TITLE OF DOCUMENT:
METODE KERJA
untuk
STRUKTUR BETON SLAB CLINKER SILO
DOCUMENT NO.:
TPJC-TQ1-WM-C6-491-002
0 3 Peb 23 IFC
REVISION HISTORY
DAFTAR ISI
1. UMUM 4
1.1 BATASAN PEKERJAAN .............................................................................................................. 4
1.2 DEFINISI DAN ISTILAH ............................................................................................................... 4
1.3 LOKASI DAN RUTE KE LOKASI PEKERJAAN ............................................................................ 5
1.4 REFERENSI ................................................................................................................................ 5
1.5 LINGKUP PEKERJAAN ............................................................................................................... 6
1.6 JADWAL PEKERJAAN................................................................................................................. 6
1.7 FLOW CHART / ALUR KERJA ..................................................................................................... 7
2. PERSIAPAN PEKERJAAN 8
2.1 SAFETY CONCERN .................................................................................................................... 8
2.2 PERSIAPAN SECARA UMUM ..................................................................................................... 8
4. PEMBESIAN TUNNEL 17
4.1 GAMBAR TUNNEL .....................................................................................................................17
4.2 SUMBER DAYA ..........................................................................................................................17
4.3 PELAKSANAAN PEKERJAAN ....................................................................................................18
1. UMUM
1.1 Batasan pekerjaan
Metode kerja ini mencakup persyaratan umum “PEKERJAAN STRUKTUR
BETON SLAB CLINKER SILO”, yaitu : persiapan, bekisting, pembesian, pasang
embedded, pengecoran, perawatan beton untuk Proyek EPC Talavera.
1.4 Referensi
1.4.1 Dokumen Proyek
1. Section V Employer’s Requirements Chapter 6 – Standard design Criteria (StDC) for Civil
Plant, section 3 Construction Material.
2. TPJC-TQ1-DW-C3-491-3S02-003, Clinker Silo Architectural Section.
3. TPJC-TQ1-DW-C6-491-3S02-002, Clinker Silo Concrete Box plan detail & Section.
4. TPJC-TQ1-DW-C6-491-3S02-003, Clinker Silo Slab El+34.700 Plan detail & Section.
5. TPJC-TQ1-DW-C6-491-3S02-016, Clinker Silo Entrance Acces loader.
6. TPJC-HK-QAQC-0005_ITP Civil Work
1.5.1 Persiapan
1.5.4 Pembesian
No Pekerjaan
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
1 Slab tunnel 1 & 2 tahap 1 (panjang 10 mtr)
1.1 Pasang shoring
1.2 Pasang bekisting
1.3 Pasang Rebar & Embedded
1.4 Cor slab
1.5 Bongkar bekisting
2 Slab tunnel 1 & 2, tahap 2 ( sisi utara & selatan)
2.1 Pasang shoring
2.2 Pasang bekisting
2.3 Pasang Rebar & Embedded
2.4 Cor slab
2.5 Bongkar bekisting
3 Dinding clinker (slipform, metode tersendiri)
4 Dinding tunnel tahap 2
4.1 Rebahkan rebar
4.2 Berdirikan rebar & pasang rebar
4.3 Pasang platform
4.4 Pasang bekisting
4.5 Cor dinding
4.4 Bongkar bekisting
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 7 of 25
START
Persiapan
Pasang Shoring
& bekisting
PERBAIKAN
INSPEKSI
No
Yes
Pasang Rebar
PERBAIKAN
INSPEKSI
No
Yes
PENGECORAN
Bongkar Bekisting
Perbaikan &
Perawatan beton
FINISH
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 8 of 25
2. PERSIAPAN PEKERJAAN
2.1 Safety concern
2.1.1 Untuk mengurangi resiko kecelakaan lalulintas, tempatkan flagman pada lokasi yang
rawan.
2.1.2 Selalu gunakan pelindung mata / kaca mata agar terlindung dari cipratan pasta beton
2.1.3 Lakukan Tool box Meeting sebelum memulai aktifitas pekerjaan.
9.00
Wall tunnel
9.00
Wall tunnel_1
Slab tunnel_1
Wall clinker, slipform
Wall tunnel_2
Slab tunnel_2
Platform
Tangga
Denah dinding tunnel clinker silo tahap 2
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 11 of 25
U-Head
60 Cm 60 Cm
Base jack
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 12 of 25
Total 8 Orang
4. PEMBESIAN TUNNEL
4.1 Gambar tunnel
Detail tunnel
Total 13 Orang
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 18 of 25
Tahu beton
1 ikat, 2 bebas
Cek
beton
5.1.2 Pasang rambu rambu untuk lalu lintas kendaraan / truck mixer & tempatkan flagman.
5.1.3 Truck masuk didalam plant, diarahkan ke tenda cek slump, dan ambil benda uji dilanjut
CP dengan jalan mundur untuk tuang beton ke pondasi, setelah selesai langsung
keluar lokasi lewat timur shelter.
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 21 of 25
5.1.4 Tempatkan Concrete Pump pada sisi utara Clinker silo untuk cor slab bagian tengah.
5.1.5 Untuk pengecoran slab bagian utara dan selatan, menggunakan bucket concrete dan
dilansir menggunakan Tower crane.
5.1.6 Untuk pengecoran slab bagian barat, tengah dan timur menggunakan bucket concrete dan
dilansir menggunakan Tower crane.
1. Slab tahap 1
3. Slab tahap 3
Tangga
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 22 of 25
Total 10 Orang
Jumlah 2388
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 23 of 25
5.3.11 Lakukan penyemprotan curing compound / sika antisol ke permukaan beton dan tutup
dengan plastic cor.
EPC Tuban Jetty Upgrade and its
Ancillary Production & Transportation
Facilities Project
(EPC Talavera)
Title Document No. TPJC-TQ1-WM-C6-491-002
METODE KERJA Revision 0
Untuk Issued Date 3 Peb 2023
STRUKTUR BETON SLAB CLINKER SILO Page No 24 of 25
Total 10 Orang
6.4.5 Lepaskan modul papan bekisting dari beton dengan menggunakan linggis atau
pengungkit.
6.4.6 Simpan material bekisting ditempat yang aman atau angkut keluar area pekerjaan
dengan truck.