RENCANA ANGGARAN BIAYA SURVEY TOPOGRAFI (PENGUKURAN)

No Uraian Pekerjaan Volume Satuan Harga Satuan Total Harga Keterangan

A. Operasional
1 Mobilisasi (Sewa Mobil) 1 Hari 600,000.00 600,000.00
2 Akomodasi Makan dan Minum 1 Hari 175,000.00 175,000.00
3 Sewa Penginapan 1 Hari 300,000.00 300,000.00
Sub Total A 1,075,000.00

B. Peralatan
1 Sewa Alat (Theodilite) 1 Set/Hari 500,000.00 500,000.00
2 Sewa Alat (Waterpass) 1 Set/Hari 300,000.00 300,000.00
3 Sewa Alat (Gps) 1 Buah 200,000.00 200,000.00
4 Meteran 1 Buah 25,000.00 25,000.00
5 Balok Patok/Pilox 60 Buah 20,000.00 1,200,000.00
Sub Total B 2,225,000.00

C. Tenaga Ahli
1 Jasa Surveyor Topografi 2 Ha 2,500,000.00 5,000,000.00
Sub Total C 5,000,000.00

Total Harga 8,300,000.00