EPC Tuban Jetty Upgrade and its Ancillary

Production & Transportation Facilities


Project
(EPC Tuban)

TITLE OF DOCUMENT:

METODE KERJA
untuk
STRUKTUR BETON SLAB CLINKER SILO

DOCUMENT NO.:
TPJC-TQ1-WM-C6-491-002

0 3 Peb 23 IFC

PREPARED REVIEWED APPROVED


REV. ISSUED DATE DESCRIPTION
CONTRACTOR
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 2 of 25

REVISION HISTORY

Revision Date Description of Changes

0 3 Peb 23 Issued for Construction


EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 3 of 25

DAFTAR ISI

1. UMUM 4
1.1 BATASAN PEKERJAAN .............................................................................................................. 4
1.2 DEFINISI DAN ISTILAH ............................................................................................................... 4
1.3 LOKASI DAN RUTE KE LOKASI PEKERJAAN ............................................................................ 5
1.4 REFERENSI ................................................................................................................................ 5
1.5 LINGKUP PEKERJAAN ............................................................................................................... 6
1.6 JADWAL PEKERJAAN................................................................................................................. 6
1.7 FLOW CHART / ALUR KERJA ..................................................................................................... 7

2. PERSIAPAN PEKERJAAN 8
2.1 SAFETY CONCERN .................................................................................................................... 8
2.2 PERSIAPAN SECARA UMUM ..................................................................................................... 8

3. BEKISTING SLAB TUNNEL 9


3.1 DENAH & POTONGAN ................................................................................................................ 9
3.2 MODEL SHORING & BEKISTING ...............................................................................................11
3.3 ANALISA BEKISTING .................................................................................................................12
3.4 SUMBER DAYA ..........................................................................................................................15
3.5 PELAKSANAAN PEKERJAAN ....................................................................................................16

4. PEMBESIAN TUNNEL 17
4.1 GAMBAR TUNNEL .....................................................................................................................17
4.2 SUMBER DAYA ..........................................................................................................................17
4.3 PELAKSANAAN PEKERJAAN ....................................................................................................18

5. PEKERJAAN COR BETON SLAB TUNNEL 20


5.1 LAYOUT & JALUR PENGECORAN ............................................................................................20
5.2 SUMBER DAYA ..........................................................................................................................22
5.3 PELAKSANAAN PENGECORAN BETON DINDING....................................................................23

6. PEKERJAAN BONGKAR BEKISTING SLAB TUNNEL 24


6.1 SUMBER DAYA ..........................................................................................................................24
6.2 SAFETY CONCERN ...................................................................................................................24
6.3 PERSIAPAN SECARA UMUM ....................................................................................................24
6.4 PEMBONGKARAN BEKISTING. .................................................................................................24
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 4 of 25

1. UMUM
1.1 Batasan pekerjaan
Metode kerja ini mencakup persyaratan umum “PEKERJAAN STRUKTUR
BETON SLAB CLINKER SILO”, yaitu : persiapan, bekisting, pembesian, pasang
embedded, pengecoran, perawatan beton untuk Proyek EPC Talavera.

1.2 Definisi dan istilah


1.2.1 Para pihak yang terkait dalam pekerjaan ini
EMPLOYER : SBI - PT Solusi Bangun Indonesia, Tbk. (SEMEN INDONESIA
GROUP)

ENJINIR : PROSYS – PT Prosys Bangun Persada

KONTRAKTOR : HK - PT Hutama Karya (Persero), Tbk.

MATERIAL REBAR : BHIRAWA STEEL

SUBKON-REBAR : ENERA – PT Enera Teknika Utama

PEMASOK BETON : SBB - PT SOLUSI BANGUN BETON / Varia Usaha Beton,


batching Tuban.

