Anda di halaman 1dari 16

ENGINEER ESTIMATE

PEKERJAAN :REHABILITAS MASJID


LOKASI : JL. ARIFIN AHMAD - PEKANBARU

PEKERJAAN PEKERJAAN
KONTRAK AWAL ADDENDUM - I
TAMBAH ( + ) KURANG ( - )
NO. URAIAN PEKERJAAN SAT
JUMLAH JUMLAH JUMLAH
HARGA HARGA
VOLUME VOLUME VOLUME VOLUME
SATUAN SATUAN
HARGA HARGA HARGA
I PEKERJAAN PENDAHULUAN
1 Pek. Bongkar Lantai Keramik WC/KM 4 Unit M 50.11 41,759 2,092,543 39.94 1,667,938 10.17 41,759
2 Pek. Bongkar Lantai Beton Bertulang WC/KM 4 Unit M 5.58 6,443,335 5.58 1,153,807
3 Pek. Bongkar Dinding Bata WC/KM 4 Unit M 2.13 1,229,958 2.13 576,903
4 Pek. Bongkar Paving Block Area Septicktank Ls 1.00 2,500,000 1.00 2,500,000

II PEKERJAAN ARSITEKTUR
1 Pek. Pasang Keramik Lantai WC/KM Uk. 30x30 cm M 4.44 305,920 1,358,285 5.73 1,752,922 10.17 305,920
2 Pek. Pasang Keramik Lantai WC/KM Uk. 20x20 cm M 45.67 261,181 11,928,136 0.86 225,869 46.53 261,181
3 Pek. Pasang Pintu PVC WC/KM Uk. 60/180 cm Bh 12.00 325,000 3,900,000 12.00 3,900,000 24.00 325,000
4 Pek. Rehab Plafond Gypsum 9 mm M 8.93 65,354 583,611 8.93 583,611
5 Pek. Urugan Tanah Kembali M 22.31 1,032,693 22.31 46,288
6 Pek. Cor Lantai Beton Adk. 1 2 : 3 M 5.58 5,802,045 5.58 1,038,971
7 Pek. Penulangan Plat Lantai Kg 424.23 7,264,318 424.23 17,124
8 Pek. Pasang Dinding 1/2 Bata Adk. 1 : 3 M 16.40 3,562,126 16.40 217,203
9 Pek. Plesteran dinding Bata Adk. 1 : 2 M 10.40 632,141 10.40 60,783
10 Pek. Pasang Dinding Keramik Uk. 20x25 cm M 18.40 5,406,524 18.40 293,833

III PEKERJAAN SANITAIR


1 Pek. Perbaikan Instalasi Pipa Air Bekas & Air Kotor Ls 1.00 1,250,000 1,250,000 1.00 1,250,000
2 Pek. Pasang Kran Air Bh 24.00 41,457 994,968 24.00 41,457
3 Pek. Pasang Floor Drain Bh 24.00 29,526 708,624 24.00 29,526
4 Pek. Pasang Kran Cuci Piring Bh 2.00 167,957 335,914 2.00 167,957
5 Pek. Perbaikan Meja Pantry Bh 2.00 750,000 1,500,000 2.00 750,000
PEKERJAAN PEKERJAAN
KONTRAK AWAL ADDENDUM - I
TAMBAH ( + ) KURANG ( - )
NO. URAIAN PEKERJAAN SAT
JUMLAH JUMLAH JUMLAH
HARGA HARGA
VOLUME VOLUME VOLUME VOLUME
SATUAN SATUAN
HARGA HARGA HARGA
6 Pek. Pasang Closet jongkok Bh 24.00 14,153,556 24.00 589,732
7 Pek. Pengecekan Pipa Air Kotor Ls 1.00 3,000,000 1.00 3,000,000
8 Pek. Instalasi Pipa PVC 2" Air Bekas M' 28.00 931,280 28.00 33,260
9 Pek. Instalasi Pipa PVC 2,5" Air Bekas M' 56.00 2,237,063 56.00 39,948
10 Pek. Instalasi Pipa PVC 3" Air Bekas M' 28.00 1,184,519 28.00 42,304
11 Pek. Instalasi Pipa PVC 4" Air Kotor (Closed) M' 72.00 38,137,464 72.00 529,687
PEKERJAAN PEKERJAAN
KONTRAK AWAL ADDENDUM - I
TAMBAH ( + ) KURANG ( - )
NO. URAIAN PEKERJAAN SAT
JUMLAH JUMLAH JUMLAH
HARGA HARGA
VOLUME VOLUME VOLUME VOLUME
SATUAN SATUAN
HARGA HARGA HARGA

