Anda di halaman 1dari 114

ANALISA BETON BERTULANG

PROYEK PEMBANGUNAN STADION "KARYA JAYA"


Lokasi KABUPATEN LUMAJANG

BETON BESI
JENIS PEKERJAAN Vol. Sat. Hrg. Sat. Vol. Sat. Hrg. Sat.

1 M3 FOOT PLAT 150 x 150 x 20


- Bahan 1.00 M3 -
- Upah (Cor Manual) 1.00 M3 72,000.00 165.76 Kg 480.00
72,000.00 79,564.80

SLOOF
Balok Sloof 30/50 = 0,15, 1 M3
- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 72,000.00 124.43 Kg 480.00

72,000.00 59,724.80

1 M Balok Sloof = 20/50 = 0.10, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 72,000.00 160.97 Kg 480.00

72,000.00 77,264.64

1 M Balok sloof = 20/30 = 0,06 M3, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 72,000.00 133.24 Kg 480.00
72,000.00 63,955.20

1 M Balok 20/50 = 0.10, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00 160.97 Kg 480.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00

42,000.00 77,264.64

1 M Ring Balk. 20/30 = 0,06 M3, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00 133.24 Kg 480.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00

42,000.00 63,955.20
KOLOM
KOLOM 50 x 50 = 0,25 M3, 1 M3
- Bahan 1.00 M3
- Upah Ready Mixed Tanpa Pump 1.00 M3 48,000.00 191.81 Kg 480.00
- Sepatu Kolom (40 x 40) 1.00 Bh 4,800.00
52,800.00 92,067.84

KOLOM 40 x 40 = 0,16 M3, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Tanpa Pump 1.00 M3 48,000.00 139.10 Kg 480.00
- Sepatu Kolom (40 x 40) 1.00 Bh 4,800.00

52,800.00 66,768.60

Kolom Praktis 15 x 15 = 0,0225 M3, 1 M3


- Bahan M3 -
- Upah Ready Mixed Tanpa Pump M3 48,000.00 136.98 Kg 480.00
48,000.00 65,751.47

BALOK
Balok utama 40/60 = 0,24 M3, 1M3
- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00 176.30 Kg 480.00
42,000.00 84,623.98

Balok anak 30/50 = 0,15, 1 M3


- Bahan 1.00 M3 -
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00 151.66 Kg 480.00
42,000.00 72,798.40

Balok sloof = Ring Balk. 20/30 = 0,06M3, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00 133.24 Kg 480.00
42,000.00 63,955.20

Balok ring 30/50 = 0,15, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00 206.81 Kg 480.00
42,000.00 99,268.00

Balok latai = Balok 15/20 = 0.03, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 72,000.00 156.31 Kg 480.00
72,000.00 75,027.20

Balok = Balok 15/30 = 0.045, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 72,000.00 131.63 Kg 480.00
72,000.00 63,180.80

Balok = Balok 15/50 = 0.075, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 72,000.00 102.01 Kg 480.00
72,000.00 48,965.12

PLAT
Grid Plat Dag = 300 x 300 x 12 = 0.12, 1 M3 =
- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00 148.76 Kg 480.00
42,000.00 71,403.73

1 M Plat Dag = 600 x 600 x 10 = 0.10, 1 M3 =


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00 172.76 Kg 480.00
42,000.00 82,924.80

1 M Plat Tangga = 100 x 100 x 15 = 0.15, 1 M3 =


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00 168.56 Kg 480.00
42,000.00 80,908.80

1 M Plat Lisplank = 100 x 100 x 7 = 0.07, 1 M3 =


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 24,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 18,000.00 100.70 Kg 480.00
42,000.00 48,336.00

1077600
BEGISTING Beton Deking Bongkaran Begisting JUMLAH
Vol. Sat. Hrg. Sat. Vol. Sat. Hrg. Sat. Vol. Sat. Hrg. Sat.

-
2.67 M2 7,800.00 4.92 M2 240.00 M2 1,800.00
20,800.00 1,180.00 - 173,544.80

6.67 M2 7,800.00 8.67 M2 240.00 M2 1,800.00

52,000.00 2,080.00 - 185,804.80

10.00 M2 7,800.00 12.00 M2 240.00 M2 1,800.00

78,000.00 2,880.00 - 230,144.64

10.00 7,800.00 13.33 240.00 1,800.00


78,000.00 3,200.00 - 217,155.20

10.00 M2 7,800.00 12.00 M2 240.00 10.00 M2 1,800.00

78,000.00 2,880.00 18,000.00 218,144.64


10.00 M2 7,800.00 13.33 M2 240.00 10.00 M2 1,800.00

78,000.00 3,200.00 18,000.00 205,155.20

4.00 M2 15,600.00 4.00 M2 240.00 4.00 M2 1,800.00

62,400.00 960.00 7,200.00 215,427.84

5.00 M2 15,600.00 5.00 M2 240.00 5.00 M2 1,800.00

78,000.00 1,200.00 9,000.00 207,768.60

3.33 M2 7,200.00 3.33 M2 240.00 3.33 M2 1,800.00


24,000.00 800.00 6,000.00 144,551.47

4.44 M2 15,600.00 6.94 M2 240.00 4.44 M2 1,800.00


69,333.33 1,666.67 8,000.00 205,623.98

5.78 M2 15,600.00 9.11 M2 240.00 5.78 M2 1,800.00


90,133.33 2,186.67 10,400.00 217,518.40

2.50 M2 7,200.00 7.50 M2 240.00 2.50 M2 1,800.00


18,000.00 1,800.00 4,500.00 130,255.20
5.78 M2 7,200.00 9.11 M2 240.00 5.78 M2 1,800.00
41,600.00 2,186.67 10,400.00 195,454.67

6.67 M2 9,000.00 13.33 M2 240.00 6.67 M2 1,800.00


60,000.00 3,200.00 12,000.00 222,227.20

6.67 M2 15,600.00 13.33 M2 240.00 6.67 M2 1,800.00


104,000.00 3,200.00 12,000.00 254,380.80

6.67 M2 15,600.00 13.33 M2 240.00 6.67 M2 1,800.00


104,000.00 3,200.00 12,000.00 240,165.12

8.33 M2 15,600.00 8.33 M2 240.00 8.33 M2 1,800.00


130,000.00 2,000.00 15,000.00 260,403.73

10.00 M2 15,600.00 10.00 M2 240.00 10.00 M2 1,800.00


156,000.00 2,400.00 18,000.00 301,324.80

6.67 M2 15,600.00 6.67 M2 240.00 6.67 M2 1,800.00


104,000.00 1,600.00 12,000.00 240,508.80

14.29 M2 15,600.00 14.29 M2 240.00 14.29 M2 1,800.00


222,857.14 3,428.57 25,714.29 342,336.00
ANALISA BETON BERTULANG
PROYEK PEMBANGUNAN STADION "KARYA JAYA"
Lokasi KABUPATEN LUMAJANG

JENIS PEKERJAAN BETON BESI


Vol. Sat. Hrg. Sat. Vol. Sat. Hrg. Sat.

