#REF!
1 0 #REF! ### #REF! ###
2 1 SATU ### #REF! ###
3 10 SEPULUH ### #REF! ###
4 11 SEBELAS ### #REF! ###
5 12 DUA BELAS ### #REF! ###
6 13 TIGA BELAS ### #REF! ###
7 14 EMPAT BELAS ### #REF! ###
8 15 LIMA BELAS ### #REF! ###
9 16 ENAM BELAS ### #REF! ###
10 17 TUJUH BELAS ### #REF! ###
11 18 DELAPAN BELAS ### #REF! ###
12 19 SEMBILAN BELAS ### #REF! ###
13 2 DUA PROGRAM INI DIBUAT ATAS KREASI : YIYI RIZAL
14 3 TIGA ALAMAT : JALAN SAMPANGAN BARU I/D.158
15 4 EMPAT SEMARANG
16 5 LIMA
17 6 ENAM
18 7 TUJUH
19 8 DELAPAN
20 9 SEMBILAN
#REF!
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 110,000
Bulat Belah m3 130,000
Pecah 10/15 m3 140,000
Pecah 5/7 m3 145,000
Pecah 3/5 m3 150,000
2 KERIKIL Timbun m3 75,000
Sawur / Koral m3 90,000
Beton 0,5/1 m3 200,000
Beton ,1/2 m3 165,000
Beton ,2/3 m3 160,000
Biasa m3 140,000
Tras Giling m3 220,000
3 BATU BATA ex lokal bh 380
Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 33,000
. 180 cm X 105 cm X 4 mm bh 38,000
. 210 cm X 105 cm X 4 mm bh 44,750
. 240 cm X 105 cm X 4 mm bh 50,000
. 270 cm X 105 cm X 4 mm bh 57,000
. 300 cm X 105 cm X 4 mm bh 63,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 11,500
. 50 cm X 200 cm X 3 mm bh 12,000
. 40 cm X 200 cm X 3 mm bh 10,500
Jabes nok
. Kerpus Genteng bh 22,500
. Stel Besar bh 39,750
. Paten Besar bh 39,000
Nokstel gelombang
. Stel Besar bh 41,500
. Patent Besar bh 18,000
. Plat besar bh 49,000
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
7 FIBRE GLASS
180 X 92 cm bh 60,000
200 X 92 cm bh 70,000
250 X 92 cm bh 73,000
180 X 105 cm bh 42,000
210 X 105 cm bh 395,000
250 X 105 cm bh 49,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 19,000
BJLS 0,20 lebar 55 cm m' 27,000
BJLS 0,28 lebar 55 cm m' 30,000
BJLS 0,30 lebar 55 cm m' 38,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 47,000
BJLS 0,20 panjang 180 cm lbr 57,000
BJLS 0,30 panjang 180 cm lbr 67,000
BJLS 0,40 panjang 180 cm lbr 73,000
III . B A H A N K A Y U
1 JATI Papan m3 19,500,000
Balok/pesagen m3 17,000,000
4 UBIN PORSELIN
Lokal 11 X 11 putih dos 27,500
11 X 11 warna dos 30,000
Lokal 15 X 15 putih dos 29,000
15 X 15 warna dos 33,000
5 MOZAIK PORSELIN
10 X 20 cm m2 35,000
15 X 15 cm m2 35,000
20 X 20 cm m2 35,000
20 X 25 cm m2 33,000
1 Keramik 30 X 30 cm m2 40,000
20 X 20 cm m2 42,000
33 x 33 cm m2 38,000
20 x 25 cm m2 42,000
15 x 20 cm m2 38,000
2 GRANITO 40 x 40 cm m2 190,000
30 x 30 cm m2 210,000
11 Marmer m2 375,000
V.BAHAN CETAK
1 BUIS BETON 10 cm - 100 cm bh 15,000
20 cm - 100 cm bh 20,000
30 cm - 100 cm bh 32,000
50 cm - 100 cm bh 55,000
60 cm - 100 cm bh 75,000
70 cm - 100 cm bh 90,000
U 10 cm - 100 cm bh 14,000
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
U 15 cm - 100 cm bh 16,000
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
U 20 cm - 100 cm bh 20,000
U 30 cm - 100 cm bh 28,000
III
1 BESI BETON besi beton polos kg 11,500
besi beton prestress kg 12,000
besi beton ulir kg 12,000
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( " ) AW JIS btg 20,000 panjang 4 m
Pipa PVC DN 25 ( " ) AW JIS btg 22,500 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 28,000 panjang 4 m
Pipa PVC DN 40 ( 1" ) btg 51,200 panjang 6 m
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
Pipa PVC DN 63 ( 2" ) btg 77,000 panjang 6 m
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
Pipa PVC DN 90 ( 3" ) btg 139,250 panjang 6 m
Pipa PVC DN 110 ( 4" ) btg 202,950 panjang 6 m
Pipa PVC DN 160 ( 6" ) btg 423,000 panjang 6 m
Pipa PVC DN 200 ( 8" ) btg 660,000 panjang 6 m
Pipa PVC DN 250 ( 10" ) btg 1,025,000 panjang 6 m
Pipa PVC DN 315 ( 12" ) btg 1,390,000 panjang 6 m
IV
1 AKUSTIK-uk : 30 X 30 lbr 4,500
30 X 60 lbr 12,000
60 X 120 lbr 38,000
List Kayu Profil m' 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 58,000
3 HARD BOARD-uk: 4'X 8' lbr 62,000
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 40,000
. 120 X 240 X 3 mm lbr 85,000
. 90 X 210 X 4 mm lbr 55,000
. 90 X 210 X 9 mm lbr 145,000
. 90 X 210 X 12 mm lbr 172,500
. 90 X 210 X 15 mm lbr 225,000
. 90 X 210 X 18 mm lbr 275,000
Tripleks
. 120 X 240 X 3 mm lbr 44,000
. 120 X 240 X 4 mm lbr 55,000
. 120 X 240 X 6 mm lbr 70,000
Multipleks
. 120 X 240 X 9 mm lbr 110,000
. 120 X 240 X 12 mm lbr 135,000
. 120 X 240 X 15 mm lbr 165,000
. 120 X 240 X 18 mm lbr 185,000
Formika ukuran pintu lbr 50,000
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
V
1 KAYU
Menie kg 15,000
Dempul plamur kg 12,000
Ambril/amplas lbr 3,200
Batu Apung kg 5,500
Cat dasar kg 13,200
. Emco kg 35,000
. Yunior 66 (nippon paint) kg 29,000
. Deculux kg 38,000
. Siralax ons 7,000
. Spiritus ltr 8,500
. Plitur jadi ltr 29,000
2 TEMBOK
Kalkarium kg 4,200
Kapur sirih kg 4,750
Plamur kg 10,000
Cat Tembok kg 54,000
Sintex 5 kg 55,000
Danabride 5 kg 62,500
Catylac 5 kg 140,000
Mowilex 5 kg 180,000
3 BESI
Menie kg 18,000
Cat mengkilat kg 37,000
Cat kg 13,000
Thinner A ltr 8,000
Minyak cat ltr 7,000
Thinner Super ltr 9,000
Residu (teer/aspal) drum 50,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 600,000
kapasitas 1100 liter. bh 900,000
Lem Aica Aibon kg 35,000
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
VI
1 POLOS 3 mm m2 55,000
5 mm m2 65,000
2 ES KABUR 3 mm m2 55,000
5 mm m2 70,000
1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 2,700
SPLN LMK 1 X 2 1/2 mm2 m' 3,150
. 1X4 mm2 m' 4,700
1X6 mm2 m' 6,900
NYY :. 2 X 1 1/2 mm2 m' 9,500
PRIMA 2 X 2 1/2 mm2 m' 10,500
. 2X4 mm2 m' 16,700
2X6 mm2 m' 20,500
3 X 1 1/2 mm2 m' 11,750
3 X 2 1/2 mm2 m' 15,750
3X4 mm2 m' 20,500
3X6 mm2 m' 28,000
NYM :. 2 X 1 1/2 mm2 m' 7,000
PRIMA 2 X 2 1/2 mm2 m' 10,000
. 2X4 mm2 m' 14,000
3 X 1 1/2 mm2 m' 9,000
3 X 2 1/2 mm2 m' 12,500
3X4 mm2 m' 18,000
3X6 mm2 m' 24,500
2 SKAKELAR
Out bauw . Seri bh 17,500
. Engkel bh 13,000
In bauw . Seri bh 15,000
. Engkel bh 11,000
VII
1 KUNCI TANAM Union : 1 X slag bh 45,000
2 X slag bh 55,000
Yale : 1 X slag bh 80,000
2 X slag bh 125,000
Kuda : 1 X slag bh 50,000
2 X slag bh 60,000
VIII
1 KLOSET DUDUK bh 900,000
2 KLOSET JONGKOK
bh 85,000
IX
1 PAKU - ukuran 1" s/d 4" kg 16,000
2 PAKU - payung kg 18,000
3 PAKU - sekrup dos 15,000
4 PAKU - beton bh 20,000
5 MUR BAUT (kuda-kuda) kg 15,000
6 ANGKUR BAUT bh 13,000
7 LEM KAYU bh 20,000
8 Tali Ijuk kg 7,000
9 Klem bh 7,500
XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 190,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 475,000
Fuji 250 watt bh 900,000
Shimizu . 100 watt bh 350,000
. 90 watt bh 220,000
Dab . 125 watt bh 250,000
. 175 watt bh 340,000
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 37,500
Merah/hitam m2 40,000
2 HOLLAND Abu-abu m2 36,000
Merah/hitam m2 41,000
3 UNIDECOR Abu-abu m2 35,000
Merah/hitam m2 40,000
4 UNI Abu-abu m2 37,000
Merah/hitam m2 42,000
5 TRIHEX Abu-abu m2 35,000
Merah/hitam m2 40,000
6 OLYMPIA HEXA Abu-abu m2 35,000
7 HEXAGONAL Abu-abu m2 37,000
Merah/hitam m2 42,000
8 CASTLE Abu-abu m2 35,000
9 TRAPEZ Abu-abu m2 35,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 42,000
11 STANDARD GRASS BLOCK ABU-ABU m2 48,000
12 BATACO bh 2,650
13 KANSTEEN m' 28,500
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000
2 Sliding Pintu J4 bh 200,000
3 Naco per Daun bh 7,500
4 Rolling door Besi m2 230,000
Rolling door Almunium m2 215,000
5 Awning Almunium m2 185,000
6 Kusen Almunium 4" Putih m' 80,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,512,000
8 ASPAL.
Aspal SPC 60/70 Ex Pertamina isi Net 160 kg drum 975,000
HARGA
NO. JENIS BAHAN BANGUNAN SATUAN SATUAN KETERANGAN
(Rp)
5 Reducer HDPE
Reducer 100 x 75 mm HDPE Rp. 500,000.00 / bh
Reducer 75 x 50 mm HDPE Rp. 400,000.00 / bh
Reducer All Flange 150 x 100 mm steel Rp. 500,000.00 / bh
Reducer All Flange 400 x 300 mm steel Rp. 1,250,000.00 / bh
Reducer All Flange 100 x 50 mm steel Rp. 450,000.00 / bh
6 Dismantling Joint
Dismantling Joint 100 mm Rp. 750,000.00 / bh
Dismantling Joint 300 mm Rp. 3,500,000.00 / bh
7 Tee All Socket PVC
Tee All Socket 50 x 50 x 50 mm PVC Rp. 292,680.00 / bh
Tee All Socket 75 x 50 x 75 mm PVC Rp. 384,360.00 / bh
Tee All Socket 75 x 75 x 75 mm PVC Rp. 384,360.00 / bh
Tee All Socket 100 x 50 x 100 mm PVC Rp. 412,560.00 / bh
Tee All Socket 100 x 75 x 100 mm PVC Rp. 416,640.00 / bh
Tee All Socket 100 x 100 x 100 mm PVC Rp. 415,200.00 / bh
Tee All Socket 150 x 50 x 150 mm PVC Rp. 531,240.00 / bh
Tee All Socket 150 x 75 x 150 mm PVC Rp. 549,000.00 / bh
Tee All Socket 150 x 100 x 150 mm PVC Rp. 566,760.00 / bh
Tee All Socket 150 x 150 x 150 mm PVC Rp. 568,680.00 / bh
Tee All Socket 200 x 50 x 200 mm PVC Rp. 627,480.00 / bh
Tee All Socket 200 x 75 x 200 mm PVC Rp. 676,680.00 / bh
Tee All Socket 200 x 100 x 200 mm PVC Rp. 729,600.00 / bh
Tee All Socket 200 x 150 x 200 mm PVC Rp. 821,160.00 / bh
Tee All Socket 200 x 200 x 200 mm PVC Rp. 947,760.00 / bh
Tee All Socket 250 x 50 x 250 mm PVC Rp. 1,050,960.00 / bh
Tee All Socket 250 x 75 x 250 mm PVC Rp. 1,092,720.00 / bh
Tee All Socket 250 x 100 x 250 mm PVC Rp. 1,132,680.00 / bh
Tee All Socket 250 x 150 x 250 mm PVC Rp. 1,221,480.00 / bh
Tee All Socket 250 x 200 x 250 mm PVC Rp. 1,478,160.00 / bh
Tee All Socket 250 x 250 x 250 mm PVC Rp. 1,599,120.00 / bh
Tee All Socket 300 x 50 x 300 mm PVC Rp. 1,367,160.00 / bh
Tee All Socket 300 x 75 x 300 mm PVC Rp. 1,501,680.00 / bh
Tee All Socket 300 x 100 x 300 mm PVC Rp. 1,560,600.00 / bh
Tee All Socket 300 x 150 x 300 mm PVC Rp. 1,649,400.00 / bh
Tee All Socket 300 x 200 x 300 mm PVC Rp. 1,800,000.00 / bh
Tee All Socket 300 x 250 x 300 mm PVC Rp. 2,100,000.00 / bh
Tee All Socket 300 x 300 x 300 mm PVC Rp. 2,391,480.00 / bh
Tee All Socket 400 x 50 x 400 mm PVC Rp. 3,167,280.00 / bh
Tee All Socket 400 x 75 x 400 mm PVC Rp. 3,415,560.00 / bh
Tee All Socket 400 x 100 x 400 mm PVC Rp. 3,480,000.00 / bh
Tee All Socket 400 x 150 x 400 mm PVC Rp. 3,780,000.00 / bh
Tee All Socket 400 x 200 x 400 mm PVC Rp. 3,996,000.00 / bh
Tee All Socket 400 x 250 x 400 mm PVC Rp. 4,200,000.00 / bh
Tee All Socket 400 x 300 x 400 mm PVC Rp. 4,500,000.00 / bh
Tee All Socket 400 x 400 x 400 mm PVC Rp. 4,782,840.00 / bh
Tee "Y" All Socket 250 x 250 x 250 mm PVC Rp. 2,900,400.00 / bh
Tee "Y" All Socket 300 x 300 x 300 mm PVC Rp. 3,323,760.00 / bh
8 All Flange Tee " Y " Steel
All Flange Tee " Y " 250 x 250 x 250 mm Stee Rp. 3,173,160.00 / bh
All Flange Tee " Y " 300 x 250 x 300 mm Stee Rp. 3,601,920.00 / bh
All Flange Tee " Y " 300 x 300 x 300 mm Stee Rp. 3,900,000.00 / bh
All Flange Tee " Y " 400 x 300 x 400 mm Stee Rp. 5,797,440.00 / bh
All Flange Tee " Y " 400 x 400 x 400 mm Stee Rp. 5,820,000.00 / bh
All Flange Tee 75 x 75 x 75 mm Steel Rp. 1,068,000.00 / bh
All Flange Tee 100 x 100 x 100 mm Steel Rp. 1,500,000.00 / bh
All Flange Tee 150 x 100 x 150 mm Steel Rp. 1,800,000.00 / bh
All Flange Tee 150 x 150 x 150 mm Steel Rp. 2,144,000.00 / bh