IV PEKERJAAN ELEKTRIKAL
1 Pas. Lampu Hemat Energy 18 Watt Bh 24.00 42,000 1,008,000 24.00 42,000

V PEKERJAAN PENGECATAN
1 Pek. Cat Plafond M 8.93 47,873 427,506 8.93 427,506
2 Pek. Cat Tembok Ruang WC/KM 4 Unit M 175.52 14,425 2,531,876 31.27 451,133 206.79 14,425

VI PEKERJAAN PENGECATAN
1 Pek. Pembersihan Seluruh Lokasi Ls 1.00 3,000,000 1.00 3,000,000
SUB TOTAL A 28,619,464 ### 3,929,055
B PEKERJAAN LANTAI - 2
I PEKERJAAN PEMBONGKARAN
1 Pek. Bongkar Lantai Keramik Uk. 30x30 cm Eksisting M 78.88 41,759 3,293,950 42.25 1,764,234 36.63 41,759

II PEKERJAAN ARSITEKTUR
1 Pek. Pasang Keramik Lantai Ruangan Uk. 30x30 cm M 78.88 305,920 24,130,970 42.25 12,924,508 36.63 305,920
2 Pek. Pasang Keramik Lantai WC/KM Uk. 20x20 cm M 8.00 261,181 2,089,448 8.00 2,089,448
3 Pek. Pasang Pintu PVC WC/KM Uk. 60/180 cm Bh 12.00 325,000 3,900,000 12.00 3,900,000 24.00 325,000
4 Pek. Rehab Plafond Gypsum 9 mm M 8.93 65,354 583,611 8.93 583,611
5 Pek. Rehab Nut Keramik Lantai dan Dinding WC/KM Ls 1.00 500,000 500,000 1.00 500,000

III PEKERJAAN SANITAIR


1 Pek. Perbaikan Instalasi Pipa Air Bekas & Air Kotor Ls 1.00 1,250,000 1,250,000 1.00 1,250,000
2 Pek. Pasang Kran Air Bh 24.00 41,457 994,968 24.00 41,457
3 Pek. Pasang Floor Drain Bh 24.00 29,526 708,624 24.00 29,526
4 Pek. Pasang Kran Cuci Piring Bh 2.00 167,957 335,914 2.00 167,957
5 Pek. Perbaikan Meja Pantry Bh 2.00 750,000 1,500,000 2.00 750,000

IV PEKERJAAN ELEKTRIKAL
1 Pas. Lampu Hemat Energy 18 Watt Bh 24.00 42,000 1,008,000 24.00 42,000
PEKERJAAN PEKERJAAN
KONTRAK AWAL ADDENDUM - I
TAMBAH ( + ) KURANG ( - )
NO. URAIAN PEKERJAAN SAT
JUMLAH JUMLAH JUMLAH
HARGA HARGA
VOLUME VOLUME VOLUME VOLUME
SATUAN SATUAN
HARGA HARGA HARGA
V PEKERJAAN PENGECATAN
1 Pek. Cat Plafond M 8.93 47,873 427,506 8.93 427,506
2 Pek. Cat Tembok Ruang WC/KM 4 Unit M 175.52 14,425 2,531,876 27.02 389,827 202.54 14,425
3 Pek. Cat Minyak Railing Tangga dan Pagar M 39.83 89,576 3,567,812 39.83 89,576
SUB TOTAL B 46,822,679 4,289,827 19,539,308
C PEKERJAAN LANTAI - 3
I PEKERJAAN PEMBONGKARAN
1 Pek. Bongkar Lantai Keramik Uk. 30x30 cm Eksisting M 58.75 41,759 2,453,341 37.60 1,570,222 21.15 41,759