1 M3 FOOT PLAT 150 x 150 x 20


- Bahan 1.00 M3 -
- Upah (Cor Manual) 1.00 M3 66,000.00 165.76 Kg 440.00
66,000.00 72,934.40

SLOOF
Balok Sloof 30/50 = 0,15, 1 M3
- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 66,000.00 124.43 Kg 440.00

66,000.00 54,747.73

1 M Balok Sloof = 20/50 = 0.10, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 66,000.00 160.97 Kg 440.00

66,000.00 70,825.92

1 M Balok sloof = 20/30 = 0,06 M3, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 66,000.00 133.24 Kg 440.00
66,000.00 58,625.60

1 M Balok 20/50 = 0.10, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00 160.97 Kg 440.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00

38,500.00 70,825.92

1 M Ring Balk. 20/30 = 0,06 M3, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00 133.24 Kg 440.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00

38,500.00 58,625.60
KOLOM
KOLOM 50 x 50 = 0,25 M3, 1 M3
- Bahan 1.00 M3
- Upah Ready Mixed Tanpa Pump 1.00 M3 44,000.00 191.81 Kg 440.00
- Sepatu Kolom (40 x 40) 1.00 Bh 4,400.00
48,400.00 84,395.52

KOLOM 40 x 40 = 0,16 M3, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Tanpa Pump 1.00 M3 44,000.00 139.10 Kg 440.00
- Sepatu Kolom (40 x 40) 1.00 Bh 4,400.00

48,400.00 61,204.55

Kolom Praktis 15 x 15 = 0,0225 M3, 1 M3


- Bahan M3 -
- Upah Ready Mixed Tanpa Pump M3 44,000.00 136.98 Kg 440.00
44,000.00 60,272.18

BALOK
Balok utama 40/60 = 0,24 M3, 1M3
- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00 176.30 Kg 440.00
38,500.00 77,571.98

Balok anak 30/50 = 0,15, 1 M3


- Bahan 1.00 M3 -
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00 151.66 Kg 440.00
38,500.00 66,731.87

Balok sloof = Ring Balk. 20/30 = 0,06M3, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00 133.24 Kg 440.00
38,500.00 58,625.60

Balok ring 30/50 = 0,15, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00 206.81 Kg 440.00
38,500.00 90,995.67

Balok latai = Balok 15/20 = 0.03, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 66,000.00 156.31 Kg 440.00
66,000.00 68,774.93

Balok = Balok 15/30 = 0.045, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 66,000.00 131.63 Kg 440.00
66,000.00 57,915.73

Balok = Balok 15/50 = 0.075, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 66,000.00 102.01 Kg 440.00
66,000.00 44,884.69

PLAT
Grid Plat Dag = 300 x 300 x 12 = 0.12, 1 M3 =
- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00 148.76 Kg 440.00
38,500.00 65,453.42

1 M Plat Dag = 600 x 600 x 10 = 0.10, 1 M3 =


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00 172.76 Kg 440.00
38,500.00 76,014.40

1 M Plat Tangga = 100 x 100 x 15 = 0.15, 1 M3 =


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00 168.56 Kg 440.00
38,500.00 74,166.40

1 M Plat Lisplank = 100 x 100 x 7 = 0.07, 1 M3 =


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 22,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 16,500.00 100.70 Kg 440.00
38,500.00 44,308.00
BEGISTING Beton Deking Bongkaran Begisting JUMLAH
Vol. Sat. Hrg. Sat. Vol. Sat. Hrg. Sat. Vol. Sat. Hrg. Sat.

-
2.67 M2 7,150.00 4.92 M2 220.00 M2 1,650.00
19,066.67 1,081.67 - 159,082.73

6.67 M2 7,150.00 8.67 M2 220.00 M2 1,650.00

47,666.67 1,906.67 - 170,321.07

10.00 M2 7,150.00 12.00 M2 220.00 M2 1,650.00

71,500.00 2,640.00 - 210,965.92

10.00 7,150.00 13.33 220.00 1,650.00


71,500.00 2,933.33 - 199,058.93

10.00 M2 7,150.00 12.00 M2 220.00 10.00 M2 1,650.00

71,500.00 2,640.00 ### 199,965.92


10.00 M2 7,150.00 13.33 M2 220.00 10.00 M2 1,650.00

71,500.00 2,933.33 ### 188,058.93

4.00 M2 14,300.00 4.00 M2 220.00 4.00 M2 1,650.00

57,200.00 880.00 6,600.00 197,475.52

5.00 M2 14,300.00 5.00 M2 220.00 5.00 M2 1,650.00

71,500.00 1,100.00 8,250.00 190,454.55

3.33 M2 6,600.00 3.33 M2 220.00 3.33 M2 1,650.00


22,000.00 733.33 5,500.00 132,505.51

4.44 M2 14,300.00 6.94 M2 220.00 4.44 M2 1,650.00


63,555.56 1,527.78 7,333.33 188,488.65

5.78 M2 14,300.00 9.11 M2 220.00 5.78 M2 1,650.00


82,622.22 2,004.44 9,533.33 199,391.87

2.50 M2 6,600.00 7.50 M2 220.00 2.50 M2 1,650.00


16,500.00 1,650.00 4,125.00 119,400.60
5.78 M2 6,600.00 9.11 M2 220.00 5.78 M2 1,650.00
38,133.33 2,004.44 9,533.33 179,166.78

6.67 M2 8,250.00 13.33 M2 220.00 6.67 M2 1,650.00


55,000.00 2,933.33 ### 203,708.27

6.67 M2 14,300.00 13.33 M2 220.00 6.67 M2 1,650.00


95,333.33 2,933.33 ### 233,182.40

6.67 M2 14,300.00 13.33 M2 220.00 6.67 M2 1,650.00


95,333.33 2,933.33 ### 220,151.36

8.33 M2 14,300.00 8.33 M2 220.00 8.33 M2 1,650.00


119,166.67 1,833.33 ### 238,703.42

10.00 M2 14,300.00 10.00 M2 220.00 10.00 M2 1,650.00


143,000.00 2,200.00 ### 276,214.40

6.67 M2 14,300.00 6.67 M2 220.00 6.67 M2 1,650.00


95,333.33 1,466.67 ### 220,466.40

14.29 M2 14,300.00 14.29 M2 220.00 14.29 M2 1,650.00


204,285.71 3,142.86 ### 313,808.00
ANALISA BETON BERTULANG
PROYEK PEMBANGUNAN STADION "KARYA JAYA"
Lokasi KABUPATEN LUMAJANG

JENIS PEKERJAAN BETON BESI


Vol. Sat. Hrg. Sat. Vol. Sat. Hrg. Sat.