All Flange Tee 200 x 100 x 200 mm Steel Rp. 2,220,000.00 / bh
All Flange Tee 200 x 200 x 200 mm Steel Rp. 2,487,000.00 / bh
All Flange Tee 250 x 100 x 250 mm Steel Rp. 2,520,000.00 / bh
All Flange Tee 250 x 200 x 250 mm Steel Rp. 2,580,000.00 / bh
All Flange Tee 250 x 250 x 250 mm Steel Rp. 2,830,100.00 / bh
All Flange Tee 300 x 100 x 300 mm Steel Rp. 3,000,000.00 / bh
All Flange Tee 300 x 50 x 300 mm Steel Rp. 2,550,000.00 / bh
All Flange Tee 300 x 300 x 300 mm Steel Rp. 3,601,900.00 / bh
All Flange Tee 400 x 100 x 400 mm Steel Rp. 4,200,000.00 / bh
All Flange Tee Reducer 250 x 400 x 250 mm Ste Rp. 5,917,400.00 / bh
Tee 400 x 100 x 400 mm Steel (Pabrikasi) Rp. 1,500,000.00 / bh
Flange Steel 300 mm Rp. 1,010,400.00 / bh
Flange Steel 400 mm Rp. 1,212,480.00 / bh
Flange Spigot PVC
Flange Spigot 50 mm PVC Rp. 133,920.00 / bh
Flange Spigot 75 mm PVC Rp. 183,960.00 / bh
Flange Spigot 100 mm PVC Rp. 228,600.00 / bh
Flange Spigot 150 mm PVC Rp. 583,080.00 / bh
Flange Spigot 200 mm PVC Rp. 557,520.00 / bh
Flange Spigot 250 mm PVC Rp. 910,320.00 / bh
Flange Spigot 300 mm PVC Rp. 1,479,480.00 / bh
Flange Spigot 400 mm PVC Rp. 2,958,840.00 / bh
Flange Spigot 250 mm For ACP CI Rp. 1,322,760.00 / bh
Flange Spigot 300 mm For ACP CI Rp. 1,691,040.00 / bh
Flange Spigot 400 mm For ACP CI Rp. 2,110,200.00 / bh
9 Flange Socket PVC
Flange Socket 50 mm PVC Rp. 144,360.00 / bh
Flange Socket 75 mm PVC Rp. 199,200.00 / bh
Flange Socket 100 mm PVC Rp. 248,880.00 / bh
Flange Socket 150 mm PVC Rp. 419,760.00 / bh
Flange Socket 200 mm PVC Rp. 624,120.00 / bh
Flange Socket 250 mm PVC Rp. 1,023,960.00 / bh
Flange Socket 300 mm PVC Rp. 1,677,720.00 / bh
Flange Socket 400 mm PVC Rp. 3,355,440.00 / bh
10 Bend All Socket PVC
Bend All Socket 50 mm x 22 PVC Rp. 45,720.00 / bh
Bend All Socket 50 mm x 45 PVC Rp. 50,400.00 / bh
Bend All Socket 50 mm x 90 PVC Rp. 59,520.00 / bh
Bend All Socket 75 mm x 11 PVC Rp. 81,240.00 / bh
Bend All Socket 75 mm x 22 PVC Rp. 88,440.00 / bh
Bend All Socket 75 mm x 45 PVC Rp. 102,480.00 / bh
Bend All Socket 75 mm x 90 PVC Rp. 117,240.00 / bh
Bend All Socket 100 mm x 11 PVC Rp. 180,000.00 / bh
Bend All Socket 100 mm x 22 PVC Rp. 225,000.00 / bh
Bend All Socket 100 mm x 45 PVC Rp. 315,840.00 / bh
Bend All Socket 100 mm x 90 PVC Rp. 372,480.00 / bh
Bend All Socket 150 mm x 11 PVC Rp. 395,400.00 / bh
Bend All Socket 150 mm x 22 PVC Rp. 418,320.00 / bh
Bend All Socket 150 mm x 45 PVC Rp. 441,240.00 / bh
Bend All Socket 150 mm x 90 PVC Rp. 464,160.00 / bh
Bend All Socket 200 mm x 11 PVC Rp. 588,000.00 / bh
Bend All Socket 200 mm x 22 PVC Rp. 624,000.00 / bh
Bend All Socket 200 mm x 45 PVC Rp. 731,640.00 / bh
Bend All Socket 200 mm x 90 PVC Rp. 839,400.00 / bh
Bend All Socket 250 mm x 11 PVC Rp. 988,440.00 / bh
Bend All Socket 250 mm x 22 PVC Rp. 1,093,200.00 / bh
Bend All Socket 250 mm x 45 PVC Rp. 1,356,840.00 / bh
Bend All Socket 250 mm x 90 PVC Rp. 1,884,120.00 / bh
Bend All Socket 300 mm x 11 PVC Rp. 1,620,000.00 / bh
Bend All Socket 300 mm x 22 PVC Rp. 1,676,280.00 / bh
Bend All Socket 300 mm x 45 PVC Rp. 2,051,520.00 / bh
Bend All Socket 300 mm x 90 PVC Rp. 2,160,000.00 / bh
Bend All Socket 400 mm x 11 PVC Rp. 2,280,000.00 / bh
Bend All Socket 400 mm x 22 PVC Rp. 2,280,000.00 / bh
Bend All Socket 400 mm x 45 PVC Rp. 2,310,000.00 / bh
Bend All Socket 400 mm x 90 PVC Rp. 2,340,000.00 / bh
11 Reducer All Socket PVC
Reducer All Socket PVC 75 x 50 mm Rp. 64,920.00 / bh
Reducer All Socket PVC 100 x 50 mm Rp. 188,400.00 / bh
Reducer All Socket PVC 100 x 75 mm Rp. 196,800.00 / bh
Reducer All Socket PVC 150 x 100 mm Rp. 250,000.00 / bh
Reducer All Socket PVC 200 x 50 mm Rp. 262,440.00 / bh
Reducer All Socket PVC 200 x 75 mm Rp. 269,640.00 / bh
Reducer All Socket PVC 200 x 100 mm Rp. 276,840.00 / bh
Reducer All Socket PVC 200 x 150 mm Rp. 284,040.00 / bh
Reducer All Socket PVC 250 x 50 mm Rp. - / bh
Reducer All Socket PVC 250 x 75 mm Rp. 450,000.00 / bh
Reducer All Socket PVC 250 x 100 mm Rp. 494,040.00 / bh
Reducer All Socket PVC 250 x 150 mm Rp. - / bh
Reducer All Socket PVC 250 x 200 mm Rp. 818,640.00 / bh
Reducer All Socket PVC 300 x 50 mm Rp. - / bh
Reducer All Socket PVC 300 x 75 mm Rp. - / bh
Reducer All Socket PVC 300 x 100 mm Rp. - / bh
Reducer All Socket PVC 300 x 150 mm Rp. - / bh
Reducer All Socket PVC 300 x 200 mm Rp. 798,720.00 / bh
Reducer All Socket PVC 300 x 250 mm Rp. - / bh
Reducer All Socket PVC 400 x 50 mm Rp. - / bh
Reducer All Socket PVC 400 x 75 mm Rp. - / bh
Reducer All Socket PVC 400 x 100 mm Rp. - / bh
Reducer All Socket PVC 400 x 150 mm Rp. - / bh
Reducer All Socket PVC 400 x 200 mm Rp. - / bh
Reducer All Socket PVC 400 x 250 mm Rp. - / bh
Reducer All Socket PVC 400 x 300 mm Rp. 1,597,560.00 / bh
Reducer All Flange Steel 100 x 75 mm Rp. 750,000.00 / bh
12 Repair Socket PVC
Repair Socket PVC 50 mm Rp. 28,200.00 / bh
Repair Socket PVC 75 mm Rp. 44,280.00 / bh
Repair Socket PVC 100 mm Rp. 62,880.00 / bh
Repair Socket PVC 150 mm Rp. 117,840.00 / bh
Repair Socket PVC 200 mm Rp. 198,480.00 / bh
Repair Socket PVC 250 mm Rp. 308,400.00 / bh
Repair Socket PVC 300 mm Rp. 525,480.00 / bh
Repair Socket PVC 400 mm Rp. 1,051,080.00 / bh
13 Collar For PVC
Collar 100 mm For PVC Rp. 1,372,200.00 / bh
Collar 150 mm For PVC Rp. 1,543,680.00 / bh
Collar 200 mm For PVC Rp. 1,715,160.00 / bh
Collar 250 mm For PVC Rp. 1,886,760.00 / bh
Collar 300 mm For PVC Rp. 2,058,240.00 / bh
Collar 400 mm For PVC Rp. 2,229,720.00 / bh
14 Foucet Socket Gip to PVC
Foucet Socket Gip to PVC 50 mm Rp. 45,720.00 / bh
Foucet Socket Gip to PVC 75 mm Rp. 138,240.00 / bh
Foucet Socket Gip to PVC 100 mm Rp. 204,720.00 / bh
Foucet Socket Gip to PVC 150 mm Rp. 212,280.00 / bh
15 Bend All Flange Steel
Bend All Flange 90 50 mm Steel Rp. 900,000.00 / bh
Bend All Flange 90 75 mm Steel Rp. 1,200,000.00 / bh
Bend All Flange 90 100 mm Steel Rp. 1,500,840.00 / bh
Bend All Flange 90 150 mm Steel Rp. 1,689,480.00 / bh
Bend All Flange 90 200 mm Steel Rp. 1,912,440.00 / bh
Bend All Flange 90 250 mm Steel Rp. 2,058,240.00 / bh
Bend All Flange 90 300 mm Steel Rp. 2,830,080.00 / bh
Bend All Flange 90 400 mm Steel Rp. 3,000,000.00 / bh
Bend All Flange 45 50 mm Steel Rp. 694,680.00 / bh
Bend All Flange 45 75 mm Steel Rp. 840,480.00 / bh
Bend All Flange 45 100 mm Steel Rp. 1,484,520.00 / bh
Bend All Flange 45 150 mm Steel Rp. 1,643,160.00 / bh
Bend All Flange 45 200 mm Steel Rp. 1,972,440.00 / bh
Bend All Flange 45 250 mm Steel Rp. 2,315,520.00 / bh
Bend All Flange 45 300 mm Steel Rp. 2,668,080.00 / bh
Bend All Flange 45 400 mm Steel Rp. 2,880,000.00 / bh
Bend All Flange 22 250 mm Steel Rp. 2,058,240.00 / bh
Bend All Flange 22 300 mm Steel Rp. 2,744,280.00 / bh
16 Kleam Pipa
Kleam Pipa 50 mm Rp. 140,280.00 / bh
Kleam Pipa 75 mm Rp. 172,680.00 / bh
Kleam Pipa 100 mm Rp. 205,080.00 / bh
Kleam Pipa 150 mm Rp. 237,480.00 / bh
Kleam Pipa 200 mm Rp. 269,760.00 / bh
Kleam Pipa 250 mm Rp. 394,320.00 / bh
Kleam Pipa 300 mm Rp. 552,000.00 / bh
Kleam Pipa 400 mm Rp. 788,640.00 / bh
17 Cup / Dop
Cup / Dop 50 mm Rp. 42,360.00 / bh
Cup / Dop 75 mm Rp. 57,120.00 / bh
Cup / Dop 100 mm Rp. 113,160.00 / bh
Cup / Dop 150 mm Rp. 168,240.00 / bh
Cup / Dop 200 mm Rp. 258,840.00 / bh
Cup / Dop 250 mm Rp. 348,600.00 / bh
Cup / Dop 300 mm Rp. - / bh
Cup / Dop 400 mm Rp. - / bh
18 Loose Flange
Loose Flange 50 mm Rp. 134,520.00 / bh
Loose Flange 75 mm Rp. 167,520.00 / bh
Loose Flange 100 mm Rp. 180,120.00 / bh
Loose Flange 125 mm Rp. 257,520.00 / bh
Loose Flange 150 mm Rp. 334,920.00 / bh
Loose Flange 200 mm Rp. 445,920.00 / bh
Loose Flange 250 mm Rp. 566,040.00 / bh
Loose Flange 300 mm Rp. 707,520.00 / bh
Loose Flange 400 mm Rp. 1,543,680.00 / bh
Loose Sleeve Steel 100 mm Rp. 294,480.00 / bh
Loose Sleeve Steel 150 mm Rp. 412,200.00 / bh
Loose Sleeve Steel 200 mm Rp. 498,000.00 / bh
Loose Sleeve Steel 250 mm Rp. 686,040.00 / bh
19 Gate Valve
Gate Valve 50 mm Rp. 2,511,120.00 / bh
Gate Valve 75 mm Rp. 2,872,920.00 / bh
Gate Valve 100 mm Rp. 3,001,560.00 / bh
Gate Valve 150 mm Rp. 5,555,520.00 / bh
Gate Valve 200 mm Rp. 11,836,680.00 / bh
Gate Valve 250 mm Rp. 14,797,080.00 / bh
Gate Valve 300 mm Rp. 19,296,120.00 / bh
Gate Valve 350 mm Rp. 20,609,400.00 / bh
Gate Valve 400 mm Rp. 22,200,000.00 / bh
20 Butterfly Valve
Butterfly Valve 50 mm Rp. 3,987,840.00 / bh
Butterfly Valve 75 mm Rp. 6,020,400.00 / bh
Butterfly Valve 100 mm Rp. 8,052,840.00 / bh
Butterfly Valve 150 mm Rp. 10,085,400.00 / bh
Butterfly Valve 200 mm Rp. 12,117,960.00 / bh
Butterfly Valve 250 mm Rp. 14,150,400.00 / bh
Butterfly Valve 300 mm Rp. 21,097,080.00 / bh
Butterfly Valve 400 mm Rp. 23,129,520.00 / bh
21 Check Valve
Check Valve 50 mm Rp. 3,987,840.00 / bh
Check Valve 75 mm Rp. 6,020,400.00 / bh
Check Valve 100 mm Rp. 8,052,840.00 / bh
Check Valve 150 mm Rp. 10,085,400.00 / bh
Check Valve 200 mm Rp. 12,117,960.00 / bh
Check Valve 250 mm Rp. 14,150,400.00 / bh
Check Valve 300 mm Rp. 21,097,080.00 / bh
Check Valve 400 mm Rp. 23,129,520.00 / bh
22 Floting Valve 250 mm Rp. 13,800,000.00 / bh
23 Screen 250 mm Rp. 6,000,000.00 / bh
24 Air Valve
Single Air Valve 50 mm Rp. 1,500,000.00 / bh
Double Air Valve 50 mm Rp. 2,500,000.00 / bh
Double Air Valve 100 mm Rp. 4,800,000.00 / bh
25 Gibault Joint CI
Gibault Joint 100 mm CI Rp. 500,000.00 / bh
Gibault Joint 150 mm CI Rp. 1,080,000.00 / bh
Gibault Joint 200 mm CI Rp. 1,500,000.00 / bh
Gibault Joint 250 mm CI Rp. 2,100,000.00 / bh
Gibault Joint 300 mm CI Rp. 2,400,000.00 / bh
Gibault Joint 400 mm CI Rp. 2,580,000.00 / bh
26 Dismantling Joint
Dismantling Joint 100 mm Rp. - / bh
Dismantling Joint 150 mm Rp. - / bh
Dismantling Joint 200 mm Rp. - / bh
Dismantling Joint 250 mm Rp. 1,792,440.00 / bh
Dismantling Joint 300 mm Rp. 2,214,360.00 / bh
Dismantling Joint 400 mm Rp. 3,169,680.00 / bh
27 Blind Flange
Blind Flange 50 mm Rp. 163,080.00 / bh
Blind Flange 75 mm Rp. 201,480.00 / bh
Blind Flange 100 mm Rp. 240,000.00 / bh
Blind Flange 150 mm Rp. 438,840.00 / bh
Blind Flange 200 mm Rp. 599,400.00 / bh
Blind Flange 250 mm Rp. 856,800.00 / bh
Blind Flange 300 mm Rp. 1,114,200.00 / bh
Blind Flange 400 mm Rp. 1,500,000.00 / bh
28 Water Meter
Water Meter 50 mm Rp. 3,000,000.00 / bh
Water Meter 75 mm Rp. 4,200,000.00 / bh
Water Meter 100 mm Rp. 4,950,000.00 / bh
Water Meter 150 mm Rp. 7,500,000.00 / bh
Water Meter 200 mm Rp. 20,040,000.00 / bh
Water Meter 250 mm Rp. 25,560,000.00 / bh
HARGA
NO JENIS BAHAN PERPIPAAN SATUAN SATUAN KETERANGAN
(Rp)
A. PIPA
I Pipa PE
1 Pipa PE 100 SDR 21 50 mm /m' 25,060.00
2 Pipa PE 100 SDR 17 50 mm /m' 31,230.00
3 Pipa PE 100 SDR 13.6 50 mm /m' 37,850.00
4 Pipa PE 100 SDR 21 75 mm /m' 51,830.00
5 Pipa PE 100 SDR 17 75 mm /m' 63,830.00
6 Pipa PE 100 SDR 13.6 75 mm /m' 76,740.00
7 Pipa PE 100 SDR 21 100 mm /m' 77,830.00
8 Pipa PE 100 SDR 17 100 mm /m' 95,240.00
9 Pipa PE 100 SDR 13.6 100 mm /m' 115,340.00
