Jl Pelabuhan No 01 Kuala Tanjung

Provinsi Sumatera Utara

PROYEK:
PERENCANAAN DESAIN PEKERJAAN TERMINAL CURAH CAIR
AREA KERETA API DI PELABUHAN KUALA TANJUNG

TAHUN ANGGARAN 2023


REKAPITULASI
BILL of QUANTITY (BoQ)

NAMA PROYEK : PEMBANGUNAN TERMINAL CURAH CAIR AREA KERETA API DI PELABUHAN KUALA TANJUNG
INSTANSI : PT.PRIMA MULTI TERMINAL
LOKASI : KUALA TANJUNG
KABUPATEN/PROVINSI : BATU BARA/SUMATERA UTARA
KONTRAKTOR : PT/CV…....................................

NO JENIS PEKERJAAN JUMLAH HARGA

A PEKERJAAN PERSIAPAN
B PEKERJAAN STRUKTUR & ARSITEKTUR
B.1 BANGUNAN OVERCAPING
B.2 PIPE RACK DARI R.POMPA KE PINGGIR JALAN REL-5
B.3 PIPE RACK CROSSING JALAN REL
B.4 BANGUNAN R.POMPA, R.PANEL & R.OPERATOR
B.5 SUPPORT PIPA DALAM SALURAN EKSISTING
B.6 PEKERJAAN BOX CULVERT 1.5 X 1.5 M
C PEKERJAAN PIPING & MEKANIKAL
C.1 PEKERJAAN PIPING & MEKANIKAL LINE 01
C.1.1 PEKERJAAN PIPA SUCTION
C.1.2 PEKERJAAN PIPA DISCHARGE
C.1.3 PEKERJAAN MEKANIKAL
C.1.4 TESTING & COMMISSIONING
C.2 PEKERJAAN PIPING & MEKANIKAL LINE 02
C.2.1 PEKERJAAN PIPA SUCTION
C.2.2 PEKERJAAN PIPA DISCHARGE
C.2.3 PEKERJAAN MEKANIKAL
C.2.4 TESTING & COMMISSIONING
D PEKERJAAN ELEKTRIKAL
PEKERJAAN LISTRIK ARUS KUAT (LAK)
D.1 PEKERJAAN INSTALASI KABEL DAYA LISTRIK TEGANGAN RENDAH
D.2 PEKERJAAN PANEL LISTRIK
D.3 PEKERJAAN INSTALASI PENERANGAN ,SAKLAR DAN STOPKONTAK
D.4 PEKERJAAN KABEL TRAY KABEL
D.5 PEKERJAAN SISTEM PENAGKAL PETIR
D.6 PEKERJAAN SISTEM PROTEKSI POMPA
D.7 PEKERJAAN TESTING DAN COMMISSIONING

TOTAL

DIBULATKAN
TERBILANG :

Kuala Tanjung, ................................

PT/CV...............................

(...........................................)
..............................

Page 2 of 75
BILL of QUANTITY (BoQ)
PEKERJAAN STRUKTUR & ARSITEKTUR

NAMA PROYEK : PEMBANGUNAN TERMINAL CURAH CAIR AREA KERETA API DI PELABUHAN KUALA TANJUNG
INSTANSI : PT.PRIMA MULTI TERMINAL
LOKASI : KUALA TANJUNG
KABUPATEN/PROVINSI : BATU BARA/SUMATERA UTARA
KONTRAKTOR : PT/CV…....................................

HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SAT
SATUAN HARGA

A PEKERJAAN PERSIAPAN
1 Pekerjaan Pemasangan Bowplank A. 2.2.1.4. 1.00 Ls
2 Gudang Material & Peralatan A. 2.2.1.7. 1.00 Ls
3 Kantor Sementara (Direksi Keet) A. 2.2.1.5. 1.00 Ls
4 Mobilisasi & Demobilisasi Alat Pancang Hitung Unit 1.00
5 Pengujian PDA Test Taksir-STR1 3.00 titik
TOTAL PEKERJAAN PERSIAPAN