1 M3 FOOT PLAT 150 x 150 x 20


- Bahan 1.00 M3 -
- Upah (Cor Manual) 1.00 M3 60,000.00 165.76 Kg 400.00
60,000.00 66,304.00

SLOOF
Balok Sloof 30/50 = 0,15, 1 M3
- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 60,000.00 124.43 Kg 400.00

60,000.00 49,770.67

1 M Balok Sloof = 20/50 = 0.10, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 60,000.00 160.97 Kg 400.00

60,000.00 64,387.20

1 M Balok sloof = 20/30 = 0,06 M3, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 60,000.00 133.24 Kg 400.00
60,000.00 53,296.00

1 M Balok 20/50 = 0.10, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00 160.97 Kg 400.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00

35,000.00 64,387.20

1 M Ring Balk. 20/30 = 0,06 M3, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00 133.24 Kg 400.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00

35,000.00 53,296.00
KOLOM
KOLOM 50 x 50 = 0,25 M3, 1 M3
- Bahan 1.00 M3
- Upah Ready Mixed Tanpa Pump 1.00 M3 40,000.00 191.81 Kg 400.00
- Sepatu Kolom (40 x 40) 1.00 Bh 4,000.00
44,000.00 76,723.20

KOLOM 40 x 40 = 0,16 M3, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Tanpa Pump 1.00 M3 40,000.00 139.10 Kg 400.00
- Sepatu Kolom (40 x 40) 1.00 Bh 4,000.00

44,000.00 55,640.50

Kolom Praktis 15 x 15 = 0,0225 M3, 1 M3


- Bahan M3 -
- Upah Ready Mixed Tanpa Pump M3 40,000.00 136.98 Kg 400.00
40,000.00 54,792.89

BALOK
Balok utama 40/60 = 0,24 M3, 1M3
- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00 176.30 Kg 400.00
35,000.00 70,519.98

Balok anak 30/50 = 0,15, 1 M3


- Bahan 1.00 M3 -
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00 151.66 Kg 400.00
35,000.00 60,665.33

Balok sloof = Ring Balk. 20/30 = 0,06M3, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00 133.24 Kg 400.00
35,000.00 53,296.00

Balok ring 30/50 = 0,15, 1 M3


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00 206.81 Kg 400.00
35,000.00 82,723.33

Balok latai = Balok 15/20 = 0.03, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 60,000.00 156.31 Kg 400.00
60,000.00 62,522.67

Balok = Balok 15/30 = 0.045, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 60,000.00 131.63 Kg 400.00
60,000.00 52,650.67

Balok = Balok 15/50 = 0.075, 1 M3


- Bahan 1.00 M3
- Upah (Cor Manual) 1.00 M3 60,000.00 102.01 Kg 400.00
60,000.00 40,804.27

PLAT
Grid Plat Dag = 300 x 300 x 12 = 0.12, 1 M3 =
- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00 148.76 Kg 400.00
35,000.00 59,503.11

1 M Plat Dag = 600 x 600 x 10 = 0.10, 1 M3 =


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00 172.76 Kg 400.00
35,000.00 69,104.00

1 M Plat Tangga = 100 x 100 x 15 = 0.15, 1 M3 =


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00 168.56 Kg 400.00
35,000.00 67,424.00

1 M Plat Lisplank = 100 x 100 x 7 = 0.07, 1 M3 =


- Bahan 1.00 M3
- Upah Ready Mixed Dengan Pump 1.00 M3 20,000.00
- Sewa Pompa (per - 8 Jam @ Rp. 1.800.000,00) 0.01 Jam 15,000.00 100.70 Kg 400.00
35,000.00 40,280.00

898000
BEGISTING Beton Deking Bongkaran Begisting JUMLAH
Vol. Sat. Hrg. Sat. Vol. Sat. Hrg. Sat. Vol. Sat. Hrg. Sat.

-
2.67 M2 6,500.00 4.92 M2 200.00 M2 1,500.00
17,333.33 983.33 - 144,620.67

6.67 M2 6,500.00 8.67 M2 200.00 M2 1,500.00

43,333.33 1,733.33 - 154,837.33

10.00 M2 6,500.00 12.00 M2 200.00 M2 1,500.00

65,000.00 2,400.00 - 191,787.20

10.00 6,500.00 13.33 200.00 1,500.00


65,000.00 2,666.67 - 180,962.67

10.00 M2 6,500.00 12.00 M2 200.00 10.00 M2 1,500.00

65,000.00 2,400.00 15,000.00 181,787.20


10.00 M2 6,500.00 13.33 M2 200.00 10.00 M2 1,500.00

65,000.00 2,666.67 15,000.00 170,962.67

4.00 M2 13,000.00 4.00 M2 200.00 4.00 M2 1,500.00

52,000.00 800.00 6,000.00 179,523.20

5.00 M2 13,000.00 5.00 M2 200.00 5.00 M2 1,500.00

65,000.00 1,000.00 7,500.00 173,140.50

3.33 M2 6,000.00 3.33 M2 200.00 3.33 M2 1,500.00


20,000.00 666.67 5,000.00 120,459.56

4.44 M2 13,000.00 6.94 M2 200.00 4.44 M2 1,500.00


57,777.78 1,388.89 6,666.67 171,353.32

5.78 M2 13,000.00 9.11 M2 200.00 5.78 M2 1,500.00


75,111.11 1,822.22 8,666.67 181,265.33

2.50 M2 6,000.00 7.50 M2 200.00 2.50 M2 1,500.00


15,000.00 1,500.00 3,750.00 108,546.00
5.78 M2 6,000.00 9.11 M2 200.00 5.78 M2 1,500.00
34,666.67 1,822.22 8,666.67 162,878.89

6.67 M2 7,500.00 13.33 M2 200.00 6.67 M2 1,500.00


50,000.00 2,666.67 10,000.00 185,189.33

6.67 M2 13,000.00 13.33 M2 200.00 6.67 M2 1,500.00


86,666.67 2,666.67 10,000.00 211,984.00

6.67 M2 13,000.00 13.33 M2 200.00 6.67 M2 1,500.00


86,666.67 2,666.67 10,000.00 200,137.60

8.33 M2 13,000.00 8.33 M2 200.00 8.33 M2 1,500.00


108,333.33 1,666.67 12,500.00 217,003.11

10.00 M2 13,000.00 10.00 M2 200.00 10.00 M2 1,500.00


130,000.00 2,000.00 15,000.00 251,104.00

6.67 M2 13,000.00 6.67 M2 200.00 6.67 M2 1,500.00


86,666.67 1,333.33 10,000.00 200,424.00

14.29 M2 13,000.00 14.29 M2 200.00 14.29 M2 1,500.00


185,714.29 2,857.14 21,428.57 285,280.00
DAFTAR HARGA BAHAN SIPIL
NAMA PROYEK : Pembangunan Rumah Persemayanan
PEKERJAAN : ……………………………………………………………
TAHUN ANGGARAN : 2006

HARGA BAHAN
NO NAMA BAHAN SAT
Rp.

