RENCANA ANGGARAN BIAYA

PROGRAM : PEMBANGUNAN SARANA IBADAH


PEKERJAAN : PENYELESAIAN PEMBANGUNAN MASJID AL MUHAJIRIN
LOKASI : JALAN RAYA SUMELAP, CILENDEK, KOTA BARU, CIBEUREUM, TASIKMALAYA

ANALISA
HARGA JUMLAH

KODE
NO. URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
(Rp.) (Rp.)

V PEKERJAAN DINDING DAN PLESTERAN


1 1 m2 PASANGAN BATAKO BESAR (8X20X30), 1 PC : 5 Ps 63.964 A-01 m² 140,573 8,991,611
2 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 15 mm 127.928 B-01 m² 56,103 7,177,145
16,168,756
VI PEKERJAAN KUSEN, PINTU DAN JENDELA
1 1 BH PEKERJAAN PINTU ALUMUNIUM TYPE PJ 2 3.000 G-01 m³ 5,788,841 17,366,523
2 1 BH PEKERJAAN JENDELA ALUMUNIUM TYPE J3 6.000 G-02 m² 1,940,740 11,644,440
3 1 BH PEKERJAAN BOUVENLIHT ALUMUNIUM TYPE BV1 3.000 G-03 m² 1,965,468 5,896,404
35,032,725
VIII PEKERJAAN RANGKA DAN PENUTUP PLAFOND
1 1 m2 LANGIT-LANGIT GYPSUM (1.20X2.40 ) Cm, RANGKA KAYU
191.138
GUNUNGC-01
KELAS IIm² 156,480 29,909,196
2 1 m' PASANG LIST PLAFOND GYPSUN 764.550 F-26 m¹ 26,917 20,579,392
50,488,588
IX PEKERJAAN LANTAI
1 1 m2 PASANG LANTAI KERAMIK 40 x 40 cm PUTIH 213.714 L-03 m² 215,292 46,010,979
2 Pas. Lantai Keramik 30 x 30 Anti Slip (Tangga) 8.338 F-02 m² 30,011 -
46,010,979
X PEKERJAAN PENGECATAN DAN LABURAN
2 1 m2 PENGECATAN BIDANG TEMBOK BARU (1 Lapis Plamir; 1 Lapis
127.928
Cat dasar;
F-012 Lapis m²
Cat Penutup) SANLEX
22,303 2,853,178
4 1 m2 PENGECATAN PLAFOND SETARA SANLEX 191.138 F-02 m² 30,011 5,736,228
14,717,628
XI PEKERJAAN INSTALASI LISTRIK
1 Pas. Instalasi Titik Lampu 13.000 U&B ttk 120,000 1,560,000
2 Pas. Instalasi Stop Kontak 4.000 U&B bh 120,000 480,000
3 Pas. Lampu SL 18 Watt 13.000 U&B bh 40,000 520,000
4 Pas. Saklar Tunggal Broco 4.000 U&B bh 13,500 54,000
5 Pas. Saklar Ganda Broco 3.000 U&B bh 18,000 54,000
2,668,000