Anda di halaman 1dari 3

PEMERINTAH KABUPATEN KEPULAUAN TALAUD

DINAS KESEHATAN
Jl. Kompleks Perkantoran PEMDA Talaud Melonguane email : dinkes_talaud@yahoo.com

DAFTAR KUANTITAS DAN HARGA SATUAN

KEGIATAN : PEMBANGUNAN RUMAH DINAS DOKTER PUSKESMAS MELONGUANE


PEKERJAAN : PEMBANGUNAN RUMAH DINAS DOKTER PUSKESMAS MELONGUANE
LOKASI : MELONGUANE, KECAMATAN MELONGUANE
TAHUN ANGGARAN : 2018

HARGA JUMLAH
NO URAIAN JENIS PEKERJAAN / KEGIATAN SATUAN VOLUME SATUAN HARGA
(Rp) (Rp)
1 2 3 5 6

A PEMBANGUNAN RUMAH DINAS DOKTER PUSKESMAS MELONGUANE 545,465,256.87


I PEKERJAAN PERSIAPAN 27,222,906.50
1 Pembongkaran Bangunan Lama Ls 1.000 5,000,000.00 5,000,000.00
2 Pengukuran dan Pasang Bouwplank M' 47.800 66,930.00 3,199,254.00
3 Pembersihan Awal & Pembuangan sisa Puing Bangunan Lama Ls 1.000 3,000,000.00 3,000,000.00
4 Stelling Kerja Ls 1.000 2,500,000.00 2,500,000.00
5 Mobilisasi dan Demobilisasi Ls 1.000 13,523,652.50 13,523,652.50

II PEKERJAAN TANAH DAN PASIR 14,639,976.79


1 Galian Tanah Pondasi Batu Kali M3 43.650 72,450.00 3,162,442.50
2 Galian Tanah Pondasi Rolaag Batako M3 0.365 72,450.00 26,444.25
2 Urugan Tanah Bekas Galian M3 14.550 52,900.00 769,695.00
3 Urugan Pasir dibawah Pondasi Batu Kali M3 2.805 741,980.00 2,081,253.90
4 Urugan Pasir dibawah Lantai M3 4.043 741,980.00 2,999,825.14
5 Urugan Tanah Peninggian Lantai M3 15.450 362,480.00 5,600,316.00

III PEKERJAAN PONDASI 69,335,003.03

3
1 Pas. Pondasi Batu Kali Sp. 1 : 4 M 25.937 2,147,567.50 55,701,458.25
3
2 Pas. Pondasi Batu Kosong M 8.046 1,509,927.00 12,148,872.64
3
3 Pas. Pondasi Rolaag Batako M 7.320 202,824.06 1,484,672.14

IV PEKERJAAN METSEL / BETON 93,546,813.33

1 Pas. Dinding 1/2 Bata Cetak tbl 8 cm Sp. 1 : 4 M2 171.317 202,824.06 34,747,260.62
2 Plesteran Sp. 1 : 4 M2 351.090 85,279.40 29,940,744.55
3 Acian M2 351.090 47,581.25 16,705,301.06
4 Cor Lantai Beton Tumbuk Sp. 1 : 3 : 5 M3 5.704 2,130,788.28 12,153,507.10

V PEKERJAAN BETON BERTULANG 69,880,870.06


3
1 Sloof 15/20 (170.139 Kg Besi + Bekisting ) M 2.040 7,050,182.60 14,382,372.51
3
2 Kolom 15/15 (241.481 Kg Besi + Bekisting ) M 1.710 10,603,597.89 18,132,152.39
3
3 Kolom Praktis 10/10 (198.950 Kg Besi + Bekisting ) M 0.229 9,752,437.48 2,234,283.43
'
4 Ring balok 15/20 (170.139 Kg Besi + Bekisting ) M 2.297 9,762,630.10 22,419,880.03
3
5 Balok Latey 10/16 ( 219.002 Kg Besi + Bekisting ) M 0.371 10,740,503.79 3,986,875.01
3
6 Plat Beton t 8 cm Kanopy 127.256 Kg Besi + Bekisting ) M 0.662 10,204,001.16 6,758,791.59
3
7 Plat Beton t 8 cm Meja Dapur 127.256 Kg Besi + Bekisting ) M 0.193 10,204,001.16 1,966,515.10

