Anda di halaman 1dari 1

1.

TAHAP KONSTRUKSI

HARGA SATUAN WAKTU / JUMLAH TOTAL


NO BIAYA KONTRUKSI SATUAN
(Rp) VOLUME (Rp) (Rp)

1 MOBILISASI PERALATAN & PERLENGKAPAN Paket 25,000,000 25,000,000 25,000,000


2 KONSTRUKSI 500,000,000
a Pembuatan Jalan Tambang Tambang &
Paket 100,000,000 100,000,000
b Pembangunan Sarana & Prasarana
c Biaya Pembuatan Kanopi 2 Unit 200,000,000 /Unit 400,000,000
3 PENGADAAN PERALATAN ` 1,559,150,000
a Mesin Lori (Modifikasi) 2 Unit 80,000,000 /Unit 160,000,000
b Rel Lori 100 Meter 60,000 /Meter 6,000,000
d Skop 10 Unit 80,000 /Unit 800,000
e Sling Baja 800 Meter 60,000 /Meter 48,000,000
f Instalasi Listrik 100 Meter 17,500 /Meter 1,750,000
g Perlengkapan Blower 8 Unit 12,500,000 /Unit 100,000,000
h Gerobak 8 Unit 200,000 /Unit 1,600,000
i Jack Hammer 8 Unit 15,000,000 /Unit 120,000,000
j Pembelian Pompa Celup 6 Unit 3,500,000 /Unit 21,000,000
k Pembelian Pompa Kolam Sedimentpond 2 Unit 350,000,000 /Unit 700,000,000
l Sewa Excavator 1 Unit 100,000,000 200 jam 100,000,000
, Sewa Dump Truck 2 Unit 25,000,000 /Bln 50,000,000
n Pembelian Kendaraan Operasional 1 Unit 200,000,000 /Unit 200,000,000
o Pembelian Motor Operasional 2 Unit 25,000,000 /Unit 50,000,000
4 PENGADAAN PERALATAN SAFETY 11,830,000
a Sepatu Safety 26 Psg 300,000 /Psg 7,800,000
b Helm + Head Lamp 26 Psg 150,000 /Psg 3,900,000
c Sarung Tangan 26 Psg 5,000 /Psg 130,000
7 OPERASIONAL & PEMELIHARAAN PERALATAN 4 Bulan 62,800,000
a Pemakaian Bahan Bakar (Solar - Bensin)
- Mesin Lori (Modifikasi) 2 Unit 11,000 /ltr 300 ltr/bln 26,400,000
- Pompa Sediment Pond 2 Unit 11,000 /ltr 300 ltr/bln 26,400,000
b Pemakaian Bahan Pelumas (Oli)
- Mesin Lori (Modifikasi) 2 Unit 30,000 /ltr 10 ltr/bln 2,400,000
- Pompa Sediment Pond 2 Unit 30,000 /ltr 15 ltr/bln 3,600,000
c Penggantian Spare Park/Servis 4 Bulan
- Mesin Lori (Modifikasi) 2 Unit 1,000,000 /bln 2,000,000
- Pompa Sediment Pond 2 Unit 1,000,000 /bln 2,000,000
9 PENGELOLAAN DAN PEMANTAUAN LINGKUNGAN 4 Bulan 6,000,000
a Pengelolaan & Pemantauan Lingkungan Paket 1,500,000 /bln 4 bulan 6,000,000
10 GAJI KARYAWAN 4 Bln 266,400,000
a Kepala Teknik Tambang 1 Orang 5,000,000 /bln 4 bulan 20,000,000
b Pengawas Operasional Lapangan 3 Orang 3,500,000 /bln 4 bulan 42,000,000
c Tenaga Ahli Kelistrikan 2 Orang 3,500,000 /bln 4 bulan 28,000,000
d Tenaga Ahli Mekanik 2 Orang 3,500,000 /bln 4 bulan 28,000,000
e Adm & Logistik 2 Orang 3,000,000 /bln 4 bulan 24,000,000
f Security 2 Orang 1,700,000 /bln 4 bulan 13,600,000
g Operator Alat Berat 1 Orang 3,000,000 /bln 4 bulan 12,000,000
h Helper Alat Berat 1 Orang 1,700,000 /bln 4 bulan 6,800,000
i Sopir Dump Truck 2 Orang 3,000,000 /bln 4 bulan 24,000,000
j Tenaga Harian / Lokal 10 Orang 1,700,000 /bln 4 bulan 68,000,000
11 ASURANSI 11,440,000
a Jamsostek 26 Orang 110,000 /bln 4 bulan 11,440,000
TOTAL INVESTASI TAHAP KONSTRUKSI 2,442,620,000