B PEKERJAAN STRUKTUR & ARSITEKTUR


B.1 BANGUNAN OVERCAPING
I PEKERJAAN TANAH & PENGUJIAN
1 Pekerjaan Galian Tanah A.2.3.1.1. 22.99 m3
2 Pekerjaan Urugan Kembali Bekas Galian A. 2.3.1.9. 6.90 m3
3 Pekerjaan Urugan Pasir A. 2.3.1.11. 4.00 m3
II PEKERJAAN PONDASI & BETON
1 Pekerjaan pondasi tiang mini 20x20 cm
a. Pengadaan pondasi tiang mini 20x20 cm A.2.1.2.5a 640.00 m
b. Upah pemancangan tiang mini A.2.1.2.3a 640.00 m
c. Penyambungan tiang mini A.2.1.2.10a 96.00 samb
d. Pemotongan kepala tiang mini F.07.a 32.00 titik
2 Pekerjaan Pemasangan Lantai Kerja f’c = 8,3 MPa A.4.1.1.1 4.00 m3
3 Pekerjaaan Pile Cap 80x80x50 cm
a. Pekerjaan Bekisting A.4.1.1.20 51.20 m2
b. Pekerjaan Pembesian
- Besi D16-150 A.4.1.1.17.b 1,313.10 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 10.24 m3
4 Pekerjaaan Sloof TB.1 uk.25x50 cm
a. Pekerjaan Bekisting A.4.1.1.21 180.00 m2
b. Pekerjaan Pembesian
- Besi 6D13 mm+2D10 mm A.4.1.1.17.b 1,481.89 kg
- Besi D10-150 mm A.4.1.1.17.b 1,331.64 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 22.50 m3
5 Pekerjaaan Kolom Pedestal
a. Pekerjaan Bekisting A.4.1.1.22 41.60 m2
b. Pekerjaan Pembesian
- Besi 12D16 mm A.4.1.1.17.b 727.25 kg
- Besi D10-150 mm A.4.1.1.17.b 319.59 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 5.20 m3
6 Pekerjaan Grouting kolom
a. Grouting t= 50 mm A.4.1.2.21 0.40 m3
b. Upah grouting A.4.1.2.22 32.00 titik
7 Pekerjaan Grouting pipe rack 1
a. Grouting t= 50 mm A.4.1.2.21 0.10 m3
b. Upah grouting A.4.1.2.22 50.00 titik
8 Box Culvert Crossing Jalan Rel 5
a. Pasangan Batu Belah A. 2.1.1.7. 1.08 m3
b. Lantai Kerja A.4.1.1.1 0.54 m3
c. Bekisiting A.4.1.1.25 30.45 m2
d. Pekerjaan Pembesian A.4.1.1.17.b 587.57 kg
e. Pekerjaan Beton Cor f’c = 25 MPa A.4.1.1.10 4.76 m3
III PEKERJAAN KONSTRUKSI BAJA
1 Base Plate kolom t=12 mm A.4.2.1.1.a 482.30 kg
2 Plat Stiffner kolom t=4 mm A.4.2.1.1.a 67.92 kg
3 Anchor Bolt kolom dia.16 mm Taksir-STR5 128.00 bh
4 Kolom Pipa Black Steel dia.8" A.4.2.1.1.a 4,512.00 kg
5 Rafter Pipa Black Steel dia.6.5" A.4.2.1.1.a 7,032.96 kg
6 Tie Beam Pipa Black Steel dia.6.5" A.4.2.1.1.a 3,564.00 kg
7 Bracing & Monitor Pipa Black Steel dia.3" A.4.2.1.1.a 1,574.39 kg
8 Gording Pipa Black Steel dia.3" A.4.2.1.1.a 10,281.92 kg
9 Ikatan angin dia.12 mm A.2.2.3.9 730.80 kg
10 Sagrod dia.10 mm A.2.2.3.9 437.22 kg
11 Support Pipe Rack 1 UNP 150 A.4.2.1.1.a 1,106.70 kg
12 Base Plate pipe rack t=6 mm A.4.2.1.1.a 94.20 kg
13 Plat Stiffner pipe rack t=6 mm A.4.2.1.1.a 94.20 kg
14 Anchor Bolt pipe rack dia.10 mm Hitung 100.00 bh
15 Support Unloading Platform UNP75 A.4.2.1.1.a 788.88 kg
16 Bracing Unloading Platform L50.50.5 A.4.2.1.1.a 367.58 kg
17 Pelat perforated 3 mm A.4.2.1.1.a 662.78 kg
18 Atap Zincalume t=0.3 mm A.2.3.5.2 1,803.20 m2
19 Pengecatan Besi dengan cat menie A.2.4.1.9 976.12 m2
20 Pengecatan Besi dengan cat besi A.2.4.1.16 976.12 m2
TOTAL BANGUNAN OVERCAPPING

Page 3 of 75
HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SAT
SATUAN HARGA

B.2 PIPE RACK DARI R.POMPA KE PINGGIR JALAN REL-5


I PEKERJAAN TANAH
1 Pekerjaan Galian Tanah A.2.3.1.1. 2.85 m3
2 Pekerjaan Urugan Kembali Bekas Galian A. 2.3.1.9. 0.86 m3
3 Pekerjaan Urugan Pasir A. 2.3.1.11. 0.62 m3
II PEKERJAAN PONDASI & BETON
1 Pekerjaan pondasi tiang mini 20x20 cm
a. Pengadaan pondasi tiang mini 20x20 cm A.2.1.2.5a 240.00 m
b. Upah pemancangan tiang mini A.2.1.2.3a 240.00 m
c. Penyambungan tiang mini A.2.1.2.10a 36.00 samb
d. Pemotongan kepala tiang mini F.07.a 12.00 titik
2 Pekerjaan Pemasangan Lantai Kerja f’c = 8,3 MPa A.4.1.1.1 0.62 m3
3 Pekerjaaan Pile Cap 80x80x50 cm
a. Pekerjaan Bekisting A.4.1.1.20 19.20 m2
b. Pekerjaan Pembesian
- Besi D16-150 A.4.1.1.17.b 492.41 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 3.84 m3
4 Pekerjaaan Sloof TB.2 uk.20x40 cm
a. Pekerjaan Bekisting A.4.1.1.21 7.20 m2
b. Pekerjaan Pembesian
- Besi 6D13 mm+2D10 mm A.4.1.1.17.b 74.09 kg
- Besi D10-150 mm A.4.1.1.17.b 53.27 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 0.72 m3
5 Pekerjaaan Kolom Pedestal
a. Pekerjaan Bekisting A.4.1.1.22 10.92 m2
b. Pekerjaan Pembesian
- Besi 12D16 mm A.4.1.1.17.b 227.27 kg
- Besi D10-150 mm A.4.1.1.17.b 79.90 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 0.94 m3
6 Pekerjaan Grouting kolom
a. Grouting t= 50 mm A.4.1.2.21 0.15 m3
b. Upah grouting A.4.1.2.22 12.00 titik
III PEKERJAAN KONSTRUKSI BAJA
1 Base Plate kolom t=16 mm A.4.2.1.1.a 127.40 kg
2 Plat Stiffner kolom t=8 mm A.4.2.1.1.a 240.30 kg
3 Anchor Bolt kolom dia.16 mm Taksir-STR5 72.00 bh
4 Kolom WF250.125.6.9 A.4.2.1.1.a 2,450.88 kg
5 Main Rafter WF200.100.5,5.8 A.4.2.1.1.a 3,450.60 kg
6 Secondary Rafter UNP 150.75.6,5.10 A.4.2.1.1.a 3,589.80 kg
7 Diagonal rafter L50.50.5 A.4.2.1.1.a 422.24 kg
8 Plat Sambungan t=8 mm A.4.2.1.1.a 281.17 kg
9 Pengecatan Besi dengan cat menie A.2.4.1.9 425.06 m2
10 Pengecatan Besi dengan cat besi A.2.4.1.16 425.06 m2
TOTAL PEKERJAAN PIPE RACK DARI R.POMPA KE PINGGIR JALAN REL-5

