RENCANA ANGGARAN BIAYA
PEMBUATAN MESS SAMPING GUNUNG GEDE
PT. PLN (Persero) UDIKLAT BOGOR
PROJECT ACADEMIA
I PEKERJAAN PERSIAPAN
1 Pekerjaan Gudang & Direksi Keet 18 m2 1,114,839 20,067,099
2 Pengukuran & Alat Bantu Ukur 171.5 m2 46,548 7,983,029
3 Perapihan Lahan 171.5 m2 8,619 1,478,088
JUMLAH I= 29,528,216
II PEKERJAAN TANAH
1 Pekerjaan Galian Tanah Pondasi Sumuran t=3m dia=80cm 30.72 m3 167,086 5,132,897
2 Pekerjaan Galian Tanah Pile Cap 120x120x30cm 6.91 m3 167,086 1,154,902
3 Pekerjaan Galian Tanah Pondasi Batukali 64.75 m3 167,086 10,818,850
4 Urug Tanah Bekas Galian Pondasi 102.38 m3 18,791 1,923,883
JUMLAH II= 19,030,533
VI PEKERJAAN PLAFON
1 Pek. Plafon Gypsum rangka Hollow 40x40mm 343 m2 120,014 41,164,726
JUMLAH VI= 41,164,726
VIIIPEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding 1312 m2 39,334 51,590,898
2 Pek. Pengecatan Plafon 343 m2 49,291 16,906,749
JUMLAH VIII= 68,497,647
2 2 tahun 4,800,000.00
2 3 tahun 5,400,000.00
3 4 tahun 6,000,000.00
Ahli Muda
1 1 tahun 9,600,000.00
2 2 tahun 11,200,000.00
3 3 tahun 12,800,000.00
4 4 tahun 14,400,000.00
5 Ahli Madya
LANTAI - 1
I PEKERJAAN PERSIAPAN 3,967,158.61
II PEKERJAAN GALIAN DAN URUGAN 6,401,104.75
III PEKERJAAN BETON 416,086,347.86
IV PEKERJAAN PASANGAN 50,103,908.26
V PEKERJAAN KUSEN 46,157,728.72
VI PEKERJAAN INSTALASI LISTRIK+ARMATUR 4,928,421.31
VII PEKERJAAN PENGECATAN/FINISHING 37,481,967.19
JUMLAH 582,290,335.49
DIBULATKAN 582,290,000.00
TERBILANG : LIMA RATUS DELAPAN PULUH DUA JUTA DUA RATUS SEMBILAN PULUH RIBU RUPIAH
Bogor, ………………………..2016
Konsultan Perencana,
CV. CATUR PRIMA KARYA
SNI 1.0000 m1 Pembuatan pagar sementara dari seng gelombang tinggi 2 meter
6.2 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 52,962.80 66,203.50
03-2835-2002 2.5000 kg PC @ Rp. 2,171.71 5,429.26
1.2000 lbr Seng gelombang 2"-5" BJLS 24 @ Rp. 59,000.00 70,800.00
0.0050 m3 Pasir beton @ Rp. 395,501.47 1,977.51
0.0090 m3 Kerikil beton @ Rp. 425,020.78 3,825.19
0.0250 m3 Kaso 5/7 kayu meranti @ Rp. 2,938,466.76 73,461.67
0.0600 kg Paku biasa 2" - 5" @ Rp. 20,634.86 1,238.09
0.4000 kg Meni besi @ Rp. 30,092.50 12,037.00
0.2000 org Tukang kayu @ Rp. 127,627.52 25,525.50
0.0200 org Kepala tukang kayu @ Rp. 147,647.50 2,952.95
0.4000 org Pekerja @ Rp. 92,592.50 37,037.00
0.0200 org Mandor @ Rp. 189,689.50 3,793.79
JUMLAH ( BELUM PPN ) 69,309.25 234,972.22 304,281.47
JASA 10 % 30,428.15
JUMLAH 69,309.25 234,972.22 334,709.61
DIBULATKAN 69,309.00 234,972.00 334,709.00
SNI 1.0000 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
6.15 0.1000 kg Plamir tembok @ Rp. 46,000.00 4,600.00
0.1000 kg Cat dasar @ Rp. 40,925.80 4,092.58
0.2600 kg Cat penutup 2 x @ Rp. 37,658.62 9,791.24
0.0630 org Tukang cat @ Rp. 127,627.52 8,040.53
0.0063 org Kepala tukang cat @ Rp. 147,647.50 930.18
0.0200 org Pekerja @ Rp. 92,592.50 1,851.85
0.0025 org Mandor @ Rp. 189,689.50 474.22
JUMLAH ( BELUM PPN ) 11,296.79 18,483.82 29,780.61
JASA 10 % 2,978.06
JUMLAH 11,296.79 18,483.82 32,758.67
DIBULATKAN 11,296.00 18,483.00 32,758.00
ANALISA SATUAN PEKERJAAN
No. Macam Pekerjaan Upah Bahan Jumlah
SNI 1.0000 m MEMBONGKAR LANTAI KERAMIK DAN PLESTERAN DIBAWAH
2
KOEF
NO URAIAN KODE Analisa
Harga Satuan
A. PEKERJAAN PERSIAPAN
1 1 M' Pagar Sementara dari Kayu Tinggi 2 m A-01 560,455.17
2 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m A-02 669,099.67
3 1 M' Pagar Sementara Kawat Duri Tinggi 1,80 m A-03 1,663,617.68
4 1 M2 Pengukuran dan Pasang Bouwplank A-04 46,548.28
5 1 M2 Pembuatan Kantor Sementara dengan Lantai diPlester A-05 1,114,838.82
6 1 M2 Pembuatan Gudang Semen dan Alat-alat A-06 1,073,389.80
7 1 M2 Pembuatan Bedeng Buruh A-07 1,183,091.61
8 1 M2 Membersihkan Lapangan & Perataan A-08 8,618.59
9 1 M3 Pembuatan Jalan Sementara A-09 521,753.35
10 1 M3 Bongkaran Beton Bertulang A-10 574,545.15
11 1 M3 Bongkaran Dinding Tembok Bata Merah A-11 574,545.15
12 1 m2 Pembuatan bak adukan ukuran 40 x 50 x 25 cm A-12 184,344.63
13 1 M' Pagar Kawat Ayam Tiang Besi L50.50.5, tinggi 1 m' A-13 392,566.70
14 1 M2 Pagar BRC lengkap dengan tiang A-14 287,387.81
15 1 M2 Steiger Werk/Perancah dari Bambu A-15 34,128.05
16 1 M' Cerucuk Bambu A -16 68,392.94
17 Pasang 1 m' Pagar Kawat Jaring Galvanis, Tinggi 1 meter A-17 55,785.62
18 Pasang 1 m' Pagar Beton Pracetak (5 x 50 x 213) cm A-18 631,659.20
19 Memasang 1 M' Pagar Besi A-19 2,739,403.14
20 Memasang 1 Unit Pintu Besi A-20 13,852,141.12
B. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter B-01 62,637.42
2 Menggali 1 m3 tanah biasa sedalam 2 meter B-02 77,567.28
3 Menggali 1 m3 tanah pondasi sumur sedalam 3 meter B-03 167,086.49
4 Menggali 1 m3 tanah keras sedalam 1 meter B-04 83,303.01
5 Menggali 1 m3 tanah cadas sedalam 1 meter B-05 126,876.42
6 Menggali 1 m3 tanah lumpur sedalam 1 meter B-06 101,020.66
7 Mengerjakan 1 m2 stripping tebing setinggi 1 meter B-07 4,709.69
8 Membuang 1 m3 tanah sejauh 15 meter B-08 27,400.30
9 Mengurug kembali 1 m3 galian B-09 18,791.22
10 Memadatkan 1 m3 tanah (per 20 cm) B-10 47,096.91
11 Mengurug 1 m3 pasir urug B-11 338,579.17
12 Memasang 1 m3 Lapisan pudel campuran 1 KP : 3 PP : 7 TL untuk stabilisasi tanah B-12 199,412.34
13 Memasang 1 m3 Lapisan pudel campuran 1 KP : 5 TL untuk stabilisasi tanah B-13 246,507.25
14 Memasang 1 m2 Lapisan Ijuk tebal 10 cm, untuk bidang resapan B-14 153,818.07
15 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan B-15 340,176.86
16 1 m3 Pasangan Batu Beronjong B-16 765,202.29
C. PEKERJAAN PONDASI
1 Memasang 1 m3 Pondasi Batu belah campuran 1 PC : 3 PS C-01 1,217,723.64
2 Memasang 1 m3 Pondasi Batu belah campuran 1 PC : 4 PS C-02 1,145,365.04
3 Memasang 1 m3 Pondasi Batu belah campuran 1 PC : 5 PS C-03 1,095,189.29
4 Memasang 1 m3 Pondasi Batu belah campuran 1 PC : 6 PS C-04 1,059,919.59
5 Memasang 1 m3 Pondasi Batu belah campuran 1 PC : 8 PP C-05 1,011,563.02
6 Memasang 1 m3 Pondasi Batu belah, campuran 1 KP : 1 SM : 2 PP C-06 792,657.12
7 Memasang 1 m3 Pondasi Batu belah, campuran 1 PC : 3 KP : 10 PP C-07 930,198.95
8 Memasang 1 m3 Pondasi Batu belah, campuran 1/4 PC : 1 KP : 4 PP C-08 895,927.47
9 Memasang 1 m3 Batu Kosong (aanstamping) C-09 615,604.60
10 Memasang 1 m3 Beton Siklop, 60% beton campuran 1 Pc : 2Pb : 3kr + 40% Batu Belah C-10 2,602,129.19
11 Memasang 1 m3 Pondasi Sumuran, diameter 100 cm C-11 1,116,703.39
12 1 M' Pembuatan Tiang Pancang (40 x 40) cm, Beton Tulang C-12 861,579.86
13 1 M' Pembuatan Tiang Pancang (35 x 35) cm, Beton Tulang C-13 651,362.06
14 1 M' Pembuatan Tiang Pancang θ40 cm, Beton Tulang C-14 927,663.78
15 1 M' Memancang Tiang Pancang Beton Bertulang C-15 129,663.99
16 1 Buah Memotong Tiang Pancang (40x40) cm Beton Bertulang C-16 295,911.10
17 1 M' Menyambung Tiang Pancang Beton Bertulang C-17 841,701.58
D. PEKERJAAN BETON
1 Membuat 1 m3 beton mutu f'c = 7,4 Mpa (K100), slump (12±2) cm, w/c = 8,7 D-01 1,153,606.56
2 Membuat 1 m3 beton mutu f'c = 9,8 Mpa (K125), slump (12±2) cm, w/c = 0,78 D-02 1,207,536.85
3 Membuat 1 m3 beton mutu f'c = 12,2 Mpa (K150), slump (12±2) cm, w/c = 0,72 D-03 1,250,275.74
4 Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 Mpa (K100), slump (3-6)cm w/c = 0,87 D-04 1,080,933.42
5 Membuat 1 m3 lantai kerja beton mutu f'c = 14,5 Mpa (K175), slump (12±2)cm w/c = 0,66 D-05 1,300,260.57
6 Membuat 1 m3 lantai kerja beton mutu f'c = 16,9 Mpa (K200), slump (12±2)cm w/c = 0,61 D-06 1,348,889.10
