF QUANTITY & PRICE

PROJECT : R. ARSIP
LOCATION : PT. KARYA BOGA MITRA
AREA : 96 M² (8 M x 12 M)
TAHUN : 2023

PRICE / UNIT TOTAL PRICE TOTAL COST


ESTIMATED
NO. JOB DESCRIPTION / SPESIFICATION UNIT
VOLUME Material Wage Material Wage Rp.
Rp. Rp. Rp. Rp.

I PEKERJAAN PERSIAPAN
1 Pekerjaan Persiapan
1,1 Mobilisasi & Demobilisasi Ls 1,00 - 15.779.614 - 15.779.614 15.779.614
1,2 Alat Keselamatan Kerja & APD Ls 1,00 - 580.000 - 580.000 580.000

II PEKERJAAN TANAH & PONDASI


1 Pekerjaan Bouwplank
1,1 Pekerjaan Bouwplank M' 28,00 30.000 6.032 840.000 168.896 1.008.896

2 Pondasi Tapak 400 x 400 mm


Jumlah Pondasi 12 Unit
2,1 Galian Tanah M³ 1,06 - 42.224 - 44.589 44.589
2,2 Urugan Tanah & Pemadatan M³ 0,51 - 37.700 - 19.170 19.170
2,3 Urugan Pasir, t = 50 mm M³ 0,10 120.000 15.080 11.520 1.448 12.968
2,4 Black Plastic Cor 0.1 mm M² 1,92 1.392 752 2.673 1.445 4.117
2,5 Bekisting M² 1,83 63.750 15.683 116.663 28.700 145.363
2,6 Pembesian
* Besi Beton Ø12 mm Btg 6,93 123.900 26.792 859.040 185.759 1.044.799
* Besi Beton Ø10 mm Btg 2,40 90.000 18.599 216.000 44.637 260.637
* Besi Beton Ø6 mm Btg 1,47 35.750 6.685 52.433 9.805 62.239
2,7 Pengecoran Beton K-225 M³ 0,45 1.122.200 211.120 506.673 95.321 601.994

III PEKERJAAN KONSTRUKSI BETON


1 Sloof Beton 100 x 150 mm
1,1 Bekisting M² 5,60 63.750 15.683 357.000 87.826 444.826
1,2 Galian Tanah M³ 1,12 - 42.224 - 47.291 47.291
1,3 Urugan Pasir, t = 50 mm M³ 0,28 120.000 15.080 33.600 4.222 37.822
1,4 Black Plastic Cor 0.1 mm M² 5,60 1.392 752 7.795 4.213 12.009
1,5 Pembesian
* Besi Beton Ø10 mm Btg 18,67 90.000 18.599 1.680.000 347.175 2.027.175
* Besi Beton Ø6 mm Btg 17,11 35.750 6.685 611.722 114.396 726.118
1,6 Pengecoran Beton K-225 M³ 0,84 1.122.200 211.120 942.648 177.341 1.119.989

2 Kolom Beton 100 x 150 mm


2,1 Bekisting M² 16,05 63.750 15.683 1.023.400 251.768 1.275.168
2,2 Pembesian
* Besi Beton Ø10 mm Btg 26,76 90.000 18.599 2.408.000 497.618 2.905.618
* Besi Beton Ø6 mm Btg 24,53 35.750 6.685 876.802 163.967 1.040.769
2,3 Pengecoran Beton K-225 M³ 1,20 1.122.200 211.120 1.351.129 254.188 1.605.317

3 Ring Balok Beton 100 x 150 mm


3,1 Bekisting M² 4,00 63.750 15.683 255.000 62.733 317.733
3,2 Pembesian
* Besi Beton Ø10 mm Btg 13,33 90.000 18.599 1.200.000 247.982 1.447.982
* Besi Beton Ø6 mm Btg 12,22 35.750 6.685 436.944 81.711 518.656
3,3 Pengecoran Beton K-225 M³ 0,60 1.122.200 211.120 673.320 126.672 799.992