B.3 PIPE RACK CROSSING JALAN REL


I PEKERJAAN TANAH
1 Pekerjaan Galian Tanah A.2.3.1.1. 2.40 m3
2 Pekerjaan Urugan Kembali Bekas Galian A. 2.3.1.9. 0.72 m3
3 Pekerjaan Urugan Pasir A. 2.3.1.11. 0.41 m3
II PEKERJAAN PONDASI & BETON
1 Pekerjaan pondasi tiang mini 20x20 cm
a. Pengadaan pondasi tiang mini 20x20 cm A.2.1.2.5a 160.00 m
b. Upah pemancangan tiang mini A.2.1.2.3a 160.00 m
c. Penyambungan tiang mini A.2.1.2.10a 24.00 samb
d. Pemotongan kepala tiang mini F.07.a 8.00 titik
2 Pekerjaan Pemasangan Lantai Kerja f’c = 8,3 MPa A.4.1.1.1 0.41 m3
3 Pekerjaaan Pile Cap 80x80x50 cm
a. Pekerjaan Bekisting A.4.1.1.20 12.80 m2
b. Pekerjaan Pembesian
- Besi D16-150 A.4.1.1.17.b 328.27 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 2.56 m3
4 Pekerjaaan Sloof TB.2 uk.20x40 cm
a. Pekerjaan Bekisting A.4.1.1.21 4.80 m2
b. Pekerjaan Pembesian
- Besi 6D13 mm+2D10 mm A.4.1.1.17.b 49.40 kg
- Besi D10-150 mm A.4.1.1.17.b 35.51 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 0.48 m3
5 Pekerjaaan Kolom Pedestal
a. Pekerjaan Bekisting A.4.1.1.22 7.28 m2
b. Pekerjaan Pembesian
- Besi 12D16 mm A.4.1.1.17.b 18.94 kg
- Besi D10-150 mm A.4.1.1.17.b 6.66 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 0.62 m3
6 Pekerjaan Grouting kolom
a. Grouting t= 50 mm A.4.1.2.21 0.10 m3
b. Upah grouting A.4.1.2.22 8.00 titik
III PEKERJAAN KONSTRUKSI BAJA
1 Base Plate kolom t=16 mm A.4.2.1.1.a 84.93 kg
2 Plat Stiffner kolom t=8 mm A.4.2.1.1.a 160.20 kg
3 Anchor Bolt kolom dia.16 mm Taksir-STR5 48.00 bh
4 Kolom WF300.150.6.9,5 A.4.2.1.1.a 2,025.84 kg
5 Main Rafter WF200.100.5,5.8 A.4.2.1.1.a 2,556.00 kg
6 Secondary Rafter UNP 150.75.6,5.10 A.4.2.1.1.a 2,734.20 kg

Page 4 of 75
HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SAT
SATUAN HARGA

7 Diagonal rafter L50.50.5 A.4.2.1.1.a 316.68 kg


8 Plat Sambungan t=8 mm A.4.2.1.1.a 216.28 kg
9 Pengecatan Besi dengan cat menie A.2.4.1.9 309.14 m2
10 Pengecatan Besi dengan cat besi A.2.4.1.16 309.14 m2
TOTAL PEKERJAAN PIPE RACK CROSSING JALAN REL

B.4 BANGUNAN R.POMPA, R.PANEL & R.OPERATOR


I PEKERJAAN TANAH
1 Pekerjaan Galian Tanah A.2.3.1.1. 20.12 m3
2 Pekerjaan Urugan Kembali Bekas Galian A. 2.3.1.9. 6.04 m3
3 Pekerjaan Urugan Tanah dibawah lantai t = 1 m A. 1.2.2.8. 130.00 m3
4 Pemadatan Urugan Tanah setiap 20 cm A. 2.3.1.10. 130.00 m3
5 Pekerjaan Urugan Pasir A. 2.3.1.11. 1.80 m3
II PEKERJAAN PONDASI & BETON
1 Pekerjaan pondasi tiang mini 20x20 cm
a. Pengadaan pondasi tiang mini 20x20 cm A.2.1.2.5a 300.00 m
b. Upah pemancangan tiang mini A.2.1.2.3a 300.00 m
c. Penyambungan tiang mini A.2.1.2.10a 30.00 samb
d. Pemotongan kepala tiang mini F.07.a 15.00 titik
2 Pekerjaan Pemasangan Lantai Kerja f’c = 8,3 MPa A.4.1.1.1 1.80 m3
3 Pekerjaaan Pile Cap P1 80x80x50 cm
a. Pekerjaan Bekisting A.4.1.1.20 38.40 m2
b. Pekerjaan Pembesian
- Besi D16-150 A.4.1.1.17.b 492.41 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 3.84 m3
4 Pekerjaaan Pile Cap P2 60x60x50 cm
a. Pekerjaan Bekisting A.4.1.1.20 7.20 m2
b. Pekerjaan Pembesian
- Besi D16-150 A.4.1.1.17.b 90.91 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 0.54 m3
5 Pekerjaaan Sloof TB.1 uk.25x50 cm
a. Pekerjaan Bekisting A.4.1.1.21 87.50 m2
b. Pekerjaan Pembesian
- Besi 6D16 mm+2D10 mm A.4.1.1.17.b 1,030.11 kg
- Besi D10-150 mm A.4.1.1.17.b 647.33 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 10.94 m3
6 Pekerjaaan Kolom 30X30 cm
a. Pekerjaan Bekisting A.4.1.1.22 79.20 m2
b. Pekerjaan Pembesian
- Besi 8D16 mm A.4.1.1.17.b 848.46 kg
- Besi D10-150 mm A.4.1.1.17.b 399.49 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 5.94 m3
7 Pekerjaaan Balok B1 uk.25x50 cm
a. Pekerjaan Bekisting A.4.1.1.21 122.50 m2
b. Pekerjaan Pembesian
- Besi 6D16 mm+2D10 mm A.4.1.1.17.b 1,153.72 kg
- Besi D10-150 mm A.4.1.1.17.b 725.00 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 12.25 m3
8 Pekerjaaan Balok B2 uk.20x40 cm
a. Pekerjaan Bekisting A.4.1.1.21 22.20 m2
b. Pekerjaan Pembesian
- Besi 6D16 mm A.4.1.1.17.b 152.66 kg
- Besi D10-150 mm A.4.1.1.17.b 131.39 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 1.78 m3
9 Pekerjaaan Balok B3 uk.12x40 cm
a. Pekerjaan Bekisting A.4.1.1.21 64.40 m2
b. Pekerjaan Pembesian
- Besi 6D13 mm A.4.1.1.17.b 240.68 kg
- Besi D10-150 mm A.4.1.1.17.b 115.08 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 3.36 m3
10 Pekerjaaan Pelat lantai t=15 cm elev.+1.000
a. Pekerjaan Bekisting A.4.1.1.24 15.50 m2
b. Pekerjaan Pembesian
- Besi M10-150 A.4.1.1.17.b 80.02 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 14.10 m3
11 Pekerjaaan Pelat pondasi R.Pompa t=15 cm elev.+1.300
a. Pekerjaan Bekisting A.4.1.1.24 7.50 m2
b. Pekerjaan Pembesian
- Besi D13-150 A.4.1.1.17.b 620.32 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 5.40 m3
12 Pekerjaaan Pelat Dak Atap t=12 cm elev.+5.000
a. Pekerjaan Bekisting A.4.1.1.24 166.50 m2
b. Pekerjaan Pembesian
- Besi M10-150 A.4.1.1.17.b 265.61 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 18.72 m3
13 Cor Pelat Lantai Tangga t=10 cm
a. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 2.06 m3
III PEKERJAAN DINDING & PLESTERAN
1 Pasangan Dinding 1/2 Bata, camp.1:2 A.2.3.1.10 73.00 m2
2 Pasangan Dinding 1/2 Bata, camp.1:4 A.2.3.1.13 277.09 m2
3 Plesteran dinding, camp.1:2 A.2.3.2.13 146.00 m2
4 Plesteran dinding, camp. 1:4 A.2.3.2.17 554.19 m2
5 Pekerjaan Acian Dinding A.2.3.2.1 700.19 m2
IV PEKERJAAN PENUTUP LANTAI & DINDING