7 Membuat 1 m3 lantai kerja beton mutu f'c = 19,3 Mpa (K225), slump (12±2)cm w/c = 0,58 D-07 1,383,982.17
8 Membuat 1 m3 lantai kerja beton mutu f'c = 21,7 Mpa (K250), slump (12±2)cm w/c = 0,56 D-08 1,408,951.21
9 Membuat 1 m3 lantai kerja beton mutu f'c = 24 Mpa (K275), slump (12±2)cm w/c = 0,53 D-09 1,451,935.36
10 Membuat 1 m3 lantai kerja beton mutu f'c = 26,4 Mpa (K300), slump (12±2)cm w/c = 0,52 D-10 1,465,290.64
11 Membuat 1 m3 lantai kerja beton mutu f'c = 28,8 Mpa (K325), slump (12±2)cm w/c = 0,49 D-11 1,563,398.54
12 Membuat 1 m3 lantai kerja beton mutu f'c = 31,2 Mpa (K350), slump (12±2)cm w/c = 0,48 D-12 1,580,901.93
13 Membuat 1 m3 beton kedap air dengan storox - 100 D-13 1,549,984.60
14 Memasang 1m' PVC waterstop lebar 150 mm D-14 98,450.55
15 Memasang 1 m' PVC Waterstop lebar 200 mm D-15 99,082.75
16 Memasang 1 m' PVC Waterstop lebar 230 mm - 320 mm D-16 151,982.48
17 Pembesian 10 kg dengan besi polos atau besi ulir D-17 129,808.25
18 Pembesian 1 kg dengan besi polos atau besi ulir HIT-1 12,980.82
19 Memasang 10 kg kabel presstressed polos/strands D-18 124,390.35
20 Memasang 1 kg jaring kawat baja/wire mesh D-19 131,273.60
21 Memasang 1 m2 bekisting untuk pondasi D-20 160,955.61
22 Memasang 1 m2 bekisting untuk Sloof D-21 170,095.79
23 Memasang 1 m2 bekisting untuk Kolom D-22 371,448.02
24 Memasang 1 m2 bekisting untuk balok D-23 380,588.20
25 Memasang 1 m2 bekisting untuk plat lantai D-24 478,692.74
26 Memasang 1 m2 bekisting untuk dinding D-25 463,995.35
27 Memasang 1m2 bekisting untuk tangga D-26 350,383.37
28 Memasang 1 m2 jembatan untuk pengecoran beton D-27 93,065.84
29 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) D-28 4,077,172.87
30 Membuat 1 M3 Tangga Beton Tulang (200 kg Besi + Bekisting) D-29 4,906,569.40
31 Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting) D-30 8,455,786.38
32 Membuat 1 m3 Sloof beton bertulang 15 x 18 cm, 6dia10-Dia 8-15 Cm(201 kg besi + bek) HIT-2 6,177,350.21
33 Membuat 1 m3 Sloof beton bertulang 20 x 30 CM, 6dia.16-Dia 8-15 (200 kg besi + bek) HIT-3 5,610,364.25
34 Membuat 1 m3 kolom beton bertulang 18 x 18 Cm, 6 Dia 10 + Dia 8 - 15 Cm (172 kg besi + bek) HIT-4 7,660,162.71
35 Membuat 1 m3 kolom beton bertulang 13 x 18cm, 6 Dia 10 - Dia 8 - 15 Cm (200 kg besi + bek) HIT-5 8,817,318.16
36 Membuat 1 m3 kolom beton bertulang 15 x 20 cm, 4 Dia 12 - Dia 8 - 15 Cm(180 kg besi + bek) HIT-6 7,970,369.32
37 Membuat 1 m3 kolom beton bertulang 20 x 20 cm, 4 dia.16 8-15 (210 kg besi + bek) HIT-7 7,740,714.03
38 Membuat 1 m3 kolom beton bertulang 20 x 20cm, 4 dia.12 8-15 (140 kg besi + bek) HIT-8 6,832,056.28
39 Membuat 1 m3 balok beton bertulang 11 x 11 cm, 4 dia.10, 8-15, (278 kg besi + bek) 8,452,544.20
40 Membuat 1 m3 kolom beton bertulang 30 x 30cm, 8dia.16, 8-15(175 kg besi + bek) HIT-9 6,048,225.08
41 Membuat 1 m3 Balok beton bertulang 20 x 30, 5 dia.16, 8-15(175 kg besi + bek) HIT-11 8,730,135.83
Membuat 1 m3 Balok beton bertulang 20 x 40, 5 dia.16, 8-15(133 kg besi + bek) HIT-11' 7,867,784.36
42 Membuat 1 m3 Balok beton bertulang 30 x 60 cm, 10 dia.16, 8-15 (125 kg besi + bek) HIT-12 6,178,153.60
43 Membuat 1 m3 Plat lantai beton tbl. 12 cm' besi dia. 8 mm (110 kg besi + bekisting) HIT-13 6,800,963.14
44 Membuat 1 m3 Listplank beton tbl. 8 cm', besi dia. 8 mm (50 kg besi + bekisting) HIT-14 3,066,999.74
45 Membuat 1 m3 kolom beton bertulang 12 x 12 cm, 4 Dia 10 - Dia 8 - 15 Cm (239 kg besi + bek) 7,498,077.91
46 Membuat 1 m3 Balok beton bertulang 13 x 18 cm, 6 dia.10, 8-15 (180 kg besi + bekisting) HIT-15.alt 6,564,410.57
47 Membuat 1 m3 Balok beton bertulang 15 x 20 cm, 4 dia.12, 8-15 (180 kg besi + bekisting) HIT-15 6,174,057.36
48 Membuat 1 m3 Balok beton bertulang 15 x 25,cm, 5 dia.12 +dia 8-15 (176 kg besi + bekisting) HIT-16 6,883,316.80
49 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) D- 31 6,669,656.96
50 Membuat 1 m3 Plat beton bertulang (150 kg besi + bekisting) D- 32 6,286,820.89
51 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) D- 33 6,047,583.67
52 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting) D- 34 6,212,570.07
53 Membuat 1 m' Kolom praktis beton bertulang (11 x 11) cm D- 35 73,014.46
54 Membuat 1 m' ring balok beton bertulang (10 x 15) cm D- 36 102,379.20
55 Pekerjaan Water Proofing D-37 511,072.96
56 Pekerjaan Water Proofing Membran D-38 141,700.72
E. PEKERJAAN PASANGAN DINDING
1 Memasang 1 M2 Bata Merah tebal 1 Bata, 1pc : 3ps E-01 337,776.04
2 Memasang 1 M2 Bata Merah tebal 1 Bata, 1pc : 4ps E-02 324,582.15
3 Memasang 1 M2 Bata Merah tebal 1 Bata. 1pc : 5ps E-03 318,307.84
4 Memasang 1 M2 Bata Merah tebal 1/2 bata, 1pc :3ps E-04 107,573.84
5 Memasang 1 M2 Bata Merah tebal 1/2 Bata, 1pc : 4ps E-05 108,642.23
6 Memasang 1 M2 Bata Merah tebal 1/2 Bata, 1pc : 5ps E-06 99,151.10
7 Memasang 1 M2 Dinding Rooster Beton 20 x 20, adk 1pc : 3ps E-07 394,110.40
8 Memasang 1 M2 Dinding Rooster Beton 20 x 20, adk 1pc : 4pc E-08 390,201.33
9 Memasang 1 M2 Dinding Rooster/Terawang (12 x 11 x 24) cm E-09 1,694,972.40
10 Memasang 1 M2 Dinding Batako Besar Pres uk. 8x20x30 adk 1pc :4ps E-10 122,444.43
11 Memasang 1 M2 Dinding Hollowblock (HB-20) E-11 210,036.66
12 Memasang 1 M2 Dinding Hollowblock (HB-15) E-12 201,484.71
13 Memasang 1 M2 Dinding Conblock (CB-20) E-13 191,588.54
14 Memasang 1 M2 Dinding Conblock (CB-20) E-14 214,475.16
15 Memasang 1 M2 Dinding Conblock (CB-15) E-15 100,261.04
16 Memasang 1 M2 Dinding untuk Conblock (CB-10) E-16 100,261.04
17 Memasang 1 M2 Dinding Keramik artistik (10 x 20) cm E-17 155,431.11
18 Memasang 1 M2 Dinding Keramik artistik (5 x 20) cm E-18 157,924.49
19 Memasang 1 M2 Dinding Keramik Corak 20 x 20 cm E-19 233,104.05
19 Memasang 1 M2 Dinding Keramik Corak 20 x 25 cm E - 20 276,966.87
19 Memasang 1 M2 Dinding Keramik Marmer E - 21. 948,265.77
19 Memasang 1 M2 Dinding Batu Tempel Hitam E - 22. 235,034.38
22 1 M' Saluran Air hujan lebar = 20 cm E - 23. 88,218.50
23 Memasang 1 M2 Dinding Porselen (10x20) cm E - 24. 150,870.61
24 Memasang 1 M2 Dinding Porselen (20x20) cm E-25 137,406.37
25 Memasang 1 M2 Wall paper, lebar 50 cm E - 26 136,845.17
26 Membuat 1 M2 Dinding Pemisah Teakwood Rangkap, Rangka kayu Klas II E - 27 256,683.54
27 Membuat 1 M2 Dinding Pemisah Plywood Rangkap, Rangka kayu klas II E - 28 316,760.04
28 Membuat 1 M2 Dinding Pemisah Triplek 4 mm Rangkap, Rangka kayu klas II E - 29 220,882.47
29 Membuat 1 M2 Dinding Pemisah GRC t = 4 mm + Rangka Besi hollow E - 30a 105,126.93
30 Membuat 1 M2 Dinding Pemisah gypsum t = 9 mm + Rangka Besi hollow E - 30b 108,381.73
31 Membuat 1 M2 Dinding Pemisah Plywood t = 4 mm + Rangka Besi hollow E - 31 128,975.66
32 Membuat 1 M2 Dinding Pemisah Teakwood t = 4 mm + Rangka Besi hollow E - 32 106,129.44
33 Memasang 1 M2 Dinding Glass Block 20 x 20 adk. 1pc : 4ps E- 33 858,535.00
34 Memasang 1 M2 Dinding Anyaman bambu, rangka kayu E - 34 126,845.90
35 Memasang 1 M2 dinding Block Bata Ringan E - 35 281,421.35
F. PEKERJAAN PLESTERAN DAN SIARAN
1 Membuat 1 m2 plesteran 1 PC : 1 PP, tebal 15 cm F-01 83,199.82
2 Membuat 1 m2 Plesteran 1 PC : 2 PS, tebal 15 mm F-02 73,143.27
3 Membuat 1 m2 Plesteran 1 PC : 3 PS, tebal 15 mm F-03 68,884.47
4 Membuat 1 m2 Plesteran 1 PC : 4 PS, tebal 15 mm F-04 65,901.24
5 Membuat 1 m2 Plesteran 1 PC : 5 PP, tebal 15 mm F-05 64,312.94
6 Membuat 1 m2 Plesteran 1PC : 6 PP, tebal 15 mm F-06 62,997.59
