Produksi/Hari
Produksi/Bulan
Produksi/Tahun
Tahun
Sasaran Produksi
Pendapatan
Produk
Harga Ton
Tahun ke
Tahun ke
mm
(Rp)
2
-
Sub Total
N
Ton
Ton
Ton
3
Tahun ke
Tahun ke
Tahun ke
Jumlah
Biaya/Unit
(Rp)
a. Biaya Eksplorasi
- Survey
- Eksplorasi
-StudiKelayakan
- Studi Amdal
-StudiUPL&UKL
-BiayaSampling(Pemboran)
Sub Total
b. Biaya Pembebasan Lahan
- Pembebasan Tanah/Hektar
- Ganti Rugi Rumah
- Ganti Tanaman/Hektar
- Ganti Rugi Pohon
- Jati
- Mahoni
- Kakao
- Kelapa
Sub Total
Total
Biaya Total
(Rp)
Biaya Perijinan
-
Biaya Iuran
- Iuran Tetap
- Iuran Pembangunan Daerah
- PBB
Sub Total
Jumlah
Unit
Biaya
(Rp)
b. Infrastrustur
- Jalan Tambang
- Instalasi Jaringan Listrik
- Instalasi Jaringan Air
- Instalasi Jaringan Telepon
Sub Total
Total
a
Total
(Rp)
CASH FLOW
URAIAN
PENDAPATAN
Hasil Pendapatan
Royalti (7%)
Pendapatan setelah royalti
Nilai Netto
BIAYA OPERASIONAL
Biaya Variable
- Biaya Pemakaian Listrik
- Biaya Pemakaian Telepon
- Biaya Pemakaian Air
- Biaya Kebutuhan BBM
- Biaya Perawatan
- Biaya K3 dan Lingkungan
- Biaya Pengembangan Masyarakat
- Biaya Reklamasi dan Pasca Tambang
Total Biaya Variable
Biaya Tetap
- Biaya Penyusutan
- Amortisasi
- Bunga Pinjaman
- Gaji Pegawai
- Jamsostek
- Biaya Iuran Tetap
- Biaya PBB
- Biaya Lain-lain
Total Biaya Tetap
Pajak
25%
Total Pajak
Pendapatan Bersih
Biaya Lain-lain
- Investasi Pengganti
- Investati Total
- Modal Kerja Kembali
- Modal Pinjaman
- Angsuran Pinjaman
- Reklamasi dan Pasca Tambang Kembali
Total Biaya Lain-lain
H FLOW
TAHUN
2
BIAYA INVENTARIS
Keterangan
Jumlah
Harga Satuan/
Harga
Umur
Tahun Ke
Tahun Ke
Unit
Unit (Rp)
Total
Alat
Meja
Kursi
Meja Kursi Rapat
Lemari Arsip
Komputer
Printer
Faximile
Telephone
Mesin Foto Copy
Dispenser
White Board
Genset
Proyektor
CCTV
Tempat sampah
AC
Kulkas
TV
Tempat Tidur + Kasur
Kipas Angin
Peralatan Masak (set)
Peralatan Makan (set)
Total
Tahun Ke
Tahun Ke
Tahun Ke
Jumlah
Jumlah
Perbulan
Pertahun
- Listrik
- Komputer
- Printer
- Faximile
- Telephone
- Dispenser
- Genset
- Proyektor
- CCTV
- AC
- Kulkas
- TV
- Kipas Angin
Sub Total
Air
Keterangan
Jumlah
Jumlah
Perbulan
Pertahun
- Kantor
- Mess
- Kantin
- Mushola
- Stock Yard
- Pos Keamanan
Sub Total
Jumlah
Jumlah
Perbulan
Pertahun
- Diklat / Kursus K3
- Safety
- Pemasangan Rambu-Rambu
- Pemeriksaaan Kesehatan
Sub Total
Keterangan
Unit
Gaji / Bulan
Jamsostek
(Rp)
(Rp)
10,500,000
210,000
Pengaawas transportasi
7,000,000
140,000
7,000,000
140,000
Pengawas Tambang
7,000,000
140,000
Mandor transportasi
5,000,000
100,000
Mandor crushing
5,000,000
100,000
5,000,000
100,000
Mandor OB
5,000,000
100,000
Operator crushing
2,000,000
40,000
10
Operator pompa
2,000,000
40,000
11
Helper
1,700,000
34,000
12
Kabag perawatan
10,000,000
200,000
13
Pengawas elektrik
7,000,000
140,000
14
