Rencana Anggaran Biaya

PEKERJAAN PENGECATAN RUANG PRODUKSI


PT. SOLUNOVA ALAMI INDONESIA
Kendal - Jawa Tengah
No RAB : 020 A / KBP - SAI / X / 2023

NO URAIAN PEKERJAAN SPESIFIKASI SAT VOL HARGA SAT JUMLAH HARGA

I PEKERJAAN PERSIAPAN
1 Survey & Pengukuran Ls 1.00 1,500,000 1,500,000
2 Mobilisasi Alat & Bahan Ls 1.00 2,500,000 2,500,000
3 Peralatan & Andang Kerja Ls 1.00 1,500,000 1,500,000
4 Kebersihan Lokasi Kerja & Plastik Pengaman Ls 1.00 2,500,000 2,500,000
5 APD & K3 Ls 1.00 1,500,000 1,500,000
6 Dokumentasi & Pelaporan Ls 1.00 500,000 500,000

Sub Total 10,000,000


II PENGECATAN RUANG PRODUKSI
1 Pre-Treatment
- Kupas/ Scraping Cat Dinding Lama (Incd. Paint Remover) ex. Propan m2 585.00 25,000 14,625,000
- Sanding Substrat Lama m2 585.00 15,000 8,775,000
2 Finish Coating
- Prime Coat 30mc & Finish Coat Acrylic Enamel 60-90mc ex. Propan m2 585.00 55,000 32,175,000

Sub Total 55,575,000


Note:
- Pekerjaan dilakukan saat kegiatan produksi off, yaitu hari sabtu & minggu
- Lama pekerjaan 6 hari efektif
- Garansi pekerjaan selama 3 bulan (cat bubbling & atau mengelupas, tidak termasuk Yellowing Defect)
- Term Of Payment :
• Down Payment (DP) sebesar 30%, Dibayarkan setelah Kontrak ditandatangani kedua belah pihak
• Termin 1 sebesar 65%, Dibayarkan setelah prestasi pekerjaan mencapai 100% (BAST 1)
• Retensi sebesar 5%, Dibayarkan 3(tiga) bulan setelah serah terima pekerjaan (BAST 2)

JUMLAH 65,575,000
JASA KONTRAKTOR 7,5 % 4,918,125.0
TOTAL 70,493,125
PEMBULATAN 70,000,000
PPN 11 % By Owner

GRAND TOTAL 70,000,000

Semarang, 20 Oktober 2023


CV. KOKOH BANGUN PERSADA

A. Renard Widarto