Page 5 of 75
HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SAT
SATUAN HARGA

1 Keramik Lantai 60x60 cm (polished) A.2.3.3.35 21.75 m2


2 Keramik Tangga 30x30 cm (unpolished) A.2.3.3.23 30.25 m2
3 Keramik Lantai KM/WC 20x25 cm (unpolished) A.2.3.3.22 2.25 m2
4 Keramik Dinding KM/WC 25x40 cm (polished) A.2.3.3.8 16.80 m2
5 Pekerjaan Acian Lantai A.2.3.3.2 90.00 m2
6 Pekerjaan Waterproofing dak atap & KM/WC A.2.4.2.4a 198.25 m2
V PEKERJAAN PINTU & JENDELA
1 Pekerjaan Pintu Besi P1 (2 Unit) A.2.3.6.70a 5.04 m2
2 Pekerjaan Pintu Besi P2 (1 Unit) A.2.3.6.70a 1.68 m2
3 Pekerjaan Pintu Aluminium P3 (1 Unit)
a. Pemasangan Kusen Aluminium A.2.3.6.48 4.90 m'
b. Pemasangan Pintu Aluminium Strip A.2.3.6.49 1.20 m2
4 Pekerjaan Jendela Aluminium J1+kaca 6 mm (2 unit)
a. Pemasangan Kusen Aluminium A.2.3.6.48 6.60 m'
b. Pemasangan Frame jendela aluminium A.2.3.6.48 19.20 m'
c. Pemasangan Kaca t=6 mm A.2.3.6.32 3.64 m'
5 Pekerjaan Jendela Aluminium J2+kaca 6 mm (3 unit)
a. Pemasangan Kusen Aluminium A.2.3.6.48 7.28 m'
b. Pemasangan Frame jendela aluminium A.2.3.6.48 14.55 m'
c. Pemasangan Kaca t=6 mm A.2.3.6.32 2.73 m'
VI PEKERJAAN PENGECATAN
1 Pekerjaan Pengecatan dinding interior A.2.4.1.17 683.19 m2
2 Pekerjaan Pengecatan Pintu P1 & P2 A.2.4.1.16 6.72 m2
TOTAL PEKERJAAN BANGUNAN R.POMPA, R.PANEL & R.OPERATOR

B.5 SUPPORT PIPA DALAM SALURAN EKSISTING


I PEKERJAAN PEMBONGKARAN BETON
1 Pekerjaan Pembongkaran Tutup Saluran Hitung 30.80 m3
II PEKERJAAN BETON & BAJA
1 Pekerjaan Pembuatan Tutup Saluran
a. Pekerjaan Bekisting A.4.1.1.24 110.00 m2
b. Pekerjaan Pembesian
- Besi D13-150 A.4.1.1.17.b 5,082.00 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 46.20 m3
2 Pekerjaan Baja Support Pipa UNP150 A.4.2.1.1.a 483.60 kg
3 Pekerjaan Dinabolt M10x60 (stainless) Hitung 148.00 bh
TOTAL PEKERJAAN SUPPORT PIPA DALAM SALURAN EKSISTING