VI PEKERJAAN LANTAI 34,489,925.57


1 Lantai Tegel 20/20 (Anti Slip) Toilet M2 1.551 307,974.31 477,569.61
2 Dinding Tegel 20/20 (Polos)Toilet M2 6.046 354,122.38 2,141,023.88
3 Dinding Tegel 20/20 (Polos)Dapur M2 2.794 354,122.38 989,382.50
4 Dinding Tegel 20/20 (Polos) Meja Dapur M2 3.612 354,122.38 1,278,985.55
5 Lantai Tegel 40/40 Interior Kwalitas 1 (Polos) M2 63.129 351,530.56 22,191,597.11
6 Pas. Tegel 20/20 Polos untuk Tempat Duduk R.tunggu Pasien M2 1.096 354,122.38 387,941.06
7 Lantai Tegel 30/30 Eksterior Kwalitas I (Anti Slip) M2 21.697 323,703.44 7,023,425.85

VII PEKERJAAN KUSEN PINTU, JENDELA 25,609,118.28


1 Pas. Kusen Kayu Kls II M3 0.683 8,876,993.75 6,058,992.08
2 Pas. Daun Pintu Panel Kayu Kls II M2 9.824 797,525.00 7,834,486.84
3 Pas. Jendela Kaca Bingkai Kayu Kls II M2 9.174 839,563.14 7,702,488.03
4 Pas. Ventilasi Kaca Bingkai Kayu Kls II M2 3.978 839,563.14 3,339,362.37
5 Pas. Jendela Kaca Mati M2 1.575 208,754.90 328,788.97
6 Pas. Kusen PVC (Pintu Toilet) Unit 1.000 345,000.00 345,000.00

VIII PEKERJAAN KUNCI DAN PENGGANTUNG 10,085,100.95


1 Kunci Tanam 2 Slaag Kwalitas I Bh 6.000 197,486.63 1,184,919.75
2 Engsel Pintu Kwalitas I Bh 18.000 89,235.40 1,606,237.20
3 Engsel Jendela dan Ventilasi Kwalitas I Bh 64.000 46,069.00 2,948,416.00
4 Grendel Kwalitas I Bh 32.000 44,229.00 1,415,328.00
5 Tarikan Kwalitas I Bh 32.000 41,589.75 1,330,872.00
6 Hak Angin Kwalitas I Psg 32.000 49,979.00 1,599,328.00
IX PEKERJAAN ATAP 101,617,370.03
1 Penutup Atap Alumunium Gelombang (Anti Karat) M2 140.670 231,626.42 32,582,842.69
2 Rangka Atap Baja Ringan M2 140.670 318,887.40 44,857,826.59
3 Bubungan Atap Alumunium Plat M' 42.413 269,525.35 11,431,486.67
4 Lisplank GRC M' 46.019 138,542.14 6,375,515.46
2
5 Penutup Atap Kanopy Alumunium Gelombang (Anti Karat) M 7.249 231,626.42 1,679,059.95
2
6 Rangka Atap Kanopy besi hollow 1 x 40.40.2 mm (Modul Sesuai Desain) M 4.685 1,001,203.56 4,690,638.68

X PEKERJAAN PLAFOND 29,551,272.06


1 Penutup Plafond GRC (120 x 240) Tebal 4 mm M2 108.394 55,355.25 6,000,193.58
2 Rangka Langit -Langit 60 x 60 cm Kayu Kelas II M2 108.394 149,442.50 16,198,715.18
3 List Profil Kayu M' 174.040 42,245.25 7,352,363.31

XI PEKERJAAN INSTALASI LISTRIK 15,192,267.57


1 Biaya Instalasi Ttk 28.000 150,000.00 4,200,000.00
2 Lampu SL 8 watt Setara Philips Bh 5.000 245,588.25 1,227,941.25
3 Lampu SL 18 watt Setara Philips Bh 7.000 261,192.60 1,828,348.20
4 Lampu SL 23 watt Setara Philips Bh 2.000 274,338.25 548,676.50
5 Stop Kontak Setara Brocco Bh 6.000 82,657.64 495,945.82
6 Saklar Ganda Setara Brocco Bh 5.000 88,407.64 442,038.18
7 Saklar Tunggal Setara Brocco Bh 3.000 82,657.64 247,972.91
8 Box Sekring NBC 3 Group Unit 1.000 131,772.99 131,772.99
9 Panel Distribusi Bh 1.000 269,571.74 269,571.74
10 Kabel Rafo 2 x 2.5 mm ( 50 meter ) Roll 2.000 650,000.00 1,300,000.00
11 Biaya Penyambungan dari PLN 900 Watt ls 1.000 4,500,000.00 4,500,000.00