1.2.2 Daftar definisi atau istilah dalam dokumen ini


Crane : Alat berat yang digunakan untuk angkat barang.
Embedded : Material yang akan ditanam pada beton, bisa ankur atau plate.
ITP : Inspection and Test Plan.
QA : Quality Assurance
QC : Quality Control
RMC : Ready Mix Concrete / Beton Siap Pakai.
TM : Truck Mixer
Selimut beton : Jarak terluar besi tulangan ke tepi beton.
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 5 of 25

1.3 Lokasi dan Rute ke lokasi Pekerjaan


1.3.1 Lokasi pekerjaan
Lokasi pekerjaan berada area dalam Pabrik SBI, sisi barat Clinker Silo yang lama.

1.4 Referensi
1.4.1 Dokumen Proyek
1. Section V Employer’s Requirements Chapter 6 – Standard design Criteria (StDC) for Civil
Plant, section 3 Construction Material.
2. TPJC-TQ1-DW-C3-491-3S02-003, Clinker Silo Architectural Section.
3. TPJC-TQ1-DW-C6-491-3S02-002, Clinker Silo Concrete Box plan detail & Section.
4. TPJC-TQ1-DW-C6-491-3S02-003, Clinker Silo Slab El+34.700 Plan detail & Section.
5. TPJC-TQ1-DW-C6-491-3S02-016, Clinker Silo Entrance Acces loader.
6. TPJC-HK-QAQC-0005_ITP Civil Work

1.4.2 Dokumen lainya


1. SNI 2847-2013 Persyaratan BETON struktural untuk bangunan gedung
2. SNI 03-3976-1995 Tata cara pengadukan Pengecoran BETON
3. SNI 6880-2016 Spesifikasi Beton Struktural.
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 6 of 25

1.5 Lingkup pekerjaan

1.5.1 Persiapan

1.5.2 Pasang shoring

1.5.3 Bekisting slab

1.5.4 Pembesian

1.5.5 Cor beton slab

1.5.6 Perawatan beton

1.5.7 Bongkar bekisting

1.5.8 Perbaikan beton

1.6 Jadwal pekerjaan

No Pekerjaan
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
1 Slab tunnel 1 & 2 tahap 1 (panjang 10 mtr)
1.1 Pasang shoring
1.2 Pasang bekisting
1.3 Pasang Rebar & Embedded
1.4 Cor slab
1.5 Bongkar bekisting
2 Slab tunnel 1 & 2, tahap 2 ( sisi utara & selatan)
2.1 Pasang shoring
2.2 Pasang bekisting
2.3 Pasang Rebar & Embedded
2.4 Cor slab
2.5 Bongkar bekisting
3 Dinding clinker (slipform, metode tersendiri)
4 Dinding tunnel tahap 2
4.1 Rebahkan rebar
4.2 Berdirikan rebar & pasang rebar
4.3 Pasang platform
4.4 Pasang bekisting
4.5 Cor dinding
4.4 Bongkar bekisting
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 7 of 25

1.7 FLOW CHART / ALUR KERJA

START

Persiapan

Pasang Shoring
& bekisting
PERBAIKAN

INSPEKSI
No
Yes

Pasang Rebar

PERBAIKAN

INSPEKSI
No
Yes

PENGECORAN

Bongkar Bekisting

Perbaikan &
Perawatan beton

FINISH
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 8 of 25

2. PERSIAPAN PEKERJAAN
2.1 Safety concern
2.1.1 Untuk mengurangi resiko kecelakaan lalulintas, tempatkan flagman pada lokasi yang
rawan.
2.1.2 Selalu gunakan pelindung mata / kaca mata agar terlindung dari cipratan pasta beton
2.1.3 Lakukan Tool box Meeting sebelum memulai aktifitas pekerjaan.