B.6 PEKERJAAN BOX CULVERT 1.5 X 1.5 M


I PEKERJAAN PEMBONGKARAN & PEMASANGAN SUPPORT
1 Pekerjaan Pembongkaran Ballas Rel 5 sep. 3 meter Hitung 1.000 Ls
2 Pemasangan Support untuk pembasangan box culvert 1.5x1.5 m Hitung 1.00 Ls
II PEKERJAAN TANAH
1 Pekerjaan Galian Tanah A.2.3.1.1. 23.18 m3
III PEKERJAAN PONDASI & BETON
1 Pekerjaan pondasi tiang mini 20x20 cm
a. Pengadaan pondasi tiang mini 20x20 cm A.2.1.2.5a 80.00 m
b. Upah pemancangan tiang mini A.2.1.2.3a 80.00 m
c. Penyambungan tiang mini A.2.1.2.10a 12.00 samb
d. Pemotongan kepala tiang mini F.07.a 4.00 titik
2 Pekerjaan Pemasangan Lantai Kerja f’c = 8,3 MPa A.4.1.1.1 0.97 m3
3 Pekerjaaan Pile Cap 80x80x50 cm
a. Pekerjaan Bekisting A.4.1.1.25 279.42 m2
b. Pekerjaan Pembesian A.4.1.1.17.b 2,220.89 kg
c. Pekerjaan Beton Cor f’c = 21.7 MPa A.4.1.1.8 16.84 m3
IV PEKERJAAN BAJA
1 Pekerjaan Baja Support Pipa UNP150 A.4.2.1.1.a 83.70 kg
2 Base Plate 4 mm A.4.2.1.1.a 3.39 kg
3 Pekerjaan Dinabolt M10x60 (stainless) Hitung 6.00 bh
4 Pengecatan Besi dengan cat menie A.2.4.1.9 2.12 m2
5 Pengecatan Besi dengan cat besi A.2.4.1.16 2.12 m2
TOTAL PEKERJAAN BOX CULVERT 1.5 x 1.5 M

Page 6 of 75
BILL of QUANTITY (BoQ)
PEKERJAAN PIPING & MEKANIKAL

NAMA PROYEK : PEMBANGUNAN TERMINAL CURAH CAIR AREA KERETA API DI PELABUHAN KUALA TANJUNG
INSTANSI : PT.PRIMA MULTI TERMINAL
LOKASI : KUALA TANJUNG
KABUPATEN/PROVINSI : BATU BARA/SUMATERA UTARA
KONTRAKTOR : PT/CV…....................................................................

HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOL. SAT.
SATUAN HARGA

C.1. PEKERJAAN PIPING & MEKANIKAL LINE 01


C.1.1 PEKERJAAN PIPA SUCTION
A Instalasi Pipa Suction
Pengadaan dan Pemasangan Pipa Carbon Steel SCH-40 ASTM-A53 Grade B (ERW) lengkap dengan support
dan peralatan bantu sesuai gambar & spesifikasi
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 4 Inch PP-02 4.00 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 8 Inch PP-03 92.00 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 10 Inch PP-04 10.00 m

B Instalasi Fitting Pipa Suction


Pengadaan dan Pemasangan Fitting Pipa lengkap dengan support dan peralatan bantu sesuai gambar &
spesifikasi
- Elbow CS L.R. 90⁰ ASTM A234 8 Inch PP-17 5.00 bh
- Elbow CS L.R. 45⁰ ASTM A234 8 Inch PP-18 8.00 bh
- Barred Equal Tee ASTM A234 8 x 8 x 8 Inch PP-19 1.00 bh
- Reducer Tee ASTM A234 8 x 8 x 4 Inch PP-20 10.00 bh

C Instalasi Aksesoris Pipa Suction


Pengadaan dan Pemasangan Aksesoris Pipa lengkap dengan support dan peralatan bantu sesuai gambar &
spesifikasi
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 4 Inch PP-05 20.00 bh
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 8 Inch PP-06 11.00 bh
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-07 10.00 bh
- Blind Flange ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-08 2.00 bh
- Gate Valve Class 150 Flange Connection 10 Inch PP-09 4.00 bh
- Gate Valve Class 150 Flange Connection 8 Inch PP-10 2.00 bh
- Gate Valve Class 150 Flange Connection 4 Inch PP-11 10.00 bh
- Ball Valve Class 150 Flange Connection 8 Inch PP-12 2.00 bh
- Stainless steel Flexible Joint 8 Inch PP-13 1.00 bh
- Y Strainer 8 Inch PP-14 1.00 bh
- Flexible Hose Camlock Coupling 4 Inch x 3 meter PP-15 10.00 set
- U-Bolt 10 Inch PP-21 9.00 set
- U-Bolt 8 Inch PP-22 26.00 set

Welding Joint Pipa & Fitting


- Welding Joint Pipa dan Fitting 10'' 10 titik PPG-01 100.00 D-Inch
- Welding Joint Pipa dan Fitting 8" 45 titik PPG-01 360.00 D-Inch
- Welding Joint Pipa dan Fitting 4" 30 titik PPG-01 120.00 D-Inch

Cat Primer dan Finishing


- Pipa SCH-40 ASTM-A53 Grade B (ERW) 4 Inch PC-01 4.00 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 8 Inch PC-01 92.00 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 10 Inch PC-01 10.00 m

D Instalasi Pig Launcher/Receiver


Include accessories : PP-16 2.00 set
- Barrel Ø10"
- Reducer Ø10" to Ø8"
- Quick Closure Ø10" (ANSI 300)
- Pig Signal
- Vent valve Ø1"
- Drain valve Ø1"
- Ball valve Ø2 1/2" (kicker valve)
- Ball valve Ø2 1/2" (throtle valve)
- Ball valve Ø2 1/2" (inlet)
TOTAL PEKERJAAN PIPA SUCTION Rp -

C.1.2 PEKERJAAN PIPA DISCHARGE


A Instalasi Pipa Discharge
Pengadaan dan Pemasangan Pipa Carbon Steel SCH-40 ASTM-A53 Grade B (ERW) lengkap dengan support
dan peralatan bantu sesuai gambar & spesifikasi
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 6 Inch PP-02a 1.00 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 8 Inch PP-03 200.00 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 10 Inch PP-04 11.00 m

B Instalasi Fitting Pipa Discharge


Pengadaan dan Pemasangan Fitting Pipa lengkap dengan support dan peralatan bantu sesuai gambar &
spesifikasi
- Elbow CS L.R. 90⁰ ASTM A234 8 Inch PP-17 3.00 bh
- Elbow CS L.R. 90⁰ ASTM A234 6 Inch PP-17a 1.00 bh
- Elbow CS L.R. 45⁰ ASTM A234 8 Inch PP-18 16.00 bh
- Barred Equal Tee ASTM A234 8 x 8 x 8 Inch PP-19 7.00 bh
- Reducer Tee ASTM A234 10 x 10 x 8 Inch PP-20a 2.00 bh
- Concentic Tee ASTM A234 8 x 6 Inch PP-20b 1.00 bh