10 Pipa PE 100 SDR 21 150 mm /m' 165,580.00
11 Pipa PE 100 SDR 17 150 mm /m' 201,710.00
12 Pipa PE 100 SDR 13.6 150 mm /m' 246,440.00
13 Pipa PE 100 SDR 21 200 mm /m' 329,550.00
14 Pipa PE 100 SDR 17 200 mm /m' 404,450.00
15 Pipa PE 100 SDR 13.6 200 mm /m' 492,220.00
16 Pipa PE 100 SDR 21 250 mm /m' 513,240.00
17 Pipa PE 100 SDR 17 250 mm /m' 627,390.00
18 Pipa PE 100 SDR 13.6 250 mm /m' 766,020.00
19 Pipa PE 100 SDR 21 300 mm /m' 647,790.00
20 Pipa PE 100 SDR 17 300 mm /m' 721,372.50
21 Pipa PE 100 SDR 13.6 300 mm /m' 974,520.00
22 Pipa PE 355 mm, SDR = 13,6 ( PN 12,5 ) /m' 1,158,530.00
23 Pipa PE 355 mm, SDR = 17 ( PN 10 ) /m' 952,210.00
24 Pipa PE 100 SDR 21 400 mm /m' 1,056,280.00
25 Pipa PE 100 SDR 17 400 mm /m' 1,292,280.00
26 Pipa PE 100 SDR 13.6 400 mm /m' 1,578,270.00
II Pipa PVC
1 Pipa PVC 10 mm (SCJ), S=12.5 (PN 10) /m' 11,930.00
2 Pipa PVC 50 mm (SCJ), S=12.5 (PN 10) /m' 15,800.00
3 Pipa PVC 75 mm (RRJ), S=12.5 (PN 10) /m' 35,500.00
4 Pipa PVC 100 mm (RRJ), S=12.5 (PN 10) /m' 75,800.00
5 Pipa PVC 150 mm (RRJ), S=12.5 (PN 10) /m' 162,800.00
7 Pipa PVC 200 mm (RRJ), S=12.5 (PN 10) /m' 253,000.00
8 Pipa PVC 250 mm (RRJ), S=12.5 (PN 10) /m' 399,700.00
9 Pipa PVC 300 mm (RRJ), S=12.5 (PN 10) /m' 639,900.00
10 Pipa PVC 350 mm (RRJ), S=12.5 (PN 10) /m' 941,470.00
11 Pipa PVC 400 mm (RRJ), S=12.5 (PN 10) /m' 1,049,000.00
12 Pipa PVC 400 mm (RRJ), S=10 (PN 12,5) /m' 1,290,000.00
13 Pipa PVC 450mm (RRJ), S=12.5 (PN 10) /m' 1,399,000.00
12 Pipa PVC 450 mm (RRJ), S=10 (PN 12,5) /m' 1,723,000.00
13 Pipa PVC 500 mm (RRJ), S=12.5 (PN 10) /m' 1,738,000.00
12 Pipa PVC 500 mm (RRJ), S=10 (PN 12,5) /m' 2,142,000.00
B. ACCESSORIES PIPA
I Wall Pipe
Wall Pipe CI 0,6 M
1 Wall pipe CI AF 100 mm /bh 600,000.00
2 Wall pipe CI AF 150 mm /bh 880,000.00
3 Wall pipe CI AF 200 mm /bh 1,400,000.00
4 Wall pipe CI AF 250 mm /bh 1,800,000.00
5 Wall pipe CI AF 300 mm /bh 2,200,000.00
6 Wall pipe CI AF 350 mm /bh 2,400,000.00
7 Wall pipe CI AF 400 mm /bh 2,600,000.00
8 Wall pipe CI AF 450 mm /bh 3,200,000.00
9 Wall pipe CI AF 500 mm /bh 3,800,000.00
10 Wall pipe CI AF 600 mm /bh 4,600,000.00
II Bend CI
1 Bend All Flange CI 50 mm x 90 /bh 178,000.00
2 Bend All Flange CI 75 mm x 90 /bh 260,000.00
3 Bend All Flange CI 100 mm x 90 /bh 340,000.00
4 Bend All Flange CI 150 mm x 90 /bh 600,000.00
5 Bend All Flange CI 200 mm x 90 /bh 816,000.00
6 Bend All Flange CI 250 mm x 90 /bh 1,200,000.00
7 Bend All Flange CI 300 mm x 90 /bh 1,700,000.00
8 Bend All Flange CI 350 mm x 90 /bh 2,200,000.00
9 Bend All Flange CI 400 mm x 90 /bh 4,680,000.00
10 Bend All Flange CI 450 mm x 90 /bh 5,600,000.00
11 Bend All Flange CI 500 mm x 90 /bh 7,200,000.00
12 Bend All Flange CI 600 mm x 90 /bh 11,000,000.00
13 Bend All Flange CI 50 mm x 45 /bh 160,000.00
14 Bend All Flange CI 75 mm x 45 /bh 240,000.00
15 Bend All Flange CI 100 mm x 45 /bh 282,000.00
16 Bend All Flange CI 150 mm x 45 /bh 500,000.00
17 Bend All Flange CI 200 mm x 45 /bh 720,000.00
18 Bend All Flange CI 250 mm x 45 /bh 1,100,000.00
19 Bend All Flange CI 300 mm x 45 /bh 1,520,000.00
20 Bend All Flange CI 350 mm x 45 /bh 1,900,000.00
21 Bend All Flange CI 400 mm x 45 /bh 2,400,000.00
22 Bend All Flange CI 450 mm x 45 /bh 4,400,000.00
23 Bend All Flange CI 500 mm x 45 /bh 5,600,000.00
24 Bend All Flange CI 600 mm x 45 /bh 7,400,000.00
25 Bend All Flange CI 50 mm x 22,5 /bh 160,000.00
26 Bend All Flange CI 75 mm x 22,5 /bh 240,000.00
27 Bend All Flange CI 100 mm x 22,5 /bh 282,000.00
28 Bend All Flange CI 150 mm x 22,5 /bh 500,000.00
29 Bend All Flange CI 200 mm x 22,5 /bh 720,000.00
30 Bend All Flange CI 250 mm x 22,5 /bh 1,100,000.00
31 Bend All Flange CI 300 mm x 22,5 /bh 1,520,000.00
32 Bend All Flange CI 350 mm x 22,5 /bh 1,900,000.00
33 Bend All Flange CI 400 mm x 22,5 /bh 2,400,000.00
34 Bend All Flange CI 450 mm x 22,5 /bh 4,400,000.00
35 Bend All Flange CI 500 mm x 22,5 /bh 5,600,000.00
36 Bend All Flange CI 600 mm x 22,5 /bh 7,400,000.00
37 Bend 45 ( Fitting Segmented PE ) 355 mm /bh 1,181,300.00
38 Bend 90 ( Fitting Segmented PE ) 355 mm /bh 1,631,300.00
39 Bend PVC D Sock RR 400 mm x 90 /bh 3,274,800.00
40 Bend PVC D Sock RR 400 mm x 45 /bh 3,274,800.00
41 Bend PVC D Sock RR 400 mm x 22,5 /bh 2,534,900.00
42 Bend PVC D Sock RR 150 mm x 45 /bh 376,550.00
VI Gate Valve
1 Gate Valve 50 mm /bh 1,400,000.00
2 Gate Valve 75 mm /bh 1,700,000.00
3 Gate Valve 100 mm /bh 2,650,000.00
4 Gate Valve 150 mm /bh 4,200,000.00
5 Gate Valve 200 mm /bh 6,300,000.00
6 Gate Valve 250 mm /bh 10,400,000.00
7 Gate Valve 300 mm /bh 13,200,000.00
8 Gate Valve 350 mm /bh 19,900,000.00
9 Gate Valve 400 mm /bh 32,000,000.00
10 Gate Valve 450 mm /bh 45,000,000.00
11 Gate Valve 500 mm /bh 75,000,000.00
12 Gate Valve 600 mm /bh 150,000,000.00
IX Las Flange
1 Las Flange 75 mm /bh 202,000.00
2 Las Flange 100 mm /bh 272,000.00
3 Las Flange 150 mm /bh 303,000.00
4 Las Flange 200 mm /bh 421,300.00
5 Las Flange 250 mm /bh 463,000.00
6 Las Flange 300 mm /bh 770,550.00
7 Las Flange 350 mm /bh 938,000.00
8 Las Flange 400 mm /bh 1,366,000.00
9 Las Flange 500 mm /bh 2,575,500.00
10 Las Flange 600 mm /bh 3,734,000.00
XXVIIIWater Meter
1 Water Meter 50 mm /bh 3,000,000.00
2 Water Meter 75 mm /bh 4,200,000.00
3 Water Meter 100 mm /bh 4,950,000.00
4 Water Meter 150 mm /bh 7,500,000.00
5 Water Meter 200 mm /bh 20,040,000.00
6 Water Meter 250 mm /bh 25,560,000.00
7 Water Meter 300 mm /bh 41,280,000.00
8 Water Meter 400 mm /bh 62,880,000.00
9 Strainer 50 mm /bh 292,160.00
10 Strainer 75 mm /bh 365,200.00
11 Strainer 100 mm /bh 456,500.00
12 Strainer 150 mm /bh 837,000.00
13 Strainer 200 mm /bh 1,304,300.00
14 Strainer 250 mm /bh 2,010,900.00
15 Strainer 300 mm /bh 2,554,300.00
16 Strainer 350 mm /bh 3,750,000.00
17 Strainer 400 mm /bh 4,565,200.00
18 Strainer 500 mm /bh 7,245,639.00
19 Strainer 600 mm /bh 9,782,600.00
20 Paking 50 mm /bh 21,000.00
21 Paking 75 mm /bh 31,560.00
22 Paking 100 mm /bh 42,120.00
23 Paking 125 mm /bh 52,560.00
24 Paking 150 mm /bh 63,120.00
25 Paking 200 mm /bh 84,120.00
26 Paking 250 mm /bh 105,120.00
27 Paking 300 mm /bh 126,240.00
28 Paking 400 mm /bh 168,240.00
29 Mur + Baut M 3 " /bh 15,720.00
30 Mur + Baut M 4 " /bh 19,920.00
31 Mur + Baut M 6 " /bh 28,320.00
32 Street Box 100 mm CI /bh 336,480.00
33 Street Box 150 mm s/d 300 mm CI /bh 389,040.00
34 Hydrophore 2 M /bh 58,884,000.00
35 Besi H WF 100 x 100 mm /bh 350,640.00
36 Besi H WF 202 x 187 mm /bh 701,400.00
37 Besi H WF 300 x 300 mm /bh 1,200,000.00
38 Besi UNP 150 x 75 mm /bh 546,840.00
39 Sambungan H WF /bh 100,000.00
40 Clamp Sadle For ACP 200 x 150 mm /bh 747,000.00
41 Clamp Sadle For ACP 250 x 75 mm /bh 715,080.00
42 Clamp Sadle For ACP 250 x 50 mm /bh 662,880.00
43 Bellmouth CI 400 mm /bh 1,620,000.00
44 Manometer 10 bar /bh 163,100.00
45 Single Air Valve 50 mm /bh 1,290,000.00
46 Single Air Valve 75 mm /bh 1,715,000.00
47 Single Air Valve 100 mm /bh 3,250,000.00
48 Double Air Valve 50 mm /bh 3,200,000.00
49 Double Air Valve 75 mm /bh 4,050,000.00
50 Double Air Valve 100 mm /bh 5,300,000.00
51 Ball valve 1/2" + accessories /bh 61,500.00
52 Blind Flange CI 350 mm /bh 609,000.00
53 Blind Flange CI 400 mm /bh 680,000.00
54 Tapping Saddle CI 355 mm x 75 mm /bh 605,000.00
55 Tapping Saddle CI 200 mm x 75 mm /bh 242,000.00
56 Stub Flange ( Fitting Segmented PE ) 355 mm /bh 3,197,700.00
57 Tapping Saddle CI 400 mm x 75 mm /bh 725,000.00
58 Street Box 150 mm /bh 103,000.00
59 Dop 300 mm HDPE m 400,000.00
60 Waterstop 20 m m 50,000.00
61 Alat Bantu Ls 100,000.00
62 Alat Bantu Ls 5,000.00
63 Mesin Las Ls 75,000.00
DAFTAR ANALISA PEKERJAAN PERPIPAAN
Hitung.P.02 Pengadaan dan Pemasangan Pipa PVC ND 75 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 75 mm (RRJ), S=12.5 (PN 10) 35,500.00 35,500.00 35,500.00
0.2906 m3 Galian Tanah 36,600.00 10,636.88 10,636.88
0.2862 m3 Urugan Kembali Dipadatkan 12,200.00 3,491.75 3,491.75
0.0350 Pekerja 35,000.00 1,225.00 1,225.00
0.0250 Tukang Pipa 45,000.00 1,125.00 1,125.00
0.0025 Kepala Tukang Pipa 50,000.00 125.00 125.00
0.0075 Mandor 50,000.00 375.00 375.00
1.0000 Ls Alat Bantu 1,000.00 1,000.00 1,000.00
2,850.00 50,628.63 53,478.63
Hitung.P.03 Pengadaan dan Pemasangan Pipa PVC ND 100 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 100 mm (RRJ), S=12.5 (PN 10) 75,800.00 75,800.00 75,800.00
0.3600 m3 Galian Tanah 36,600.00 13,176.00 13,176.00
0.3522 m3 Urugan Kembali Dipadatkan 12,200.00 4,296.23 4,296.23
0.2550 Pekerja 35,000.00 8,925.00 8,925.00
0.0850 Tukang Pipa 45,000.00 3,825.00 3,825.00
0.0080 Kepala Tukang Pipa 50,000.00 400.00 400.00
0.0120 Mandor 50,000.00 600.00 600.00
1.0000 Ls Alat Bantu 1,500.00 1,500.00 1,500.00
13,750.00 94,772.23 108,522.23
Hitung.P.04 Pengadaan dan Pemasangan Pipa PVC ND 150 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 150 mm (RRJ), S=12.5 (PN 10) 162,800.00 162,800.00 162,800.00
0.5850 m3 Galian Tanah 36,600.00 21,411.00 21,411.00
0.5673 m3 Urugan Kembali Dipadatkan 12,200.00 6,921.52 6,921.52
0.4000 Pekerja 35,000.00 14,000.00 14,000.00
0.1350 Tukang Pipa 45,000.00 6,075.00 6,075.00
0.0130 Kepala Tukang Pipa 50,000.00 650.00 650.00
0.0200 Mandor 50,000.00 1,000.00 1,000.00
1.0000 Ls Alat Bantu 2,000.00 2,000.00 2,000.00
21,725.00 193,132.52 214,857.52
Hitung.P.05 Pengadaan dan Pemasangan Pipa PVC ND 200 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 200 mm (RRJ), S=12.5 (PN 10) 253,000.00 253,000.00 253,000.00
0.7000 m3 Galian Tanah 36,600.00 25,620.00 25,620.00
0.6686 m3 Urugan Kembali Dipadatkan 12,200.00 8,156.92 8,156.92
0.4460 Pekerja 35,000.00 15,610.00 15,610.00
0.1720 Tukang Pipa 45,000.00 7,740.00 7,740.00
0.0186 Kepala Tukang Pipa 50,000.00 930.00 930.00
0.0260 Mandor 50,000.00 1,300.00 1,300.00
1.0000 Ls Alat Bantu 2,500.00 2,500.00 2,500.00
25,580.00 289,276.92 314,856.92
Hitung.P.06 Pengadaan dan Pemasangan Pipa PVC ND 250 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 250 mm (RRJ), S=12.5 (PN 10) 399,700.00 399,700.00 399,700.00
0.8525 m3 Galian Tanah 36,600.00 31,201.50 31,201.50
0.8034 m3 Urugan Kembali Dipadatkan 12,200.00 9,801.94 9,801.94
0.6200 Pekerja 35,000.00 21,700.00 21,700.00
0.1860 Tukang Pipa 45,000.00 8,370.00 8,370.00
0.0186 Kepala Tukang Pipa 50,000.00 930.00 930.00
0.0280 Mandor 50,000.00 1,400.00 1,400.00
1.0000 Ls Alat Bantu 3,000.00 3,000.00 3,000.00
32,400.00 443,703.44 476,103.44
Hitung.P.07 Pengadaan dan Pemasangan Pipa PVC ND 300 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 300 mm (RRJ), S=12.5 (PN 10) 639,900.00 639,900.00 639,900.00
0.9600 m3 Galian Tanah 36,600.00 35,136.00 35,136.00
0.8894 m3 Urugan Kembali Dipadatkan 12,200.00 10,850.07 10,850.07
0.7450 Pekerja 35,000.00 26,075.00 26,075.00
0.1900 Tukang Pipa 45,000.00 8,550.00 8,550.00
0.0190 Kepala Tukang Pipa 50,000.00 950.00 950.00