2.2 Persiapan secara umum


2.2.1 Pastikan ada ijin kerja dan masih berlaku.
2.2.2 Pastikan area kerja sudah terisolasi / terpasang pagar / barikade.
2.2.3 Saat pekerjaan dimalam hari, pastikan cukup penerangan
2.2.4 Pastikan tim kerja dalam kondisi sehat.
2.2.5 Pastikan peralatan kerja layak digunakan.
2.2.6 Pastikan APD sudah sesuai.
2.2.7 Siapkan APD Tambahan seperti Jas hujan
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 9 of 25

3. BEKISTING SLAB TUNNEL


3.1 Denah & potongan
3.1.1 Denah slab tahap 1

9.00

Wall tunnel

Slab tunnel thp 1


Tangga

Denah slab tunnel clinker silo tahap 1


EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 10 of 25

3.1.2 Denah slab tahap 2

9.00

Wall tunnel_1
Slab tunnel_1
Wall clinker, slipform
Wall tunnel_2

Slab tunnel_2
Platform
Tangga
Denah dinding tunnel clinker silo tahap 2
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 11 of 25

3.2 Model shoring & bekisting


Multiplex 12 mm
20 Cm 25 Cm Steel pipe dia 48x3.2 mm
Tepi Tengah Steel Hollow 80x40x3.2 mm
Tepi Tepi

U-Head

Shoring pipa scaffolding

60 Cm 60 Cm
Base jack
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 12 of 25

3.3 Analisa Bekisting


3.3.1 Analisa multiplex 12 mm.
Tebal beton, t = 0.8 M Bj = 2400 kg/m3 Comb fac
q beton = 0.8 x 2400 = 1920 kg/m2 x 1.4 = 2,688 kg/m2
q alat & pekerja = 150 kg/m2 x 1.6 = 240 kg/m2
q Combinasi => 2,928 kg/m2
=> 0.29 kg/cm2
Jarak antar rusuk
L1 = 20 cm, L2 = 25 cm
Panel multiplek Tebal Panel t = 12 mm ==> 1.2 Cm
Arah pasang = Searah serat
2
Tegangan ijin lentur Fb = 240 Kg/cm Searah serat
Fb = 138 Kg/cm 2 melintang serat
DipakaiFb = 240 Kg/cm 2

Modulus Elastis ( E ) E Multiplek kg/cm2


mm 9 12 15 18 21 24 2
Searah Serat 75,000 70,000 65,000 60,000 55,000 50,000
Melintang Serat 15,000 20,000 25,000 30,000 35,000 40,000

E MultiplekE = 70,000 Kg/cm 2

Momen Inersia ( I ) I = 1/12 x b x t3


I = 1/12 x 100 x 1.728 ==> dipakai b = 100 Cm 14.4 Cm4

Momen Lawan ( Z ) Z = 1/6 x b x t2


Z = 1/6 x 100 x 1.44 ==> dipakai b = 100 Cm 24.0 Cm3
Lendut papan
Check lendut ( d ) area 1 L1 = 20 cm,
4
5xqxL 5. x 29.28 x 20 4
d1= 384 x E x I ==> 384. x 70000. x 14.4
23,424,000
d1= ==> 0.06 cm
387,072,000
Lendut ijin dijin = 1/200 x L ==> 1/200 x 20 ==> 0.10 cm

Lendut ijin > Max. lendut ( d max) papan


0.10 > 0.06 cm Rasio = 0.61 ==> OK

Check lendut ( d ) area 2 L2 = 25 cm


q x L4 29.28 x 25 4
d2= 128 x E x I ==> 128. x 70000. x 14.4
11,437,500
d2= ==> 0.09 cm
129,024,000
Lendut ijin dijin = 1/200 x L ==> 1/200 x 25 ==> 0.13 cm

Lendut ijin > Max. lendut ( d max) papan


0.10 > 0.09 cm Rasio = 0.89 ==> OK
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 13 of 25

3.3.2 Analisa rusuk bawah multiplex.


Tebal beton, t = 0.8 M Bj = 2400 kg/m3 Comb fac
q beton = 0.8 x 2400 = 1920 kg/m2 x 1.4 = 2,688 kg/m2
q alat & pekerja = 150 kg/m2 x 1.6 = 240 kg/m2
q Combinasi => 2,928 kg/m2
0.29 kg/cm2
Jarak antar rusuk = 25.00 cm
Beban rusuk q= 7.32 kg/cm
Jarak antar beam support rusuk
L1 = 120 cm, L2 = 120 cm
Panel multiplek Tebal Panel t= 12 mm ==> 1.2 Cm