Page 7 of 75
HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOL. SAT.
SATUAN HARGA
C Instalasi Aksesoris Pipa Discharge
Pengadaan dan Pemasangan Aksesoris Pipa lengkap dengan support dan peralatan bantu sesuai gambar &
spesifikasi
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 6 Inch PP-05a 1.00 bh
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 8 Inch PP-06 19.00 bh
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-07 10.00 bh
- Blind Flange ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-08 2.00 bh
- Gate Valve Class 150 Flange Connection 10 Inch PP-09 4.00 bh
- Gate Valve Class 150 Flange Connection 8 Inch PP-10 6.00 bh
- Ball Valve Class 150 Flange Connection 8 Inch PP-12 1.00 bh
- Stainless steel Flexible Joint 8 Inch PP-13 1.00 bh
- Check Valve Class 150 Flange Connection 8 Inch PP-14a 1.00 bh
- Flow Meter Transmitter Ø200 mm 8 Inch PP-15a 2.00 bh
- Pressure Gauge Ø200 mm 8 Inch PP-15b 1.00 bh
- U-Bolt 10 Inch PP-21 9.00 set
- U-Bolt 8 Inch PP-22 33.00 set

Welding Joint Pipa & Fitting


- Welding Joint Pipa dan Fitting 10'' 6 titik PPG-01 60.00 D-Inch
- Welding Joint Pipa dan Fitting 8" 100 titik PPG-01 800.00 D-Inch
- Welding Joint Pipa dan Fitting 4" 4 titik PPG-01 24.00 D-Inch

Cat Primer dan Finishing


- Pipa SCH-40 ASTM-A53 Grade B (ERW) 4 Inch PC-01 1.00 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 8 Inch PC-01 200.00 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 10 Inch PC-01 11.00 m

D Instalasi Pig Launcher/Receiver


Include accessories : PP-16 3.00 set
- Barrel Ø10"
- Reducer Ø10" to Ø8"
- Quick Closure Ø10" (ANSI 300)
- Pig Signal
- Vent valve Ø1"
- Drain valve Ø1"
- Ball valve Ø2 1/2" (kicker valve)
- Ball valve Ø2 1/2" (throtle valve)
- Ball valve Ø2 1/2" (inlet)
TOTAL PEKERJAAN DISCHARGE Rp -

C.1.3 PEKERJAAN MEKANIKAL


A Instalasi Pompa Unloading Line 01 PM-01 1.00 unit
Pengadaan dan pemasangan Pompa Unloading lengkap dengan Aksesoris
- Type pompa : Double Suction Centrifugal Pump
- Kapasitas : 340 m3/jam
- Total Head : 63 meter
- Desain Tekanan : 6,3 bar
- Densitas Zat Cair : 886,2 kg/m3
- Viskositas Zat Cair : 42,66 cSt
- NPSHA : 6 meter
- Putaran : 1500 rpm
- Daya Zat Cair : 51,57 kW
- Kecepatan spesifik : 159,44
- Efisiensi pompa rencana : 70%
- Daya pompa rencana : 75 kW

B Instalasi Rotary Screw Air Compressor


Pengadaan dan Pemasangan Rotary Screw Air Compressor lengkap dengan aksesoris dan support bantu
sesuai gambar & spesifikasi
- Pengadaan dan Pemasangan Rotary Screw Air Compressor c/w accessories PM-04 1.00 unit

C Instalasi Exhaust Fan


Pengadaan dan Pemasangan Exhaust Fan lengkap dengan aksesoris dan support bantu sesuai gambar &
spesifikasi
- Pengadaan dan Pemasangan Wall Exhaust Fan CKE ESND10/1YL 10 inch- Pump & Panel House EF-06 4.00 unit

D Item Pemadam Kebakaran


Pengadaan dan Pemasangan Item Pemadam Kebakaran sesuai gambar dan spesifikasi
- Pengadaan dan Pemasangan Fire Extinguisher Chemical Dry Powder 3 KG- Pump & Panel House PM-03 4.00 bh
TOTAL PEKERJAN MEKANIKAL Rp -

C.1.4 TESTING & COMMISSIONING 1.00 Ls Rp -


TOTAL PEKERJAAN TESTING & COMISSIONING Rp -
C.2 PEKERJAAN PIPING & MEKANIKAL LINE 02
C.2.1 PEKERJAAN PIPA SUCTION
A Instalasi Pipa Suction
Pengadaan dan Pemasangan Pipa Carbon Steel SCH-40 ASTM-A53 Grade B (ERW) lengkap dengan support
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 4 Inch PP-02 4 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 8 Inch PP-03 92 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 10 Inch PP-04 10 m

B Instalasi Fitting Pipa Suction


Pengadaan dan Pemasangan Fitting Pipa lengkap dengan support dan peralatan bantu sesuai gambar &
- Elbow CS L.R. 90⁰ ASTM A234 8 Inch PP-17 5 bh
- Elbow CS L.R. 45⁰ ASTM A234 8 Inch PP-18 8 bh
- Barred Equal Tee ASTM A234 8 x 8 x 8 Inch PP-19 1 bh
- Reducer Tee ASTM A234 8 x 8 x 4 Inch PP-20 10 bh

Page 8 of 75
HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOL. SAT.
SATUAN HARGA
C Instalasi Aksesoris Pipa Suction
Pengadaan dan Pemasangan Aksesoris Pipa lengkap dengan support dan peralatan bantu sesuai gambar &
spesifikasi
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 4 Inch PP-05 20 bh
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 8 Inch PP-06 11 bh
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-07 10 bh
- Blind Flange ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-08 2 bh
- Gate Valve Class 150 Flange Connection 10 Inch PP-09 4 bh
- Gate Valve Class 150 Flange Connection 8 Inch PP-10 2 bh
- Gate Valve Class 150 Flange Connection 4 Inch PP-11 10 bh
- Ball Valve Class 150 Flange Connection 8 Inch PP-12 2 bh
- Stainless steel Flexible Joint 8 Inch PP-13 1 bh
- Y Strainer 8 Inch PP-14 1 bh
- Flexible Hose Camlock Coupling 4 Inch x 3 meter PP-15 10 set
- U-Bolt 10 Inch PP-21 9 set
- U-Bolt 8 Inch PP-22 26 set