7 Membuat 1 m2 Plesteran 1 PC : 7 PP, tebal 15 mm F-07 62,307.68
8 Membuat 1 m2 Plesteran 1 PC : 8 PP, tebal 15 mm F-08 61,617.77
9 Membuat 1 m2 Plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm F-09 104,090.41
10 Membuat 1 m2 Plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm F-10 59,520.76
11 Membuat 1 m2 Plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm F-11 52,819.66
12 Membuat 1 m2 Plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm F-12 41,071.88
13 Membuat 1 m2 Plesteran 1 PC : 2 PP, tebal 20 mm F-13 97,962.18
14 Membuat 1 m2 Plesteran 1 PC : 3 PP, tebal 20 mm F-14 79,897.44
15 Membuat 1 m2 Plesteran 1 PC : 4 PP, tebal 20 mm F-15 88,188.64
16 Membuat 1 m2 Plesteran 1 PC : 5 PP, tebal 20 mm F-16 86,188.41
17 Membuat 1 m2 Plesteran 1 PC : 6 PP, tebal 20 mm F-17 84,317.10
18 Membuat 1 m2 Plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm F-18 74,909.64
19 Membuat 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm F-19 42,510.60
20 Membuat 1 m' Plesteran Skoning lebar 10 mm 1 PC : 2 PP F-20 158,987.09
21 Membuat 1 m2 Plesteran Granit, 1 PC : 2 Granit, tebal 10 mm F-21 158,987.09
22 Membuat 1 m2 Plesteran Teraso, 1 PC : 2 batu teraso, tebal 10 mm F-22 131,566.56
23 Membuat 1 m2 Plesteran ciprat/kamprotan, 1 PC : 2 PP F-23 49,375.10
24 Membuat 1 m2 Finishing siar pasangan dinding bata merah (=20 m') F-24 28,836.82
25 Membuat 1 m2 Finishing siar pasangan dinding conblock ekspose (= 8 m') F-25 13,858.02
26 Membuat 1 m2 Finishing siar pasangan dinding batu kali adukan 1 PC : 2 PP F-26 61,888.26
27 Membuat 1 m2 Acian F-27 20,981.26
28 Membuat 1 m2 Acian Semen Instan F-28 44,047.99
G. PEKERJAAN ATAP
1 1 M2 Pasang Atap Genteng Palentong G - 01. 69,311.54
2 1 M2 Pasang Genteng Bubung Palentong G - 02. 123,283.91
3 1 M2 Pasang Atap Genteng Murando Natural G - 03. 207,669.20
4 1 M2 Pasang Nok Genteng Murando natural G - 04. 95,676.78
5 1 M2 Pasang Atap Genteng Murando Glazur. G - 05. 223,276.94
6 1 M2 Pasang Nok Genteng Murando Glazur G - 06. 117,677.68
7 1 M' Pasang Nok Genteng tepi morando G - 07. 96,578.08
8 1 M2 Pasang Atap Genteng Metal G - 08. 132,884.06
9 1 M' Pasang Nok Genteng Metal G - 09. 124,340.73
10 1 M2 Pasang Atap Genteng spandek G - 10. 181,179.95
11 1 M' Pasang Nok Genteng spandek G - 11. 345,131.87
H. PEKERJAAN PLAFOND
1 1 M2 Plafond Asbes (1,00 x 1,00) m, tebal 4 mm H-01 49,051.26
2 1 M2 Plafond Asbes (1,00 x 1,00) m, tebal 3,5 mm H-02 41,485.15
3 1 M2 Plafond Triplek 4 mm + Rangka Kayu Kelas II H-03 183,383.79
4 1 M2 Plafond Gypsum Board, tebal 9 mm + Rangka Besi Hollow H-04 120,013.78
5 1 M2 Langit-langit GRC t = 4 mm + Rangka Besi Hollow H-05 113,317.77
6 1 M2 Langit-langit Gypsum t = 9 mm + Rangka Kayu Borneo Super H-06 186,691.33
7 1 M2 Langit-langit GRC t = 4 mm + Rangka Kayu H-07 182,128.51
8 1 M' List Plafond Kayu 1/4 Cm. 17,597.15
9 1 M' List Plafond Kayu Profil 4 cm H- 09 29,715.71
10 1 M' List Langit-langit Gypsum 10 cm H -10 30,519.61
11 1 M' Lisplang uk 2/10 + 2/15 cm, GRC tebal 8 mm. H -11 88,447.06
12 1 M2 Pasang kuda-kuda baja ringan (pabrikasi) 180,000.00
I. PEKERJAAN LANTAI
1 Memasang 1 M2 Lantai Keramik corak 20 x 20 cm setara Mulia I - 01 160,389.85
2 Memasang 1 M2 Lantai Keramik polos 30 x 30 cm setara Mulia I - 02 165,836.47
3 Memasang 1 M2 Lantai Keramik corak 30 x 30 cm setara Mulia I - 03 210,030.37
4 Memasang 1 M2 Lantai Keramik Corak 20 x 20 cm setara Roman I - 04 218,257.95
5 1 M' Plint Keramik ukuran (10 x 40) cm I - 05 20,654.86
6 1 M' Plint Keramik ukuran (10 x 30) cm I - 06 22,884.62
7 1 M' Plint Keramik ukuran (10 x 20) cm I - 07 32,322.56
8 Memasang 1 m' plint keramik ukuran (10 x 10) cm I - 08 23,021.46
9 Memasang 1 m' Plint keramik ukuran (5 x 20) cm I - 09 20,639.79
10 Memasang 1 m2 floor hardener I - 10 38,232.80
11 Memasang 1 M2 Paving Block Natural 8 cm I - 11 207,420.24
12 Memasang 1 M2 Paving Block Warna 8 cm I - 12 195,710.61
13 Memasang 1 M2 Paving Block Natural 6 cm I - 13 186,669.29
14 Memasang 1 M2 Paving Block Warna 6 cm I - 14 249,864.63
15 Memasang 1 M2 Glass Block 20 x 20 I - 15 702,883.04
16 Memasang 1 M2 Glass Block 30 x 30 I - 16 448,325.71
17 Pekerjaan bekisting untuk Lantai bahan Bondex I - 17 376,544.56
18 Lantai keramik polos 40x40 setara mulia l-38 178,347.05
J. PEKERJAAN KAYU
1 Memasang dan membuat 1 m3 Kusen Pintu & Jendela Kayu kelas 1 J-01 7,225,363.36
2 Membuat dan memasang 1 m3 Kusen Pintu & Jendela Kayu kelas II atau kelas III J-02 7,144,109.62
3 Membuat dan memasang 1 m2 pintu klamp standar, kayu kelas II J-03 284,256.84
4 Membuat dan memasang 1 m2 pintu klamp sederhana, kayu kelas III untuk gudang sementara J-04 284,256.84
5 Membuat dan memasang 1 m2 daun pintu panel, kayu kelas II J-05 598,538.29
6 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I atau II J-06 448,495.12
7 Membuat dan memasang 1 m2 pintu dan jendela jalusi kayu kelas I atau II J-07 674,584.55
8 Membuat dan memasang daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kelas II (lebar sampai 90 cm) J-08 438,297.63
9 Membuat 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II J-09 1,131,197.39
10 Memasang 1 m2 jalusi kusen, kayu kelas I atau II J-10 540,596.06
11 Memasang 1 m2 teakwood rangkap, rangka expose kayu kelas I J-11 645,331.99
12 Memasang 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II J-12 926,089.13
13 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter J-13 6,939,574.99
14 Memasang 1 m3 konstruksi kuda-kuda expose, kayu kelas I J-14 8,511,706.00
15 Memasang 1 m3 konstruksi, gording kayu kelas II J-15 6,170,947.18
16 Memasang 1 m2 rangka atap genteng keramik, kayu kelas II J-16 110,155.33
17 Memasang 1 m2 rangka atap genteng beton, kayu kelas II J-17 110,251.85
18 Memasang 1 m2 rangka atap sirap, kayu kelas II J-18 632,147.82
19 Memasang 1 m2 rangka plafond (50 x 100) cm, kayu kelas II atau kelas III J-19 156,617.99
20 Memasang 1 m2 rangka plafond (60 x 60), kayu kelas II atau kelas III J-20 156,564.93
21 Memasang 1 m' lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II J-21 68,947.88
22 Memasang 1 m' lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II J-22 68,549.86
23 Memasang 1 m2 rangka dinding pemisah ( 60 x 120) cm, kayu kelas II atau III J-23 172,574.38
24 Memasang 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II J-24 448,045.54
25 Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II J-25 470,308.50
26 Memasang 1 m2 dinding lambrizing dari papan kayu kelas I J-26 292,553.54
27 Memasang 1 m2 dinding lambrizing dari plywood ukuran (120 x 240) cm J-27 127,663.83
28 Memasang 1 m2 dinding bilik, rangka kayu kelas III atau IV J-28 145,732.59
K. PEKERJAAN BESI DAN ALUMINIUM
1 Memasang 1 Kg Besi Profil K-01 24,586.74
2 Memasang 1 Kg Rangka kuda-kuda baja WF K-02 31,566.46
3 Mengerjakan 100 kg pekerjaan perakitan K-03 88,352.81
4 Membuat 1 m2 Pintu besi plat tebal 2 mm rangkap rangka baja siku K-04 1,773,295.78
5 Mengerjakan 10 cm pengelasan dengan las listrik K-05 137,646.84
6 Membuat 1 m2 rangka jendela besi scuare tube (25 x 5) cm K-06 608,337.61
7 Memasang 1 m2 pintu rolling door besi K-07 967,377.55
8 Memasang 1 m2 pintu lipat (folding door) K-08 819,153.91
9 Memasang 1 m2 sunscreen alluminium K-09 738,628.49
10 Memasang 1 m2 rolling door alluminium K-10 760,959.77
11 Memasang 1 m' kusen pintu alluminium K-11 249,194.45