0.0300 Mandor 50,000.00 1,500.00 1,500.00
1.0000 Ls Alat Bantu 3,500.00 3,500.00 3,500.00
37,075.00 689,386.07 726,461.07
Hitung.P.08 Pengadaan dan Pemasangan Pipa PVC ND 350 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 350 mm (RRJ), S=12.5 (PN 10) 941,470.00 941,470.00 941,470.00
1.0725 m3 Galian Tanah 36,600.00 39,253.50 39,253.50
0.9763 m3 Urugan Kembali Dipadatkan 12,200.00 11,911.32 11,911.32
0.8100 Pekerja 35,000.00 28,350.00 28,350.00
0.1930 Tukang Pipa 45,000.00 8,685.00 8,685.00
0.0193 Kepala Tukang Pipa 50,000.00 965.00 965.00
0.0310 Mandor 50,000.00 1,550.00 1,550.00
1.0000 Ls Alat Bantu 4,000.00 4,000.00 4,000.00
39,550.00 996,634.82 1,036,184.82
Hitung.P.09 Pengadaan dan Pemasangan Pipa PVC ND 400 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 400 mm (RRJ), S=12.5 (PN 10) 1,049,000.00 1,049,000.00 1,049,000.00
1.5200 m3 Galian Tanah 36,600.00 55,632.00 55,632.00
1.3944 m3 Urugan Kembali Dipadatkan 12,200.00 17,011.68 17,011.68
0.9100 Pekerja 35,000.00 31,850.00 31,850.00
0.1960 Tukang Pipa 45,000.00 8,820.00 8,820.00
0.0196 Kepala Tukang Pipa 50,000.00 980.00 980.00
0.0320 Mandor 50,000.00 1,600.00 1,600.00
1.0000 Ls Alat Bantu 4,500.00 4,500.00 4,500.00
43,250.00 1,126,143.68 1,169,393.68
Hitung.P.10 Pengadaan dan Pemasangan Pipa PVC ND 450 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 450 mm (RRJ), S=12.5 (PN 10) 1,399,000.00 1,399,000.00 1,399,000.00
1.6575 m3 Galian Tanah 36,600.00 60,664.50 60,664.50
1.4985 m3 Urugan Kembali Dipadatkan 12,200.00 18,282.16 18,282.16
1.0000 Pekerja 35,000.00 35,000.00 35,000.00
0.1980 Tukang Pipa 45,000.00 8,910.00 8,910.00
0.0198 Kepala Tukang Pipa 50,000.00 990.00 990.00
0.0330 Mandor 50,000.00 1,650.00 1,650.00
1.0000 Ls Alat Bantu 5,000.00 5,000.00 5,000.00
46,550.00 1,482,946.66 1,529,496.66
Hitung.P.11 Pengadaan dan Pemasangan Pipa PVC ND 450 mm (RRJ), S=10 (PN 12,5) per m'
1.0000 m' Pipa PVC ND 450 mm (RRJ), S=10 (PN 12,5) 1,723,000.00 1,723,000.00 1,723,000.00
1.6575 m3 Galian Tanah 36,600.00 60,664.50 60,664.50
1.4985 m3 Urugan Kembali Dipadatkan 12,200.00 18,282.16 18,282.16
1.0000 Pekerja 35,000.00 35,000.00 35,000.00
0.1980 Tukang Pipa 45,000.00 8,910.00 8,910.00
0.0198 Kepala Tukang Pipa 50,000.00 990.00 990.00
0.0330 Mandor 50,000.00 1,650.00 1,650.00
1.0000 Ls Alat Bantu 5,000.00 5,000.00 5,000.00
46,550.00 1,806,946.66 1,853,496.66
Hitung.P.12 Pengadaan dan Pemasangan Pipa PVC ND 500 mm (RRJ), S=12.5 (PN 10) per m'
1.0000 m' Pipa PVC ND 500 mm (RRJ), S=12.5 (PN 10) 1,738,000.00 1,738,000.00 1,738,000.00
1.8000 m3 Galian Tanah 36,600.00 65,880.00 65,880.00
1.6038 m3 Urugan Kembali Dipadatkan 12,200.00 19,565.75 19,565.75
1.0900 Pekerja 35,000.00 38,150.00 38,150.00
0.2000 Tukang Pipa 45,000.00 9,000.00 9,000.00
0.0200 Kepala Tukang Pipa 50,000.00 1,000.00 1,000.00
0.0400 Mandor 50,000.00 2,000.00 2,000.00
1.0000 Ls Alat Bantu 6,500.00 6,500.00 6,500.00
50,150.00 1,829,945.75 1,880,095.75
Hitung.P.17 Pengadaan dan Pemasangan Pipa GI ND 200 mm per m' dan Klem
1.0000 m' Pipa GI F 200 mm 1,080,860.00 1,080,860.00 1,080,860.00
0.2100 kg kawat las 19,000.00 3,989.05 3,989.05
1.0099 lt solar 11,285.00 11,396.16 11,396.16
0.1340 lot Mesin las 75,000.00 10,050.00 10,050.00
0.3160 lot Alat bantu 100,000.00 31,600.00 31,600.00
2.0000 bh Klem 7,500.00 15,000.00 15,000.00
0.3160 Pekerja 35,000.00 11,060.00 11,060.00
0.1340 Tukang Las 45,000.00 6,030.00 6,030.00
0.1340 Tukang Pipa 45,000.00 6,030.00 6,030.00
0.0130 Kepala Tukang Pipa 50,000.00 650.00 650.00
0.0480 Mandor 50,000.00 2,400.00 2,400.00
0.1000 Biaya Overhead Pemasangan 26,170.00 2,617.00 2,617.00
28,787.00 1,137,895.21 1,181,682.21
PVC
Taksir Bend PVC F 50 mm x 90O
1.0000 bh Bend PVC F 50 mm x 90O 59,520.00 59,520.00 59,520.00
0.0200 lot Alat bantu 100,000.00 2,000.00 2,000.00
0.0200 Pekerja 35,000.00 700.00 700.00
0.1000 Tukang Pipa 45,000.00 4,500.00 4,500.00
0.0100 Kepala Tukang Pipa 50,000.00 500.00 500.00
0.0020 Mandor 50,000.00 100.00 100.00
5,800.00 61,520.00 67,320.00
Taksir Bend PVC F 75 mm x 90O
1.0000 bh Bend PVC F 75 mm x 90O 117,240.00 117,240.00 117,240.00
0.0200 lot Alat bantu 100,000.00 2,000.00 2,000.00
0.0200 Pekerja 35,000.00 700.00 700.00
0.1000 Tukang Pipa 45,000.00 4,500.00 4,500.00
0.0100 Kepala Tukang Pipa 50,000.00 500.00 500.00
0.0020 Mandor 50,000.00 100.00 100.00
5,800.00 119,240.00 125,040.00
GI
Taksir Tee All Flange F 75 x 75 x 75 mm
1.0000 bh Tee All Flange F 75 x 75 x 75 mm 342,400.00 342,400.00 342,400.00
0.1000 lot Alat bantu 100,000.00 10,000.00 10,000.00
0.1250 Pekerja 35,000.00 4,375.00 4,375.00
0.2500 Tukang Pipa 45,000.00 11,250.00 11,250.00
0.0250 Kepala Tukang Pipa 50,000.00 1,250.00 1,250.00
0.0025 Mandor 50,000.00 125.00 125.00
0.1000 Biaya Overhead Pemasangan 17,000.00 1,700.00 1,700.00
18,700.00 352,400.00 371,100.00
HARGA SATUAN
NO. KODE ANALISA JENIS PEKERJAAN
(Rp.)
III PENGADAAN DAN PEMASANGAN BEND (termasuk mur baut dan packing)
Taksir Bend All Flange CI F 75 mm x 90O 275,200.00
Taksir Bend All Flange CI F 150 mm x 90O 615,200.00
Taksir Bend All Flange CI F 200 mm x 90O 840,850.00
Taksir Bend All Flange CI F 250 mm x 90O 1,224,850.00
Taksir Bend All Flange CI F 300 mm x 90O 1,739,720.00
Taksir Bend All Flange CI F 350 mm x 90O 2,239,720.00
Taksir Bend All Flange CI F 400 mm x 90O 4,733,745.00
Taksir Bend All Flange CI F 450 mm x 90O 5,653,745.00
Taksir Bend All Flange CI F 500 mm x 90O 7,269,245.00
Taksir Bend All Flange CI F 600 mm x 90O 11,069,245.00
Taksir Bend All Flange CI F 150 mm x 45O 175,200.00
Taksir Bend All Flange CI F 200 mm x 45O 744,850.00
Taksir Bend All Flange CI F 350 mm x 45O 1,939,720.00
Taksir Bend All Flange CI F 400 mm x 45O 2,453,745.00
Taksir Bend All Flange CI F 450 mm x 45O 4,453,745.00
Taksir Bend All Flange CI F 500 mm x 45O 5,669,245.00
Taksir Bend All Flange CI F 350 mm x 22,5O 1,939,720.00
Taksir Bend All Flange CI F 400 mm x 22,5O 2,453,745.00
Taksir Bend All Flange CI F 450 mm x 22,5O 4,453,745.00
Taksir Bend All Flange CI F 500 mm x 22,5O 5,669,245.00
Taksir Bend PVC F 50 mm x 90O 67,320.00
Taksir Bend PVC F 75 mm x 90O 125,040.00
Taksir Bend PVC F 100 mm x 90O 382,680.00
Taksir Bend PVC F 150 mm x 90O 474,360.00
Taksir Bend PVC F 200 mm x 90O 858,250.00
Taksir Bend PVC F 250 mm x 90O 1,902,970.00
Taksir Bend PVC F 300 mm x 90O 2,189,920.00
Taksir Bend PVC F 350 mm x 90O 2,336,237.10
Taksir Bend PVC F 400 mm x 90O 2,388,790.00
Taksir Bend PVC F 450 mm x 90O 2,622,790.00
Taksir Bend PVC F 50 mm x 45O 58,200.00
Taksir Bend PVC F 75 mm x 45O 110,280.00
Taksir Bend PVC F 100 mm x 45O 326,040.00
Taksir Bend PVC F 150 mm x 45O 451,440.00
Taksir Bend PVC F 200 mm x 45O 750,490.00
Taksir Bend PVC F 250 mm x 45O 1,375,690.00
Taksir Bend PVC F 300 mm x 45O 2,081,440.00
I PERSIAPAN #REF!
JUMLAH #REF!
PPN 10% #REF!
TOTAL #REF!
PEMBULATAN #REF!
Terbilang :
#REF!
NO URAIAN PEKERJAAN A
VOLUME HARGA SATUAN JUMLAH HARGA
N
A
1 Direksi keet / Gudang Material 1.00 Ls L 5,000,000.00 5,000,000.00
2 Papan Nama proyek 1.00 Ls I 500,000.00 500,000.00
3 Papan rambu lalu lintas 8.00 Ls S 250,000.00 2,000,000.00
4 Administrasi & Perijinan 1.00 Ls A 10,000,000.00 10,000,000.00
5 Air kerja 1.00 Ls 2,000,000.00 2,000,000.00
6 Listrik kerja 1.00 Ls 2,500,000.00 2,500,000.00
7 Pengukuran kembali #REF! m 300.00 #REF!
JUMLAH #REF!
RENCANA ANGGARAN BIAYA
BAK PELEPAS TEKAN
I PERSIAPAN
1 Pengukuran dan pemasangan bouwplank 1.00 Ls Rp 1,500,000.00 Rp 1,500,000.00
2 Direksi keet / Gudang Material 1.00 Ls Rp 2,500,000.00 Rp 2,500,000.00
3 Papan Nama proyek 1.00 Ls Rp 500,000.00 Rp 500,000.00
4 Air kerja 1.00 Ls Rp 1,000,000.00 Rp 1,000,000.00
5 Listrik kerja 1.00 Ls Rp 1,000,000.00 Rp 1,000,000.00
6 Pembersihan lahan 1.00 Ls Rp 1,000,000.00 Rp 1,000,000.00
Sub Jumlah I Rp 7,500,000.00
II PEKERJAAN TANAH
1 Galian Tanah 149.12 m Rp 33,750.00 Rp 5,032,732.50
2 Urugan Tanah Kembali 6.71 m Rp 11,250.00 Rp 75,442.50
3 Urugan Pasir dibawah pondasi 1.44 m Rp 131,000.00 Rp 188,247.00
4 Urugan Pasir dibawah Plat Lantai 6.00 m Rp 131,000.00 Rp 786,000.00
Sub Jumlah II Rp 6,082,422.00
III PEK. PASANGAN & PLESTERAN
1 Pas. Pondasi Batu Belah 1 : 4 10.23 m Rp 481,000.00 Rp 4,920,630.00
2 Pas. Aanstamping 3.02 m Rp 247,950.00 Rp 748,238.72
3 Pas. Batu bata 1 : 3 7.20 m2 Rp 63,138.50 Rp 454,597.20
4 Plesteran 1:3 ( termasuk Acian ) 38.20 m2 Rp 26,154.80 Rp 999,113.36
5 Pasang Manhole 2.00 Unit Rp 400,000.00 Rp 800,000.00
6 Pasang Plat Penutup Valve 2.00 Unit Rp 500,000.00 Rp 1,000,000.00
7 Pas. Saluran U-20 50.00 m' Rp 80,000.00 Rp 4,000,000.00
Sub Jumlah III Rp 12,922,579.28
IV PEKERJAAN BETON
1 Lantai Kerja 1:3:5 3.00 m3 Rp 495,292.99 Rp 1,485,878.97
2 Beton Sloof 20/30 K - 250 3.24 m3 Rp 3,598,500.00 Rp 11,659,140.00
3 Beton Plat Lantai T=20 Cm K - 250 12.00 m3 Rp 3,598,500.00 Rp 43,182,000.00
4 Beton Dinding T=20 Cm K - 250 23.10 m3 Rp 4,567,160.00 Rp 105,501,396.00
5 Beton Kolom 20/30 K - 250 2.16 m 3
Rp 6,665,515.00 Rp 14,397,512.40
6 Beton Plat Atas T=15 Cm K - 250 9.00 m 3
Rp 4,748,615.00 Rp 42,737,535.00
7 Beton Balok 20/30 K - 250 3.24 m 3
Rp 5,080,415.00 Rp 16,460,544.60
8 Thrust Block K-225 -ND 200 mm 2.00 bh Rp 59,030.92 Rp 118,061.84
9 Thrust Block K-225 -ND 300 mm 1.00 bh Rp 115,294.77 Rp 115,294.77
10 #REF! 81.00 m' Rp 57,541.67 Rp 4,660,875.00
Sub Jumlah IV Rp 240,318,238.58
V PEKERJAAN PERPIPAAN
1 Wall Pipe CI 350 mm 2.00 bh Rp 2,423,015.00 Rp 4,846,030.00
2 Wall Pipe CI 200 mm 2.00 bh Rp 1,414,300.00 Rp 2,828,600.00
3 Wall Pipe CI 150 mm 2.00 bh Rp 894,300.00 Rp 1,788,600.00
4 Air Vent GI 75 mm tinggi 60 cm 2.00 unit #REF! #REF!
5 Pipa GI Med A 350 mm 8.00 m Rp 1,712,314.21 Rp 13,698,513.66
6 Pipa GI Med A 200 mm 6.00 m Rp 1,166,682.21 Rp 7,000,093.24
7 Pipa GI Med A 150 mm 3.00 m Rp 657,249.56 Rp 1,971,748.68
8 Bend All Flange CI 350 mm x 90 3.00 bh Rp 2,239,720.00 6,719,160.00
9 Bend All Flange PVC 350 mm x 90 2.00 bh Rp 2,336,237.10 4,672,474.21
10 Bend All Flange CI 200 mm x 90 2.00 bh Rp 840,850.00 1,681,700.00
10 Bend All Flange CI 150 mm x 90 1.00 bh Rp 615,200.00 Rp 615,200.00
11 Gate Valve CI 350 mm 2.00 bh Rp 20,020,926.25 Rp 40,041,852.50
12 Gate Valve CI 150 mm 2.00 bh Rp 4,258,320.00 Rp 8,516,640.00
12 Screen / Strainer CI 350 mm 1.00 bh Rp 3,830,621.57 Rp 3,830,621.57
13 Flange Las CI 350 mm 4.00 bh Rp 1,139,121.81 Rp 4,556,487.24
14 Flange Las CI 200 mm 6.00 bh Rp 678,949.23 Rp 4,073,695.37
15 Flange Las CI 150 mm 6.00 bh Rp 459,658.73 Rp 2,757,952.37
16 Tee All Flange F 200 x 150 x 200 mm 1.00 bh Rp 1,033,300.00 Rp 1,033,300.00
17 Gilbout Joint 350 mm 2.00 bh Rp 1,316,661.00 Rp 2,633,322.00
Sub Jumlah V #REF!
VI PEKERJAAN LAIN-LAIN
1 Pengecatan Dinding Beton 92.00 m2 Rp 26,249.00 Rp 2,414,908.00
2 Pengecatan Plat Penutup Bak Gate Valve 0.72 m 2
Rp 79,600.00 Rp 57,312.00
Sub Jumlah VI Rp 2,472,220.00
Jumlah Total #REF!
Jumlah 3 Bak Pelepas Tekan #REF!