Welding Joint Pipa & Fitting


- Welding Joint Pipa dan Fitting 10'' 10 titik PPG-01 100 D-Inch
- Welding Joint Pipa dan Fitting 8" 45 titik PPG-01 360 D-Inch
- Welding Joint Pipa dan Fitting 4" 30 titik PPG-01 120 D-Inch

Cat Primer dan Finishing


- Pipa SCH-40 ASTM-A53 Grade B (ERW) 4 Inch PC-01 4 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 8 Inch PC-01 92 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 10 Inch PC-01 10 m

D Instalasi Pig Launcher/Receiver


Include accessories : PP-16 2 set
- Barrel Ø10"
- Reducer Ø10" to Ø8"
- Quick Closure Ø10" (ANSI 300)
- Pig Signal
- Vent valve Ø1"
- Drain valve Ø1"
- Ball valve Ø2 1/2" (kicker valve)
- Ball valve Ø2 1/2" (throtle valve)
- Ball valve Ø2 1/2" (inlet)
TOTAL PEKERJAAN PIPA SUCTION Rp -

C.2.2 PEKERJAAN PIPA DISCHARGE


A Instalasi Pipa Discharge
Pengadaan dan Pemasangan Pipa Carbon Steel SCH-40 ASTM-A53 Grade B (ERW) lengkap dengan support
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 6 Inch PP-02a 1 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 8 Inch PP-03 200 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 10 Inch PP-04 11 m

B Instalasi Fitting Pipa Discharge


Pengadaan dan Pemasangan Fitting Pipa lengkap dengan support dan peralatan bantu sesuai gambar &
- Elbow CS L.R. 90⁰ ASTM A234 8 Inch PP-17 3 bh
- Elbow CS L.R. 90⁰ ASTM A234 6 Inch PP-17a 1 bh
- Elbow CS L.R. 45⁰ ASTM A234 8 Inch PP-18 16 bh
- Barred Equal Tee ASTM A234 8 x 8 x 8 Inch PP-19 7 bh
- Reducer Tee ASTM A234 10 x 10 x 8 Inch PP-20a 2 bh
- Concentic Tee ASTM A234 8 x 6 Inch PP-20b 1 bh

C Instalasi Aksesoris Pipa Discharge


Pengadaan dan Pemasangan Aksesoris Pipa lengkap dengan support dan peralatan bantu sesuai gambar &
spesifikasi
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 6 Inch PP-05a 1 bh
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 8 Inch PP-06 19 bh
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-07 10 bh
- Blind Flange ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-08 2 bh
- Gate Valve Class 150 Flange Connection 10 Inch PP-09 4 bh
- Gate Valve Class 150 Flange Connection 8 Inch PP-10 6 bh
- Ball Valve Class 150 Flange Connection 8 Inch PP-12 1 bh
- Stainless steel Flexible Joint 8 Inch PP-13 1 bh
- Check Valve Class 150 Flange Connection 8 Inch PP-14a 1 bh
- Flow Meter Transmitter Ø200 mm 8 Inch PP-15a 2 bh
- Pressure Gauge Ø200 mm 8 Inch PP-15b 1 bh
- U-Bolt 10 Inch PP-21 9 set
- U-Bolt 8 Inch PP-22 33 set

Welding Joint Pipa & Fitting


- Welding Joint Pipa dan Fitting 10'' 6 titik PPG-01 60 D-Inch
- Welding Joint Pipa dan Fitting 8" 100 titik PPG-01 800 D-Inch
- Welding Joint Pipa dan Fitting 4" 4 titik PPG-01 24 D-Inch

Cat Primer dan Finishing


- Pipa SCH-40 ASTM-A53 Grade B (ERW) 4 Inch PC-01 1 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 8 Inch PC-01 200 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 10 Inch PC-01 11 m

Page 9 of 75
HARGA JUMLAH
NO URAIAN PEKERJAAN ANALISA VOL. SAT.
SATUAN HARGA
D Instalasi Pig Launcher/Receiver
Include accessories : PP-16 3 set
- Barrel Ø10"
- Reducer Ø10" to Ø8"
- Quick Closure Ø10" (ANSI 300)
- Pig Signal
- Vent valve Ø1"
- Drain valve Ø1"
- Ball valve Ø2 1/2" (kicker valve)
- Ball valve Ø2 1/2" (throtle valve)
- Ball valve Ø2 1/2" (inlet)

E Instalasi Pipa Header Percabangan


Pengadaan dan Pemasangan Pipa Carbon Steel SCH-40 ASTM-A53 Grade B (ERW) lengkap dengan support
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 8 Inch PP-03 6 m
- Pipa SCH-40 ASTM-A53 Grade B (ERW) 10 Inch PP-04 2.5 m

F Instalasi Aksesoris Pipa Header Percabangan


Pengadaan dan Pemasangan Pipa Header Percabangan lengkap dengan support dan peralatan bantu sesuai
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 8 Inch PP-06 12 bh
- Flange Slip On ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-07 2 bh
- Blind Flange ASTM A106 ANSI B16.5 c/w Gasket 10 Inch PP-08 2 bh
- Gate Valve Class 150 Flange Connection 8 Inch PP-10 6 bh

TOTAL PEKERJAAN DISCHARGE Rp -

C.2.3 PEKERJAAN MEKANIKAL


A Instalasi Pompa Unloading Line 02 PM-01 1 unit
Pengadaan dan pemasangan Pompa Unloading lengkap dengan Aksesoris
- Type pompa : Double Suction Centrifugal Pump
- Kapasitas : 340 m3/jam
- Total Head : 63 meter
- Desain Tekanan : 6,3 bar
- Densitas Zat Cair : 886,2 kg/m3
- Viskositas Zat Cair : 42,66 cSt
- NPSHA : 6 meter
- Putaran : 1500 rpm
- Daya Zat Cair : 51,57 kW
- Kecepatan spesifik : 159,44
- Efisiensi pompa rencana : 70%
- Daya pompa rencana : 75 kW
TOTAL PEKERJAN MEKANIKAL Rp -

