2hitiung Fondasi Tapak Bujur Sangkar 2
2hitiung Fondasi Tapak Bujur Sangkar 2
Project : Ruko Permata Juanda Surabaya Client : Mr Bunawan Engineer Name Date Lutfi 10/31/2012 7:11 Checked Ari Approved
Data Struktur :
Pu Mu
3 4 5 6
b h s B L ht fc' fy' D c
= = = = = = = = = =
b Muka Tanah
L KN/m3 L
Data Tanah : 6 7 8 Daya dukung tanah Berat tanah Tebal tanah diatas pondasi t t ha = = = 105 Kpa 17.20 KN/m3 1.20 m h B B=L 9 Beban P ultimate 10 Beban M ultimate Pult Mult = = 384 18.25 KN KNm
Data Beban :
b Result Cek Status Pondasi : Tegangan yang terjadi pada tanah maks min .Vc Vu .Vc Vu = = = = = = 104.8277 88.98566 422.617 168.620 1007.237 508.641 < < 105 105 OK! OK!
<
422.617
OK!
<
1007.237
OK!
19
219
Mu,x + 1/6
Mu,y + B x L
2
Menghitung tegangan tanah didasar fondasi Pult maks = B x L Pult min = B x L 2 1/6 B x L
Kontrol gaya geser 1 arah maks Vu Dimana L a = min + L fc' Vc Syarat : = 6 x B x d - a x maks - min = a x B 2 + a
Vu
Vc
dengan
= 0.75
+ 2
- b
h + d
fc'
bo 6 fc'
bo 12
bo d
= 0.75
D/2
2)
= min
maks 3 x
min
1000
0.85
600
+ fy
225 x
5)
Kmaks
6)
a'
= 1 - 1
x a fy
7)
As(1)
8)
fc' maka
31.36
Mpa
1.4 As(2)
b fy
fc' maka
>
31.36
Mpa
fc' As(3) =
b 4 fy
x d
9)
Jarak tulangan 0.25 s = As terpilih s s 2 x ht 450 Pilih "s" yang terkecil x phi x D
2
Pu Syarat :
= Pult
0.85 Pu
fc'
..... ( = 0,7 )
Referensi : Asroni, A., Buku Kolom Fondasi & Balok T Beton Bertulang,
Notasi : t Pult B,L Mu,x Mu,y q t ht ha c t Vu Vc c t bo s = = = = = = = = = = = = = = = = = Tegangan yang terjadi pada dasar fondasi ........... Daya dukung tanah ........... Beban axial terfaktor pada kolom........... Panjang dan lebar fondasi Momen terfaktor kolom searah sumbu X ........... Momen terfaktor kolom searah sumbu Y ........... Beban terbagi rata akibat beban sendiri fondasi ditambah beban tanah diatas fondasi ........... Tebal fondasi 150 mm (lihat pasal 17.7 SNI 03-2847-2002) Tebal tanah diatas fondasi ........... Berat per volume beton ........... Berat per volume tanah ........... Gaya geser pons terfaktor........... Gaya geser yang sanggup ditahan oleh beton........... Faktor keamanan = 0,7 (lihat SNI) Rasio dari sisi panjang terhadap sisi pendek pada kolom, daerah beban terpusat / atau daerah reaksi Keliling penampang krisis dari fondasi ........... Suatu konstanta yang digunakan untuk menghitung Vc , yang nilai tergantung pada letak fondasi, 40 = Kolom dalam 30 = Kolom tepi 20 = Kolom sudut Tegangan tanah minimum ........... Tegangan tanah maksimum ........... Tegangan tanah sejarak "a" dari tepi fondasi .......... Tegangan tanah sejarak "x" dari tepi fondasi .......... Jarak dari area bidang yang menerima tekanan keatas dari tanah (area keruntuhan) Kuat tekan beton ........... Mutu beton ........... decking minimal = 75 mm (berhubungan dengan tanah) Diameter tulangan ........... Tinggi blok tegangan beton teka persegi ekivalen Momen yang terjadi padafondasi Faktor momen pikul Jarak tulangan ........... Luas besi tulangan yang dibutuhkan ...........