Tegangan ijin baja Fb = 2400 Kg/cm 2


Modulus Elastis ( E ) E = 2,100,000 Kg/cm 2
Profil pipa dia 48 H= 48 mm ==> 4.8 cm
B= 48 mm ==> 4.8 cm
t= 3.2 mm ==> 0.3 cm
h= 42 mm ==> 4.2 cm
b = 42 mm ==> 4.2 cm

Momen Inersia ( I ) I = 1/12 x (B x H3 - b x h3)


I = 1/12 x (4.8x 110.592 - 4.16 x 71.991296 ) ==> 19.28 Cm4

Momen Lawan ( Z ) Z = 1/6 x (B x H2 - b x h2)


Z = 1/6 x (4.8x 23.04 - 4.16 x 17.3056 ) ==> 6.4 Cm3
Lendut rusuk
Check lendut ( d ) area 1 L1 = 120 cm,
5 x q x L4 5. x 7.32 x 120 4
d1= 384 x E x I ==> 384. x 2100000. x 19.28
7,589,376,000
d1= ==> 0.49 cm
15,547,244,741
Lendut ijin dijin = 1/200 x L ==> 1/200 x 120 ==> 0.60 cm

Lendut ijin > Max. lendut ( d max) area 1


0.60 > 0.49 cm Rasio = 0.81 ==> OK

Check lendut ( d ) area 2 L2 = 120 cm


4
qxL 7.32 x 120 4
d2= 128 x E x I ==> 128. x 2100000. x 19.28
1,517,875,200
d2= ==> 0.29 cm
5,182,414,914
Lendut ijin dijin = 1/200 x L ==> 1/200 x 120 ==> 0.60 cm

Lendut ijin > Max. lendut ( d max) area 2


0.60 > 0.29 cm Rasio = 0.49 ==> OK
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 14 of 25

3.3.3 Analisa beam bawah rusuk.


Tebal beton, t = 0.8 M Bj = 2400 kg/m3 Comb fac
q beton = 0.8 x 2400 = 1920 kg/m2 x 1.4 = 2,688 kg/m2
q alat & pekerja = 150 kg/m2 x 1.6 = 240 kg/m2
q Combinasi => 2,928 kg/m2
0.29 kg/cm2
Jarak antar beam = 120.00 cm
Beban rusuk q= 35.14 kg/cm
Jarak antar beam support rusuk
L1 = 60 cm, L2 = 60 cm
Panel multiplek Tebal Panel t = 12 mm ==> 1.2 Cm

Tegangan ijin baja Fb = 2400 Kg/cm 2


Modulus Elastis ( E ) E = 2,100,000 Kg/cm 2
Profil hollow H= 80 mm ==> 8.0 cm
B= 40 mm ==> 4.0 cm
t= 3 mm ==> 0.3 cm
h= 74 mm ==> 7.4 cm
b = 34 mm ==> 3.4 cm

Momen Inersia ( I ) I = 1/12 x (B x H3 - b x h3)


I = 1/12 x (4x 512 - 3.4 x 405.224 ) ==> 55.85 Cm4

Momen Lawan ( Z ) Z = 1/6 x (B x H2 - b x h2)


Z = 1/6 x (4x 64 - 3.4 x 54.76 ) ==> 11.6 Cm3
Lendut rusuk
Check lendut ( d ) area 1 L1 = 60 cm,
4
5xqxL 5. x 35.14 x 60 4
d1= 384 x E x I ==> 384. x 2100000. x 55.85
2,276,812,800
d1= ==> 0.05 cm
45,040,020,480
Lendut ijin dijin = 1/200 x L ==> 1/200 x 60 ==> 0.30 cm

Lendut ijin > Max. lendut ( d max) area 1


0.30 > 0.05 cm Rasio = 0.17 ==> OK

Check lendut ( d ) area 2 L2 = 60 cm


q x L4 35.14 x 60 4
d2= 128 x E x I ==> 128. x 2100000. x 55.85
455,362,560
d2= ==> 0.03 cm
15,013,340,160
Lendut ijin dijin = 1/200 x L ==> 1/200 x 60 ==> 0.30 cm