Pengawas mekanik
7,000,000
140,000
15
Mandor bangunan
5,000,000
100,000
16
Operator las
2,000,000
40,000
17
Operator generator
1,700,000
34,000
18
Helper
1,700,000
34,000
19
Pengawas camp
3,500,000
70,000
3,500,000
70,000
21
3,500,000
70,000
22 Operator komputer
2,000,000
40,000
23 Petugas K3
2,000,000
40,000
24 Petugas satpam
1,700,000
34,000
25 Juru masak
1,700,000
34,000
26 Supir
1,700,000
34,000
27 Helper
1,700,000
34,000
Sub Total
46
112,900,000
2,258,000
General Manager
25,000,000
500,000
Manager Tambang
20,000,000
400,000
Sekretaris
3,500,000
70,000
Kabag Perencanaan
8,500,000
170,000
7,000,000
140,000
Kepala Lingkungan
5,000,000
100,000
4,000,000
80,000
Pit geologist
5,500,000
110,000
Surveyor
3,500,000
70,000
10
Operator Komputer
3,000,000
60,000
11
Juru gambar
3,000,000
60,000
12
Helper
1,700,000
34,000
13
6,500,000
130,000
14
5,000,000
100,000
15
Kepala Keuangan
5,000,000
100,000
16
Hubungan masyarakat
5,000,000
100,000
17
4,000,000
80,000
18
4,000,000
80,000
19
Staff/pembantu keuangan
3,500,000
70,000
Sub Total
23
122,700,000
2,454,000
Total
69
235,600,000
4,712,000
Tunjangan
Gaji / Netto
Gaji Netto
Jabatan
(Rp)
Disetahunkan
500,000
9,790,000
117,480,000
500,000
6,360,000
76,320,000
500,000
6,360,000
76,320,000
500,000
6,360,000
76,320,000
500,000
4,400,000
52,800,000
500,000
4,400,000
52,800,000
500,000
4,400,000
52,800,000
500,000
4,400,000
52,800,000
500,000
1,460,000
17,520,000
500,000
1,460,000
17,520,000
500,000
1,166,000
13,992,000
500,000
9,300,000
111,600,000
500,000
6,360,000
76,320,000
500,000
6,360,000
76,320,000
500,000
4,400,000
52,800,000
500,000
1,460,000
17,520,000
500,000
1,166,000
13,992,000
500,000
1,166,000
13,992,000
500,000
2,930,000
35,160,000
500,000
2,930,000
35,160,000
500,000
2,930,000
35,160,000
500,000
1,460,000
17,520,000
500,000
1,460,000
17,520,000
500,000
1,166,000
13,992,000
500,000
1,166,000
13,992,000
500,000
1,166,000
13,992,000
500,000
1,166,000
13,992,000
13,500,000
97,142,000
1,165,704,000
500,000
24,000,000
288,000,000
500,000
19,100,000
229,200,000
500,000
2,930,000
35,160,000
500,000
7,830,000
93,960,000
500,000
6,360,000
76,320,000
500,000
4,400,000
52,800,000
500,000
3,420,000
41,040,000
500,000
4,890,000
58,680,000
500,000
2,930,000
35,160,000
500,000
2,440,000
29,280,000
500,000
2,440,000
29,280,000
500,000
1,166,000
13,992,000
500,000
5,870,000
70,440,000
500,000
4,400,000
52,800,000
500,000
4,400,000
52,800,000
500,000
4,400,000
52,800,000
500,000
3,420,000
41,040,000
500,000
3,420,000
41,040,000
500,000
2,930,000
35,160,000
9,500,000
110,746,000
1,328,952,000
23,000,000
207,888,000
2,494,656,000
- Mess
- Kantin
- Mushola
- Stock Yard
- Pos Keamanan
Sub Total
3
Sub Total
TOTAL
Tahun
Total Ekskalasi
1
5%
2
-
4
-
5
-
JENIS ALAT
BBM /
Harga BBM
Hari/