1 Kabel NYM 2 x 2.5 mm M 6,500.00


2 Kabel NYM 3 x 2.5 mm M 8,000.00
3 Stop Kontak 10 A Bh 15,000.00
4 Dos Bh 1,000.00
5 Saklar Cam Unit 75,000.00
5 MCB 16 A Unit 50,000.00
6 Box Sekring Unit 75,000.00
7 Lampu Sorot 400 W Bh 950,000.00

Harga Bahan Proyek ....... 04/13/2019 HAL : 25


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN
JUMLAH HARGA SATUAN
NO JENIS PEKERJAAN KOEF STN HARGA BAHAN (Rp) (Rp)

1 Box Sekering
Bahan
MCB 16 A 1 Ph 1.000 Unit 50,000.00 50,000.00
Box Sekring 1.000 Bh 75,000.00 75,000.00
Jumlah 125,000.00
Tenaga
Tukang Listik 0.200 Oh 40,000.00 8,000.00
Pekerja 0.400 Oh 25,000.00 10,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.020 Oh 60,000.00 1,200.00
Jumlah 20,200.00
Total 145,200.00
2 Stop Kontak
Bahan
Stop Kontak 1.000 Bh 15,000.00 15,000.00
Kabel NYM 3 x 2.5 mm 10.000 M 8,000.00 80,000.00
Dos 1.000 Bh 1,000.00 1,000.00
Jumlah 96,000.00
Tenaga
Tukang Listik 0.200 Oh 40,000.00 8,000.00
Pekerja 0.300 Oh 25,000.00 7,500.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.020 Oh 60,000.00 1,200.00
Jumlah 17,700.00
Total 113,700.00
3 Instalasi Lampu
Bahan
Kabel 2 x 2.5 mm 20.000 m 6,500.00 130,000.00
Jumlah 130,000.00
Tenaga
Tukang Listik 2.000 Oh 40,000.00 80,000.00
Pekerja 1.000 Oh 25,000.00 25,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 118,000.00
Total 248,000.00
4 Saklar Cam
Bahan
Saklar Cam 1.000 Unit 75,000.00 75,000.00
Jumlah 75,000.00
Tenaga
Tukang Listik 1.500 Oh 40,000.00 60,000.00
Pekerja 1.000 Oh 25,000.00 25,000.00
Kepala Tukang 0.150 Oh 50,000.00 7,500.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 95,500.00
Total 170,500.00

Lampu Sorot
Bahan
Lampu Sorot 400 W 1.000 Unit 950,000.00 950,000.00
Jumlah 950,000.00
Tenaga
Tukang Listik 1.500 Oh 40,000.00 60,000.00
Pekerja 1.000 Oh 25,000.00 25,000.00
Kepala Tukang 0.150 Oh 50,000.00 7,500.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 95,500.00
Total 1,045,500.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 26


DAFTAR HARGA BAHAN SIPIL
NAMA PROYEK : Pembangunan Rumah Persemayanan
PEKERJAAN : ……………………………………………………………
TAHUN ANGGARAN : 2006

HARGA BAHAN
NO NAMA BAHAN SAT
Rp.

BATU
1 Agregat Halus M3 -
2 Agregat Kasar M3 -
3 Batu Bulat Sungai M3 -
4 Batu Belah 10 - 15 / 15 - 20 Cm M3 112,700.00
5 Batu Pecah 5 - 7 Cm M3 112,700.00
6 Batu Pecah 3 - 5 Cm M3 112,700.00
7 Batu Pecah 2 - 3 Cm M3 122,950.00
8 Batu Pecah 1 - 2 Cm M3 122,950.00
9 Batu Pecah 4 - 6 Cm M3 112,700.00
10 Batu Koral Pecah 2 - 3 Cm M3 122,950.00
1 Batu Koral Pecah 1 - 2 Cm M3 122,950.00
2 Batu Koral Pecah 0,5 - 1 Cm M3 128,050.00
3 Batu Palimanan M2 -
4 Batu Ampyang Kg -
5 Batu Teraso Kg -
6 Batu Tempel Hitam (Batu Candi) M2 -
7 Batu Paras M2 -
8 Krikil Sungai tidak tersaring M3 -
9 Batu Granito Kg -

PASIR
1 Pasir Urug / Timbunan M3 66,600.00
2 Pasir Pasang M3 79,400.00
3 Pasir Beton M3 92,200.00
4 Pasir Silika Kg -
5 Sirtu M3 61,500.00
6 Grosok M3 -
7 Tanah Urug M3 46,100.00
8 Timbunan Pilihan M3 -
9 Pitrun M3 -

BATU MERAH / BATACO


1 Batu Merah Bj 300.00
2 Bataco Bj 2,050.00
3 Batacote M2
4 Roster Bata Bh -
5 Bata pelapis dinding Bh -
6 Bata Pelapis Klinker Bh -

KAPUR
1 Kapur Zak -
2 Kapur M3 -
3 Gamping M3 -
4 Gamping Kg -

KAYU
1 Kayu Jati Balok 8/12,6/12 X 4 M' M3 -
2 Kayu Jati Papan 2/20 X 4 M' M3 -
3 Kayu Kamper Balok 8/12, 8/15, 6/12 X 4 M' M3 -
4 Kayu Kamper Papan 2/20, 3/30, 3/30 X 4 M' M3 -
5 Kayu Kamper Usuk 5/7, 4/6 X 4 M' M3 -
6 Kayu Kamper Reng 2/3, 3/5 X 4 M' M3 -
7 Kayu Kruing Balok 8/12, 8/15, 6/12 X 4 M' M3 -
8 Kayu Kruing Papan 2/20, 3/30, 3/30 X 4 M' M3 -
9 Kayu Kruing Usuk 5/7, 4/6 X 4 M' M3 -
10 Kayu Kruing Reng 2/3, 3/5 X 4 M' M3 -
1 Kayu Meranti Balok 8/12, 8/15, 6/12 X 4 M' M3 1,895,150.00
2 Kayu Meranti Papan 2/20, 3/30, 3/30 X 4 M' M3 1,690,300.00
3 Kayu Meranti Usuk 5/7, 4/6 X 4 M' M3 1,434,200.00
4 Kayu Meranti Reng 2/3, 3/5 X 4 M' M3 -
4 Kayu Begisting M3 717,100.00
5 Formitie/penjaga jarak bekisting/spacer Btg -
6 List Kayu 2/4 M' -
5 Dolken 4 m btg 8,750.00
6 Perancah Kayu M3 -
7 Kayu Bakar M3