IV PEKERJAAN PASANGAN
1 Pemasangan Dinding Batako
1,1 Pasangan Dinding Batako 1 Pc : 4 Ps M² 166,56 31.250 15.080 5.204.844 2.511.649 7.716.493
1,2 Plesteran Dinding 1 Pc : 4 Ps + Aci M² 338,56 24.897 10.556 8.429.139 3.573.787 12.002.926

V PEKERJAAN LANTAI
1 Lantai Beton K-200
1,1 Urugan Tanah & Pemadatan M³ 4,80 - 37.700 - 180.960 180.960
1,2 Urugan Pasir, t = 50 mm M³ 4,80 120.000 15.080 576.000 72.384 648.384
1,3 Pengecoran Lantai T = 100 mm, K-200 M³ 9,60 1.079.400 211.120 10.362.240 2.026.752 12.388.992

2 Lantai Selasar Beton K-175


2,1 Urugan Tanah & Pemadatan M³ 1,60 - 37.700 - 60.320 60.320
2,2 Urugan Pasir, t = 50 mm M³ 1,60 120.000 15.080 192.000 24.128 216.128
2,3 Pengecoran Lantai T = 80 mm, K-175 M³ 2,56 1.036.300 211.120 2.652.928 540.467 3.193.395

VI PEKERJAAN ATAP
1 Kuda-Kuda Atap
1,1 Kuda-Kuda Atap Baja Ringan Kanal C 0.75 mm Merk Kaso Btg 101,00 135.000 12.064 13.635.000 1.218.464 14.853.464
1,2 Reng Baja Ringan, Tebal 0.45 mm Btg 35,00 68.000 8.294 2.380.000 290.290 2.670.290

2 Penutup Atap
1,1 Atap Spandek Warna Merah Maroon M² 150,76 103.000 7.842 15.528.499 1.182.216 16.710.715

3 List Plank
1,1 Pasang lisplank GRC, lebar 20 cm M' 46,40 22.917 7.540 1.063.333 349.856 1.413.189
PRICE / UNIT TOTAL PRICE TOTAL COST
ESTIMATED
NO. JOB DESCRIPTION / SPESIFICATION UNIT
VOLUME Material Wage Material Wage Rp.
Rp. Rp. Rp. Rp.
VII PEKERJAAN PLAFOND
1 Rangka Plafond
1,1 Pasang Rangka Plafond Hollow Zincalume 40x40x0,3 mm Btg 113,00 40.000 4.072 4.520.000 460.091 4.980.091

2 Plafond
2,1 Pasang Plafond Gypsum 9 mm M² 99,20 70.000 6.032 6.944.000 598.374 7.542.374

3 List Plafond
3,1 Pasang List Plafond Gypsum M' 80,00 35.000 2.111 2.800.000 168.896 2.968.896

VIII PEKERJAAN KUSEN, PINTU, JENDELA, & PENGGANTUNG


1 Kusen Pintu + Daun Pintu
1,1 Kusen & Daun Pintu Panel Uk. 90x205 cm + Ventilasi Unit 1,00 800.000 45.240 800.000 45.240 845.240

2 Kusen Jendela + Daun Jendela


2,1 Kusen Jendela + Daun Jendela - 2 Daun Uk. 115x110 cm + Ventilasi Unit 3,00 1.040.000 54.288 3.120.000 162.864 3.282.864