+ 2
min
min
fc'
(Kpa) atau KN/m2 (Kpa) atau KN/m2 KN m KNm KNm (KN/m2) mm mm KN/m3 KN/m3 KN KN
mm
(Kpa) atau KN/m2 (Kpa) atau KN/m2 (Kpa) atau KN/m2 (Kpa) atau KN/m2 mm Mpa Mpa mm mm mm
mm mm2
Job No.
Program Hitung Pondasi Tapak
Sheet No
1
Part Ref Enginner File
Job Title Client. Analisa q = = = = Berat Fondasi ht x c 0.40 x 24 30.24 KN/m2 + + + Berat Tanah x t x 17.20 Ruko Permata Juanda Surabaya Mr Bunawan
Lutfi
Date Date/time
10/31/2012 7:11
ha 1.20
Cek Fondasi Terhadap Tegangan Izin Tanah Tegangan yang terjadi pada tanah Pult maks = B x 384 = 2.40 = = 66.66667 104.828 Pult min = B x 384 = 2.40 = = 66.66667 88.986 x 2.40 7.921 + 1/6 30.24 105 Save! 2.40 x 2.40
2
Mult + L 1/6 B x 18.25 + + 1/6 + 30.24 105 Save! Mult L 1/6 B x 18.25 + 30.24 105 L2 + q t 2.40 x 2.40
2
+ L2
30.24
105
x +
2.40 7.921
Kontrol Tegangan Geser 1 Arah 0.40 ds = = = = = = = = = = = = 2.40 0.4 = 100.306 KN/m2 75 75 85.00 ht 400 315.00 B/2 1200 685.00 0.685 min 88.986 + + mm D/2 9.50
ds 85.00
mm m + +
b/2 200
d 315.00
B 2.40
a 0.685
x x
maks 104.828
min 88.986
b 2.40
Gaya tekan ke atas dari tanah (Vu) Vu 0.4 = = 0.685 168.620 x KN 2.40 x 104.828 + 100.306 2 = a x B x maks + a 2
Job No.
Program Hitung Pondasi Tapak
Sheet No
1
Part Ref Enginner File Gaya geser yang dapat ditahan oleh beton (.Vc) fc' .Vc = x 6 20 = 0.315 = 2.40 .Vc = 422.617 > Vu = 168.620 ......... Save! 422.617 KN 0.75 x 6 x 2.40 x 315.00 x B x d
Job Title Client. Ruko Permata Juanda Surabaya Mr Bunawan 0.40 0.315 0.685
Lutfi
Date Date/time
10/31/2012 7:11
min 88.986
a 100.306
maks 104.828
Kontrol Tegangan Geser 2 Arah (Geser Pons) Dimensi Kolom, b h b h Gaya Tekan Ke Atas (Geser Pons) maks Vu = B
2
= = + +
400 400 d d = = 400.00 400 + + 315.00 315.00 = = 715.00 715.00 mm mm = = 0.715 0.715 m m
+ 2
min
104.828 = = 2.40 508.6413 hk c = Bk bo bo = = = 2 2 2860 x x mm = 400 bk 400 + + d 315.00 + + hk 400 + + 400 = 1.000
2
+ 2
88.986
0.715
0.715
d 315.00
Gaya geser yang ditahan oleh beton 2 Vc1 0.158 0.40 0.158 Vc1 = = 2014473.641 2014.474 Vc1 = 1 + 1.000 N KN = 1 + c 2 x 6 20 x 6 2860 315.00 fc' bo d
0.843
0.843 s Vc2 = 2 + bo 30 Vc2 0.315 0.085 Vc2 = = 1445114.832 1445.115 = 2 + 2860 N KN 315.00 x 12 20 d x 12 2860 315.00 fc' bo d
2.40
Job No.
Program Hitung Pondasi Tapak
Sheet No
1
Part Ref Enginner File
Lutfi
Date Date/time
10/31/2012 7:11
1 Vc3 = 3 1 min 88.986 Vc3 maks 104.828 = = Jadi Vc1 Vc2 Vc3 Vc .Vc = = = = = = = 2014.474 1445.115 1342.982 1342.982 0.75 1007.237 1007.237 KN x KN > = 3 1342982.427 1342.982 N KN x 20 2860 315.00 x fc' bo d
1342.982
.Vc
Vu
508.641
.........