II PEKERJAAN ARSITEKTUR
1 Pek. Pasang Keramik Lantai Ruangan Uk. 30x30 cm M 58.75 305,920 17,972,800 37.60 11,503,204 21.15 305,920
2 Pek. Pasang Keramik Lantai WC/KM Uk. 20x20 cm M 8.00 261,181 2,089,448 8.00 2,089,448
3 Pek. Pasang Pintu PVC WC/KM Uk. 60/180 cm Bh 12.00 325,000 3,900,000 16.00 325,000
4 Pek. Rehab Plafond Gypsum 9 mm M 8.93 65,354 583,611 8.93 583,611
5 Pek. Rehab Nut Keramik Lantai dan Dinding WC/KM Ls 1.00 500,000 500,000 1.00 500,000

III PEKERJAAN SANITAIR


1 Pek. Perbaikan Instalasi Pipa Air Bekas & Air Kotor Ls 1.00 1,250,000 1,250,000 1.00 1,250,000
2 Pek. Pasang Kran Air Bh 24.00 41,457 994,968 24.00 41,457
3 Pek. Pasang Floor Drain Bh 24.00 29,526 708,624 24.00 29,526
4 Pek. Pasang Kran Cuci Piring Bh 2.00 167,957 335,914 2.00 167,957
5 Pek. Perbaikan Meja Pantry Bh 2.00 750,000 1,500,000 2.00 750,000

IV PEKERJAAN ELEKTRIKAL
1 Pas. Lampu Hemat Energy 18 Watt Bh 24.00 42,000 1,008,000 24.00 42,000

V PEKERJAAN PENGECATAN
1 Pek. Cat Plafond M 5.95 47,873 284,844 5.95 284,844
2 Pek. Cat Tembok Ruang WC/KM 4 Unit M 175.52 14,425 2,531,876 27.02 389,827 202.54 14,425
3 Pek. Cat Minyak Railing Tangga dan Pagar M 39.83 89,576 3,567,812 39.83 89,576
SUB TOTAL C 39,681,239 389,827 17,781,329
D PEKERJAAN LANTAI - 4
PEKERJAAN PEKERJAAN
KONTRAK AWAL ADDENDUM - I
TAMBAH ( + ) KURANG ( - )
NO. URAIAN PEKERJAAN SAT
JUMLAH JUMLAH JUMLAH
HARGA HARGA
VOLUME VOLUME VOLUME VOLUME
SATUAN SATUAN
HARGA HARGA HARGA
I PEKERJAAN PEMBONGKARAN
1 Pek. Bongkar Lantai Keramik Uk. 30x30 cm Eksisting M 134.21 41,759 5,604,475 100.46 4,194,942 33.75 41,759

II PEKERJAAN ARSITEKTUR
1 Pek. Pasang Keramik Lantai Ruangan Uk. 30x30 cm M 134.21 305,920 41,057,523 100.46 30,731,500 33.75 305,920
2 Pek. Pasang Keramik Lantai WC/KM Uk. 20x20 cm M 8.00 261,181 2,089,448 8.00 2,089,448
3 Pek. Pasang Pintu PVC WC/KM Uk. 60/180 cm Bh 12.00 325,000 3,900,000 16.00 325,000
4 Pek. Rehab Plafond Gypsum 9 mm M 8.93 65,354 583,611 157.77 10,311,097 166.70 65,354
5 Pek. Rehab Nut Keramik Lantai dan Dinding WC/KM Ls 1.00 500,000 500,000 1.00 500,000

III PEKERJAAN SANITAIR


1 Pek. Perbaikan Instalasi Pipa Air Bekas & Air Kotor Ls 1.00 1,250,000 1,250,000 1.00 1,250,000
2 Pek. Pasang Kran Air Bh 24.00 41,457 994,968 24.00 41,457
3 Pek. Pasang Floor Drain Bh 24.00 29,526 708,624 24.00 29,526
4 Pek. Pasang Kran Cuci Piring Bh 2.00 167,957 335,914 2.00 167,957
5 Pek. Perbaikan Meja Pantry Bh 2.00 750,000 1,500,000 2.00 750,000