12 Memasang 1 m2 pintu alluminium strip lebar 8 cm K-12 2,238,585.52
13 Memasang 1 m2 pintu kaca rangka alluminium K-13 3,405,475.51
14 Memasang 1 m2 Tirai (Venetion blinds and vertikal blinds) K-14 663,353.87
15 Memasang 1 m2 terali besi strip (2 x 3) mm K-15 878,069.19
16 Memasang 1 m2 Kawat Harmonika K-16 166,884.70
17 1 M2 Jendela Nako & Teralis (10 Klips) K-17 906,615.71
18 Memasang 1 m'Talang datar / jurai seng BJLS 28 lebar 90 cm K-18 165,587.97
19 Memasang 1 m' talang 1/2 lingkaran D-15 cm, seng plat BJLS 30 lebar 45 cm K-19 124,539.47
20 Pemasangan 1 m2 Aluminium Composite Panel K-20 524,787.16
L. PEKERJAAN KACA DAN KUNCI
1 Pasang 1 buah kunci tanam antik L-01 254,938.47
2 Pasang 1 buah Kunci Tanam Biasa L-02 221,467.03
3 Pasang 1 buah Kunci Tanam Kamar Mandi L-03 107,443.05
4 Pasang 1 buah Engsel Pintu L-04 33,370.80
5 Pasang 1 buah Engsel Pintu Klaim L-05 71,050.44
6 Pasang 1 buah Kait Angin Pintu L-06 42,861.53
7 Pasang 1 buah Door Closer L-07 829,889.13
8 Pasang 1 buah Door Holder L-08 119,632.82
9 Pasang 1 buah Door Stoper L-09 122,700.78
10 Pasang 1 buah Gerendel L-10 130,621.35
11 Memasang 1 m2 kaca polos tebal 2 mm L-11 162,069.12
12 Memasang 1 m2 kaca polos tebal 3 mm L-12 162,069.12
13 Memasang 1 m2 kaca polos tebal 3 mm dengan kisi-kisi L-13 191,773.08
14 Memasang 1 m2 kaca raiben tebal 5 mm L-14 236,621.66
15 Memasang 1 m2 kaca raiben tebal 12 mm L-15 1,059,020.93
16 Memasang 1 m2 kaca es tebal 5 mm L-16 309,807.30
17 Memasang 1 m2 kaca lukis L-17 199,256.36
M. PEKERJAAN SANITASI
1 Memasang 1 buah closet duduk M-01 2,590,193.82
2 Memasang 1 buah closet jongkok M-02 612,668.26
3 Memasang 1 buah Urinoir M-03 4,565,498.25
4 Memasang 1 buah Wastafel M-04 1,645,334.26
5 1 Buah Shower Stand plus acessories M-05 779,233.71
6 Memasang 1 buah bak mandi bata merah volume 0,3 m3 M-06 1,741,957.68
7 1 M' Saluran Air Limbah Buis Beton d = 30 cm - 60 cm M-07 254,137.45
8 Memasang 1 m pipa penyalur air limbah jenis pipa tanah M-08 62,592.96
9 Memasang 1 m3 pipa beton M-09 114,322.91
10 1 Buah Bak Kontrol Pas Bata Merah Uk (60 x 60) cm M-10 882,480.74
11 1 Buah Bak Kontrol Pas Bata Merah Uk (30 x 30) cm M-11 605,767.50
12 1 M' Pipa PVC θ 1/2" (AW) M-12 85,748.25
13 1 M' Pipa PVC θ 1" (AW) M-13 108,952.14
14 1 M' Pipa PVC θ 1 1/2" (AW) M-14 176,914.72
15 1 M' Pipa PVC θ 2" (AW) M-15 229,239.89
16 1 M' Pipa PVC θ 4" (AW) M-16 84,711.02
17 1 M' Pipa PVC θ 3/4" (AW) M-17 29,696.58
18 1 Buah Bak Cuci Piring Stainless Steel M-18 704,127.27
19 1 Buah Kran θ 1/2" - 3/4" M-19 64,610.82
20 1 Buah Floor Drain M-20 100,013.55
21 1 M' Grafel Beton U 30cm - 60cm M-21 104,835.35
22 1 M' Pasang Talang Plastik PVC U 15 cm (AW) M-22 166,487.96
23 1 M' Saluran Air Limbah Buis Beton θ 60 cm M-23 389,086.63
24 1 Buah Tangki Air Fiberglass Volume 1 M3 M-24 847,464.35
25 1 Unit Septictank 2 x 1,50 x 1,50 m + Rembesan M-25 8,346,287.12
26 1 Unit Septictank 1 x 1,50 x 1,50 m + Rembesan M-26 4,006,361.94
27 Pekerjaan Septictank Komunal (Bio Fill 5000 kap 3,6 m3) M-27 12,883,797.29
N. PEKERJAAN PENGECATAN
1 Mengikis/Mengerok 1 m2 Perawatan Cat Tembok Lama N-01 14,326.21
2 Mendempul dan Menggosok 1 m2 Kayu N-02 12,656.08
3 Mengecat 1 m2 Bidang Kayu Lama N-03 45,448.23
4 Mengecat 1 m2 bidang kayu baru ( 1 lps plamir, 1 lps cat dasar, 2 lps cat penutup) N-04 51,712.28
5 Mengecat 1 m2 bidang kayu baru ( 1 lps plamir, 1 lps cat dasar, 3 lps cat penutup) N-05 69,352.42
6 Mengecat 1 m2 Tembok Lama (1 lps cat dasar, 2 lps cat penutup) N - 06 19,328.48
7 Mengecatan 1 m2 Plafond Vinilex (3x) N - 07 73,936.22
8 Mengecatan 1 m2 Plafond set Vinilex ( 2x) N - 08 49,290.81
9 Mengecat 1 m2 Tembok Baru Set Vinilex (1 lps plamir, 1 lps cat dasar,3 lps cat penutup) N - 09 39,334.32
10 Mengecat 1 m2 Tembok Baru Set Vinilex (1 lps plamir, 1 lps cat dasar,2 lps cat penutup) N - 09 29,266.31
11 Mengecatan 1 m2 Plafond (3x) luar 2 lantai / lebih N - 11 94,460.06
P. PEKERJAAN KUSEN ALUMUNIUM
1 1 UNIT Pasang partisi Alumunium, Daun partisi Multiplek rangka kayu klas II 2,530,202.90
2 1 UNIT Pek. Kusen Jendela Alumunium uk. 2 X 1,50 M' ( 3 lubang ) dgn 2 Daun Jendela 3,515,393.63
3 1 UNIT Pek. Kusen Pintu Jendela Alumunium uk. 2,2 X 2,70 M' ( 2 lb. Jendela + 1 lb. Pintu ) 4,372,057.82
4 1 UNIT Pekerjaan Kusen Pintu Alumunium uk. 0,8 X 2,70 M' 2,354,191.27
5 1 m2 Pintu pelat baja tebal 2mm rangkap, rangka baja siku 1,596,485.22
6 1 UNIT Pekerjaan Kusen Pintu Alumunium uk. 0,8 X 2,70 M' (daun pintu besi plat tbl 2 mm) 3,927,867.53
7 1 UNIT Pekerjaan Kusen Pintu Alumunium KM/WC Lapis Formika uk. 0,8 X 2,70 M' 2,598,774.46
8 1 UNIT Pek. Kusen Jendela Alumunium uk. 2,65 X 1,50 M' ( 4 lubang ) dgn 2 Daun Jendela 4,290,454.81
9 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk. 2,85 X 2,70 M' ( 3 lb. Jendela + 1 lb. Pintu ) 5,591,389.60
10 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,30 X 2,80 M' ( 2 Daun Pintu ) 3,301,916.56
11 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,50 X 2,70 M' ( 2 Daun Pintu ) 3,387,448.11
12 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk.1,55 X 2,70 M' ( 1 lb. Jendela + 1 lb. Pintu ) 3,237,990.31
13 1 UNIT Pekerjaan Jalusi Alumunium Sofi-sofi 1,592,806.26
14 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 1 lubang ) uk. 0,70 x 0,60 m 800,433.22
15 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 2 lubang ) uk. 1,35 x 0,60 m 933,853.94
16 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 3 lubang ) uk. 2,00 x 0,60 m 1,334,079.66
17 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 4 lubang ) uk. 2,65 x 0,60 m 1,734,305.38
18 1 UNIT Pek. Kusen Jendela Alm.uk. 2,65 X 1,50 M' ( 4 lubang ) dgn 2 Daun Jendela tampa BV 3,528,154.81
19 1 UNIT Pek. Kusen Pintu & Jendela Alm.1,55 X 2,70 M' ( 1 lb. Jendela + 1 lb. Pintu ) tampa BV 2,696,413.11
20 1 UNIT Pek. Kusen Jendela Alm.uk. 2,00 X 1,50 M' ( 3 lubang ) dgn 2 Daun Jendela tampa BV 3,156,465.23
21 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,50 X 2,00 M' ( 2 Daun Pintu )tampa BV 3,047,536.21
22 1 UNIT Pek. Kusen Pintu & Jendela Alum uk. 2,85 X 2,70 M' ( 3 lb. Jendela + 1 lb. Pintu ) tampa BV 4,384,315.91
23 1 UNIT Pek. Kusen Pintu & Jendela Alm.3,1 X 2,70 M' ( 2 lb. Jendela + 2 lb. Pintu ) 5,848,689.18
24 1 UNIT Pek. Kusen Pintu Jendela Alumunium uk. 2,2 X 2,70 M' ( 2 lb. Jendela + 1 lb. Pintu ) 3,666,930.32
C. HARGA SATUAN DASAR BAHAN DAN MATERIAL
HARGA
NO BAHAN / MATERIAL SPESIFIKASI BAHAN SAT SATUAN HARGA
KONTRAKTUAL
10 x 20 dan 20 x 20 KW 1 DN Putih/polos
23 Keramik buah 2,822.00 3,104.20
Roman
10 x 20 KW 1 DN Corak/Warna/Anti Slip
24 Keramik buah 3,259.41 3,585.35
Roman
O. BAHAN ELEKTRIKAL
1 Kabel NYA 1 x 1.5 Prima ( 1 rol = 50 m' ) ROLL 158,361.23 174,197.36
2 Kabel NYA 1 x 2.5 Prima ( 1 ml = 50 m' ) ROLL 241,995.91 266,195.50
3 Kabel NYM 2 x 1.5 Prima ( 1 ml = 50 m' ) m' 7,574.72 8,332.19
4 Kabel NYM 3 x 1.5 Prima ( 1 rol = 50 m' ) m' 9,563.76 10,520.13
5 Kabel NYM 2 x 2.5 Prima ( 1 ml = 50 m' ) m' 12,552.73 13,808.00
6 Kabel NYM 3 x 2.5 Prima ( 1 rol = 50 m' ) m' 15,488.55 17,037.40
7 Kabel NYM 4 x 2.5 Prima ( 1 ml = 50 m' ) m' 8,978.19 9,876.01
8 Kabel NYM 2 x 4 Prima ( 1 rol = 50 m' ) m' 7,553.08 8,308.39
9 Kabel NYM 3 x 4 Prima ( 1 rol = 50 m' ) m' 18,832.15 20,715.36
10 Kabel NYM 4 x 4 Prima ( 1 rol = 50 m' ) m' 25,413.99 27,955.39
11 Kabel NYM 2 x 6 Supreme ( 1 rol = 50 m' ) m' 13,538.55 14,892.40
12 Kabel NYM 3 x 6 Supreme ( 1 rol = 50 m' ) m' 17,813.88 19,595.26