Harga Bahan Proyek ....... 04/13/2019 HAL : 27


HARGA BAHAN
NO NAMA BAHAN SAT
Rp.
GENTENG
1 Genteng Biasa Bj -
2 Genteng Gandu Sari Bj -
3 Genteng tipe Karang pilang Bj -
4 Genteng Bubung tipe Karang pilang Bj -
5 Genteng Press Bj -
6 Genteng Bubung press Bj -
7 Genteng Decra Bond Bj -
8 Genteng Aspal Lbr -
9 Genteng Beton Bj -
10 Genteng Metal Lbr -
11 Genteng Sirap Bh -
1 Atap Zincalum M2 49,375.00
2 Glaswool M2 9,750.00
3 Roof mash (kawat kasa utk atap) M2 7,250.00
4 Nok Genteng Beton Bh -

GORONG-GORONG
1 Gorong-2 Ø 40 cm M' -
2 Gorong-2 Ø 50 cm M' -
3 Gorong-2 Ø 60 cm M' -
4 Gorong-2 Ø 80 cm M' -
5 Buis Beton U 20 cm Bh -
6 Buis Beton U 30 cm Bh -
7 Buis Beton D 100 cm M' -
8 Buis Beton D 80 cm M' -
9 Buis Beton D 60 cm M' -
10 Buis Beton D 40 cm M' -
11 Buis Beton D 30 cm M' -
12 Buis Beton D 20 cm M' -

PORTLAND CEMENT ( PC )
1 Semen 50 Kg Zak 41,000.00
2 Semen 40 Kg Zak 32,800.00
3 Semen PC Kg 820.00
4 Semen Putih Kg 2,050.00
5 Semen Merah M3 8,750.00
6 Semen Warna Kg -
7 Semen Tahan Asam Kg -
8 Betagum ex Holland 4 mm M2 -

PAKU
1 Paku Reng / Papan Kg 8,750.00
2 Paku Usuk Kg 10,250.00
3 Paku Eternit Kg -
4 Baut Kail / Kait Stel -
5 Angker Kusen / paku dook Kg -
3 Paku Seng / Sumbat Kg 13,850.00
4 Paku Skrup Bh 350.00
5 Paku Kalsiboard Kg -
6 Paku Hak pig Kg -
7 Paku Pancing Kg -
Paku Asbes Kg
MUR BAUT
1 Angker 5/8 -30 cm Bh -
2 Angker 3/4 -50 cm Bh -
1 Mur Baut & Set Ankur 1/2 " Bh 1,250.00
2 Mur Baut 3/8 " Bh 750.00
3 Mur Baut 5/8 " Bh 1,550.00
4 Mur Baut 3/4 " Bh -
5 Dynabolt (terpasang) Bh -
4 Jarum keras Bh 4,350.00
5 Ankur Ø 19 Bh 32,000.00

KAWAT
1 Bendrat / Kawat Beton Kg 9,250.00
2 Kawat Bronjong / duri Ø 4 mm Kg -
3 Kawat Harmonika M2 -
4 Kawat Jaring M2 -
5 Kawat Kasa M2 -
6 Kawat Seng Polos Kg -
7 Kawat Duri Kg

BESI
1 Besi Beton Kg 5,000.00
2 Besi Beugel Klem Stell -

Harga Bahan Proyek ....... 04/13/2019 HAL : 28


HARGA BAHAN
NO NAMA BAHAN SAT
Rp.
3 Besi Klem Kuda - kuda Stell -
4 Besi Baja Profil Kg -
5 Besi Canal C Kg -
6 Besi Pelat Strip M2 -
7 Besi Presstressed polos Kg -
8 Nok Stel Gelombang M' -
9 Besi Profil Siku Kg -
10 Profil Alumunium "T" M' -
11 Kerangka Naco Daun -
2 Besi Profil WF Kg 10,250.00
3 Besi Profil C Kg 12,300.00
4 Baja Plat 1.2 mm M2 966,165.00

SENG
1 Seng BWG 30 ( 80 X 300 Cm ) gelombang Lbr -
2 Seng BJLS 30 ( 80 X 180 Cm ) gelombang Lbr -
1 Seng Plat 3"× 6" BJLS Lbr 37,800.00
2 Seng Gelombang 3"×6" BJLS 28 Lbr -
3 Seng Plat Alumunium Lbr -
4 Seng Talang BWG 30 Lbr. 60 cm M' -
5 Seng Talang BWG 30 Lbr. 90 cm M' -
6 Seng Plat Datar Lbr -
7 Lapis Aluminium 4 x 8 x 4 mm Lbr -

TRIPLEK
1 Triplek 120 X 240 X 4 mm Lbr -
2 Triplek 90 X 210 X 4 mm Lbr -
3 Triplek 120 x 240 x 3 mm Lbr -
4 Multiplek t = 9 mm Lbr -
5 Teaxwood 90 x 210 x 4 mm Lbr -
6 Teaxwood 120 x 240 x 4 mm Lbr -
7 Teaxwood 120 X 240 x 3 mm Lbr -
8 Playwood 4' X 8' x 4 mm Lbr -
9 Playwood 4' X 8' x 6 mm Lbr -
10 Playwood 4 Lbr -
1 Playwood 9 mm Lbr 82,000.00
2 Formika Lbr -
3 Akustik ukuran 30×30 cm Lbr -
4 Akustik ukuran 30×60 cm Lbr -
5 Akustik arm strong ukuran 60×120 cm Lbr -