IV PEKERJAAN ELEKTRIKAL
1 Pas. Lampu Hemat Energy 18 Watt Bh 24.00 42,000 1,008,000 24.00 42,000

V PEKERJAAN PENGECATAN
1 Pek. Cat Plafond M 5.95 47,873 284,844 160.75 7,695,728 166.70 47,873
2 Pek. Cat Tembok Ruang WC/KM 4 Unit M 175.52 14,425 2,531,876 27.02 389,827 202.54 14,425
3 Pek. Cat Minyak Railing Tangga dan Pagar M 39.83 89,576 3,567,812 39.83 89,576
SUB TOTAL D 65,917,096 18,396,652 38,765,890
E PEKERJAAN LANTAI DAK
I PEKERJAAN PEMBONGKARAN
1 Pek. Bongkar Atap Polycarbonate M 80.88 21,965 1,776,529 1.12 24,601 82.00 21,965

II PEKERJAAN ARSITEKTUR
1 Pek. Pasang Atap Plastik Transparan M 8.83 105,719 933,499 4.60 485,990 13.43 105,719
2 Pek. Pasang Atap Longspan M 72.05 114,614 8,257,939 1.95 223,268 74.00 114,614
PEKERJAAN PEKERJAAN
KONTRAK AWAL ADDENDUM - I
TAMBAH ( + ) KURANG ( - )
NO. URAIAN PEKERJAAN SAT
JUMLAH JUMLAH JUMLAH
HARGA HARGA
VOLUME VOLUME VOLUME VOLUME
SATUAN SATUAN
HARGA HARGA HARGA
3 Pek. Pasang Perabung Atap Longspan M 16.85 72,266 1,217,682 16.85 72,266
4 Pek. Water Proofing Plat Dag M 214.58 59,989 12,872,440 214.58 59,989
SUB TOTAL E 25,058,088 733,859 -
F PEKERJAAN LUAR BANGUNAN
I PEKERJAAN SANITAIR
1 Pek. Instalasi Pipa PVC 2" Air Bekas M' 103.20 33,260 3,432,432 103.20 3,432,432
2 Pek. Instalasi Pipa PVC 4" Air Kotor (Closed) M' 108.00 529,687 57,206,196 108.00 57,206,196
3 Pek. Pembuatan Septicktank Uk. 2 x 3 x 1.5 m Unit 4.00 3,750,000 15,000,000 4.00 3,750,000
4 Pek. Pembuatan Sumur Resapan = 1,5 m x 1,5 m Unit 4.00 2,500,000 10,000,000 4.00 2,500,000
5 Pek. Instalasi Pipa PVC 4" Dari Sumur resapan Ke Saluran Terbuka M' 27.00 14,301,549 27.00 529,687
6 Pek. Instalasi Pipa PVC 4" Air Hujan M' 45.90 24,312,633 45.90 529,687
7 Pek. Cor Beton Selasar Adk. 1 : 2 : 3 M 2.79 2,898,728 2.79 1,038,971
SUB TOTAL F 85,638,628 38,614,182 60,638,628

ASRAMA STIKES BANGKINANG


A PEKERJAAN LANTAI - 1
I PEKERJAAN PENDAHULUAN
1 Pek. Pembongkaran Lantai Keramik M 7.44 41,759 310,687 0.39 16,370 7.05 41,759

II PEKERJAAN ARSITEKTUR
1 Pek. Rehab Pintu Plywood 6 mm M 4.92 259,911 1,278,762 4.92 259,911
2 Pek. Rehab Kusen Alluminium Ls 1.00 2,500,000 2,500,000 1.00 2,500,000
3 Pek. Pasang Kunci Tanam 2 Slag Bh 23.00 200,876 4,620,148 23.00 200,876
4 Pek. Rehab Nut Keramik WC/KM Ls 1.00 500,000 500,000 1.00 500,000
5 Pek. Pasang Kunci Tanam 2 Slag Pintu Entrance Bh 1.00 500,000 1.00 500,000