13 Kabel NYM 4 x 6 Supreme ( 1 ml = 50 m' ) m' 29,317.76 32,249.53
14 Kabel NYM 2 x 10 Supreme (1 rol = 50 m') m' 22,374.23 24,611.65
15 Kabel NYM 3 x 10 Supreme (1 rol = 50 m') m' 29,642.29 32,606.52
16 Kabel NYM 4 x 10 Supreme (1 rol = 50 m') m' 32,635.02 35,898.52
17 Kabel NYM 4 x 16 Supreme (1 rol = 50 m') m' 44,605.94 49,066.54
18 Kabel NYY 2 x 4 Supreme ( 1 rol = 50 m' ) m' 13,538.55 14,892.40
19 Kabel NYY 3 x 4 Supreme ( 1 rol = 50 m' ) m' 20,624.12 22,686.53
20 Kabel NYY 4 x 4 Supreme ( 1 ml = 50 m' ) m' 30,438.09 33,481.90
21 Kabel NYY 2 x 6 Supreme ( 1 rol = 50 m' ) m' 13,396.03 14,735.64
22 Kabel NYY 3 x 6 Supreme ( 1 rol = 50 m' ) m' 26,580.42 29,238.46
23 Kabel NYY 4 x 6 Supreme ( 1 rol = 50 m' ) m' 27,647.13 30,411.85
24 Kabel NYY 2 x 10 Supreme ( 1 rol = 50 m') m' 23,799.34 26,179.27
25 Kabel NYY 3 x 10 Supreme ( 1 rol = 50 m') m' 32,492.51 35,741.76
26 Kabel NYY 4 x 10 Supreme ( 1 rol = 50 m') m' 50,119.66 55,131.63
27 Kabel NYY 4 x 16 Supreme ( 1 rol = 50 m') m' 63,559.91 69,915.90
28 NSFB FUJI EA - 100 A bh 1,254,096.80 1,379,506.48
29 NSFB FUJI EA - 150 A bh 2,565,198.00 2,821,717.80
30 Rumah Panel 30 x 60 cm ( Kosong ) unt 213,766.50 235,143.15
31 Skring Kas 2 grop Biasa unt 267,337.47 294,071.21
32 Skring Kas 3 grop Biasa unt 327,380.22 360,118.24
33 Skring Kas 5 grop Biasa unt 672,134.55 739,348.01
34 MCB 1 PAS bh 78,943.97 86,838.37
35 MCB 3 PAS bh 96,311.64 105,942.80
36 Tahanan 50 A Merk Fuji bh 766,709.18 843,380.10
37 Saklar Broko Tunggal Standard ( 1 Phase ) bh 29,524.52 50,191.68
38 Saklar Broko Seri Standard ( 1 Phase ) bh 32,692.70 55,577.59
39 Stop Kontak Broko Standard ( 1 Phase ) bh 32,369.63 55,028.37
40 Stop Kontak Broko 3 Phase (Out Bow) bh 121,134.35 133,247.79
41 Stop Kontak Broko 3 Phase ( In Bow) bh 205,215.84 225,737.42
42 Stop Kontak Handle 3 Phase bh 119,709.24 131,680.16
43 Instalasi Titik Lampu / Stop Kontak (Upah dan Alat) ttk 179,600.00 197,560.00
44 Lampu pijar 25 Watt s/d 100 Watt bh 13,519.73 14,871.70
45 Lampu Neon Phillips 20 Watt bh 45,246.07 49,770.67
46 Lampu Neon Phillips 40 Watt bh 62,272.13 68,499.35
47 Trapo TL 20 W (Phillips) bh 67,692.73 74,462.00
48 Trapo TL 40 W (Phillips) bh 71,255.50 78,381.05
49 Trapo TL 20 W (Sinar) bh 35,627.75 39,190.53
50 Trapo TL 40 W (sinar) bh 42,753.30 47,028.63
51 Stater Neon Phillips bh 7,125.55 7,838.11
52 Stater Neon Biasa bh 4,987.89 5,486.67
53 Rumah TL In Bow / Out Bow 2 x 20 W (kosongan Sonora) bh 178,138.75 195,952.63
54 Down Light + SL 18 W bh 234,500.00 257,950.00
55 Lampu SL Philip 18 W bh 38,500.00 42,350.00
56 Lampu TL 20 W Lengkap bh 71,500.00 78,650.00
57 Lampu Mercuri 80 W bh 171,746.92 188,921.61
58 Lampu Taman + Tiang + Lampu 1 Buah bh 541,541.80 595,695.98
59 Lampu Baret 30 cm + Neon bh 315,775.87 347,353.46
60 Lampu Neon Arcrilik 2 x 40 W Lengkap bh 1,054,581.40 1,160,039.54
61 Jarum Penangkal Petir 16 bh 149,993.54 164,992.89
62 Kawat BC ( Tembaga ) kg 63,155.17 69,470.69
63 Pentanahan Penangkal Petir ttk 663,129.33 729,442.26
64 Pentanahan Panel ttk 256,519.80 282,171.78
65 Balk TL 1 x 18 W bh 1,061,372.54 1,167,509.80
66 Balk TL 1 x 36 W bh 1,116,999.81 1,228,699.79
67 TKO TL 1 x 18 W bh 43,360.03 47,696.03
68 TKO TL 2 x 18 W bh 58,866.92 64,753.61
69 TKO TL 1 x 36 W bh 91,698.07 100,867.87
70 TKO TL 2 x 36 W bh 115,491.76 127,040.94
71 Kabel NYGBY ml 155,147.92 170,662.71
72 Panel ACB 4 Pase ACB Ml0H1 4P Jenis Tarik 1000 A Tanpa Unit Trip MG bh 31,393,254.34 34,532,579.77
73 Panel ACB 4 Pase ACB Ml0H1 4P Jenis Tetap 1000 A Tanpa Unit Trip MG bh 31,238,580.52 34,362,438.57
74 Panel ACB 4 Pase ACB Ml0H1 4P Jenis Tetap 1250 A Tanpa Unit Trip MG bh 31,038,670.04 34,142,537.04
75 Panel ACB 4 Pase ACB Ml0H1 4P Jenis Tetap 1250 A Tanpa Unit Trip MG bh 32,030,419.61 35,233,461.57
76 Panel ACB 4 Pase ACB Ml0H1 4P Jenis Tetap 2500 A Tanpa Unit Trip MG bh 55,250,752.76 60,775,828.04
77 Panel ACB 4 Pase ACB Ml0H1 4P Jenis Tetap 2500 A Tanpa Unit Trip MG bh 56,244,971.58 61,869,468.74
78 Panel ACB 4 Pase ACB Ml0H1 4P Jenis Tetap 1000 A Tanpa Unit Trip MG bh 31,474,344.51 34,621,778.96
79 Panel ACB 4 Pase ACB Ml0H1 4P Jenis Tetap 3200 A Tanpa Unit Trip MG bh 60,870,271.91 66,957,299.10
80 Panel MCCB 3 Pase MCCB 125 - 160 A, 36 KA (NS160N) MG bh 4,392,795.75 4,832,075.33
81 Panel MCCB 3 Pase MCCB 50 - 63 A, 25 KA (NS100N) MG bh 4,334,422.68 4,767,864.95
82 . Panel MCCB 3 Pase MCCB 40 - 50 A, 25 KA (NS100N) MG bh 1,088,149.09 1,196,964.00
83 Panel MCCB 3 Pase MCCB 32 - 50 A, 25 KA (NS100N) MG bh 790,160.00 869,176.00
84 Panel MCCB 3 Pase MCCB 32 - 50 A, 10 KA (NC45H) MG bh 6,026,254.01 6,628,879.41
85 Panel MCCB 3 Pase MCCB 20 - 10 A, 10 KA (NC45H) MG bh 3,970,060.15 4,367,066.17
86 Panel MCCB 3 Pase MCCB 160 - 200 A, 36 KA (NS250N) MG bh 3,997,616.98 4,397,378.68
87 Panel MCCB 3 Pase MCCB 80 - 100 A, 26 KA (NS100) MG bh 2,477,250.37 2,724,975.41
88 Panel MCCB 3 Pase MCCB 20 - 25 A, KA (NS100) MG bh 397,549.25 437,304.18
89 Panel MCCB 3 Pase MCCB 13 - 16 A, KA (NS100) MG bh 405,036.02 445,539.62
90 Panel MCCB 3 Pase MCCB 16 A, 5 KA (NC45a) MG bh 344,628.28 379,091.11
91 Panel MCCB 3 Pase MCCB 10 A, 5 KA (NC45a) MG bh 319,313.53 351,244.89
92 Panel MCCB 3 Pase MCCB 6 A, 5 KA (NC45a) MG bh 159,602.44 175,562.69
93 Panel MCCB 3 Pase MCCB 25 A, 25 KA (NS100N) MG bh 87,608.99 96,369.89
94 Panel MCCB 3 Pase MCCB 16 A, 5 KA (NS100N) MG bh 3,761,260.37 4,137,386.41
95 Panel MCCB 3 Pase MCCB 32 A, 25 KA MG bh 3,801,558.53 4,181,714.38
96 Panel MCCB 3 Pase MCCB 80 - 100 A, 25 KA (NS100) MG bh 585,212.25 643,733.48
97 Panel MCCB 3 Pase MCCB 50 - 63 A,(NS100) MG bh 549,101.94 604,012.13
98 Panel MCCB 3 Pase MCCB 350 - 500 A / 70 KA / 3 Pole NS630 bN/H/L bh 583,651.68 642,016.85
99 Panel MCCB 3 Pase MCCB 224 - 320 A / 70 KA / 3 Pole NS400 bN/H/L bh 560,944.46 617,038.91
100 Panel MCCB 3 Pase MCCB 175 -.250 A / 70 KA / 3 Pole NS250 bN/H/L bh 564,964.40 621,460.84
101 Panel MCCB 3 Pase MCCB 160 - 300 A / 70 KA / 3 Pole NS400 bN/H/L bh 569,201.63 626,121.80
102 Panel MCCB 3 Pase MCCB 64 - 80 A / 70 KA / 3 Pole NS100 bN/H/L bh 549,753.82 604,729.20
103 Panel MCCB 3 Pase MCCB 44 - 63 A / 70 KA / 3 Pole NS100 bN/H/L bh 639,170.30 703,087.33
104 Panel MCCB 3 Pase MCCB 32 - 40 A / 70 KA / 3 Pole NS100 bN/H/L bh 651,990.65 717,189.71
105 Panel MCCB 3 Pase Contraktor 400 A / 3 Pole LCI - F3304 bh 1,648,718.23 1,813,590.05
106 Panel MCCB 3 Pase Contraktor 250 A / 3 Pole LCI - F1504 bh 2,485,082.83 2,733,591.11
107 Panel MCCB 3 Pase Contraktor 200 A / 3 Pole LCI - F1154 bh 560,025.90 616,028.49
108 Panel MCCB 3 Pase Contraktor 160 A / 3 Pole LCI - F1154 bh 571,048.63 628,153.50
109 Panel MCB 3 Pase MCB 16 A, 5 KA (NC45a) MG bh 401,993.90 442,193.29
110 Panel MCB 3 Pase MCB 10 A, 5 KA (NC45a) MG bh 396,452.90 436,098.19
111 Panel MCB 3 Pase MCB 6 A, 5 KA (NC45a) MG bh 260,329.50 286,362.45
112 Panel MCB 3 Pase MCB 10 A, 6 KA, 10 A, 6 K MG bh 260,329.50 286,362.45
113 Panel MCB 3 Pase MCB 50 A, 10 A (NC100H) MG bh 591,209.00 650,329.90
114 Panel MCB 3 Pase MCB 16 A, 6 KA (NC45aD) MG bh 260,329.50 286,362.45
115 Panel MCB 3 Pase MCB 6 A, 6 KA (NC45aD) MG bh 311,831.00 343,014.10
116 Panel MCB 3 Pase MCB 63 A, 10 KA (NC100H) MG bh 591,209.00 650,329.90
117 Panel MCB 3 Pase MCB 32 A, 10 KA (NC100H) MG bh 302,659.50 332,925.45
118 Panel MCB 3 Pase MCB 16 A, 8 KA (NC10014) MG bh 301,650.64 331,815.70