Lendut ijin > Max. lendut ( d max) area 2


0.30 > 0.03 cm Rasio = 0.10 ==> OK
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 15 of 25

3.4 Sumber daya


3.4.1 Tenaga kerja tidak langsung
No Personil Jumlah Satuan Keterangan
1 Superitendent / Supervisor 1 Orang
2 Surveyor dan asst. 2 Orang
3 Mekanik & electrical 1 Orang
4 Safety officer 1 Orang
5 Safety inspector 1 Orang
6 QC 1 Orang
7 Flagman 1 Orang

Total 8 Orang

3.4.2 Tenaga kerja Alat berat


No Personil Jumlah Satuan Keterangan
1 Operator Concrete pump 1 Orang
2 Mekanik concrete pump 2 Orang
3 Operator Tower Crane 1 Orang
4 Rigger 1 Orang
Total 5 Orang

3.4.3 Tenaga kerja pasang scaffolding


No Personil Jumlah Satuan Keterangan
1 Scafolder 2 Orang
2 Pembantu 4 Orang
Total 6 Orang

3.4.4 Tenaga kerja pasang bekisting


No Personil jumlah Satuan Keterangan
1 Mandor 1 Orang
2 Tukang kayu / bekisting 2 Orang
3 Pembantu 6 Orang
Total 9 Orang
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 16 of 25

3.4.5 Alat kerja umum


No Nama alat Jumlah Satuan Keterangan
1 TMC 1 unit u/mobilisasi dari laydown /
fabrikasi
2 Tower Crane 1 unit u/lansir material
3 Compressor 1 unit u/ pembersihan
4 Lampu penerangan 400 ~ 600 W 8 set

3.4.6 Alat kerja shoring scaffolding untuk 1 tunnel


No Nama alat Jumlah Satuan Keterangan
1 Scafolding pipe 6.0 mtr 54 ea ikatan kolom
2 Scafolding pipe 3.5 mtr 80 ea ikatan kolom
3 Scafolding pipe 3.0 mtr 133 ea kolom
4 Basejack 133 ea
5 Uhead 133 ea
6 Fix clamp 532 ea
7 Swivel clamp 67 ea

3.4.7 Alat kerja pekerjaan bekisting untuk 1 tunnel


No Nama alat Jumlah Satuan Keterangan
1 Multiplex 12 mm 50 br
2 Holow 80x40x3.2 x 6 mtr 64 ea Rusuk
3 Holow 80x40x3.2 x 4 mtr 40 ea beam

3.5 Pelaksanaan pekerjaan


3.5.1 Pasang shoring scafolding dengan jarak 60 x 120 Cm pada base jack.
3.5.2 Ikat antar shoring dengan scaffolding, menggunakan fix clamp.
3.5.3 Pasang u-head jack pada bagian atas shoring.
3.5.4 Pasang beam steel hollow pada u-head, ikat menggunakan kawat putih.
3.5.5 Pasang rusuk pada beam steel hollow dengan jarak 20 Cm pada bagian tepi
sambungan multiplek dan 25 Cm pada bagian tengah multiplek.
3.5.6 Pasang multiplex diatas rusuk dan ikat dengan bolt screw.
3.5.7 Pasang Embedded pada bekisting.
3.5.8 Lakukan inspeksi Bersama dengan enjinir dan employer.
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 17 of 25

4. PEMBESIAN TUNNEL
4.1 Gambar tunnel

Detail tunnel

4.2 Sumber daya


4.2.1 Tenaga kerja pasang pembesian
No Personil jumlah Satuan Keterangan
1 Mandor 1 Orang
2 Tukang besi 3 Orang
3 Pembantu 9 Orang

Total 13 Orang
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 18 of 25

4.2.2 Alat kerja pekerjaan pasang pembesian


No Nama alat Jumlah Satuan Keterangan
1 Gerinda potong / Blander potong 1 set u/potong besi (penyesuaian)