NO URAIAN PEKERJAAN VOLUME HARGA SUB TOTAL
I PERSIAPAN
1 Pengukuran dan pemasangan bouwplank 1.00 Ls 1,500,000.00 1,500,000.00
2 Direksi keet / Gudang Material 1.00 Ls 2,500,000.00 2,500,000.00
3 Papan Nama proyek 1.00 Ls 500,000.00 500,000.00
4 Air kerja 1.00 Ls 1,000,000.00 1,000,000.00
5 Listrik kerja 1.00 Ls 1,000,000.00 1,000,000.00
6 Pembersihan lahan 1.00 Ls 1,000,000.00 1,000,000.00
Sub Jumlah I Rp 7,500,000.00
II PEKERJAAN TANAH
1 Galian Tanah 149.12 m Rp 33,750.00 Rp 5,032,732.50
2 Urugan Tanah Kembali 6.71 m Rp 11,250.00 Rp 75,442.50
3 Urugan Pasir dibawah pondasi 1.44 m Rp 131,000.00 Rp 188,247.00
4 Urugan Pasir dibawah Plat Lantai 6.00 m Rp 131,000.00 Rp 786,000.00
Sub Jumlah II Rp 6,082,422.00
III PEK. PASANGAN & PLESTERAN
1 Pas. Pondasi Batu Belah 1 : 4 10.23 m Rp 481,000.00 Rp 4,920,630.00
2 Pas. Aanstamping 3.02 m Rp 247,950.00 Rp 748,238.72
3 Pas. Batu bata 1 : 3 7.20 m2 Rp 63,138.50 Rp 454,597.20
4 Plesteran 1:3 ( termasuk Acian ) 38.20 m2 Rp 26,154.80 Rp 999,113.36
5 Pasang Manhole 2.00 Unit Rp 400,000.00 Rp 800,000.00
6 Pasang Plat Penutup Valve 2.00 Unit Rp 500,000.00 Rp 1,000,000.00
7 Pas. Saluran U-20 50.00 m' Rp 80,000.00 Rp 4,000,000.00
Sub Jumlah III Rp 12,922,579.28
IV PEKERJAAN BETON
1 Lantai Kerja 1:3:5 3.00 m3 Rp 495,292.99 Rp 1,485,878.97
2 Beton Sloof 20/30 K - 250 3.24 m3 Rp 3,598,500.00 Rp 11,659,140.00
3 Beton Plat Lantai T=20 Cm K - 250 12.00 m3 Rp 3,598,500.00 Rp 43,182,000.00
4 Beton Dinding T=20 Cm K - 250 23.10 m3 Rp 4,567,160.00 Rp 105,501,396.00
5 Beton Kolom 20/30 K - 250 2.16 m3 Rp 6,665,515.00 Rp 14,397,512.40
6 Beton Plat Atas T=15 Cm K - 250 9.00 m3 Rp 4,748,615.00 Rp 42,737,535.00
7 Beton Balok 20/30 K - 250 3.24 m3 Rp 5,080,415.00 Rp 16,460,544.60
8 Thrust Block K-225 -ND 200 mm 2.00 bh Rp 59,030.92 Rp 118,061.84
9 Thrust Block K-225 -ND 300 mm 1.00 bh Rp 115,294.77 Rp 115,294.77
10 Water stop 20 cm 81.00 m' Rp 57,541.67 Rp 4,660,875.00
Sub Jumlah IV Rp 240,318,238.58
V PEKERJAAN PERPIPAAN
1 Wall Pipe CI 400 mm 1.00 bh Rp 2,629,290.00 Rp 2,629,290.00
2 Wall Pipe CI 350 mm 1.00 bh Rp 2,423,015.00 Rp 2,423,015.00
3 Wall Pipe CI 200 mm 2.00 bh Rp 1,414,300.00 Rp 2,828,600.00
3 Wall Pipe CI 150 mm 1.00 bh Rp 894,300.00 Rp 894,300.00
4 Air Vent GI 75 mm tinggi 60 cm 2.00 unit #REF! #REF!
5 Pipa GI Med A 400 mm 5.00 m Rp 1,877,087.32 Rp 9,385,436.60
6 Pipa GI Med A 350 mm 3.00 m Rp 1,712,314.21 Rp 5,136,942.62
7 Pipa GI Med A 200 mm 6.00 m Rp 1,166,682.21 Rp 7,000,093.24
8 Pipa GI Med A 150 mm 2.00 m Rp 657,249.56 Rp 1,314,499.12
9 Bend All Flange CI 400 mm x 90 1.00 bh Rp 4,733,745.00 Rp 4,733,745.00
10 Bend All Flange CI 350 mm x 90 2.00 bh Rp 2,239,720.00 Rp 4,479,440.00
11 Bend PVC 400 mm x 90 1.00 bh Rp 2,388,790.00 Rp 2,388,790.00
12 Bend PVC 350 mm x 90 1.00 bh Rp 2,336,237.10 Rp 2,336,237.10
13 Bend All Flange CI 200 mm x 90 2.00 bh Rp 840,850.00 Rp 1,681,700.00
14 Bend All Flange CI 150 mm x 90 1.00 bh Rp 615,200.00 Rp 615,200.00
15 Gate Valve CI 400 mm 1.00 bh Rp 32,145,125.00 Rp 32,145,125.00
16 Gate Valve CI 350 mm 1.00 bh Rp 20,020,926.25 Rp 20,020,926.25
17 Screen / Strainer CI 400 mm 1.00 bh Rp 4,681,394.50 Rp 4,681,394.50
18 Flange Las CI 400 mm 4.00 bh Rp 1,609,071.50 Rp 6,436,286.02
19 Flange Las CI 350 mm 16.00 bh Rp 1,139,121.81 Rp 18,225,948.96
20 Flange Las CI 200 mm 6.00 bh Rp 678,949.23 Rp 4,073,695.37
21 Flange Las CI 150 mm 4.00 bh Rp 459,658.73 Rp 1,838,634.91
22 Tee All Flange F 200 x 150 x 200 mm 1.00 bh Rp 1,033,300.00 Rp 1,033,300.00
23 Gilbout Joint 400 mm 1.00 bh Rp 1,617,916.50 Rp 1,617,916.50
24 Gilbout Joint 350 mm 1.00 bh Rp 1,316,661.00 Rp 1,316,661.00
Sub Jumlah V #REF!
VI PEKERJAAN LAIN-LAIN
1 Pengecatan Dinding Beton 92.00 m2 Rp 26,249.00 Rp 2,414,908.00
2 Pengecatan Plat Penutup Bak Gate Valve 0.72 m2 Rp 79,600.00 Rp 57,312.00
Sub Jumlah VI Rp 2,472,220.00
Jumlah Total #REF!
RENCANA ANGGARAN BIAYA
PEKERJAAN RESERVOIR 500 M3
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bouwplank 1.00 Ls 2,000,000.00 2,000,000.00
2 Direksi keet / Gudang Material 1.00 Ls 2,500,000.00 2,500,000.00
3 Papan Nama proyek 1.00 Ls 500,000.00 500,000.00
4 Administrasi & Perijinan 1.00 Ls 2,000,000.00 2,000,000.00
6 Air kerja 1.00 Ls 1,000,000.00 1,000,000.00
7 Listrik kerja 1.00 Ls 1,000,000.00 1,000,000.00
8 Pembersihan lahan 1.00 Ls 1,000,000.00 1,000,000.00
Sub Jumlah I Rp 10,000,000.00
II PEKERJAAN TANAH
1 Galian tanah Max. 2 m 254.53 m3 Rp 33,750.00 Rp 8,590,320.00
2 Timbunan kembali dipadatkan 84.84 m3 Rp 11,250.00 Rp 954,480.00
3 Buangan Tanah 190.90 m3 Rp 12,050.00 Rp 2,300,296.80
4 Urugan pasir urug 31.40 m3 Rp 131,000.00 Rp 4,112,876.00
Sub Jumlah II Rp 15,957,972.80
III PEK. PASANGAN & PLESTERAN
1 Plesteran 1:3 ( termasuk Acian ) 138.50 m2 Rp 26,154.80 Rp 3,622,439.80
2 Pas. Batu bata 1:3 21.90 m2 Rp 63,138.50 Rp 1,382,733.15
3 Pas. Saluran U-20 100.00 m' Rp 80,000.00 Rp 8,000,000.00
Sub Jumlah III Rp 13,005,172.95
IV PEKERJAAN BETON
1 Lantai Kerja 1:3:5 28.88 m3 Rp 495,292.99 Rp 14,304,061.53
2 Water stop 20 cm 282.00 m' Rp 57,541.67 Rp 16,226,750.00
3 Plesteran 1 : 2 ( termasuk Acian ) 654.88 m2 Rp 28,335.20 Rp 18,556,155.78
4 Beton Bertulang K - 250
a. Sloof 19.68 m3 Rp 3,598,500.00 Rp 70,818,480.00
b. Lantai 72.20 m3 Rp 3,598,500.00 Rp 259,811,700.00
c. Dinding 22.34 m3 Rp 4,567,160.00 Rp 102,030,354.40
d. Kolom 3.45 m3 Rp 6,665,515.00 Rp 22,996,026.75
e. Balok 11.81 m3 Rp 5,080,415.00 Rp 59,989,540.32
f. Plat Penutup 42.33 m3 Rp 4,748,615.00 Rp 201,008,872.95
5 Beton Tangga Inspeksi 0.36 bh Rp 4,748,615.00 Rp 1,709,501.40
6 Thrust Block K-225 -ND 400 mm 2.00 bh Rp 199,229.36 Rp 398,458.71
7 Thrust Block K-225 -ND 500 mm 2.00 bh Rp 199,229.36 Rp 398,458.71
Sub Jumlah IV Rp 768,248,360.56
V PEKERJAAN PERPIPAAN
1 Wall Pipe CI 500 mm 1.00 bh Rp 3,832,790.00 Rp 3,832,790.00
2 Wall Pipe CI 400 mm 1.00 bh Rp 2,629,290.00 Rp 2,629,290.00
3 Wall Pipe CI 300 mm 1.00 bh Rp 2,223,015.00 Rp 2,223,015.00
4 Wall Pipe CI 75 mm 2.00 bh Rp 314,300.00 Rp 628,600.00
5 Air Vent GI 75 mm tinggi 60 cm 8.00 unit Rp 200,000.00 Rp 1,600,000.00
6 Pipa GI Med A 500 mm 3.00 m Rp 2,506,123.32 Rp 7,518,369.96
7 Pipa GI Med A 400 mm 5.00 m Rp 1,877,087.32 Rp 9,385,436.60
8 Pipa GI Med A 300 mm 3.00 m Rp 1,452,622.21 Rp 4,357,866.62
9 Pipa GI Med A 75 mm 5.00 m Rp 353,242.47 Rp 1,766,212.34
10 Bend All Flange CI 400 mm x 90 2.00 bh Rp 4,733,745.00 Rp 9,467,490.00
11 Bend All Flange CI 300 mm x 90 2.00 bh Rp 1,739,720.00 Rp 3,479,440.00
12 Bend All Flange CI 75 mm x 90 1.00 bh Rp 275,200.00 Rp 275,200.00
13 Gate Valve CI 500 mm 1.00 bh Rp 75,208,963.13 Rp 75,208,963.13
14 Gate Valve CI 400 mm 1.00 bh Rp 32,145,125.00 Rp 32,145,125.00
15 Gate Valve CI 75 mm 1.00 bh Rp 1,740,500.00 Rp 1,740,500.00
16 Tee All Flange CI 75 mm x 75 mm 1.00 bh Rp 371,100.00 Rp 371,100.00
17 Gilbout Joint 500 mm 1.00 bh Rp 2,630,065.20 Rp 2,630,065.20
18 Gilbout Joint 400 mm 1.00 bh Rp 1,617,916.50 Rp 1,617,916.50
19 Screen / Strainer CI 500 mm 1.00 bh Rp 7,361,833.50 Rp 7,361,833.50
20 Flange Las CI 500 mm 2.00 bh Rp 2,818,571.50 Rp 5,637,143.01
21 Flange Las CI 400 mm 4.00 bh Rp 1,609,071.50 Rp 6,436,286.02
22 Flange Las CI 75 mm 8.00 bh Rp 309,373.73 Rp 2,474,989.83
Sub Jumlah V Rp 182,787,632.70
VI PEKERJAAN LAIN-LAIN
1 Tutup Manhole Baja 60 x 60 4.00 unit Rp 400,000.00 Rp 1,600,000.00
2 Tangga Monyet 19 mm 4.00 unit Rp 400,000.00 Rp 1,600,000.00
3 Railing Tangga Inspeksi (Pipa Besi 2") 4.00 m' Rp 300,000.00 Rp 1,200,000.00
4 Pengecatan Pipa dan Aksesoris 1.00 ls Rp 750,000.00 Rp 750,000.00
5 Pengecatan Tembok 138.50 m2 Rp 31,552.50 Rp 4,370,021.25
6 Angkur 19 mm utk pas. Bata 16.00 bh Rp 50,000.00 Rp 800,000.00
7 Tiang Pancang Dolken 12 cm , L = 3 m 81.00 Btg Rp 75,000.00 Rp 6,075,000.00
Sub Jumlah VI Rp 16,395,021.25
Jumlah Total Rp 1,006,394,160.26
RENCANA ANGGARAN BIAYA
PEKERJAAN RESERVOIR 250 M3
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bouwplank 1.00 Ls
2 Direksi keet / Gudang Material 1.00 Ls
3 Papan Nama proyek 1.00 Ls
4 Administrasi & Perijinan 1.00 Ls
5 Air kerja 1.00 Ls
6 Listrik kerja 1.00 Ls
7 Pembersihan lahan 1.00 Ls
Sub Jumlah I
II PEKERJAAN TANAH
1 Galian tanah Max. 2 m 119.00 m3
2 Timbunan kembali dipadatkan 39.67 m3
3 Buangan Tanah 89.25 m3
4 Urugan pasir urug 14.68 m3
Sub Jumlah II
III PEKERJAAN PASANGAN & PLESTERAN
1 Pas. Pondasi Batu Belah 1 : 4 5.10 m3
2 Pas. Aanstamping 1.20 m3
3 Plesteran 1:3 ( termasuk Acian ) 135.24 m2
4 Pas. Batu bata 1:3 67.62 m2
5 Pas. Saluran U-20 100.00 m'
Sub Jumlah III
IV PEKERJAAN BETON
1 Lantai Kerja 1:3:5 7.21 m3
2 Water stop 20 cm 48.40 m'
3 Plesteran beton 1 : 2 ( termasuk Acian ) 96.80 m2
4 Beton Bertulang K - 250
a. Balok Sloof 9.53 m3
b. Lantai 28.83 m3
c. Dinding 38.91 m3
d. Kolom 4.41 m3
e. Balok Plat Atap 7.26 m3
f. Plat Penutup 21.62 m3
5 Beton Tangga Inspeksi 0.18 m3
6 Thrust Block K-225 -ND 200 mm 2.00 bh
7 Thrust Block K-225 -ND 300 mm 2.00 bh
Sub Jumlah IV
V PEKERJAAN PERPIPAAN
1 Wall Pipe CI 250 mm 1.00 bh
2 Wall Pipe CI 300 mm 1.00 bh
3 Wall Pipe CI 150 mm 1.00 bh
4 Wall Pipe CI 75 mm 2.00 bh
5 Air Vent GI 75 mm tinggi 60 cm 8.00 unit
6 Pipa GI Med A 250 mm 5.00 m
7 Pipa GI Med A 300 mm 3.00 m
8 Pipa GI Med A 150 mm 3.00 m
9 Pipa GI Med A 75 mm 5.00 m
10 Bend All Flange CI 250 mm x 90 2.00 bh
11 Bend All Flange CI 150 mm x 90 2.00 bh
12 Bend All Flange CI 75 mm x 90 1.00 bh
13 Bend PVC 250 mm x 90 1.00 bh
14 Bend PVC 300 mm x 90 1.00 bh
15 Gate Valve CI 250 mm 1.00 bh
16 Gate Valve CI 300 mm 1.00 bh
17 Gate Valve CI 75 mm 2.00 bh
18 Water Meter All Flange F 250 mm 1.00 bh
19 Tee All Flange CI 75 mm x 75 mm 1.00 bh
20 Gilbout Joint 250 mm 1.00 bh
21 Gilbout Joint 300 mm 1.00 bh
22 Screen / Strainer CI 300 mm 1.00 bh
23 Flange Las CI 250 mm 4.00 bh
24 Flange Las CI 300 mm 2.00 bh
25 Flange Las CI 75 mm 8.00 bh
Sub Jumlah V
VI PEKERJAAN LAIN-LAIN
1 Tutup Manhole Baja 60 x 60 4.00 unit
2 Tangga Monyet 19 mm 2.00 unit
3 Railing Tangga Inspeksi (Pipa Besi 2") 4.00 m'
4 Pengecatan Pipa dan Aksesoris 1.00 ls
5 Pengecatan Tembok 96.80 m2
6 Angkur 19 mm utk pas. Bata 16.00 bh
7 Tiang Pancang Dolken 12 cm , L = 3 m 36.00 Btg
Sub Jumlah VI
Jumlah Total
RAN BIAYA
VOIR 250 M3
RI MA MOGA
Rp 2,000,000.00 Rp 2,000,000.00
Rp 2,500,000.00 Rp 2,500,000.00
Rp 500,000.00 Rp 500,000.00
Rp 2,000,000.00 Rp 2,000,000.00
Rp 1,000,000.00 Rp 1,000,000.00
Rp 1,000,000.00 Rp 1,000,000.00
Rp 1,000,000.00 Rp 1,000,000.00
Sub Jumlah I Rp 10,000,000.00
Rp 481,000.00 Rp 2,453,100.00
Rp 247,950.00 Rp 297,540.00
Rp 26,154.80 Rp 3,537,175.15 18.00
Rp 63,138.50 Rp 4,269,425.37 9.00
Rp 80,000.00 Rp 8,000,000.00 100.00
Sub Jumlah III Rp 18,557,240.52
Rp 1,820,720.00 Rp 1,820,720.00
Rp 2,223,015.00 Rp 2,223,015.00
Rp 894,300.00 Rp 894,300.00
Rp 314,300.00 Rp 628,600.00
Rp 200,000.00 Rp 1,600,000.00
Rp 1,234,002.21 Rp 6,170,011.04
Rp 1,452,622.21 Rp 4,357,866.62
Rp 657,249.56 Rp 1,971,748.68
Rp 353,242.47 Rp 1,766,212.34
Rp 1,224,850.00 Rp 2,449,700.00
Rp 615,200.00 Rp 1,230,400.00
Rp 275,200.00 Rp 275,200.00
Rp 1,902,970.00 Rp 1,902,970.00
Rp 2,189,920.00 Rp 2,189,920.00
Rp 10,483,986.88 Rp 10,483,986.88
Rp 13,300,777.50 Rp 13,300,777.50
Rp 1,740,500.00 Rp 3,481,000.00
Rp 25,619,653.39 Rp 25,619,653.39
Rp 371,100.00 Rp 371,100.00
Rp 855,085.50 Rp 855,085.50
Rp 1,115,085.50 Rp 1,115,085.50
Rp 2,634,921.57 Rp 2,634,921.57
Rp 725,424.23 Rp 2,901,696.91
Rp 1,032,974.23 Rp 2,065,948.46
Rp 309,373.73 Rp 2,474,989.83
Sub Jumlah V Rp 94,784,909.21
Rp 400,000.00 Rp 1,600,000.00
Rp 400,000.00 Rp 800,000.00
Rp 300,000.00 Rp 1,200,000.00
Rp 500,000.00 Rp 500,000.00
Rp 26,249.00 Rp 2,540,903.20
Rp 50,000.00 Rp 800,000.00
Rp 75,000.00 Rp 2,700,000.00
Sub Jumlah VI Rp 10,140,903.20
Jumlah Total Rp 635,936,548.28
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
II DT 91-0006 PEKERJAAN TANAH
2007
6.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 23,437.50 27,500.00
6.1.2 Tenaga 23,437.50 27,500.00