119 Panel MCB 3 Pase MCB 16 A, 5 KA (NC45N) MG bh 302,038.66 332,242.53
120 Panel MCB 3 Pase MCB 16 A, 10 KA (NC100H) MG bh 301,340.22 331,474.24
121 Panel MCB 3 Pase MCB 25 A, 8 KA (NC45N) MG bh 285,353.59 313,888.94
122 Panel MCB 3 Pase MCB 40 A, 8 KA L (NC45N) MG bh 262,149.69 288,364.66
123 Panel MCB 3 Pase MCB 10 A, 8 KA (NC45N) MG bh 283,491.07 311,840.17
124 Panel MCB 1 Pase MCB 20 A, 10 KA (NC45N) MG bh 130,609.22 143,670.14
125 Panel MCB 1 Pase MCB 10 A, 8 KA (NC45N) MG bh 62,860.05 69,146.06
126 Panel MCB 1 Pase MCB 6 A, 8 KA (NC45N) MG bh 55,029.00 60,531.90
127 Panel MCB 1 Pase MCB 20 A, 8 KA (NC45N) MG bh 55,029.00 60,531.90
128 Panel MCB 1 Pase MCB 20 A, 5 KA (NC45Na) MG bh 62,860.05 69,146.06
129 Panel MCB 1 Pase MCB 10 A, 5 KA (NC45Na) MG bh 64,955.39 71,450.92
130 Panel MCB 1 Pase MCB 6 A, 5 KA (NC45Na) MG bh 65,809.04 72,389.94
131 Panel MCB 1 Pase MCB 25 A, 5 KA (NC45Na) MG bh 71,862.23 79,048.45
132 Panel MCB 1 Pase MCB 16 A, 5 KA (NC45Na) MG bh 65,653.83 72,219.21
133 Panel MCB 1 Pase MCB 16 A, 5 KA (NC45N) MG bh 65,110.60 71,621.65
134 Panel MCB 1 Pase MCB 6 A, 6 KA (NC45aD) MG bh 65,809.04 72,389.94
135 Panel MCB 1 Pase MCB 20 A, 8 KA (NC45N) MG bh 65,809.04 72,389.94
136 Panel MCB 1 Pase MCB 10 A, 8 KA (NC45N) MG bh 65,809.04 72,389.94
137 Panel MCB 1 Pase MCB 16 A, 5 KA (NC45N) MG bh 65,809.04 72,389.94
138 Panel MCB 1 Pase MCB 6 A, 5 KA (NC45N) MG bh 158,857.44 174,743.18
139 Panel MCB 1 Pase MCB 25 A, 5 KA (NC45N) MG bh 156,529.29 172,182.21
140 Panel MCB 1 Pase MCB 50 A, 10 KA (NC100H) MG bh 656,383.09 722,021.40
P. BAHAN ALAT PENGANTUNG DAN KUNCI
1 Kunci Silinder ALFA untuk Pintu Alumunium bh 451,131.98 496,245.17
2 Tarikan Pintu Alumunium bh 460,973.70 507,071.07
3 Kunci 2 Slaag ROYAL bh 184,666.98 203,133.67
4 Rel Henderson Lengkap bh 1,198,722.11 1,318,594.32
5 Rel maraton I Pintu unt 257,789.70 283,568.67
6 Kunci 2 Slaag Silinder SEIS Asli Tipe 210 s/d type 226 bh 408,366.92 449,203.61
7 Kunci 2 Slaag Ancor Asli bh 198,433.63 218,277.00
8 Kunci 2 Slaag ISO bh 260,654.03 286,719.43
9 Kunci KM Bulat Kualitas Biasa bh 94,687.51 104,156.26
10 Kunci kM Bulat ALFA bh 78,769.08 86,645.98
11 Kunci 2 Slaag Silinder Utama Standard bh 771,936.94 849,130.63
12 Kunci Gembok Besar bh 93,586.93 102,945.62
13 Kunci 2 Slaag Kuda Terbang bh 131,695.74 144,865.31
14 Kunci Lemari bh 113,613.72 124,975.09
15 Espangolet ps 67,141.45 73,855.60
16 Espangolet St. Steel bh 533,358.00 586,693.80
17 Casement ps 766,426.98 843,069.68
18 Grendel 15 cm bh 47,058.94 51,764.83
19 Grendel 5 cm bh 14,486.09 15,934.70
20 Grendel 7 cm bh 98,015.58 107,817.14
21 Hak Angin Kait Jendela Biasa ps 25,246.44 27,771.08
22 Hak Angin Jendela Antik ps 36,449.71 40,094.68
23 Hak Angin Sendok Stainless / Kuningan bh 43,693.97 48,063.36
24 Sloot Pintu Berikut Rantai bh 34,549.75 38,004.72
25 Sloot Jendela Tunggal bh 34,283.57 37,711.93
26 Sloot Handle Jendela bh 27,203.62 29,923.98
27 Engsel Pintu Union Standard ps 16,618.50 18,280.35
28 Engsel Jendela Unilon ps 38,776.50 42,654.15
29 Engsel Patrun ps 14,251.10 15,676.21
30 Engsel Harmonika ps 20,142.03 22,156.23
31 Floor Hinge ps 3,259,410.00 3,585,351.00
32 Door Closer Kelas Standard ( Kelas Sedang ) unt 715,967.08 787,563.79
33 Door Closer Kelas Standard ( Kelas Balk) unt 748,795.27 823,674.80
34 Door Closer Kelas Rendah unt 293,890.42 323,279.46
35 Door Holder unt 97,827.57 107,610.33
36 Door Stoper unt 97,827.57 107,610.33
37 Tarikan Almari Rata-rata bh 23,709.24 26,080.16
38 Rambuncis bh 559,720.55 615,692.61
39 Seng BJLS 30 Lebar 60 cm ( 1 rol 50 m' ) ml 136,499.59 150,149.55
40 Seng BJLS 30 Lebar 90 cm ( 1 rol 50 m' ) ml 136,499.59 150,149.55
41 Seng BJLS 30 / 3 x 0.3 mm lbr 114,351.51 125,786.66
42 Seng Plat lbr 77,277.55 85,005.31
43 Waterstop Lebar 200 mm ml 78,721.99 86,594.19
44 Kunci Tanam biasa buah 146,685.96 161,354.56
45 Kunci Tanam antik buah 166,185.00 182,803.50
46 Kunci Tanam Kamar Mandi buah 70,351.65 77,386.82
Keterangan :
Untuk harga material di atas sudah termasuk keuntungan dan ketentuan pajak yang berlaku.
STANDAR HARGA SATUAN
A. HARGA SATUAN UPAH
Persiapan - Hal 47
A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN
Persiapan - Hal 48
A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN
Persiapan - Hal 49
A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN
A-13 1 M' Pagar Kawat Ayam Tiang Besi L50.50.5, tinggi 1 m'
Kawat Ram Ayam Lbr 0.4340 22,117.43 9,598.96
Besi Siku L50.50.5 Kg 6.0660 52,800.00 320,284.80
Besi Pelat (1,2 x 3) mm Kg 0.0424 21,729.40 921.33
Baut bh 4.0000 1,164.08 4,656.30
Semen Portland kg 2.5000 2,171.71 5,429.26
Pasir Beton M3 0.0050 395,501.47 1,977.51
Koral Beton M3 0.0090 263,667.65 2,373.01
Pekerja Oh 0.3750 78,177.92 29,316.72
Tukang Batu Oh 0.1250 107,758.75 13,469.84
Kepala Tukang Oh 0.0120 124,662.08 1,495.94
Mandor Oh 0.0190 160,159.08 3,043.02
Jumlah 392,566.70
A-14 1 M2 Pagar BRC lengkap dengan tiang
BRC lengkap dengan tiang Lbr 0.4340 214,946.45 93,286.76
Semen Portland kg 2.0000 2,171.71 4,343.41
Kawat duri Kg 2.2000 62,764.36 138,081.59
Pasir Beton M3 0.0050 395,501.47 1,977.51
Koral Beton M3 0.0090 263,667.65 2,373.01
Pekerja Oh 0.3750 78,177.92 29,316.72
Tukang Batu Oh 0.1250 107,758.75 13,469.84
Kepala Tukang Oh 0.0120 124,662.08 1,495.94
Mandor Oh 0.0190 160,159.08 3,043.02
Jumlah 287,387.81
A-15 1 M2 Steiger Werk/Perancah dari Bambu
Bambu θ 6-10 (600) cm Btg 1.0000 22,000.00 22,000.00
Tali Ijuk Kg 0.2500 23,281.50 5,820.38
Pekerja Oh 0.0170 78,177.92 1,329.02
Tukang Kayu Oh 0.0250 105,890.40 2,647.26
Kepala Tukang Oh 0.0020 124,662.08 249.32
Mandor Oh 0.0130 160,159.08 2,082.07
Jumlah 34,128.05
A -16 1 M' Cerucuk Bambu
Bambu θ 7-10 (400) cm Btg 1.1500 22,000.00 25,300.00
Pekerja Oh 0.5000 78,177.92 39,088.96
Mandor Oh 0.0250 160,159.08 4,003.98
Jumlah 68,392.94
A-17 Pasang 1 m' Pagar Kawat Jaring Galvanis, Tinggi 1 meter
Pagar Kawat Jaring lbr 0.434 110,548.32 47,977.97
Pekerja Oh 0.042 70,593.60 2,964.93
Persiapan - Hal 50
A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN
Persiapan - Hal 51
A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN
Persiapan - Hal 52
B. ANALISA HARGA SATUAN PEKERJAAN TANAH
Pondasi - Hal 55
C. ANALISA HARGA SATUAN PEKERJAAN PONDASI
Pondasi - Hal 56
C. ANALISA HARGA SATUAN PEKERJAAN PONDASI
Pondasi - Hal 57
C. ANALISA HARGA SATUAN PEKERJAAN PONDASI
Pondasi - Hal 58
C. ANALISA HARGA SATUAN PEKERJAAN PONDASI
Pondasi - Hal 59
C. ANALISA HARGA SATUAN PEKERJAAN PONDASI
Pondasi - Hal 60
D. ANALISA HARGA SATUAN PEKERJAAN BETON
HIT-12 Membuat 1 m3 Balok beton bertulang 30 x 60 cm, 10 dia.16, 8-15 (125 kg besi + bek)
Bekisting 1x Pakai m2 8.3333 380,588.20 3,171,568.32
Besi U.24 rata-rata Kg 125.0000 12,980.82 1,622,603.11
Membuat 1 m3 beton mutu (K225) m3 1.0000 1,383,982.17 1,383,982.17
JUMLAH 6,178,153.60
HIT-13 Membuat 1 m3 Plat lantai beton tbl. 12 cm' besi dia. 8 mm (110 kg besi + bekisting)
Bekisting 1x Pakai m2 8.3333 478,692.74 3,989,090.23
Besi U.24 rata-rata Kg 110.0000 12,980.82 1,427,890.74
Plesteran - Hal 85
F. ANALISA HARGA SATUAN PEKERJAAN PLESTERAN
Plesteran - Hal 86
F. ANALISA HARGA SATUAN PEKERJAAN PLESTERAN
Plesteran - Hal 88
G. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP
Plafond - Hal 91
H. ANALISA HARGA SATUAN PEKERJAAN PLAFOND
Plafond - Hal 92
I. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI
Lantai - Hal 93
HARGA 2016.