III PEKERJAAN SANITAIR


1 Pek. Pasang Floor Drain Bh 32.00 29,526 944,832 20.00 590,520 12.00 29,526
2 Pek. Saluran Air Kotor + Besi Grill Saluran WC/KM M' 37.20 125,000 4,650,000 1.96 245,000 35.24 125,000

IV PEKERJAAN PENGECATAN
1 Pek. Cat Vernis Pintu M 75.44 40,865 3,082,856 75.44 40,865
PEKERJAAN PEKERJAAN
KONTRAK AWAL ADDENDUM - I
TAMBAH ( + ) KURANG ( - )
NO. URAIAN PEKERJAAN SAT
JUMLAH JUMLAH JUMLAH
HARGA HARGA
VOLUME VOLUME VOLUME VOLUME
SATUAN SATUAN
HARGA HARGA HARGA
SUB TOTAL A 17,887,285 500,000 851,890
B PEKERJAAN LANTAI - 2
I PEKERJAAN PENDAHULUAN
1 Pek. Pembongkaran Lantai Keramik M 7.44 41,759 310,687 0.23 9,688 7.21 41,759

II PEKERJAAN ARSITEKTUR
1 Pek. Rehab Pintu Plywood 6 mm M 9.84 259,911 2,557,524 1.64 426,254 11.48 259,911
2 Pek. Rehab Kusen Alluminium Ls 1.00 2,500,000 2,500,000 1.00 2,500,000
3 Pek. Pasang Kunci Tanam 2 Slag Bh 24.00 200,876 4,821,024 24.00 200,876
4 Pek. Rehab Nut Keramik WC/KM Ls 1.00 500,000 500,000 1.00 500,000

III PEKERJAAN SANITAIR


1 Pek. Pasang Floor Drain Bh 32.00 29,526 944,832 23.00 679,098 9.00 29,526
2 Pek. Saluran Air Kotor + Besi Grill Saluran WC/KM M' 37.20 125,000 4,650,000 1.16 145,000 36.04 125,000
3 Pek. Water Proofing Plat Dag Teras M 22.32 59,989 1,338,954 22.32 59,989

IV PEKERJAAN PENGECATAN
1 Pek. Cat Vernis Pintu M 78.72 40,865 3,216,893 78.72 40,865
SUB TOTAL B 20,839,914 426,254 833,786

JUMLAH HARGA ### ### ###


PPN ( 10 % ) 33,046,439 16,764,691 14,233,989
TOTAL HARGA ### 184,411,603 ###
### ### ###

Diperiksa oleh:
Diajukan ole
Konsultan Supervisi
Kontraktor Pelak
CV. BARAU KONSULTAN
CV. BUANA MAN
PEKERJAAN PEKERJAAN
Diperiksa oleh: KONTRAK AWAL ADDENDUM - I
TAMBAH ( + ) KURANG ( - ) Diajukan ole
NO. Konsultan Supervisi
URAIAN PEKERJAAN SAT
JUMLAH JUMLAH JUMLAH Kontraktor Pelak
CV. BARAU KONSULTAN HARGA HARGA
VOLUME VOLUME VOLUME VOLUME CV. BUANA MAN
SATUAN SATUAN
HARGA HARGA HARGA

SAID KHAIRIANSYAH,
PUJI ASTUT
ST.
Direktur
Direktur
EER ESTIMATE

ADDENDUM - I KETERANGAN
(THD. VOLUME
JUMLAH
KONTRAK AWAL)
HARGA

424,606 Volume Berkurang


6,443,335 Item Baru
1,229,958 Item Baru
2,500,000 Item Baru

3,111,206 Volume Bertambah


12,154,006 Volume Bertambah
7,800,000 Volume Bertambah
Volume Berkurang
1,032,693 Item Baru
5,802,045 Item Baru
7,264,318 Item Baru
3,562,126 Item Baru
632,141 Item Baru
5,406,524 Item Baru