4 Aksesoris Pintu & Jendela


4,1 Pasang Kunci Tanam Merk Belluci Setara 10'' Unit 1,00 85.000 15.080 85.000 15.080 100.080
4,2 Pasang Engsel Pintu 4" Pcs 3,00 20.000 2.262 60.000 6.786 66.786
4,3 Grendel Pintu Stainless 3" Pcs 2,00 10.000 3.016 20.000 6.032 26.032
4,4 Pasang Engsel Jendela 3" Pcs 4,00 15.000 2.262 60.000 9.048 69.048
4,5 Handle Jendela Stainless Standart 4'' Pcs 2,00 11.100 1.810 22.200 3.619 25.819
4,6 Hak Angin Jendela 8'' Pcs 4,00 8.000 2.262 32.000 9.048 41.048
4,7 Grendel Jendela Stainless 2" Pcs 4,00 10.000 3.016 40.000 12.064 52.064

IX PEKERJAAN RAK BAJA


1 Pekerjaan Rak Baja
1,1 L 50 x 50 x 5 x 6m Kg 2.195,11 5.586 2.513 12.261.884 5.516.311 17.778.196
1,2 Triplek, t = 18 mm Lbr 54,00 390.000 15.683 21.060.000 846.882 21.906.882

X PEKERJAAN INSTALASI LISTRIK


1 Pekerjaan Instalasi Listrik
1,1 Titik Stop Kontak merk "Panasonic" + Instalasi Ttk 2,00 74.250 67.860 148.500 135.720 284.220
1,2 Titik Lampu merk "Philips" 18 watt + Instalasi Ttk 5,00 104.250 67.860 521.250 339.300 860.550
1,3 Saklar Ganda Tanam Merk Panasonic + Instalasi Ttk 2,00 94.200 67.860 188.400 135.720 324.120
1,4 Saklar Tunggal Tanam Merk Panasonic + Instalasi Ttk 1,00 72.200 67.860 72.200 67.860 140.060
1,5 MCB 1 Phase Schneider - 4A Include Box MCB Schneider/Setara Set 1,00 139.200 33.176 139.200 33.176 172.376

XI PEKERJAAN PENGECATAN
1 Pengecatan Dinding
1,1 Cat Dasar Merk Vinilex Wall Sealer (Alkali-Resisting) (1 Lapis) M² 338,56 1.563 3.016 528.992 1.021.082 1.550.074
1,2 Cat Finishing Exterior Merk Nippon Vinilex - Glory Yellow (2 Lapis) M² 169,28 5.000 3.016 846.388 510.541 1.356.928
1,3 Cat Finishing Interior Merk Nippon Vinilex - Extra White (2 Lapis) M² 169,28 4.375 3.016 740.589 510.541 1.251.130

2 Pengecatan Plafond
2,1 Cat Dasar Merk Vinilex /Setara Wall Sealer (Alkali-Resisting) (1 Lapis) M² 99,20 1.563 3.468 155.000 344.065 499.065
2,2 Cat Finishing Interior Merk Nippon Vinilex - Extra White (2 Lapis) M² 99,20 4.375 3.468 434.000 344.065 778.065

3 Cat Minyak - Kayu


3,1 Cat Dasar Merk Nippon Paint/Setara Bodelac Undercoat White (1 Lapis) M² 0,30 7.143 6.786 2.107 2.002 4.109
3,2 Cat Finishing Merk Nippon Paint/Setara Warna Merah Maroon (2 Lapis) M² 0,54 10.857 6.786 5.863 3.664 9.527

XII PEKERJAAN FINISHING


1 Pembersihan Lokasi Kerja
1,1 Pembersihan Lokasi Kerja Ls 1,00 - 723.840 - 723.840 723.840

TOTAL BIAYA 130.093.919 43.491.673 173.585.592


DIBULATKAN Rp 173.585.000

LUAS BANGUNAN (M') 8,00 12,00 96,00


RP/M² 1.808.183

Terbilang : Seratus Tujuh Puluh Tiga Juta Lima Ratus Delapan Puluh Lima Ribu Rupiah

Dibuat Oleh : Diperiksa Oleh : Disetujui Oleh : Diketahui Oleh :

Amru Pohan Manunggal AE Jonathan Bangkit


Civil Engineering Askep Teknik Manager Teknik Kadiv Teknik