XII PEKERJAAN SANITASI 28,137,307.97


1 Kloset Jongkok Bh 1.000 629,236.88 629,236.88
2 Washtafel Bh 1.000 746,249.38 746,249.38
3 Bak Air Lapis Keramik Bh 1.000 971,822.52 971,822.52
4 Bak Cuci Piring Stainless steel, Bh 1.000 546,767.50 546,767.50
5 Mata Kran Bh 2.000 118,103.85 236,207.70
6 Floor Drain Bh 1.000 57,625.78 57,625.78
8 Instalasi Air Bersih Pipa PVC dia. 3/4" M' 3.000 228,988.00 686,964.00
8 Instalasi Air Bersih Pipa PVC dia. 1" M' 2.000 230,230.00 460,460.00
8 Instalasi Air Bersih Pipa PVC dia. 2" M' 14.500 244,789.00 3,549,440.50
8 Instalasi Air Bersih Pipa PVC dia. 3" M' 12.500 288,655.75 3,608,196.88
9 Instalasi Air Kotor Pipa PVC dia. 4" M' 7.000 310,111.99 2,170,783.93
10 Septicktank dan Peresapan Unit 1.000 14,473,552.92 14,473,552.92

XIII PEKERJAAN PENGECATAN DAN FINISHING 21,157,324.72


1 Cat Dinding Setara Catylac 2X M2 351.090 39,238.00 13,776,069.42
2 Cat Plafond Setara Catylac 2X M2 108.394 39,238.00 4,253,175.54
2
3 Cat Kusen Kwalitas Setara Glotex M 22.999 55,382.85 1,273,722.48
4 Politur Daun Pintu dan Jendela M2 38.029 48,761.15 1,854,357.28

XIV PEKERJAAN LAIN - LAIN 5,000,000.00


1 Dokumentasi dan Administrasi Ls 1.000 3,500,000.00 3,500,000.00
2 Pembersihan Akhir Lokasi Ls 1.000 1,500,000.00 1,500,000.00

Mengetahui : Melonguane, Maret 2017


KEPALA DINAS KESEHATAN
KABUPATEN KEPULAUAN TALAUD PEJABAT PEMBUAT KOMITMEN

dr. KERRY D. MONANGIN, ME EPRAIM J. ALUSINSING, ST


NIP. 19630118 199803 1 003 NIP. 19790709 200604 1 019
PEMERINTAH KABUPATEN KEPULAUAN TALAUD
DINAS KESEHATAN
Jl. Kompleks Perkantoran PEMDA Talaud Melonguane email : dinkes_talaud@yahoo.com

REKAPITULASI
KEGIATAN : PEMBANGUNAN RUMAH DINAS DOKTER PUSKESMAS MELONGUANE
PEKERJAAN : PEMBANGUNAN RUMAH DINAS DOKTER PUSKESMAS MELONGUANE
LOKASI : MELONGUANE, KECAMATAN MELONGUANE
TAHUN ANGGARAN : 2017

A PEMBANGUNAN RUMAH DINAS DOKTER PUSKESMAS MELONGUANE 545,465,256.87

I PEKERJAAN PERSIAPAN 27,222,906.50


II PEKERJAAN TANAH DAN PASIR 14,639,976.79
III PEKERJAAN PONDASI 69,335,003.03
IV PEKERJAAN METSEL / BETON 93,546,813.33
V PEKERJAAN BETON BERTULANG 69,880,870.06
VI PEKERJAAN LANTAI 34,489,925.57
VII PEKERJAAN KUSEN PINTU, JENDELA 25,609,118.28
VIII PEKERJAAN KUNCI DAN PENGGANTUNG 10,085,100.95
IX PEKERJAAN ATAP 101,617,370.03
X PEKERJAAN PLAFOND 29,551,272.06
XI PEKERJAAN INSTALASI LISTRIK 15,192,267.57
XII PEKERJAAN SANITASI 28,137,307.97
XIII PEKERJAAN PENGECATAN DAN FINISHING 21,157,324.72
XIV PEKERJAAN LAIN - LAIN 5,000,000.00

(A) JUMLAH BIAYA KONSTRUKSI 545,465,256.87


(B) PAJAK ( 10% x A ) 54,546,525.69
(C) JUMLAH TOTAL (A+B ) 600,011,782.55
(D) DIBULATKAN 600,000,000.00

Terbilang : Enam Ratus Lima Puluh Juta Rupiah

Mengetahui : Melonguane, Maret 2017


KEPALA DINAS KESEHATAN
KABUPATEN KEPULAUAN TALAUD PEJABAT PEMBUAT KOMITMEN

dr. KERRY D. MONANGIN, ME EPRAIM J. ALUSINSING, ST


NIP. 19630118 199803 1 003 NIP. 19790709 200604 1 019

Anda mungkin juga menyukai