2 Bar cutter 1 unit


3 Bar bender 1 unit
4 Tang / catut / gegep 8 ea
5 Meteran 4 ea

4.2.3 Material pekerjaan pembesian


No Material Berat Satuan Keterangan
1 Besi D32@100 63.00 ton
2 Chairset 1.10 ton
3 Kawat Bendrat 0.18 ton

Total 64.29 ton

4.3 Pelaksanaan pekerjaan


4.3.1 Pastikan besi harus bersih dari kotoran dan minyak
4.3.2 Pasang penuntun rebar arah memanjang pada tahu beton setebal 40mm.
4.3.3 Pasang rebar arah pendek dengan diameter dan jarak sesuai gambar.
4.3.4 Pasang dan ikat rebar arah memanjang diameter dan jarak sesuai dengan gambar.
4.3.5 Pasang chairset untuk menahan rebar lapisan atas.
4.3.6 Pasang rebar arah memanjang diameter dan jarak sesuai dengan gambar.
4.3.7 Pasang dan ikat rebar arah pendek dengan diameter dan jarak sesuai gambar.
4.3.8 Ikatan besi maximal berseling 1 ikat & 2 bebas.
4.3.9 Pastikan pemasangan rapi dan tidak ada perubahan bentuk maupun jarak pada saat
pengecoran
4.3.10 Inspeksi pembesian dilakukan agar sesuai dengan perencanaan, dan dilakukan
inspeksi dengan owner sebelum dilakukan pengecoran.
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 19 of 25

4.3.11 Sambungan overlap besi

Tahu beton
1 ikat, 2 bebas

Overlap Overlap Overlap


EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 20 of 25

5. PEKERJAAN COR BETON SLAB TUNNEL


5.1 Layout & jalur pengecoran
5.1.1 Rute Truck mixer ke Clinker silo

Cek
beton

Rute Truck Mixer ke Clinker Silo

5.1.2 Pasang rambu rambu untuk lalu lintas kendaraan / truck mixer & tempatkan flagman.
5.1.3 Truck masuk didalam plant, diarahkan ke tenda cek slump, dan ambil benda uji dilanjut
CP dengan jalan mundur untuk tuang beton ke pondasi, setelah selesai langsung
keluar lokasi lewat timur shelter.
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 21 of 25

5.1.4 Tempatkan Concrete Pump pada sisi utara Clinker silo untuk cor slab bagian tengah.
5.1.5 Untuk pengecoran slab bagian utara dan selatan, menggunakan bucket concrete dan
dilansir menggunakan Tower crane.
5.1.6 Untuk pengecoran slab bagian barat, tengah dan timur menggunakan bucket concrete dan
dilansir menggunakan Tower crane.

1. Slab tahap 1

3. Slab tahap 3

Tangga
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 22 of 25

5.2 Sumber daya


5.2.1 Tenaga kerja langsung saat pengecoran
No Personil jumlah Satuan Keterangan
1 Mandor 1 Orang
2 Pengarah beton 3 Orang
3 Tenaga Vibrator 3 Orang
4 Tenaga storing bekisting 3 Orang

Total 10 Orang

5.2.2 Alat kerja pekerjaan cor beton


No Nama alat Jumlah Satuan Keterangan
1 Concrete Pump 1 Unit
2 Tower crane 1 Unit
3 Concrete Bucket 1 Unit
4 Vibrator Beton 2.5" 3 Unit Radius 250 mm
5 Timba cor 5 ea u/ adukan bonding agent
6 Raskam kayu 4 ea u/ perataan permukaan

5.2.3 Material utama


No Material M Volume Sat.
1 Beton fc'35 Mpa, Slump 12 ±2Cm 208.00 Keterangan

Material kg/M³
1.1 Semen 350 72.80 Ton
1.2 fly ash 150 31.20 Ton
1.3 Fine Agregate pasir 800 166.40 Ton
1.4 Aggregate 5~10 127 26.42 Ton
1.5 Agregate 10~20 mm 778 161.82 Ton
1.6 Air 180 37.44 Ton
1.7 Additive type D 1.25 0.26 M³
1.8 Additive type F 1.75 0.36 M³