GYPSUM
1 Gypsum board M2 -
2 List Gypsum M' -
3 Kalsiboard M2 -

PENUTUP ATAP
1 Polycarbonat M2 -
2 Multiroof M2 -
3 Fiberglass M2 -
4 Roof light fibreglass Lbr -
5 Plastic aerator Bh -
6 Atap Aluminium Lbr
KACA
1 Kaca Bening 3 mm M2 -
2 Kaca Bening 5 mm M2 -
3 Kaca Bening 8 mm M2 -
4 Kaca Bening 10 mm M2 -
5 Kaca Bening 12 mm M2 -
6 Kaca Rayband 3 mm M2 -
7 Kaca Rayband 5 mm M2 -
8 Kaca Rayband 10 mm M2 -
9 Kaca Rayband 12 mm M2 -
10 Kaca Painting 5 mm M2 -
11 Kaca Sun glass 5 mm berwarna M2 -
12 Glass blok polos Bh -
13 Glass blok motif Bh -
14 Kaca Cermin tebal 5 mm M2 -
15 Kaca Cermin tebal 6 mm M2 -
16 Kaca Cermin tebal 8 mm M2 -
17 Kaca wireglass tebal 5 mm M2 -
18 Kaca Es T = 5 mm M2 -

ALAT PENGGANTUNG & KUNCI


1 Kunci Tanam Biasa Bh -
2 Kunci Tanam Antik Bh -

Harga Bahan Proyek ....... 04/13/2019 HAL : 29


HARGA BAHAN
NO NAMA BAHAN SAT
Rp.
3 Kunci Pintu khusus Bh -
4 Kunci Silinder Bh -
5 Kunci Selot Bh -
6 Grendel Tanam Pintu Bh -
7 Grendel Jendela Bh -
8 Engsel biasa pintu Stel -
9 Engsel biasa jendela Stel -
10 Hak Angin Biasa Bh -
11 Handle Alumunium Bh -
12 Door holder Bh -
13 Door closer Bh -
14 Door stop Bh -
15 Spring Knip Bh -

PINTU
1 Pintu Rolling door aluminium M2 -
2 Pintu Gulung Besi M2 -
3 Pintu Lipat M2 -
4 Pintu Sun Sreem Alumunium M2 -
5 Pintu Alumunium M2 -
6 Rel Pintu Dorong Bh -

ALUMINIUM KUSEN
1 Aluminium 4" Putih M' -
2 Aluminium 4" Coklat M' -
3 Aluminium 3" Putih M' -
4 Aluminium 3" Coklat M' -
5 Karet kaca M' -
6 Metal Furing M2 -

TEGEL & KERAMIK.


1 Ubin Granito 30 x 30 polished M2 -
2 Ubin Granito 40 x 40 polished M2 -
3 Ubin Granito 30 x 30 unpolished M2 -
4 Ubin Granito 40 x 40 unpolished M2 -
5 Ubin Teralux Kerang 30 x 30 cm Bh -
6 Ubin Teralux Kerang 40 x 40 cm Bh -
7 Ubin Teraso 30 x 30 cm Bh -
8 Ubin Tahan Asam M2 -
9 Keramik Dinding 20/20 - 20/25 Cm warna M2 -
10 Keramik Dinding 20/20 - 20/25 Cm motif M2 -
11 Keramik Dinding 10 x 20 cm Biasa M2 -
12 Keramik Dinding 10 x 20 cm Motif M2 -
13 Keramik Dinding 15 x 15 cm biasa M2 -
14 Keramik Lantai KM 20/20 Cm warna Bh -
15 Keramik 15 x15 cm Bh -
16 Keramik 25 x25 cm Bh -
17 Keramik 15 x 20 cm Bh -
18 Keramik 33 x 33 cm Bh -
19 Keramik 10 x 33 cm Bh -
20 Keramik 25 x25 cm warna polos Bh -
21 Keramik 30/30 Cm warna polos putih M2 -
22 Keramik 30/30 Cm warna / gelap M2 -
23 Keramik 30/30 Cm warna / motif M2 -
24 Keramik 40/40 Cm warna polos M2 -
25 Keramik 40/40 Cm warna / motif M2 -
26 Keramik mosaik 30 x 30 cm Bh -
27 List Keramik uk. 10 X 20 Cm Bh -
28 List Keramik uk. 10 X 20 Cm motif Bh -
29 List Keramik uk. 20 X 40 Cm Bh -
30 Keramik Kuku macan polos Bh -
31 Keramik Kuku macan motif / warna Bh -
32 Parquet jati M2 -
33 Plint Keramik M' -
34 Plint Keramik 10 x 20 cm biasa Bh -
35 Plint Keramik 15 x 20 cm biasa Bh -
36 Plint Keramik 10 x 30 cm biasa Bh -
37 Plint Keramik 10 x 40 cm biasa Bh -
38 Plint Keramik 10 x 60 cm biasa Bh -
39 Plint Keramik 10 x 10 cm motif Bh -
40 Plint Keramik 5 x 20 cm motif Bh -
41 Plint Keramik 10 x 20 cm motif Bh -
42 Plint Keramik 10 x 30 cm motif Bh -
43 Plint Keramik 10 x 40 cm motif Bh -
44 Plint Ubin Teraso 10 x 20 cm Bh -
45 Plint Ubin Teraso 10 x 30 cm Bh -

Harga Bahan Proyek ....... 04/13/2019 HAL : 30


HARGA BAHAN
NO NAMA BAHAN SAT
Rp.
46 Plint Ubin Teraso 10 x 40 cm Bh -
47 Tegel abu-abu Uk. 20 x 20 Cm Bh -
48 Tegel abu-abu Uk. 30 x 30 Cm Bh -
49 Tegel abu-abu Uk. 40 x 40 Cm Bh -
50 Tegel wafel Uk. 20 x 20 Cm Bh -
51 Tegel warna Uk. 20 x 20 Cm Bh -
52 Tegel warna Uk. 30 x 30 Cm Bh -
53 Tegel warna Uk. 40 x 40 Cm Bh -
54 Tegel wafel Uk. 20 x 20 Cm Bh -
51 Marmer ( Home Industri ) M2 -
52 Marmer ( Export ) M2 -
53 Marmer ( Import ) M2 -
54 Ubin teralux marmer 30 X 30cm Bh -
55 Ubin teralux marmer 40 X 40cm Bh -
56 Ubin teralux marmer 60 X 60cm Bh -
57 Porselen 11x11 cm Bh -
58 Porselen 15 x 15 cm Bh -
59 Porselen 10 x 20 cm warna Bh -
60 Porselen 11x11 cm warna Bh -
61 Porselen 15 x 15 cm warna Bh -
62 Porselen 20 x 20 cm warna Bh -
63 Vinyk Karet 30 x 30 cm KL I Bh -
64 Vinyk Karet 30 x 30 cm KL II Bh -
65 Vinyl Asbes Bh -
66 Vinyl Motif kembang 30 x 30 cm Bh -
67 Vinyl wall covering lebar 50 cm M2 -

CAT KAYU & CAT TEMBOK.