Save!
Hitungan Penulangan Fondasi 0.40 ds = = = = = = 75 103.500 0.105 ht 0.40 0.295 295 B 2.40 x = 2 2400 x min 88.986 x x = = = min 88.986 98.227 x 98.227 + + KN/m3 maks Mu = 0.5 x x
2
+ mm m m mm
19
9.5
1.00 1.20
ds 0.105
0.40
0.295 0.105
x x
3 3
x x
2
+ 104.828 98.227
= =
0.5 51.314
98.227 KNm Mu
= x b x d
2
Job No.
Program Hitung Pondasi Tapak
Sheet No
1
Part Ref Enginner File + + + + fy fy 320 320
2 2
Job Title Client. Ruko Permata Juanda Surabaya Mr Bunawan 382.5 Kmaks = 600 382.5 Kmaks = 600 = K K < = 5.599 Kmaks 0.737 Mpa x 0.85 x 600 x 0.85 x 600 225 x
Lutfi
Date Date/time
10/31/2012 7:11
fc'
225
0.85
20
<
Kmaks
5.599 .........
OK!
2 a' = 1 1 0.85 2 = 1 1 0.85 = 13.080 0.85 As(1) = fy 0.85 = 320 = Jika fc' maka As 694.877 mm2 x 20 x 13.080 mm x fc' x a'
x x x x
1000
31.36 1.4
>
31.36 fc'
fc'
(R.1)
1.4 As(2) =
b fy
fc'
x 4
b fy 0 4 0 ...........
d ....... (R.2)
1.4 =
1000 320
295 =
1290.625
mm2 ...........
As dipakai
#DIV/0!
mm2
As tidak Dipakai!
Dipilih yang terbesar dari As(1) dan As(2)......... Sehingga, As(1) As(2) = = 694.877 1290.625 mm2 As mm2 = 1290.625 mm2
Job No.
Program Hitung Pondasi Tapak
Sheet No
1
Part Ref Enginner File
Lutfi
Date Date/time
10/31/2012 7:11
phi
1000
2 2 800 450
x x
ht 400
mm = = 219.572 D 19 mm 219
Job No.
Sheet No
2
Program Hitung Pondasi Tapak
Job Title Client. Ruko Permata Juanda Surabaya Mr Bunawan Part Ref Enginner File
Date Date/time
10/31/2012 7:11
Cek Panjang Penyaluran Tegangan Tulangan 9 Panjang penyaluran tegangan (d) = c 10 fc' db 9 = 75 10 20 19 9 = 10 = 391.544 392 B Panjang Tersedia (t) = 2 2400 = 2 = Panjang Tersedia (t) 925 > > 925 2 2 400 75 mm mm Bk 75 > 20 2.5 x 320 x 1 1 x 0.8 x 1 19 + 0 x 320 x 1 1 x 0.8 x 1 19 + Ktr x fy x x x db
300 mm
Kuat Dukung Fondasi Pu = = = = Pu,k Pu = = 0.7 x x N KN KN > Pu,k = 384 ....... OK! 0.85 0.85 x x fc' 20 x x A 160000
Job No.
Sheet No
2
Program Hitung Pondasi Tapak
Job Title Client. Ruko Permata Juanda Surabaya Mr Bunawan Part Ref Enginner File
Date Date/time
10/31/2012 7:11
SKSNI 03-2847-2002
Job No.
Sheet No
2
Program Hitung Pondasi Tapak
Job Title Client. Ruko Permata Juanda Surabaya Mr Bunawan Part Ref Enginner File
Date Date/time
10/31/2012 7:11
Job No.
Sheet No
3
Program Hitung Pondasi Tapak
Job Title Client. Ruko Permata Juanda Surabaya Mr Bunawan 2.40 Part Ref Enginner File
Date Date/time
10/31/2012 7:11
1
2.40
19
219
DETAIL PONDASI
Non Scale 400
19
219
400
POTONGAN 1-1
Non Scale SNI 03-2847-2002 (Pasal 17.4.3)
Job No.
Sheet No
3
Program Hitung Pondasi Tapak
Job Title Client. Ruko Permata Juanda Surabaya Mr Bunawan Part Ref Enginner File
Date Date/time
10/31/2012 7:11