No URAIAN SATUAN VOLUME
SATUAN JUMLAH
I - 05 1 M' Plint Keramik ukuran (10 x 40) cm
Plint Keramik buah 2.6500 3,439.14 9,113.73
Semen Portland kg 0.0200 2,171.71 43.43
Pasir Pasang M3 0.0030 352,512.17 1,057.54
semen Warna kg 0.1000 16,622.53 1,662.25
Pekerja Oh 0.0600 78,177.92 4,690.68
Tukang batu Oh 0.0300 107,758.75 3,232.76
Kepala Tukang Oh 0.0030 124,662.08 373.99
Mandor Oh 0.0030 160,159.08 480.48
Jumlah 20,654.86
I - 06 1 M' Plint Keramik ukuran (10 x 30) cm
Plint Keramik (10 x 30) cm buah 4.3000 1,833.33 7,883.33
Semen Portland zak 0.0500 2,171.71 108.59
Pasir Pasang M3 0.0032 352,512.17 1,128.04
semen Warna Kg 0.3000 16,622.53 4,986.76
Pekerja Oh 0.0600 78,177.92 4,690.68
Tukang batu Oh 0.0300 107,758.75 3,232.76
Kepala Tukang Oh 0.0030 124,662.08 373.99
Mandor Oh 0.0030 160,159.08 480.48
Jumlah 22,884.62
I - 07 1 M' Plint Keramik ukuran (10 x 20) cm
Plint Keramik buah 5.3000 1,833.33 9,716.67
Semen Portland kg 1.1400 2,171.71 2,475.74
Pasir Pasang m3 0.0030 352,512.17 1,057.54
semen Warna Kg 0.0250 16,622.53 415.56
Pekerja Oh 0.0900 78,177.92 7,036.01
Tukang batu Oh 0.0900 107,758.75 9,698.29
Kepala Tukang Oh 0.0090 124,662.08 1,121.96
Mandor Oh 0.0050 160,159.08 800.80
Jumlah 32,322.56
I - 08 Memasang 1 m' plint keramik ukuran (10 x 10) cm
Plint keramik artistik buah 10.6000 -
Semen Portland kg 1.1400 2,171.71 2,475.74
Pasir Pasang m3 0.0030 352,512.17 1,057.54
semen Warna Kg 0.0500 16,622.53 831.13
Pekerja Oh 0.0900 78,177.92 7,036.01
Tukang batu Oh 0.0900 107,758.75 9,698.29
Kepala Tukang Oh 0.0090 124,662.08 1,121.96
Mandor Oh 0.0050 160,159.08 800.80
Jumlah 23,021.46
I - 09 Memasang 1 m' Plint keramik ukuran (5 x 20) cm
Plint keramik buah 5.3000 -
Semen Portland kg 0.5700 2,171.71 1,237.87
Pasir Pasang m3 0.0015 352,512.17 528.77
semen Warna kg 0.0130 16,622.53 216.09
Pekerja Oh 0.0900 78,177.92 7,036.01
Tukang batu Oh 0.0900 107,758.75 9,698.29
Kepala Tukang Oh 0.0090 124,662.08 1,121.96
Mandor Oh 0.0050 160,159.08 800.80
Jumlah 20,639.79
Lantai - Hal 94
HARGA 2016.
No URAIAN SATUAN VOLUME
SATUAN JUMLAH
I - 10 Memasang 1 m2 floor hardener
Floor hardener kg 5.0000 -
Pekerja Oh 0.1200 78,177.92 9,381.35
Tukang Batu Oh 0.1200 107,758.75 12,931.05
Kepala Tukang Oh 0.1200 124,662.08 14,959.45
Mandor Oh 0.0060 160,159.08 960.95
Jumlah 38,232.80
I - 11 Memasang 1 M2 Paving Block Natural 8 cm
Paving block natural M2 1.0100 94,681.80 95,628.62
Pasir pasang Kg 0.1000 352,512.17 35,251.22
Pekerja Oh 0.2500 78,177.92 19,544.48
Tukang Batu Oh 0.5000 107,758.75 53,879.37
Kepala Tukang Oh 0.0250 124,662.08 3,116.55
Mandor Oh 0.0025 160,159.08 400.40
Jumlah 207,420.24
I - 12 Memasang 1 M2 Paving Block Warna 8 cm
Paving block warna M2 1.0100 83,088.11 83,918.99
Pasir pasang Kg 0.1000 352,512.17 35,251.22
Pekerja Oh 0.2500 78,177.92 19,544.48
Tukang Batu Oh 0.5000 107,758.75 53,879.37
Kepala Tukang Oh 0.0250 124,662.08 3,116.55
Mandor Oh 0.0025 160,159.08 400.40
Jumlah 195,710.61
I - 13 Memasang 1 M2 Paving Block Natural 6 cm
Paving block natural M2 1.0100 74,136.30 74,877.66
Pasir pasang Kg 0.1000 352,512.17 35,251.22
Pekerja Oh 0.2500 78,177.92 19,544.48
Tukang Batu Oh 0.5000 107,758.75 53,879.37
Kepala Tukang Oh 0.0250 124,662.08 3,116.55
Mandor Oh 0.0025 160,159.08 400.40
Jumlah 186,669.29
I - 14 Memasang 1 M2 Paving Block Warna 6 cm
Paving block warna M2 1.0100 136,705.94 138,073.00
Pasir pasang Kg 0.1000 352,512.17 35,251.22
Pekerja Oh 0.2500 78,177.92 19,544.48
Tukang Batu Oh 0.5000 107,758.75 53,879.37
Kepala Tukang Oh 0.0250 124,662.08 3,116.55
Mandor Oh 0.0025 160,159.08 400.40
249,864.63
I - 15 Memasang 1 M2 Glass Block 20 x 20
Grass block buah 25.0000 23,643.66 591,091.42
Pasir pasang Kg 0.1000 352,512.17 35,251.22
Pekerja Oh 0.2500 78,177.92 19,544.48
Tukang Batu Oh 0.5000 107,758.75 53,879.37
Kepala Tukang Oh 0.0250 124,662.08 3,116.55
Mandor Oh 0.0025 160,159.08 400.40
Jumlah 702,883.04
Lantai - Hal 95
HARGA 2016.
No URAIAN SATUAN VOLUME
SATUAN JUMLAH
I - 16 Memasang 1 M2 Glass Block 30 x 30
Grass block buah 12.2500 27,472.17 336,534.08
Pasir pasang Kg 0.1000 352,512.17 35,251.22
Pekerja Oh 0.2500 78,177.92 19,544.48
Tukang Batu Oh 0.5000 107,758.75 53,879.37
Kepala Tukang Oh 0.0250 124,662.08 3,116.55
Mandor Oh 0.0025 160,159.08 400.40
Jumlah 448,325.71
I - 17 Pekerjaan bekisting untuk Lantai bahan Bondex
Plat bondex m2 1.0300 154,000.00 158,620.00
Kayu Kelas II m3 0.0400 3,168,594.00 126,743.76
Paku 5 - 12 cm kg 0.1000 20,634.86 2,063.49
Minyak Bekisting liter 0.0500 55,686.14 2,784.31
Multiplek tebal 9 mm Lbr 0.0900 237,300.88 21,357.08
Dolken kayu galam (8-10) cm, pjng 4 m btg 1.5000 26,811.18 40,216.77
Pekerja Oh 0.1700 78,177.92 13,290.25
Tukang kayu Oh 0.0800 107,758.75 8,620.70
Kepala Tukang Oh 0.0100 124,662.08 1,246.62
Mandor Oh 0.0100 160,159.08 1,601.59
JUMLAH 376,544.56
I - 18 Memasang 1 M2 Lantai keramik setara mulia ukuran 40 x 40 cm
keramik 40 x 40 cm buah 6.6300 12,500.00 82,875.00
Semen Portland kg 9.8000 2,171.71 21,282.71
Pasir Pasang M3 0.0450 352,512.17 15,863.05
Semen Warna Kg 1.3000 16,622.53 21,609.29
Pekerja Oh 0.2500 78,177.92 19,544.48
Tukang Batu Oh 0.1250 107,758.75 13,469.84
Kepala Tukang Oh 0.0130 124,662.08 1,620.61
Mandor Oh 0.0130 160,159.08 2,082.07
JUMLAH 178,347.05
I - 19 Memasang 1 M2 Lantai Geranit ukuran 60 x 60 cm
Geranit 60 x 60 cm m2 1.0000 420,000.00 420,000.00
Lantai - Hal 96
J. ANALISA HARGA SATUAN PEKERJAAN KAYU
Aluminium composite panel type PVDF 0.3 warna silver m2 1.0000 495,000.00 495,000.00
1 1 UNIT Pasang partisi Alumunium, Daun partisi Multiplek rangka kayu klas II
Bahan 7.6200 m' Kusen Alumunium Natural Uk 4" + upah 20% 181,500.00 1,383,030.00
1.3500 lbr Multiplek 9 mm 237,300.88 320,356.18
0.0300 m3 Kayu papan Kelas II 3,168,594.00 95,057.82
11.7000 m' List kayu profil 1 cm 14,444.40 168,999.44
0.1000 kg Paku biasa ½" - 1" 26,653.36 2,665.34
0.2500 kg Lem putih FOX 49,867.58 12,466.89
4.0000 bh Grendel jendela 2" 15,934.70 63,738.80
2.0000 bh Handle partisi 40,094.68 80,189.36
1.5400 m2 Cat kayu 51,712.28 79,636.91
4.8600 m2 Cat tembok 29,266.31 142,234.26
Jumlah I 2,348,375.01
4 1 UNIT Pekerjaan Kusen Pintu Alumunium KM/WC Lapis Formika uk. 0,8 X 2,70 M'
Bahan 7.0000 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,270,500.00
0.3700 m2 Kaca polos 5 mm 151,322.30 55,989.25
1.6800 m2 Daun pintu rangkap triplek 4 mm 576,950.23 969,276.39
rangka ky. Kelas II lapis formika
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 bh Grendel pintu 2" 15,934.70 15,934.70
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 114,788.28 114,788.28
JUMLAH 2,598,774.458
5 1 UNIT Pek. Kusen Jendela Alumunium uk. 2,65 X 1,50 M' ( 4 lubang ) dgn 2 Daun Jendela
Bahan 15.4500 m' Profil aluminium 4" natural + upah 20% 181,500.00 2,804,175.00
5.4000 m' Profil daun jendela alm. + upah 20% 130,548.00 704,959.20
2.5500 m2 Kaca polos 5 mm 151,322.30 385,871.87
2.0000 ps Engsel jendela 3" 42,654.15 85,308.30
2.0000 bh Slot Handle jendela 29,923.98 59,847.96
2.0000 bh Hak Kait angin jendela biasa 27,771.08 55,542.17
0.0000 ls Acesories ( 5 % ) 194,750.30 194,750.30
JUMLAH 4,290,454.808
6 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk. 2,85 X 2,70 M' ( 3 lb. Jendela + 1 lb. Pintu )
Bahan 17.5500 m' Profil aluminium 4" natural + upah 20% 181,500.00 3,185,325.00
5.4000 m' Profil daun jendela alm. + upah 20% 130,548.00 704,959.20
2.4000 m2 Kaca polos 5 mm 151,322.30 363,173.53
1.6800 m2 Daun pintu panel Multiplek 9 mm 438,297.63 736,340.02
rangka ky. Kelas II
2.0000 ps Engsel jendela 3" 42,654.15 85,308.30
2.0000 bh Slot Handle jendela 29,923.98 59,847.96
2.0000 bh Hak Kait angin jendela biasa 27,771.08 55,542.17
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 bh Grendel pintu 2" 15,934.70 15,934.70
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 212,672.89 212,672.89
JUMLAH 5,591,389.600
7 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,30 X 2,80 M' ( 2 Daun Pintu )
Bahan 8.9000 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,615,350.00
0.6500 m2 Kaca polos 5 mm 151,322.30 98,359.50
2.7300 m2 Daun pintu panel Multiplek 9 mm 438,297.63 1,196,552.53
rangka ky. Kelas II
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 ps Espagnolet tanam 73,855.60 73,855.60
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 145,513.10 145,513.10
JUMLAH 3,301,916.559
8 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,50 X 2,70 M' ( 2 Daun Pintu )
Bahan 8.8000 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,597,200.00
0.7000 m2 Kaca polos 5 mm 151,322.30 105,925.61
2.9400 m2 Daun pintu panel Multiplek 9 mm 438,297.63 1,288,595.03
rangka ky. Kelas II
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 ps spagnolet tanam 73,855.60 73,855.60
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 149,586.03 149,586.03
JUMLAH 3,387,448.107
9 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk.1,55 X 2,70 M' ( 1 lb. Jendela + 1 lb. Pintu )