1 Cat Tembok dalam ruangan Gln -
2 Cat Tembok di luar ruangan Gln -
3 Cat Genteng Gln -
1 Cat Tembok Kg 12,500.00
2 Cat Besi Kg 28,700.00
3 Cat Kayu Kg -
4 Cat Bronze Kg -
5 Cat Thermoplastic ltr -
6 Kalkarium Kg -
7 Meni Kayu Kg -
3 Meni Besi/Flincote Kg 12,300.00
4 Minyak Cat Ltr -
5 Thinner Ltr -
4 Ter / Minyak Bekisting Ltr 2,600.00
5 Plamir Tembok Kg 10,250.00
6 Plamir Kayu Kg -
7 Dempul Kg -
8 Stempet Kg -
9 Glass bitt Kg -
10 Soda Api Kg -
11 Sabun Kg -
12 BBM Ltr -

LEM.
1 Lem Kayu Kg -
2 Lem PVC Kg -
3 Sealent Kg -
4 Lem vinyl Kg -

POLITURAN
1 Spirtus Ltr -
2 Serlak Ltr -
3 Plitur Ltr -
4 Plitur Jadi Ltr -
5 Vernis Jadi Ltr -
6 Kertas gosok air Lbr -
7 Kertas gosok biasa Lbr -
8 Oker Kg -

KUAS
1 Alang - Alang / Saput Ikat -
1 Kuas Bh 4,000.00

Harga Bahan Proyek ....... 04/13/2019 HAL : 31


HARGA BAHAN
NO NAMA BAHAN SAT
Rp.

ALUMUNIUM
1 Asbes gelombang 300 x 80 cm Lbr -
2 Asbes gelombang 300 x 1.05 cm Lbr -
3 Asbes gelombang 240 x 80 cm Lbr -
4 Asbes gelombang 180 x 80 cm Lbr -
5 Asbes gelombang 150 x 80 cm Lbr -
6 Bubung Asbes Gelombang Lbr -
7 Eternit Asbes Bh -
8 Atap Alumunium Gelombang t.0.55 M2 -
9 Nok Standart 40 cm 18 SWG 22 M2 -
1 Alumunium Foil M2 4,950.00
2 Screening Alumunium M2 600,000.00
2 Plat Asbes tb.6 mm Lbr -
3 Plat Asbes tb.5 mm Lbr -
4 Plat Asbes tb.4 mm Lbr -
5 Plat Asbes tb.3.5 mm Lbr -

SANITAIR
1 Kloset Monoblok Bh -
2 Kloset Duduk Bh -
3 Kloset Jongkok Bh -
4 Kran Air D 1/2" Bh -
5 Kran Air D 3/4" Bh -
6 Kran shower Bh -
7 Stop Kran Bh -
8 Pipa / Slang Spiral Saluran Kran Set -
9 Pipa Stainless M' -
10 Rol TBA / Seal Tape Bh -
11 Septictank Asbes Kotak ( 10 Pemakai ) 1000 1 Bh -
12 Septictank Asbes Kotak ( 5 Pemakai ) 500 1 Bh -
13 Sifon Wasser Set -
14 Sumur Peresapan Bh -
15 Watermur Bh -
16 Water Drain + Aksesoris Set -
17 Wastafel Bh -
18 Urinoir Bh -
19 Bak Fibreglass Bh -
20 Bak Teraso Bh -
21 Bak Cuci Teraso Bh -
22 Bak Dip Bh -
23 Floor Drain Bh -
24 Tempat Sabun Bh -
25 Kichen Zink 1 lubang Bh -
26 Hand Shower Bh -
27 Tempat Tissue Bh -
28 Tangki Air Fiberglass 1000 Ltr Unit -
29 Tangki Air Fiberglass 2000 Ltr Unit -
30 Tangki Air Fiberglass 3000 Ltr Unit -

AKSESORIS
1 Venetions Blinds M2 -
2 Vertikal Blinds M2 -
3 Wall paper M3 -

PIPA
1 Pipa Besi 4" biasa Lj -
2 Pipa Besi 3" biasa Lj -
3 Pipa Besi 2 1/2" biasa Lj -
4 Pipa Besi 2" biasa Lj -
5 Pipa Besi 1" biasa Lj -
6 Pipa Besi 3/4" biasa Lj -
7 Pipa Besi 1/2" biasa Lj -
8 Pipa Besi 4" ( Medium) Lj -
9 Pipa Besi 3" (Medium) Lj -
10 Pipa Besi 2 1/2" (Medium) Lj -
11 Pipa Besi 2" (Medium) Lj -
12 Pipa Besi 1" (Medium) Lj -
13 Pipa Besi 3/4" (Medium) Lj -
14 Pipa Besi 1/2" (Medium) Lj -
15 Pipa PVC AW 4" ( 4 M' ) Lj -
16 Pipa PVC AW 3" ( 4 M' ) Lj -
17 Pipa PVC AW 2 1/2" ( 4 M' ) Lj -
18 Pipa PVC AW 2" ( 4 M' ) Lj -
19 Pipa PVC AW 1 1/2" ( 4 M' ) Lj -

Harga Bahan Proyek ....... 04/13/2019 HAL : 32


HARGA BAHAN
NO NAMA BAHAN SAT
Rp.
20 Pipa PVC AW 1" ( 4 M' ) Lj -
21 Pipa PVC AW 3/4" ( 4 M' ) Lj -
22 Pipa PVC AW 1/2" ( 4 M' ) Lj -
1 Pipa PVC biasa D 4" ( 4 M' ) Lj 121,000.00
2 Pipa PVC biasa D 3" ( 4 M' ) Lj -
3 Pipa PVC biasa D 2 1/2" ( 4 M' ) Lj -
4 Pipa PVC biasa D 2" ( 4 M' ) Lj -
5 Pipa PVC biasa D 1" ( 4 M' ) Lj -
6 Pipa PVC biasa D 3/4" ( 4 M' ) Lj -
7 Pipa PVC biasa D 1/2" ( 4 M' ) Lj -
8 Pipa Air Krum ( 3/4" ) Lj -
9 Pipa Tanah Bh -
10 Pipa Beton Bh -
11 Pipa Galvanis M' -
12 Talang PVC U ( 4 M' ) Lj -
13 Tahanan Talang PVC Lj -
14 Tutup PVC D 4" Bh -
15 Tutup PVC D 3" Bh -
16 Tutup PVC D 2 1/2" Bh -
17 Tutup PVC D 2" Bh -
18 Tutup PVC D 1" Bh -
19 Tutup PVC D 3/4" Bh -
20 Tutup PVC D 1/2" Bh -
21 Corong PVC Bh -
22 Sok PVC 4" Bh -
23 Sok PVC 3" Bh -
24 Sok PVC 2 1/2" Bh -
25 Sok PVC 2" Bh -
26 Sok PVC 1" Bh -
27 Sok PVC 3/4" Bh -
28 Sok PVC 1/2" Bh -
29 Keni PVC 4" Bh -
30 Keni PVC 3" Bh -
31 Keni PVC 2 1/2" Bh -
32 Keni PVC 2" Bh -
33 Keni PVC 1" Bh -
34 Keni PVC 3/4" Bh -
35 Keni PVC 1/2" Bh -
36 Water Stop 150 mm M' -
37 Water Stop 200 mm M' -
38 Water Stop 230 mm M' -
39 Water Stop 250 mm M' -
40 Water Stop 300 mm M' -
41 Water Stop 320 mm M' -