Jumlah 2388
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 23 of 25

5.2.4 Material Pendukung


No Material Volume Sat. Keterangan
1 Bonding agent, SikaBond NV 50.00 ltr Antisipasi cold joint
2 Curing compound, Sika Antisol E-125 75.00 ltr Untuk curing
3 Mortar untuk start CP 2.00 M³ Start CP
4 Plastik cor 291.20 M2

5.3 Pelaksanaan pengecoran beton dinding


5.3.1 Lakukan LST sebelum pelaksanaan dimulai.
5.3.2 Buat mortar 1~1.5 M³ semen : pasir (1:4) untuk pengisian awal Concrete pump.
5.3.3 Order beton ke Batching plant oleh supervisor.
5.3.4 Beton datang ke lokasi, dilakukan pengambilan benda uji beton segar ±18 ltr,
a. test slump, 14±2 Cm.
b. buat benda uji silinder dia. 15x30 Cm, 1 benda uji tiap 4 TM atau tiap 24 M³
atau 1 set (5 benda uji, umur 7, 14, 28 hari, independent & spare) tiap 100 M³.
5.3.5 Arahkan Tuck mixer ke area penuangan Concrete pump.
5.3.6 Pasang penutup Corong Concrete Mixer pada saat Concrete mixer habis tuang.
5.3.7 Urutan pengecoran sesuai denah tunnel
5.3.8 Tinggi jatuh bebas beton maximal 150 Cm dari tremi CP ke permukaan beton.
5.3.9 Padatkan tiap lapisan beton dengan memasukkan vibrator ke dalam beton basah
maximal 30 cm, tiap jarak 25 Cm selama 5 ~ 15 detik dan angkat untuk pindah ke titik
berikutnya.
5.3.10 Haluskan permukaan beton dengan raskam kayu.

5.3.11 Lakukan penyemprotan curing compound / sika antisol ke permukaan beton dan tutup
dengan plastic cor.
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 24 of 25

6. PEKERJAAN BONGKAR BEKISTING SLAB TUNNEL


6.1 Sumber daya
6.1.1 Tenaga kerja Bongkar bekisting
Shift
No Personil Satuan Keterangan
siang
1 Tukang 2 Orang
2 Pembantu umum 8 Orang

Total 10 Orang

6.1.2 Alat kerja bongkar bekisting


No Nama alat Jumlah Satuan Keterangan
1 Kubut / linggis 2 Unit
2 Blander/gerinda potong 1 set

6.2 Safety concern


6.2.1 Ada potensi tangan rawat terjepit dan terkena serpihan kayu, gunakan sarung tangan.
6.2.2 Potensi kaki terkena paku dan kejatuhan papan, selalu gunakan sepatu safety.
6.2.3 Lakukan LST sebelum memulai aktifitas pekerjaan.

6.3 Persiapan secara umum


6.3.1 Pastikan ada ijin kerja dan masih berlaku.
6.3.2 Saat pekerjaan dimalam hari, pastikan cukup penerangan
6.3.3 Pastikan APD sudah sesuai.

6.4 Pembongkaran bekisting.


6.4.1 Setelah beton berumur lebih dari 4 Hari atau kekuatan beton 60% dari kekuatan
rencana, maka bisa dilakukan pembongkaran bekisting.
6.4.2 Kendorkan mur support basejack dan lepaskan pipa scaffolding.
6.4.3 Lepas paku / ikatan antara basejack ke kayu / bekisting secara hati hati.
6.4.4 Bawa semua material support keluar lokasi pekerjaan dan angkut dengan truck.
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 25 of 25

6.4.5 Lepaskan modul papan bekisting dari beton dengan menggunakan linggis atau
pengungkit.
6.4.6 Simpan material bekisting ditempat yang aman atau angkut keluar area pekerjaan
dengan truck.