Volume Berkurang
994,968 Volume Tetap
708,624 Volume Tetap
335,914 Volume Tetap
1,500,000 Volume Tetap
ADDENDUM - I KETERANGAN
(THD. VOLUME
JUMLAH
KONTRAK AWAL)
HARGA
14,153,556 Item Baru
3,000,000 Item Baru
931,280 Item Baru
2,237,063 Item Baru
1,184,519 Item Baru
38,137,464 Item Baru
ADDENDUM - I KETERANGAN
(THD. VOLUME
JUMLAH
KONTRAK AWAL)
HARGA

1,008,000 Volume Tetap

Volume Berkurang
2,983,009 Volume Bertambah

3,000,000 Item Baru


###

1,529,716 Volume Berkurang

11,206,461 Volume Berkurang


Volume Berkurang
7,800,000 Volume Bertambah
Volume Berkurang
Volume Berkurang

Volume Berkurang
994,968 Volume Tetap
708,624 Volume Tetap
335,914 Volume Tetap
1,500,000 Volume Tetap

1,008,000 Volume Tetap


ADDENDUM - I KETERANGAN
(THD. VOLUME
JUMLAH
KONTRAK AWAL)
HARGA

Volume Berkurang
2,921,703 Volume Bertambah
3,567,812 Volume Tetap
31,573,198

883,119 Volume Berkurang

6,469,596 Volume Berkurang


Volume Berkurang
5,200,000 Volume Bertambah
Volume Berkurang
Volume Berkurang

Volume Berkurang
994,968 Volume Tetap
708,624 Volume Tetap
335,914 Volume Tetap
1,500,000 Volume Tetap

1,008,000 Volume Tetap

Volume Berkurang
2,921,703 Volume Bertambah
3,567,812 Volume Tetap
23,589,737
ADDENDUM - I KETERANGAN
(THD. VOLUME
JUMLAH
KONTRAK AWAL)
HARGA

1,409,533 Volume Berkurang

10,326,024 Volume Berkurang


Volume Berkurang
5,200,000 Volume Bertambah
10,894,708 Volume Bertambah
Volume Berkurang

Volume Berkurang
994,968 Volume Tetap
708,624 Volume Tetap
335,914 Volume Tetap
1,500,000 Volume Tetap

1,008,000 Volume Tetap

7,980,573 Volume Bertambah


2,921,703 Volume Bertambah
3,567,812 Volume Tetap
46,847,859

1,801,130 Volume Bertambah

1,419,489 Volume Bertambah


8,481,207 Volume Bertambah
ADDENDUM - I KETERANGAN
(THD. VOLUME
JUMLAH
KONTRAK AWAL)
HARGA
1,217,682 Volume Tetap
12,872,440 Volume Tetap
25,791,948

Volume Berkurang
Volume Berkurang
15,000,000 Volume Tetap
10,000,000 Volume Tetap
14,301,549 Item Baru
24,312,633 Item Baru
2,898,728 Item Baru
63,614,182

294,317 Volume Berkurang

1,278,762 Volume Tetap


2,500,000 Volume Tetap
4,620,148 Volume Tetap
500,000 Volume Tetap
500,000 Item Baru

354,312 Volume Berkurang


4,405,000 Volume Berkurang

3,082,856 Volume Tetap


ADDENDUM - I KETERANGAN
(THD. VOLUME
JUMLAH
KONTRAK AWAL)
HARGA
17,535,395

300,999 Volume Berkurang

2,983,778 Volume Bertambah


2,500,000 Volume Tetap
4,821,024 Volume Tetap
500,000 Volume Tetap

265,734 Volume Berkurang


4,505,000 Volume Berkurang
1,338,954 Volume Tetap

3,216,893 Volume Tetap


20,432,382

###
35,837,142
###
###

Diajukan oleh:
Kontraktor Pelaksana
CV. BUANA MANDIRI
ADDENDUM - I
Diajukan oleh: KETERANGAN
Kontraktor Pelaksana (THD. VOLUME
JUMLAH
KONTRAK AWAL)
CV. BUANA MANDIRI
HARGA

PUJI ASTUTI.
Direktur

Anda mungkin juga menyukai