0.75 OH Pekerja 30,000.00 35,000.00 22,500.00 26,250.00
0.025 OH Mandor 37,500.00 50,000.00 937.50 1,250.00
6.15 1 m3 Mengurug Sirtu Padat untuk Peninggian Lantai Bangunan 104,437.50 118,000.00
6.15.1 Bahan 96,000.00 108,000.00
1.2 m3 Sirtu 80,000.00 90,000.00 96,000.00 108,000.00
6.6 1 m3 Memasang Pondasi Batu Kali 1Kp : 1Sm : 2Pp 288,132.50 340,000.00
6.6.1 Bahan 215,300.00 253,750.00
1.2 m3 Batu Belah 15/20 110,000.00 130,000.00 132,000.00 156,000.00
0.17 m3 Kapur Pasang (KP) 180,000.00 195,000.00 30,600.00 33,150.00
0.17 Kg Semen Merah (SM) 110,000.00 120,000.00 18,700.00 20,400.00
0.340 m3 Pasir Pasang 100,000.00 130,000.00 34,000.00 44,200.00
6.10 1 m3 Pasang Pondasi Siklop, 60% Beton Camp. 1PC : 2PB : 3KR & 40% Batu Belah 1,964,495.00 2,009,660.00
6.10.1 Bahan 1,833,425.00 1,854,660.00
0.480 m3 Batu Belah 15/20 cm 110,000.00 130,000.00 52,800.00 62,400.00
126 Kg Besi Beton 11,700.00 11,500.00 1,474,200.00 1,449,000.00
194 Kg Portland Semen 962.50 1,050.00 186,725.00 203,700.00
0.312 m3 Pasir Beton 120,000.00 145,000.00 37,440.00 45,240.00
0.468 m3 Koral Beton 120,000.00 140,000.00 56,160.00 65,520.00
1.8 Kg Kawat Beton 14,500.00 16,000.00 26,100.00 28,800.00
6.2 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 3PP 114,479.38 132,127.50
6.2.1 Bahan 87,014.38 99,627.50
140 Buah Bata Merah 330.00 380.00 46,200.00 53,200.00
32.95 Kg Portland Semen (PC) 962.50 1,050.00 31,714.38 34,597.50
0.091 m3 Pasir Pasang (PP) 100,000.00 130,000.00 9,100.00 11,830.00
6.3 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 4PP 108,519.38 125,667.50
6.3.1 Bahan 81,054.38 93,167.50
140 Buah Bata Merah 330.00 380.00 46,200.00 53,200.00
26.55 Kg Portland Semen (PC) 962.50 1,050.00 25,554.38 27,877.50
0.093 m3 Pasir Pasang (PP) 100,000.00 130,000.00 9,300.00 12,090.00
6.4 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 5PP 105,232.50 122,270.00
6.4.1 Bahan 77,767.50 89,770.00
140 Buah Bata Merah 330.00 380.00 46,200.00 53,200.00
22.2 Kg Portland Semen (PC) 962.50 1,050.00 21,367.50 23,310.00
0.102 m3 Pasir Pasang (PP) 100,000.00 130,000.00 10,200.00 13,260.00
6.5 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 6PP 103,671.25 120,985.00
6.5.1 Bahan 76,206.25 88,485.00
140 Buah Bata Merah 330.00 380.00 46,200.00 53,200.00
18.5 Kg Portland Semen (PC) 962.50 1,050.00 17,806.25 19,425.00
0.122 m3 Pasir Pasang (PP) 100,000.00 130,000.00 12,200.00 15,860.00
6.6 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 3 KP :10PP 97,567.00 113,671.50
6.6.1 Bahan 70,102.00 81,171.50
140 Buah Bata Merah 330.00 380.00 46,200.00 53,200.00
10.08 Kg Portland Semen (PC) 962.50 1,050.00 9,702.00 10,584.00
0.0925 m3 Pasir Pasang (PP) 100,000.00 130,000.00 9,250.00 12,025.00
0.0275 m3 Kapur Pasang (KP) 180,000.00 195,000.00 4,950.00 5,362.50
6.7 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 2PP 58,871.88 67,687.50
6.7.1 Bahan 45,139.38 51,437.50
70 Buah Bata Merah 5 x 11 x 22 330.00 380.00 23,100.00 26,600.00
18.95 Kg Portland Semen 962.50 1,050.00 18,239.38 19,897.50
0.038 m3 Pasir Pasang 100,000.00 130,000.00 3,800.00 4,940.00
6.8 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 3PP 54,663.63 63,138.50
6.8.1 Bahan 40,931.13 46,888.50
70 Buah Bata Merah 5 x 11 x 22 330.00 380.00 23,100.00 26,600.00
14.37 Kg Portland Semen 962.50 1,050.00 13,831.13 15,088.50
0.04 m3 Pasir Pasang 100,000.00 130,000.00 4,000.00 5,200.00
6.9 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 4PP 52,201.25 60,515.00
6.9.1 Bahan 38,468.75 44,265.00
70 Buah Bata Merah 5 x 11 x 22 330.00 380.00 23,100.00 26,600.00
11.50 Kg Portland Semen 962.50 1,050.00 11,068.75 12,075.00
0.043 m3 Pasir Pasang 100,000.00 130,000.00 4,300.00 5,590.00
6.10 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 5PP 50,649.50 58,864.00
Bahan 36,917.00 42,614.00
6.10.1 70 Buah Bata Merah 5 x 11 x 22 330.00 380.00 23,100.00 26,600.00
9.68 Kg Portland Semen 962.50 1,050.00 9,317.00 10,164.00
0.045 m3 Pasir Pasang 100,000.00 130,000.00 4,500.00 5,850.00
6.11 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 6PP 54,663.63 63,138.50
6.11.1 Bahan 40,931.13 46,888.50
70 Buah Bata Merah 5 x 11 x 22 330.00 380.00 23,100.00 26,600.00
14.37 Kg Portland Semen 962.50 1,050.00 13,831.13 15,088.50
0.04 m3 Pasir Pasang 100,000.00 130,000.00 4,000.00 5,200.00
6.12 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 8PP 54,663.63 63,138.50
6.12.1 Bahan 40,931.13 46,888.50
70 Buah Bata Merah 5 x 11 x 22 330.00 380.00 23,100.00 26,600.00
14.37 Kg Portland Semen 962.50 1,050.00 13,831.13 15,088.50
0.04 m3 Pasir Pasang 100,000.00 130,000.00 4,000.00 5,200.00
6.13 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 3KP : 10PP 48,863.75 57,000.00
6.13.1 Bahan 35,131.25 40,750.00
70 Buah Bata Merah 5 x 11 x 22 330.00 380.00 23,100.00 26,600.00
4.5 Kg Portland Semen 962.50 1,050.00 4,331.25 4,725.00
0.05 m3 Pasir Pasang 100,000.00 130,000.00 5,000.00 6,500.00
0.015 m3 Kapur Padam 180,000.00 195,000.00 2,700.00 2,925.00
6.24 1 m2 Memasang Finishing Siar Pasangan Dinding Bata Merah (=20 m') 10,710.45 12,413.40
6.24.1 Bahan 2,991.45 3,263.40
3.108 Kg Portland Semen 962.50 1,050.00 2,991.45 3,263.40
6.25 1 m2 Memasang Finishing Siar Pasangan Dinding Conblock ekspose (=8 m') 5,420.50 6,280.00
6.25.1 Bahan 1,540.00 1,680.00
1.600 Kg Portland Semen 962.50 1,050.00 1,540.00 1,680.00
6.26 1 m2 Memasang Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp 22,702.75 26,467.00
6.26.1 Bahan 7,302.25 8,217.00
6.34 Kg Pc 962.50 1,050.00 6,102.25 6,657.00
0.012 m3 PP 100,000.00 130,000.00 1,200.00 1,560.00
VI DT 91-0011 PEKERJAAN K A Y U
2007 6.1 1 m3 Membuat Kosen Pintu & Jendela Kayu klas I 18,652,000.00 20,075,000.00
6.1.2 Bahan 17,636,750.00 18,740,000.00
1.1 m3 Kayu Klas I (Jati) , Balok 16,000,000.00 17,000,000.00 17,600,000.00 18,700,000.00
1.25 kg Paku Biasa 2" - 5 " 15,000.00 16,000.00 18,750.00 20,000.00
1 kg Lem Kayu 18,000.00 20,000.00 18,000.00 20,000.00
6.1.2 Tenaga 1,015,250.00 1,335,000.00
6 OH Pekerja 30,000.00 35,000.00 180,000.00 210,000.00
20 OH Tukang Kayu 37,000.00 50,000.00 740,000.00 1,000,000.00
2 OH Kepala Tukang 42,000.00 55,000.00 84,000.00 110,000.00
0.3 OH Mandor 37,500.00 50,000.00 11,250.00 15,000.00
6.2 1 m3 Membuat Kosen Pintu & Jendela Kayu klas II atau III 6,452,000.00 7,375,000.00
6.2.1 Bahan 5,436,750.00 6,040,000.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 4,500,000.00 5,000,000.00 5,400,000.00 6,000,000.00
1.25 kg Paku Biasa 2" - 5 " 15,000.00 16,000.00 18,750.00 20,000.00
1 kg Lem Kayu 18,000.00 20,000.00 18,000.00 20,000.00
6.2.2 Tenaga 1,015,250.00 1,335,000.00
6 OH Pekerja 30,000.00 35,000.00 180,000.00 210,000.00
20 OH Tukang Kayu 37,000.00 50,000.00 740,000.00 1,000,000.00
2 OH Kepala Tukang 42,000.00 55,000.00 84,000.00 110,000.00
0.3 OH Mandor 37,500.00 50,000.00 11,250.00 15,000.00
6.3 1 m2 Membuat Pintu KlampStandard Kayu Klas II (Kayu Kamfer) 275,185.00 300,225.00
6.3.1 Bahan 220,750.00 228,800.00
0.040 m3 Kayu Klas II (Kamfer), papan 5,500,000.00 5,700,000.00 220,000.00 228,000.00
0.05 Kg Paku Biasa 2" - 5 " 15,000.00 16,000.00 750.00 800.00
6.5 1 m2 Membuat Daun Pintu Panel Kayu Klas I atau II 355,775.00 405,250.00
6.5.1 Bahan 220,900.00 229,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 5,500,000.00 5,700,000.00 220,000.00 228,000.00
0.050 kg Lem Kayu 18,000.00 20,000.00 900.00 1,000.00
6.5.2 Tenaga 134,875.00 176,250.00
1 OH Pekerja 30,000.00 35,000.00 30,000.00 35,000.00
2.5 OH Tukang Kayu 37,000.00 50,000.00 92,500.00 125,000.00
0.25 OH Kepala Tukang 42,000.00 55,000.00 10,500.00 13,750.00
0.05 OH Mandor 37,500.00 50,000.00 1,875.00 2,500.00
6.6 1 m2 Membuat Pintu & Jendela Kaca Kayu Klas I atau II 245,300.00 283,800.00
6.6.1 Bahan 137,400.00 142,800.00
0.024 m3 Kayu Klas II (Kamfer), papan 5,500,000.00 5,700,000.00 132,000.00 136,800.00
0.300 kg Lem Kayu 18,000.00 20,000.00 5,400.00 6,000.00
6.6.2 Tenaga 107,900.00 141,000.00
0.8 OH Pekerja 30,000.00 35,000.00 24,000.00 28,000.00
2 OH Tukang Kayu 37,000.00 50,000.00 74,000.00 100,000.00
0.2 OH Kepala Tukang 42,000.00 55,000.00 8,400.00 11,000.00
0.04 OH Mandor 37,500.00 50,000.00 1,500.00 2,000.00
6.7 1 m2 Membuat Pintu & Jendela Jalusi Kayu Klas I atau II 1,380,475.00 1,462,000.00
6.7.1 Bahan 1,225,000.00 1,258,000.00
0.064 m3 Kayu Klas I (Jati), papan 19,000,000.00 19,500,000.00 1,216,000.00 1,248,000.00
0.5 kg Lem Kayu 18,000.00 20,000.00 9,000.00 10,000.00
6.7.2 Tenaga 155,475.00 204,000.00
1 OH Pekerja 30,000.00 35,000.00 30,000.00 35,000.00
3 OH Tukang Kayu 37,000.00 50,000.00 111,000.00 150,000.00
0.3 OH Kepala Tukang 42,000.00 55,000.00 12,600.00 16,500.00
0.05 OH Mandor 37,500.00 50,000.00 1,875.00 2,500.00
6.8 1 m2 Membuat Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 cm) 299,850.00 341,980.00
6.8.1 Bahan 197,950.00 207,980.00
0.025 m3 Kayu Klas II (Kamfer), papan 5,500,000.00 5,700,000.00 137,500.00 142,500.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 16,000.00 450.00 480.00
0.5 Ltr Lem Kayu 18,000.00 20,000.00 9,000.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 51,000.00 55,000.00 51,000.00 55,000.00
6.9 1 m2 Membuat Pintu Plywood rangkap, rangka expose kayu klas I atau II 309,150.00 352,400.00
6.9.1 Bahan 201,250.00 211,400.00
0.0256 m3 Kayu Klas II (Kamfer), papan 5,500,000.00 5,700,000.00 140,800.00 145,920.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 16,000.00 450.00 480.00
0.5 Ltr Lem Kayu 18,000.00 20,000.00 9,000.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 51,000.00 55,000.00 51,000.00 55,000.00
6.9.2 Tenaga 107,900.00 141,000.00
0.8 OH Pekerja 30,000.00 35,000.00 24,000.00 28,000.00
2 OH Tukang Kayu 37,000.00 50,000.00 74,000.00 100,000.00
0.2 OH Kepala Tukang 42,000.00 55,000.00 8,400.00 11,000.00
0.04 OH Mandor 37,500.00 50,000.00 1,500.00 2,000.00
6.10 1 m2 Membuat Jalusi mati Kosen Kayu Klas I atau II 1,240,587.50 1,302,150.00
6.10.1 Bahan 1,142,250.00 1,172,400.00
0.06 m3 Kayu Klas I (Jati), papan 19,000,000.00 19,500,000.00 1,140,000.00 1,170,000.00
0.15 Kg Paku Biasa 1/2" - 1" 15,000.00 16,000.00 2,250.00 2,400.00
6.11 1 m2 Membuat Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I 639,750.00 689,980.00
6.11.1 Bahan 531,850.00 548,980.00
0.025 m3 Kayu Klas I (Jati), papan 19,000,000.00 19,500,000.00 475,000.00 487,500.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 16,000.00 450.00 480.00
0.3 kg Lem Kayu 18,000.00 20,000.00 5,400.00 6,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 51,000.00 55,000.00 51,000.00 55,000.00
6.12 1 m2 Membuat Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II 341,390.00 393,330.00
6.12.1 Bahan 212,890.00 224,580.00
0.025 m3 Kayu Klas II (Kamfer), papan 5,500,000.00 5,700,000.00 137,500.00 142,500.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 16,000.00 450.00 480.00
0.08 kg Lem Kayu 18,000.00 20,000.00 1,440.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 51,000.00 55,000.00 51,000.00 55,000.00
0.5 Lbr Formika 45,000.00 50,000.00 22,500.00 25,000.00
6.12.2 Tenaga 128,500.00 168,750.00
0.8 OH Pekerja 30,000.00 35,000.00 24,000.00 28,000.00
2.5 OH Tukang Kayu 37,000.00 50,000.00 92,500.00 125,000.00
0.25 OH Kepala Tukang 42,000.00 55,000.00 10,500.00 13,750.00
0.04 OH Mandor 37,500.00 50,000.00 1,500.00 2,000.00
6.13 1 m3 Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter 5,865,900.00 6,629,600.00
6.13.1 Bahan 5,244,000.00 5,814,600.00
1.1 m3 Kayu Kamfer, balok 4,500,000.00 5,000,000.00 4,950,000.00 5,500,000.00
15 Kg Besi Strip 14,000.00 15,000.00 210,000.00 225,000.00
5.6 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 84,000.00 89,600.00
6.16 1 m2 Memasang Rangka Atap Genteng Keramik, Kayu Klas II 236,057.50 263,300.00
6.16.1 Bahan 228,750.00 254,000.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 4,500,000.00 5,000,000.00 63,000.00 70,000.00