Bahan 10.7500 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,951,125.00
1.0700 m2 Kaca polos 5 mm 151,322.30 161,914.86
1.6800 m2 Daun pintu panel Multiplek 9 mm 438,297.63 736,340.02
rangka ky. Kelas II
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 ps spagnolet tanam 73,855.60 73,855.60
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 142,468.99 142,468.99
JUMLAH 3,237,990.309
10 1 UNIT Pekerjaan Jalusi Alumunium Sofi-sofi
Bahan 5.1000 m' Profil aluminium 4" natural + upah 20% 181,500.00 925,650.00
8.0000 m2 Jalusi Alm 73,913.54 591,308.34
0.0000 ls Acesories ( 5 % ) 75,847.92 75,847.92
JUMLAH 1,592,806.261
11 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 1 lubang ) uk. 0,70 x 0,60 m
Bahan 4.0000 m' Profil aluminium 4" natural + upah 20% 181,500.00 726,000.00
0.2400 m2 Kaca polos 5 mm 151,322.30 36,317.35
0.0000 ls Acesories ( 5 % ) 38,115.87 38,115.87
JUMLAH 800,433.220
12 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 2 lubang ) uk. 1,35 x 0,60 m
Bahan 4.5000 m' Profil aluminium 4" natural + upah 20% 181,500.00 816,750.00
0.4800 m2 Kaca polos 5 mm 151,322.30 72,634.71
0.0000 ls Acesories ( 5 % ) 44,469.24 44,469.24
JUMLAH 933,853.941
13 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 3 lubang ) uk. 2,00 x 0,60 m
Bahan 6.4000 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,161,600.00
0.7200 m2 Kaca polos 5 mm 151,322.30 108,952.06
0.0000 ls Acesories ( 5 % ) 63,527.60 63,527.60
JUMLAH 1,334,079.661
14 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 4 lubang ) uk. 2,65 x 0,60 m
Bahan 8.3000 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,506,450.00
0.9600 m2 Kaca polos 5 mm 151,322.30 145,269.41
0.0000 ls Acesories ( 5 % ) 82,585.97 82,585.97
JUMLAH 1,734,305.381
15 1 UNIT Pek. Kusen Jendela Alm.uk. 2,65 X 1,50 M' ( 4 lubang ) dgn 2 Daun Jendela tampa BV
Bahan 11.4500 m' Profil aluminium 4" natural + upah 20% 181,500.00 2,078,175.00
5.4000 m' Profil daun jendela alm. + upah 20% 130,548.00 704,959.20
2.5500 m2 Kaca polos 5 mm 151,322.30 385,871.87
2.0000 ps Engsel jendela 3" 42,654.15 85,308.30
2.0000 bh Slot Handle jendela 29,923.98 59,847.96
2.0000 bh Hak Kait angin jendela biasa 27,771.08 55,542.17
0.0000 ls Acesories ( 5 % ) 158,450.30 158,450.30
JUMLAH 3,528,154.808
16 1 UNIT Pek. Kusen Pintu & Jendela Alm.1,55 X 2,70 M' ( 1 lb. Jendela + 1 lb. Pintu ) tampa BV
Bahan 8.2000 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,488,300.00
0.7200 m2 Kaca polos 5 mm 151,322.30 108,952.06
1.6800 m2 Daun pintu panel Multiplek 9 mm 438,297.63 736,340.02
rangka ky. Kelas II
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 ps spagnolet tanam 73,855.60 73,855.60
1.0000 bh Kunci tanam 2 slaagh (Royal) 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 116,679.60 116,679.60
JUMLAH 2,696,413.113
17 1 UNIT Pek. Kusen Jendela Alm.uk. 2,00 X 1,50 M' ( 3 lubang ) dgn 2 Daun Jendela tampa BV
Bahan 10.2500 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,860,375.00
5.4000 m' Profil daun jendela alm. + upah 20% 130,548.00 704,959.20
1.6500 m2 Kaca polos 5 mm 151,322.30 249,681.80
2.0000 ps Engsel jendela 3" 42,654.15 85,308.30
2.0000 bh Slot Handle jendela 29,923.98 59,847.96
2.0000 bh Hak Kait angin jendela biasa 27,771.08 55,542.17
0.0000 ls Acesories ( 5 % ) 140,750.80 140,750.80
JUMLAH 3,156,465.232
18 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,50 X 2,00 M' ( 2 Daun Pintu )tampa BV
Bahan 7.6000 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,379,400.00
2.9400 m2 Daun pintu panel Multiplek 9 mm 438,297.63 1,288,595.03
rangka ky. Kelas II
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 ps spagnolet tanam 73,855.60 73,855.60
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 133,399.75 133,399.75
JUMLAH 3,047,536.215
19 1 UNIT Pek. Kusen Pintu & Jendela Alum uk. 2,85 X 2,70 M' ( 3 lb. Jendela + 1 lb. Pintu ) tampa BV
Bahan 12.3000 m' Profil aluminium 4" natural + upah 20% 181,500.00 2,232,450.00
5.4000 m' Profil daun jendela alm. + upah 20% 130,548.00 704,959.20
1.1000 m2 Kaca polos 5 mm 151,322.30 166,454.53
1.6800 m2 Daun pintu panel Multiplek 9 mm 438,297.63 736,340.02
rangka ky. Kelas II
2.0000 ps Engsel jendela 3" 42,654.15 85,308.30
2.0000 bh Slot Handle jendela 29,923.98 59,847.96
2.0000 bh Hak Kait angin jendela biasa 27,771.08 55,542.17
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 bh Grendel pintu 2" 15,934.70 15,934.70
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 155,193.19 155,193.19
JUMLAH 4,384,315.907
20 1 UNIT Pek. Kusen Pintu & Jendela Alm.3,1 X 2,70 M' ( 2 lb. Jendela + 2 lb. Pintu )
Bahan 19.5000 m' Profil aluminium 4" natural + upah 20% 181,500.00 3,539,250.00
2.1400 m2 Kaca polos 5 mm 151,322.30 323,829.73
3.3600 m2 Daun pintu panel Multiplek 9 mm 438,297.63 1,472,680.03
rangka ky. Kelas II -
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 ps spagnolet tanam 73,855.60 73,855.60
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 266,787.99 266,787.99
JUMLAH 5,848,689.184
3 1 UNIT Pek. Kusen Pintu Jendela Alumunium uk. 2,2 X 2,70 M' ( 2 lb. Jendela + 1 lb. Pintu )
Bahan 10.4000 m' Profil aluminium 4" natural + upah 20% 181,500.00 1,887,600.00
2.7000 m' Profil daun jendela alm. + upah 20% 130,548.00 352,479.60
1.6500 m2 Kaca polos 5 mm 151,322.30 249,681.80
1.6800 m2 Daun pintu panel Multiplek 9 mm 438,297.63 736,340.02
rangka ky. Kelas II -
1.0000 ps Engsel jendela 3" 42,654.15 42,654.15
1.0000 bh Slot Handle jendela 29,923.98 29,923.98
2.0000 bh Hak Kait angin jendela biasa 27,771.08 55,542.17
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 bh Grendel pintu 2" 15,934.70 15,934.70
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 124,488.07 124,488.07
JUMLAH 3,666,930.325
2 1 UNIT Pek. Kusen Jendela Alum warna uk. 2 X 1,50 M' ( 3 lubang ) dgn 2 Daun Jendela
Bahan 12.0000 m' Profil aluminium 4" warna + upah 20% 215,424.00 2,585,088.00
5.4000 m' Profil daun jendela alm. + upah 20% 186,252.00 1,005,760.80
1.8100 m2 Kaca polos 5 mm 151,322.30 273,893.37
2.0000 ps Engsel jendela 3" 22,156.23 44,312.46
2.0000 bh Slot Handle jendela 29,923.98 59,847.96
2.0000 bh Hak Kait angin jendela biasa 27,771.08 55,542.17
0.0000 ls Acesories ( 5 % ) 193,237.11 193,237.11
JUMLAH 4,217,681.864
3 1 UNIT Pek. Kusen Pintu Jendela Alumunium uk. 2,2 X 2,70 M' ( 2 lb. Jendela + 1 lb. Pintu )
Bahan 14.1000 m' Profil aluminium 4" warna + upah 20% 215,424.00 3,037,478.40
2.7000 m' Profil daun jendela alm. + upah 20% 186,252.00 502,880.40
1.6500 m2 Kaca polos 5 mm 151,322.30 249,681.80
1.6800 m2 Daun pintu alumunium warna tanpa kaca 515,573.48 866,163.44
1.0000 ps Engsel jendela 3" 22,156.23 22,156.23
1.0000 bh Slot Handle jendela 29,923.98 29,923.98
2.0000 bh Hak Kait angin jendela biasa 27,771.08 55,542.17
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 bh Grendel pintu 2" 15,934.70 15,934.70
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 189,502.03 189,502.03
Jumlah 5,141,548.985
4 1 UNIT Pekerjaan Kusen Pintu Alumunium uk. 0,8 X 2,70 M'
Bahan 7.0000 m' Profil aluminium 4" warna + upah 20% 215,424.00 1,507,968.00
0.3700 m2 Kaca polos 5 mm 151,322.30 55,989.25
1.6800 m2 Daun pintu alumunium warna tanpa kaca 515,573.48 866,163.44
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 bh Grendel pintu 2" 15,934.70 15,934.70
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 121,506.03 121,506.03
Jumlah I 2,739,847.264
8 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,50 X 2,70 M' ( 2 Daun Pintu )
Bahan 8.8000 m' Profil aluminium 4" warna + upah 20% 215,424.00 1,895,731.20
0.7000 m2 Kaca polos 5 mm 151,322.30 105,925.61
2.9400 m2 Daun pintu alumunium warna tanpa kaca 515,573.48 1,515,786.02
1.5000 ps Engsel pintu 4" 18,280.35 27,420.53
1.0000 ps spagnolet tanam 15,934.70 15,934.70
1.0000 bh Kunci tanam 2 slaagh 144,865.31 144,865.31
0.0000 ls Acesories ( 5 % ) 175,872.14 175,872.14
JUMLAH 3,881,535.511
11 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 1 lubang ) uk. 0,70 x 0,60 m
Bahan 4.0000 m' Profil aluminium 4" warna+ upah 20% 215,424.00 861,696.00
0.2400 m2 Kaca polos 5 mm 144,865.31 34,767.68
0.0000 ls Acesories ( 5 % ) 44,823.18 44,823.18
JUMLAH 941,286.859
13 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 3 lubang ) uk. 2,00 x 0,60 m
Bahan 6.4000 m' Profil aluminium 4" warna + upah 20% 215,424.00 1,378,713.60
0.7200 m2 Kaca polos 5 mm 144,865.31 104,303.03
0.0000 ls Acesories ( 5 % ) 74,150.83 74,150.83
JUMLAH 1,557,167.457
2 1 UNIT Pek. Kusen Jendela Alumunium ( 2 lubang ) dgn 2 Daun Jendela
Bahan 12.0000 m' Profil aluminium 4" warna + upah 20% 215,424.00 2,585,088.00
3.6000 m' Profil daun jendela alm. + upah 20% 186,252.00 670,507.20
1.8100 m2 Kaca polos 5 mm 144,865.31 262,206.22
2.0000 ps Engsel jendela 3" 22,156.23 44,312.46
2.0000 bh Slot Handle jendela 29,923.98 59,847.96
2.0000 bh Hak Kait angin jendela biasa 27,771.08 55,542.17
0.0000 ls Acesories ( 5 % ) 175,890.07 175,890.07
JUMLAH 3,853,394.076