PENGAJUAN Galian Sedimentasi Kab. Kuningan
PENGAJUAN Galian Sedimentasi Kab. Kuningan
RUMAH JAGA
14 PETA LOKASI
KANDANG AYAM
Koordinator Petugas OP Nama Petugas OP
Sabur
APORAN INSPEKSI BULANAN PETUGAS OP
Sabur
S.6°50'21.5736" - E.108°28'17.9256"
KETERANGAN
a)Volume = (1/2 x 10,53 x 8,25 ) x 1,30
43,43 x 1,30
56,45 m3
b)Volume = (1/2 x 10,53 x 5,75 ) x 1,30
30,27 x 1,30
39,35 m3
Total :
PETA LOKASI
Nama Petugas OP
Sabur
RENCANA ANGGARAN BIAYA
(RAB)
LOKASI :
PROVINSI : JAWA BARAT
TAHUN ANGGARAN : 2022
A. PEMELIHARAAN RUTIN
BELANJA PEMELIHARAAN JARINGAN (523132)
PEKERJAAN GALIAN LUMPUR SEDALAM > 0 s/d 1 M (SECARA MANUAL)
I. UPAH TENAGA KERJA
1. SEDIMENTASI SALURAN INFL0W 1.7.10.1.C (a 95.80 M3 89,500.00 8,574,100.00
95.80 M3 87,300.00
MENYETUJUI :
PEJABAT PEMBUAT KOMITMEN
OPERASI DAN PEMELIHARAAN
SUMBER DAYA AIR II,
A TENAGA
1 PEKERJA L.01 OH 1.0000 77,000.00 77,000.00
4 MANDOR L.04 OH 0.1000 125,000.00 12,500.00
JUMLAH HARGA TENAGA KERJA 89,500.00
OVERHEAD + PROFIT 10% 0.00
JUMLAH HARGA TENAGA KERJA 89,500.00
JUMLAH HARGA TENAGA KERJA DIBULATKAN 89,500.00
B BAHAN
C PERALATAN
A TENAGA
1 PEKERJA L.01 OH 1.0000 100,000.00 100,000.00
4 MANDOR L.04 OH 0.1000 125,000.00 12,500.00
JUMLAH HARGA TENAGA KERJA 112,500.00
OVERHEAD + PROFIT 10% 0.00
JUMLAH HARGA TENAGA KERJA 112,500.00
JUMLAH HARGA TENAGA KERJA DIBULATKAN 112,500.00
B BAHAN
C PERALATAN