C.2.4 TESTING & COMMISSIONING 1.00 Ls

TOTAL PEKERJAAN TESTING & COMISSIONING Rp -

Page 10 of 75
BILL of QUANTITY (BoQ)
PEKERJAAN ELEKTRIKAL

NAMA PROYEK : PEMBANGUNAN TERMINAL CURAH CAIR AREA KERETA API DI PELABUHAN KUALA TANJUNG
INSTANSI : PT.PRIMA MULTI TERMINAL
LOKASI : KUALA TANJUNG
KABUPATEN/PROVINSI : BATU BARA/SUMATERA UTARA
KONTRAKTOR : PT/CV…............................................

NO. URAIAN PEKERJAAN ANALISA SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

D PEKERJAAN ELEKTRIKAL
PEKERJAAN LISTRIK ARUS KUAT (LAK)
D.1 PEKERJAAN INSTALASI KABEL DAYA LISTRIK TEGANGAN RENDAH
1 Dari Panel LVMDP POWER HOUSE 2 ke Panel SDP
Pekerjaan Kabel NYFGBY 1 X 4C X 240mm² NYFGBY 4.240 m 133
2 Dari Panel SDP Ke Panel Penerangan
Pekerjaan Kabel NYY 4 x 6mm² + Kabel NYA 1 x 6mm² NYY 4.6 m 10
3 Dari Panel SDP Ke Motor Pompa 75 kW
Pekerjaan Kabel N2XY 4 x 95mm² N2XY.4.95 m 39
4 Inslatasi Kontrol Motor Pompa 75 kW Dari Panel SDP Ke Pompa
Pekerjaan Kabel NYMHY 2 x 1.5mm² TS.NYH m 39
5 Dari Panel SDP Ke PIT
Pekerjaan Kabel N2XY 4 x 2.5mm² N2XY.4.2.5 m 46
6 Inslatasi Kontrol PIT Dari Panel SDP Ke Pompa
Pekerjaan Kabel NYMHY 2 x 1.5mm² TS.NYH m 46
7 Dari Panel SDP Ke Cpmpressor
Pekerjaan Kabel N2XY 4 x 25mm² N2XY.4.25 m 27

D.2 PEKERJAAN PANEL LISTRIK


1 SDP. GEDUNG POMPA CURAH CAIR PP.SDP unit 1
2 PP-LP-PENERANGAN PP.LP.P unit 1

JUMLAH PEKERJAAN PANEL LISTRIK TEGANGAN RENDAH Rp -

D.3 PEKERJAAN INSTALASI PENERANGAN ,SAKLAR DAN STOPKONTAK


1 Lampu Highbay LED 100 Watt G4 IP65 P.IN.SO bh 27
2 Lampu RM TL LED 2x18 watt (TCW 097) P.IN.TL3 bh 15
3 Lampu RM TL LED 1x18 watt (TCW 097) P.IN.TL1 bh 3
4 Lampu Downlight LED 7 watt P.IN.DL1 bh 1
5 Pekerjaan Saklar Single P.IN.SS bh 3
6 Pekerjaan Saklar Double P.IN.SD bh 2
7 Industrial Switch P.IN.IS bh 3
8 Stopkontak Dinding 200 Watt P.IN.SDD1 bh 7
9 Instalasi Penerangan, NYM 3x1,5 mm2, c/w Conduit Diameter. 20 mm P.IN.PK meter 631
10 Instalasi Stopkontak Dinding 1 phasa, NYY 3x2.5 mm2, c/w Conduit Diameter. 20 mm P.IN.SW meter 41

JUMLAH PEKERJAAN INSTALASI PENERANGAN ,SAKLAR DAN STOPKONTAK Rp -

D.4 PEKERJAAN KABEL TRAY KABEL


1 Pekerjaan Cable ledder 300 x 100 mm P.CL 300 meter 123
2 Pekerjaan kabel tray 100 x 100mm P.TY 100 meter 5
3 Pekerjaan Tee tray 100 x 100mm P.TY T 100 bh 1
4 Pekerjaan Elbow tray 100 x 100mm P.TY L 100 bh 1
5 Pekerjaan kabel tray 200 x 100mm P.TY 200 meter 17
6 Pekerjaan Tee tray 200 x 100mm P.TY T 200 bh 2
7 Pekerjaan Elbow tray 200 x 100mm P.TY L 200 bh 1
8 Pekerjaan kabel tray 300 x 100mm P.TY 300 meter 14
9 Pekerjaan Tee tray 300 x 100mm P.TY T 300 bh 1
10 Pekerjaan elbow tray 300 x 100mm P.TY L 300 bh 4

JUMLAH PEKERJAAN KABEL TRAY Rp -

D.5 PEKERJAAN SISTEM PENAGKAL PETIR


1 Air Terminal 700 mm P AT .1 bh 26
2 Cable BC 50 mm P PG .35 bh 327
3 Klem L Kabel BC P PG .KL bh 327
4 Bak Control C/W Terminal Grounding P PG .4 bh 8
5 Earthing Rod 5/8" P PG .1 bh 8

JUMLAH PEKERJAAN SISTEM PENANGKAL PETIR Rp -

D.6 PEKERJAAN SISTEM PROTEKSI POMPA


1 Industrial Preasure Aquipment P.SW.1 set 2
2 Pekerjaan Instalasi Kabel NYM 3 x 2.5mm² P.IN.PK meter 39

JUMLAH PEKERJAAN SISTEM PROTEKSI POMPA Rp -

D.7 PEKERJAAN TESTING DAN COMMISSIONING


1 Pekerjaan Pekerjaan Testing & Commissioning Pekerjaan Listrik Arus Kuat PTC.LAK ls 1

JUMLAH PEKERJAAN TESTING DAN COMMISSIONING Rp -

Page 11 of 75