0.036 m3 Reng (2x3) cm 4,500,000.00 5,000,000.00 162,000.00 180,000.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 3,750.00 4,000.00
6.17 1 m2 Memasang Rangka Atap Genteng Beton, Kayu Klas II 330,557.50 368,300.00
6.17.1 Bahan 323,250.00 359,000.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 4,500,000.00 5,000,000.00 63,000.00 70,000.00
0.057 m3 Reng (2x3) cm 4,500,000.00 5,000,000.00 256,500.00 285,000.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 3,750.00 4,000.00
6.19 1 m2 Memasang Rangka Langit-langit (1,00x1,00) m, kayu Klas II atau III 89,912.50 103,075.00
6.19.1 Bahan 72,300.00 80,200.00
0.0154 m3 Kayu Klas II (Kamfer), balok 4,500,000.00 5,000,000.00 69,300.00 77,000.00
0.2 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 3,000.00 3,200.00
6.20 1 m2 Memasang Rangka Langit-langit (60x60) cm, kayu Klas II atau III 95,835.00 109,650.00
6.20.1 Bahan 77,100.00 85,500.00
0.0163 m3 Kayu Klas II (Kamfer), balok 4,500,000.00 5,000,000.00 73,350.00 81,500.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 3,750.00 4,000.00
6.21 1 m' Memasang Listplank Uk. (3x20)cm Kayu klas I atau II 218,337.50 227,325.00
6.21.1 Bahan 206,700.00 212,200.00
0.0108 m3 Kayu klas I (Jati), papan 19,000,000.00 19,500,000.00 205,200.00 210,600.00
0.10 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 1,500.00 1,600.00
6.22 1 m' Memasang Listplank Uk. (3x30)cm Kayu klas I atau klas II 72,677.50 78,350.00
6.22.1 Bahan 61,250.00 63,500.00
0.011 m3 Kayu klas II (Kamfer), papan 5,500,000.00 5,700,000.00 60,500.00 62,700.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 750.00 800.00
6.23 1 m2 Memasang Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III 151,590.00 173,025.00
6.23.1 Bahan 128,250.00 142,400.00
0.028 m3 Kayu klas II (Kamfer), balok 4,500,000.00 5,000,000.00 126,000.00 140,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 2,250.00 2,400.00
6.24 1 m2 Memasang Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II 205,530.00 231,525.00
6.24.1 Bahan 182,190.00 200,900.00
0.028 m3 Kayu klas II (Kamfer), balok 4,500,000.00 5,000,000.00 126,000.00 140,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 2,250.00 2,400.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 51,000.00 55,000.00 43,860.00 47,300.00
0.56 Ltr Lem 18,000.00 20,000.00 10,080.00 11,200.00
6.27 1 m2 Memasang Dinding Lambriziring dari Plywood ukuran (120x240) cm 25,038.75 27,902.50
6.27.1 Bahan 21,150.00 22,800.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 51,000.00 55,000.00 20,400.00 22,000.00
0.05 Kg Paku Biasa 1/2" - 1" 15,000.00 16,000.00 750.00 800.00
6.28 1 m2 Memasang Dinding Bilik, Rangka Kayu Klas III atau IV 77,510.10 86,790.00
6.28.1 Bahan 72,262.60 80,265.00
1.5 m2 Bilik Bambu 15,000.00 17,500.00 22,500.00 26,250.00
0.014 m3 Kayu Klas III (Meranti) 3,500,000.00 3,800,000.00 49,000.00 53,200.00
0.05 Kg Paku Biasa 1/2" - 1" 15,000.00 16,000.00 750.00 800.00
0.003 m' List Kayu 2/4 4,200.00 5,000.00 12.60 15.00
6.2 1 m3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (122)cm, w/c = 0,78 492,827.98 558,867.79
6.2.1 Bahan 428,726.98 483,192.79
276 Kg Portland Semen 962.50 1,050.00 265,650.00 289,800.00
828 kg Pasir Beton 85.71 103.57 70,971.43 85,757.14
1,012 kg Kerikil (maksimum 30 mm) 88.89 103.70 89,955.56 104,948.15
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.2.2 Tenaga 64,101.00 75,675.00
1.65 OH Pekerja 30,000.00 35,000.00 49,500.00 57,750.00
0.275 OH Tukang Batu 37,500.00 45,000.00 10,312.50 12,375.00
0.028 OH Kepala Tukang 42,000.00 50,000.00 1,176.00 1,400.00
0.083 OH Mandor 37,500.00 50,000.00 3,112.50 4,150.00
6.3 1 m3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (122)cm, w/c = 0,72 512,924.21 580,532.74
6.3.1 Bahan 448,823.21 504,857.74
299 Kg Portland Semen 962.50 1,050.00 287,787.50 313,950.00
799 kg Pasir Beton 85.71 103.57 68,485.71 82,753.57
1,017 kg Kerikil (maksimum 30 mm) 88.89 103.70 90,400.00 105,466.67
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.3.2 Tenaga 64,101.00 75,675.00
1.65 OH Pekerja 30,000.00 35,000.00 49,500.00 57,750.00
0.275 OH Tukang Batu 37,500.00 45,000.00 10,312.50 12,375.00
0.028 OH Kepala Tukang 42,000.00 50,000.00 1,176.00 1,400.00
0.083 OH Mandor 37,500.00 50,000.00 3,112.50 4,150.00
6.4 1 m3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 435,771.75 495,292.99
6.4.1 Bahan 391,206.75 442,992.99
230 Kg Portland Semen 962.50 1,050.00 221,375.00 241,500.00
893 kg Pasir Beton 85.71 103.57 76,542.86 92,489.29
1,027 kg Kerikil (maksimum 30 mm) 88.89 103.70 91,288.89 106,503.70
200 ltr Air 10.00 12.50 2,000.00 2,500.00
6.4.2 Tenaga 44,565.00 52,300.00
1.2 OH Pekerja 30,000.00 35,000.00 36,000.00 42,000.00
0.2 OH Tukang Batu 37,500.00 45,000.00 7,500.00 9,000.00
0.02 OH Kepala Tukang 42,000.00 50,000.00 840.00 1,000.00
0.006 OH Mandor 37,500.00 50,000.00 225.00 300.00
6.5 1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66 535,459.52 604,662.90
6.5.1 Bahan 472,534.52 530,412.90
326 Kg Portland Semen 962.50 1,050.00 313,775.00 342,300.00
760 Kg Pasir Beton 85.71 103.57 65,142.86 78,714.29
1,029 Kg Kerikil (maksimum 30 mm) 88.89 103.70 91,466.67 106,711.11
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.5.2 Tenaga 62,925.00 74,250.00
1.65 OH Pekerja 30,000.00 35,000.00 49,500.00 57,750.00
0.250 OH Tukang Batu 37,500.00 45,000.00 9,375.00 11,250.00
0.025 OH Kepala Tukang 42,000.00 50,000.00 1,050.00 1,250.00
0.080 OH Mandor 37,500.00 50,000.00 3,000.00 4,000.00
6.6 1 m3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (122)cm, w/c = 0,61 558,176.59 629,166.73
6.6.1 Bahan 495,251.59 554,916.73
352 Kg Portland Semen 962.50 1,050.00 338,800.00 369,600.00
731 Kg Pasir Beton 85.71 103.57 62,657.14 75,710.71
1,031 Kg Kerikil (maksimum 30 mm) 88.89 103.70 91,644.44 106,918.52
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.6.2 Tenaga 62,925.00 74,250.00
1.65 OH Pekerja 30,000.00 35,000.00 49,500.00 57,750.00
0.25 OH Tukang Batu 37,500.00 45,000.00 9,375.00 11,250.00
0.025 OH Kepala Tukang 42,000.00 50,000.00 1,050.00 1,250.00
0.08 OH Mandor 37,500.00 50,000.00 3,000.00 4,000.00
6.7 1 m3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 575,057.74 647,358.13
6.7.1 Bahan 512,132.74 573,108.13
371 Kg Portland Semen 962.50 1,050.00 357,087.50 389,550.00
698 Kg Pasir Beton 85.71 103.57 59,828.57 72,292.86
1,047 Kg Kerikil (maksimum 30 mm) 88.89 103.70 93,066.67 108,577.78
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.7.2 Tenaga 62,925.00 74,250.00
1.65 OH Pekerja 30,000.00 35,000.00 49,500.00 57,750.00
0.25 OH Tukang Batu 37,500.00 45,000.00 9,375.00 11,250.00
0.025 OH Kepala Tukang 42,000.00 50,000.00 1,050.00 1,250.00
0.08 OH Mandor 37,500.00 50,000.00 3,000.00 4,000.00
6.8 1 m3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (122)cm, w/c = 0,56 586,344.84 659,557.08
6.8.1 Bahan 523,419.84 585,307.08
384 Kg Portland Semen 962.50 1,050.00 369,600.00 403,200.00
692 Kg Pasir Beton 85.71 103.57 59,314.29 71,671.43
1,039 Kg Kerikil (maksimum 30 mm) 88.89 103.70 92,355.56 107,748.15
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.8.2 Tenaga 62,925.00 74,250.00
1.65 OH Pekerja 30,000.00 35,000.00 49,500.00 57,750.00
0.25 OH Tukang Batu 37,500.00 45,000.00 9,375.00 11,250.00
0.025 OH Kepala Tukang 42,000.00 50,000.00 1,050.00 1,250.00
0.08 OH Mandor 37,500.00 50,000.00 3,000.00 4,000.00
6.9 1 m3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (122)cm, w/c = 0,53 605,678.57 680,480.36
6.9.1 Bahan 542,753.57 606,230.36
406 Kg Portland Semen 962.50 1,050.00 390,775.00 426,300.00
684 kg Pasir Beton 85.71 103.57 58,628.57 70,842.86
1,026 kg Kerikil (maksimum 30 mm) 88.89 103.70 91,200.00 106,400.00
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.9.2 Tenaga 62,925.00 74,250.00
1.65 OH Pekerja 30,000.00 35,000.00 49,500.00 57,750.00
0.25 OH Tukang Batu 37,500.00 45,000.00 9,375.00 11,250.00
0.03 OH Kepala Tukang 42,000.00 50,000.00 1,050.00 1,250.00
0.08 OH Mandor 37,500.00 50,000.00 3,000.00 4,000.00
6.10 1 m3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (122)cm, w/c = 0,52 611,714.48 687,001.12
6.10.1 Bahan 548,789.48 612,751.12
413 Kg Portland Semen 962.50 1,050.00 397,512.50 433,650.00
681 Kg Pasir Beton 85.71 103.57 58,371.43 70,532.14
1,021 Kg Kerikil (maksimum 30 mm) 88.89 103.70 90,755.56 105,881.48
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.10.2 Tenaga 62,925.00 74,250.00
1.65 OH Pekerja 30,000.00 35,000.00 49,500.00 57,750.00
0.25 OH Tukang Batu 37,500.00 45,000.00 9,375.00 11,250.00
0.025 OH Kepala Tukang 42,000.00 50,000.00 1,050.00 1,250.00
0.08 OH Mandor 37,500.00 50,000.00 3,000.00 4,000.00
6.11 1 m3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (122)cm, w/c = 0,49 653,070.79 733,606.28
6.11.1 Bahan 571,538.29 637,356.28
439 Kg Portland Semen 962.50 1,050.00 422,537.50 460,950.00
670 Kg Pasir Beton 85.71 103.57 57,428.57 69,392.86
1,006 Kg Kerikil (maksimum 30 mm) 88.89 103.70 89,422.22 104,325.93
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.11.2 Tenaga 81,532.50 96,250.00
2.1 OH Pekerja 30,000.00 35,000.00 63,000.00 73,500.00
0.35 OH Tukang Batu 37,500.00 45,000.00 13,125.00 15,750.00
0.035 OH Kepala Tukang 42,000.00 50,000.00 1,470.00 1,750.00
0.105 OH Mandor 37,500.00 50,000.00 3,937.50 5,250.00
6.12 1 m3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (122)cm, w/c = 0,48 660,942.82 742,123.35
6.12.1 Bahan 579,410.32 645,873.35
448 Kg Portland Semen 962.50 1,050.00 431,200.00 470,400.00
667 Kg Pasir Beton 85.71 103.57 57,171.43 69,082.14
1,000 Kg Kerikil (maksimum 30 mm) 88.89 103.70 88,888.89 103,703.70
215 ltr Air 10.00 12.50 2,150.00 2,687.50
6.12.2 Tenaga 81,532.50 96,250.00
2.10 OH Pekerja 30,000.00 35,000.00 63,000.00 73,500.00
0.350 OH Tukang Batu 37,500.00 45,000.00 13,125.00 15,750.00
0.035 OH Kepala Tukang 42,000.00 50,000.00 1,470.00 1,750.00
0.105 OH Mandor 37,500.00 50,000.00 3,937.50 5,250.00
6.28 1 m3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 2,767,320.00 2,883,700.00
6.28.1 Bahan 2,511,195.00 2,566,950.00
0.2 m3 Kayu Klas III (Terentang) 525,000.00 640,000.00 105,000.00 128,000.00
1.5 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 22,500.00 24,000.00
0.4 Ltr Minyak Bekisting 16,800.00 17,500.00 6,720.00 7,000.00
157.5 Kg Besi Beton Polos 11,700.00 11,500.00 1,842,750.00 1,811,250.00
2.25 Kg Kawat Beton 14,500.00 16,000.00 32,625.00 36,000.00
336 Kg Portland Semen 962.50 1,050.00 323,400.00 352,800.00
0.54 m3 Pasir Beton 120,000.00 145,000.00 64,800.00 78,300.00
0.81 m3 Kerikil Beton 140,000.00 160,000.00 113,400.00 129,600.00
6.29 1 m3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 3,473,125.00 3,598,500.00
6.29.1 Bahan 3,183,930.00 3,239,000.00
0.27 m3 Kayu Klas III (Terentang) 525,000.00 640,000.00 141,750.00 172,800.00
2 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 30,000.00 32,000.00
0.6 Ltr Minyak Bekisting 16,800.00 17,500.00 10,080.00 10,500.00
210 Kg Besi Beton Polos 11,700.00 11,500.00 2,457,000.00 2,415,000.00
3 Kg Kawat Beton 14,500.00 16,000.00 43,500.00 48,000.00
336 Kg Portland Semen 962.50 1,050.00 323,400.00 352,800.00
0.54 m3 Pasir Beton 120,000.00 145,000.00 64,800.00 78,300.00
0.81 m3 Kerikil Beton 140,000.00 160,000.00 113,400.00 129,600.00
6.30 1 m3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 6,366,538.50 6,665,515.00
6.30.1 Bahan 5,975,950.00 6,177,700.00
0.4 m3 Kayu Klas III (Terentang) 525,000.00 640,000.00 210,000.00 256,000.00
4 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 60,000.00 64,000.00
2 Ltr Minyak Bekisting 16,800.00 17,500.00 33,600.00 35,000.00
315 kg Besi Beton Polos 11,700.00 11,500.00 3,685,500.00 3,622,500.00
4.5 kg Kawat Beton 14,500.00 16,000.00 65,250.00 72,000.00
336 Kg Portland Semen 962.50 1,050.00 323,400.00 352,800.00
0.54 m3 Pasir Beton 120,000.00 145,000.00 64,800.00 78,300.00
0.81 m3 Kerikil Beton 140,000.00 160,000.00 113,400.00 129,600.00