Jumlah
Liter
Liter (Rp)
Liter
Unit
Kebutuhan/ Hari/
Liter
- Excavator PC 200
- Excavator PC 300
- Excavator PC 400
- Dozer
- Tronton
- Trackloader,motorgrader&backhoe
- Dumptruck
- Mobil
- Motor
TOTAL
Biaya / Tahun
2
Jumlah
Harga Satuan/
Nilai Sisa
Umur
Tahun Ke
Alat
Unit
Unit (Rp)
Total
Alat
Sub Total
- Caterpilar 14 H
Sub Total
- Compactor CD 33D
Sub Total
e. Alat Angkut Batu Bara & Alat Angkut OB (Dump Truck)
- Trusck PS
- DT Tronton Hino
- Caterpilar 773 D
- Caterpilar AT 740
- Kerak 350
- Volvo FM 12
- Komatsu HM 400
- Nissan CWB 520
Sub Total
f. Alat Penyiram Jalan (Water Truck)
- Isuzu
- Renault Kerak 350
- WT Hino
Sub Total
g. Pompa Air Tambang
- MF 380
- MF 290
- Sykes HH-150
- Torishima
Sub Total
II. Peralatan Pendukung Operasional
- Genset
- Mobil Operasional
- Camp
- Sepeda Motor
Tahun Ke
Tahun Ke
Tahun Ke
Tahun Ke
INVESTASI TOTAL
NO.
JENIS INVESTASI
1
BIAYA
INVESTASI AWAL
Biaya Persiapan
Investasi Alat
Sub Total
MODAL KERJA
T O T A L
MODAL SENDIRI
50%
PINJAMAN
50%
BUNGA PINJAMAN
12%
ANGSURAN PINJAMAN
20%
TAHUN
POKOK PINJAMAN
ANGSURAN
BUNGA
CICILAN
SISA PINJAMAN
-
PENDAPATAN
Hasil Pendapatan
Royalti (7%)
Pendapatan setelah royalti
Nilai Netto
BIAYA OPERASIONAL
Biaya Variable
- Biaya Pemakaian Listrik
- Biaya Perawatan
Biaya Tetap
- Biaya Penyusutan
- Amortisasi
- Bunga Pinjaman
- Biaya PBB
- Biaya Lain-lain
- Gaji Pegawai
- Jamsostek
- Biaya Iuran Tetap
25%
Total Pajak
Pendapatan Bersih
BIAYA JAM
No
1
K
Biaya Langsung
a.
b.
c.
d.
e.
f
g.
Pengamanan semua bukaan tambang yang berpotensi bahaya terhadap manusia (shaft, raise, stope, edit, decline, tunnel, d
Fasilitas Pengolahan atau Pemulihan
Pembongkaran fasilitas pengolahan dan pemurnian
Reklamasi lahan bekas fasilitas pengolahan dan pemurnian
Reklamasi lahan bekas kolam tailing dan upaya stabilisasinya
Reklamasi lahan bekas timbunan konsentrat
Pemulihan (remediasi) tanah yang terkontaminasi bahan kimiaminyak dan Bahan Berbahaya dan Beracun (B3) serta Limbah
Fasilitas Penunjang
Reklamasi lahan bekas landfill
Pembongkaran sisa bangunan, transmisi Iistrik, pipa, pelabuhan (udara dan air), dan fasilitas lainnya
Reklamasi lahan bekas bangunan, transmisi listrik, pipa pelabuhan (udara dan air), dan fasilitas lainnya
Pembongkaran peralatan, mesin, tangki SBM dan pelumas
Penanganan sisa BBM, pelumas, serta bahan kimia
Reklamasi lahan bekas sarana transportasi
Reklamasi lahan bekas bangunan dan pondasi beton
Pemulihan (remediasi) tanah yang terkontaminasi bahan kimia minyak dan B3d
Sosial dan Ekonomi
Pemeliharaan dan Perawatan
Pemantauan Lain-Lain
Lain-lain
Sub Total
Biaya Tidak Langsung
Biaya mobilisasi dan demobilisasi alat
Biaya perencanaan dan Kegiatan
Biaya perencanaan dan Kegiatan
Biaya administrasi dan keuntungan kontraktor
Sub Total
Total
Biaya