0.15 m3 Kayu Klas II Balok 4,200,000.00 4,800,000.00 630,000.00 720,000.00
3.5 Lbr Plywood 9 mm 140,000.00 145,000.00 490,000.00 507,500.00
20 Btg Dolken diameter 8 / 4rm 15,000.00 17,000.00 300,000.00 340,000.00
6.31 1 m3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 4,804,416.00 5,080,415.00
6.31.1 Bahan 4,464,980.00 4,657,700.00
0.32 m3 Kayu Klas III (Terentang) 525,000.00 640,000.00 168,000.00 204,800.00
3.2 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 48,000.00 51,200.00
1.6 Ltr Minyak Bekisting 16,800.00 17,500.00 26,880.00 28,000.00
210 Kg Besi Beton Polos 11,700.00 11,500.00 2,457,000.00 2,415,000.00
3 Kg Kawat Beton 14,500.00 16,000.00 43,500.00 48,000.00
336 Kg Portland Semen 962.50 1,050.00 323,400.00 352,800.00
0.54 m3 Pasir Beton 120,000.00 145,000.00 64,800.00 78,300.00
0.81 m3 Kerikil Beton 140,000.00 160,000.00 113,400.00 129,600.00
0.14 m3 Kayu Klas II Balok 4,200,000.00 4,800,000.00 588,000.00 672,000.00
2.8 Lbr Plywood 9 mm 140,000.00 145,000.00 392,000.00 406,000.00
16 Btg Dolken diameter 8 / 4rm 15,000.00 17,000.00 240,000.00 272,000.00
6.32 1 m3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) 4,273,047.50 4,562,525.00
6.32.1 Bahan 3,995,855.00 4,217,950.00
0.32 m3 Kayu Klas III (Terentang) 525,000.00 640,000.00 168,000.00 204,800.00
3.2 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 48,000.00 51,200.00
1.6 Ltr Minyak Bekisting 16,800.00 17,500.00 26,880.00 28,000.00
157.5 Kg Besi Beton Polos 11,700.00 11,500.00 1,842,750.00 1,811,250.00
2.25 Kg Kawat Beton 14,500.00 16,000.00 32,625.00 36,000.00
336 Kg Portland Semen 962.50 1,050.00 323,400.00 352,800.00
0.54 m3 Pasir Beton 120,000.00 145,000.00 64,800.00 78,300.00
0.81 m3 Kerikil Beton 140,000.00 160,000.00 113,400.00 129,600.00
0.12 m3 Kayu Klas II Balok 4,200,000.00 4,800,000.00 504,000.00 576,000.00
2.8 Lbr Plywood 9 mm 140,000.00 145,000.00 392,000.00 406,000.00
32 Btg Dolken diameter 8 / 4rm 15,000.00 17,000.00 480,000.00 544,000.00
6.32.2 Tenaga 277,192.50 344,575.00
5.3 OH Pekerja 30,000.00 35,000.00 159,000.00 185,500.00
0.275 OH Tukang batu 37,000.00 50,000.00 10,175.00 13,750.00
1.3 OH Tukang Kayu 37,000.00 50,000.00 48,100.00 65,000.00
1.05 OH Tukang Besi 37,000.00 50,000.00 38,850.00 52,500.00
0.265 OH Kepala Tukang 42,000.00 55,000.00 11,130.00 14,575.00
0.265 OH Mandor 37,500.00 50,000.00 9,937.50 13,250.00
6.33 1 m3 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting) 4,278,921.50 4,567,160.00
6.33.1 Bahan 4,001,855.00 4,222,750.00
0.24 m3 Kayu Klas III (Terentang) 525,000.00 640,000.00 126,000.00 153,600.00
3.2 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 48,000.00 51,200.00
1.6 Ltr Minyak Bekisting 16,800.00 17,500.00 26,880.00 28,000.00
157.5 Kg Besi Beton Polos 11,700.00 11,500.00 1,842,750.00 1,811,250.00
2.25 Kg Kawat Beton 14,500.00 16,000.00 32,625.00 36,000.00
336 Kg Portland Semen 962.50 1,050.00 323,400.00 352,800.00
0.54 m3 Pasir Beton 120,000.00 145,000.00 64,800.00 78,300.00
0.81 m3 Kerikil Beton 140,000.00 160,000.00 113,400.00 129,600.00
0.16 m3 Kayu Klas II Balok 4,200,000.00 4,800,000.00 672,000.00 768,000.00
2.8 Lbr Plywood 9 mm 140,000.00 145,000.00 392,000.00 406,000.00
24 Btg Dolken diameter 8 / 4rm 15,000.00 17,000.00 360,000.00 408,000.00
6.33.2 Tenaga 277,066.50 344,410.00
5.3 OH Pekerja 30,000.00 35,000.00 159,000.00 185,500.00
0.275 OH Tukang batu 37,000.00 50,000.00 10,175.00 13,750.00
1.3 OH Tukang Kayu 37,000.00 50,000.00 48,100.00 65,000.00
1.05 OH Tukang Besi 37,000.00 50,000.00 38,850.00 52,500.00
0.262 OH Kepala Tukang 42,000.00 55,000.00 11,004.00 14,410.00
0.265 OH Mandor 37,500.00 50,000.00 9,937.50 13,250.00
6.34 1 m3 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) 4,512,883.50 4,748,615.00
6.34.1 Bahan 4,199,510.00 4,357,200.00
0.25 m3 Kayu Klas III (Terentang) 525,000.00 640,000.00 131,250.00 160,000.00
3 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 45,000.00 48,000.00
1.2 Ltr Minyak Bekisting 16,800.00 17,500.00 20,160.00 21,000.00
210 Kg Besi Beton Polos 11,700.00 11,500.00 2,457,000.00 2,415,000.00
3 Kg Kawat Beton 14,500.00 16,000.00 43,500.00 48,000.00
336 Kg Portland Semen 962.50 1,050.00 323,400.00 352,800.00
0.54 m3 Pasir Beton 120,000.00 145,000.00 64,800.00 78,300.00
0.81 m3 Kerikil Beton 140,000.00 160,000.00 113,400.00 129,600.00
0.105 m3 Kayu Klas II Balok 4,200,000.00 4,800,000.00 441,000.00 504,000.00
2.5 Lbr Plywood 9 mm 140,000.00 145,000.00 350,000.00 362,500.00
14 Btg Dolken diameter 8 / 4rm 15,000.00 17,000.00 210,000.00 238,000.00
6.35 1 m' Membuat Kolom Penguat Beton Bertulang (11 x 11) cm 56,864.50 59,730.00
6.35.1 Bahan 48,655.00 49,650.00
0.002 m3 Kayu Klas III (Terentang) 525,000.00 640,000.00 1,050.00 1,280.00
0.01 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 150.00 160.00
3 Ltr Besi Beton Polos 11,700.00 11,500.00 35,100.00 34,500.00
0.45 Kg Kawat Beton 14,500.00 16,000.00 6,525.00 7,200.00
4 Kg Portland Semen 962.50 1,050.00 3,850.00 4,200.00
0.006 m3 Pasir Beton 120,000.00 145,000.00 720.00 870.00
0.009 m3 Kerikil Beton 140,000.00 160,000.00 1,260.00 1,440.00
6.35.2 Tenaga 8,209.50 10,080.00
0.18 OH Pekerja 30,000.00 35,000.00 5,400.00 6,300.00
0.02 OH Tukang batu 37,000.00 50,000.00 740.00 1,000.00
0.02 OH Tukang Kayu 37,000.00 50,000.00 740.00 1,000.00
0.02 OH Tukang Besi 37,000.00 50,000.00 740.00 1,000.00
0.006 OH Kepala Tukang 42,000.00 55,000.00 252.00 330.00
0.009 OH Mandor 37,500.00 50,000.00 337.50 450.00
6.36 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 66,374.25 70,065.00
6.36.1 Bahan 53,193.75 53,920.00
0.003 m3 Kayu Klas III (Terentang) 525,000.00 640,000.00 1,575.00 1,920.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 300.00 320.00
3.6 Ltr Besi Beton Polos 11,700.00 11,500.00 42,120.00 41,400.00
0.05 Kg Kawat Beton 14,500.00 16,000.00 725.00 800.00
5.5 Kg Portland Semen 962.50 1,050.00 5,293.75 5,775.00
0.009 m3 Pasir Beton 120,000.00 145,000.00 1,080.00 1,305.00
0.015 m3 Kerikil Beton 140,000.00 160,000.00 2,100.00 2,400.00
6.5 1 m2 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm 25,945.00 29,305.00
6.5.1 Bahan 19,575.00 21,105.00
0.375 Lbr Tripleks (4 mm) 51,000.00 55,000.00 19,125.00 20,625.00
0.03 Kg Paku Tripleks 15,000.00 16,000.00 450.00 480.00
6.8 1 m2 Memasang Langit-langit Akuatik Uk (60x120) cm & Rangka Allumunium 117,050.00 128,950.00
6.8.1 Bahan 91,650.00 95,550.00
3.6 m' Profil Allumunium "T" 3,500.00 4,000.00 12,600.00 14,400.00
0.15 kg Kawat 4 mm 6,500.00 7,000.00 975.00 1,050.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akuatik 60 x 120 cm 37,000.00 38,000.00 55,500.00 57,000.00
6.8.2 Tenaga 25,400.00 33,400.00
0.15 OH Pekerja 30,000.00 35,000.00 4,500.00 5,250.00
0.5 OH Tukang Kayu 37,000.00 50,000.00 18,500.00 25,000.00
0.05 OH Kepala Tukang 42,000.00 55,000.00 2,100.00 2,750.00
0.008 OH Mandor 37,500.00 50,000.00 300.00 400.00
X PEKERJAAN SANITASI
6.1 1 Unit Memasang Closet Duduk / Mono Blok 999,542.00 1,038,775.00
6.1.1 Bahan 927,500.00 954,000.00
1 Buah Kloset Duduk / Monoblok 875,000.00 900,000.00 875,000.00 900,000.00
0.06 Kelengkapan 6% dari harga Kloset 875,000.00 900,000.00 52,500.00 54,000.00
6.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 693,122.73 814,000.00
6.8.1 Bahan 376,772.73 439,000.00
0.4 m3 Batu Bata 247,500.00 285,000.00 99,000.00 114,000.00
120 Kg Portland Semen 962.50 1,050.00 115,500.00 126,000.00
0.3 m3 Pasir Pasang 100,000.00 130,000.00 30,000.00 39,000.00
360 buah Porselen 11 x 11 cm 242.42 277.78 87,272.73 100,000.00
6 Kg Semen Nat 7,500.00 10,000.00 45,000.00 60,000.00
6.33 1 Buah Memasang Bak Cuci Piring Stainles Steel 301,816.25 333,875.00
6.33.1 Bahan 290,000.00 320,000.00
1 Buah Bak Cuci Stainles Steel 145,000.00 160,000.00 145,000.00 160,000.00
1 Set Water Drain & assesories 145,000.00 160,000.00 145,000.00 160,000.00
6.18 1 m' Memasang Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm 117,825.00 132,815.00
6.18.1 Bahan 95,600.00 103,940.00
1.05 Lbr Seng Plaat 27,500.00 30,000.00 28,875.00 31,500.00
0.015 Kg Paku Biasa 1 - 2,5 cm 15,000.00 16,000.00 225.00 240.00
0.019 m3 Kayu Papan Klas II atau III 3,500,000.00 3,800,000.00 66,500.00 72,200.00
6.19 1 m' Memasang Talang 1/2 Lingkaran 15 cm, Seng Plaat BJLS 30 Lebar 45 cm 59,972.50 69,410.00
6.19.1 Bahan 42,850.00 47,160.00
1.05 Lbr Seng Plaat 34,000.00 38,000.00 35,700.00 39,900.00
0.01 Kg Paku Biasa 1 - 2,5 cm 15,000.00 16,000.00 150.00 160.00
0.5 Kg Besi strip 14,000.00 14,200.00 7,000.00 7,100.00
6.57 1 m2 Memasang Dinding Batu Paros / Batu Tempel Hitam 125,954.38 142,012.50
6.57.1 Bahan 91,809.38 99,387.50
1.10 m2 Batu Paros 70,000.00 75,000.00 77,000.00 82,500.00
11.75 Kg Portland Semen 962.50 1,050.00 11,309.38 12,337.50
0.035 m3 Pasir Pasang 100,000.00 130,000.00 3,500.00 4,550.00
6.63 1 m' Memasang Plint Kayu Klas II Ukuran 2x10 cm 25,274.00 28,265.50
6.63.1 Bahan 16,505.00 17,105.50
0.003 m3 Papan Kayu Klas II 5,500,000.00 5,700,000.00 16,500.00 17,100.00
0.05 kg Paku Sekrup 5 cm 100.00 110.00 5.00 5.50
6.2 1 m2 Mencuci Bidang Permukaan Tembok yang Pernah dicat 5,143.75 6,000.00
6.2.1 Bahan 550.00 625.00
0.05 Kg Sabun 11,000.00 12,500.00 550.00 625.00
6.3 1 m2 Mengerok Karat Cat Lama permukaan Baja dg cara manual 5,143.75 6,000.00
6.3.1 Bahan 550.00 625.00
0.05 Kg Sabun 11,000.00 12,500.00 550.00 625.00
6.12 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 4,056.25 4,675.00
6.12.1 Bahan 831.25 875.00
0.35 Ltr Residu atau Ter 2,375.00 2,500.00 831.25 875.00
6.14 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 8,644.85 17,308.50
2 lap. Cat Penutup)
6.14.1 Bahan 5,324.00 13,680.00
0.1 Kg Plamir 8,500.00 10,000.00 850.00 1,000.00
0.1 Kg Cat Dasar 12,500.00 54,000.00 1,250.00 5,400.00
0.26 Kg Cat Penutup 2 kali 12,400.00 28,000.00 3,224.00 7,280.00
6.14.2 Tenaga 3,320.85 3,628.50
0.02 OH Pekerja 30,000.00 35,000.00 600.00 700.00
0.063 OH Tukang Cat 37,500.00 40,000.00 2,362.50 2,520.00
0.0063 OH Kepala Tukang 42,000.00 45,000.00 264.60 283.50
0.0025 OH Mandor 37,500.00 50,000.00 93.75 125.00
6.15 1 m2 Pengecat Tembok Lama (1lap.Plamir, 2lap Cat Penutup) 6,167.15 13,414.00
6.15.1 Bahan 3,482.00 10,440.00
0.1 Kg Cat Dasar 12,500.00 54,000.00 1,250.00 5,400.00
0.18 Kg Cat Penutup 2 kali 12,400.00 28,000.00 2,232.00 5,040.00
6.21 1 m2 Pengecatan Permukaan Baja dg Meni Besi & Perancah 19,833.75 22,567.50
6.21.1 Bahan 2,670.00 3,430.00
0.1 Kg Meni Besi 13,000.00 18,000.00 1,300.00 1,800.00
0.01 Kg Perekat / Lem 32,000.00 35,000.00 320.00 350.00
0.002 m3 Perancah Kayu 525,000.00 640,000.00 1,050.00 1,280.00
6.24 1 m2 Pengecatan Permukaan Baja lapis Seng (Galvanis) secara 70,880.00 79,600.00
Manual sistem 3 lap. Cat Konvensional dg Tebal 200 m
6.24.1 Bahan 5,780.00 6,600.00
0.11 Kg Cat dasar 12,500.00 13,000.00 1,375.00 1,430.00
0.17 Kg Cat Antara 12,500.00 13,000.00 2,125.00 2,210.00
0.08 Kg Cat Penutup 28,500.00 37,000.00 2,280.00 2,960.00
6.24.2 Tenaga 65,100.00 73,000.00
0.5 OH Pekerja 30,000.00 35,000.00 15,000.00 17,500.00
0.8 OH Tukang Cat 37,500.00 40,000.00 30,000.00 32,000.00
0.3 OH Kepala Tukang 42,000.00 45,000.00 12,600.00 13,500.00
0.2 OH Mandor 37,500.00 50,000.00 7,500.00 10,000.00
#REF! : #REF!
#REF! : #REF!
#REF!
6.2 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 126,959.85 138,158.40
6.2.1 Bahan 105,969.85 112,058.40
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 15,000.00 17,000.00 18,750.00 21,250.00
2.5 Kg Portalnd Semen 962.50 1,050.00 2,406.25 2,625.00
1.2 Lbr Seng Gelombang 3" - 5" 65,000.00 67,000.00 78,000.00 80,400.00
0.005 m3 Pasir Beton 120,000.00 145,000.00 600.00 725.00
0.009 m3 Koral Beton 120,000.00 140,000.00 1,080.00 1,260.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 58,800.00 67,200.00 4,233.60 4,838.40
0.06 Kg Paku Biasa 2" - 5" 15,000.00 16,000.00 900.00 960.00
0.45 Kg Meni Besi 13,000.00 18,000.00 5,850.00 8,100.00