PAVING STONE
1 Pavingstone warna abu-abu 8 Cm (K 125) M2 -
2 Pavingstone warna abu-abu 6 Cm (K 125) M2 -
3 Pavingstone warna abu-abu 8 Cm (K 225) M2 -
4 Pavingstone warna abu-abu 6 Cm (K 225) M2 -
5 Pavingstone warna abu-abu 8 Cm (K 400) M2 -
6 Pavingstone warna abu-abu 8 Cm (K 300) M2 -
7 Pavingstone warna abu-abu 6 Cm (K 300) M2 -
8 Pavingstone warna 8 Cm (K 125) M2 -
9 Pavingstone warna 6 Cm (K 125) M2 -
10 Pavingstone warna 8 Cm (K 225) M2 -
11 Pavingstone warna 6 Cm (K 225) M2 -
12 Pavingstone warna 8 Cm (K 400) M2 -
13 Pavingstone warna 8 Cm (K 300) M2 -
14 Pavingstone warna 6 Cm (K 300) M2 -
15 Kansteen besar M' -
16 Kansteen kecil M' -

ASPAL
1 Aspal Bitumen Kg -
2 Aspal Curah Kg -
3 Aspal Beton Ton -
4 Kerosina Ltr -
5 Solar Ltr -
6 Bensin Ltr -
7 Olie (minyak pelumas) Ltr -
8 Minyak Bekisting Ltr -

TANAMAN
1 Cemara Bh -
2 Beringin Bh -

Harga Bahan Proyek ....... 04/13/2019 HAL : 33


HARGA BAHAN
NO NAMA BAHAN SAT
Rp.
3 Palm Bh -
4 Pohon Peneduh Bh -
5 Bambu Bh -
6 Rumput taman M2 -
7 Rumput Tabal M2 -
8 Gebalan rumput M2 -

LAIN - LAIN.
1 Gedek M2 -
2 Bambu Ljr -
3 Tali Ijuk Kg -
4 Ijuk M3 -
5 Panel Beton pracetak M' -
6 Kolom Beton pracetak M' -
7 Holoowblok ( HB 10 ) Bh -
8 Holoowblok ( HB 15 ) Bh -
9 Holoowblok ( HB 20 ) Bh -
10 Concrete blok Bh -
11 Bondeam Bh -
12 Pintu Besi Baja M2 -
13 Jendela Besi M2 -
14 Jendela Besi Tahan Api M2 -
15 Bahan Teralux Cor M2 -
16 Carpet M2 -
17 Carpet 100 % wool M2 -
18 Carpet 80 % wool, 20 % nylon M2 -
19 Gymfloor M2 -

Bubung stel gelombang ( 0.92 m ) Lbr


Nok Paten M2
Nok Stel rata Lbr
Soft Board 4' x 8' x 4 mm M3
Kloset Jongkok Porselen Bh
Kloset Jongkok Teraso Bh
Kayu ramin Lbr
Beton 1:1 1/2 : 2 1/2 M3
Ubin Porselen M2
Batu Kerikil M3
Pipa Galvanis 1/2" M'
Pipa Galvanis 3/4" M'
Pipa Galvanis 1" M'
Pipa Galvanis 2" M'
Pipa Galvanis 3" M'
Pipa Galvanis 4" M'

Bak Cuci Stenless Steel Bh


Internal cove 5 x 5 x 20 Bh
Floor Hardener Kg
Mastercron "S" Kg
Teak Oil Ltr

Harga Bahan Proyek ....... 04/13/2019 HAL : 34


HARGA SATUAN UPAH SIPIL
NAMA PROYEK : Pembangunan Rumah Persemayanan
PEKERJAAN : ……………………………………………………………
TAHUN ANGGARAN : 2006

NO. NAMA PERSONIL SAT UPAH / HARI

1 Mandor Lapangan Oh Rp. 60,000.00


2 Kepala Tukang Oh Rp. 50,000.00
3 Tukang Batu Oh Rp. 40,000.00
4 Tukang Kayu Oh Rp. 40,000.00
5 Tukang Besi Oh Rp. 35,000.00
6 Tukang Gali Oh Rp. 30,000.00
7 Tukang Listrik Oh Rp. 40,000.00
8 Tukang Cat Oh Rp. 35,000.00
9 Tukang Las Oh Rp. 35,000.00
10 Sopir Material / Truck Oh Rp. 35,000.00
11 Pembantu Sopir / Kernet Oh Rp. 25,000.00
12 Pekerja Oh Rp. 25,000.00
SEWA PERALATAN
1 Sewa Alat Bantu Strouss Pile Jam Rp. 10,000.00

Harga Satuan Upah Proyek .......................04/13/2019 Hal : 35


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

A ANALISA BIAYA KONSTRUKSI PEK. PERSIAPAN

A.1 1 M' Pagar sementara dari kayu tinggi 2 meter


A.1.1 Bahan
Dolken kayu Ø 8-10, 400 cm 1.250 Btg 8,750.00 10,937.50
Semen Portland 2.500 Kg 820.00 2,050.00
Pasir beton 0.005 M3 92,200.00 461.00
Koral beton 0.009 M3 122,950.00 1,106.55
Kayu meranti 5/7 cm 0.072 M3 1,434,200.00 103,262.40
Paku 2" - 5" 0.060 Kg 10,250.00 615.00
Residu 0.400 Ltr 2,600.00 1,040.00
Jumlah 119,472.45
A.1.2 Tenaga
Tukang kayu 0.200 Oh 40,000.00 8,000.00
Pekerja 0.400 Oh 25,000.00 10,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.020 Oh 60,000.00 1,200.00
Jumlah 20,200.00
Total 139,672.45

A.2 1 M' Pagar sementara dari seng gelombang tinggi 2 meter


A.2.1 Bahan
Dolken kayu D 8-10 / 400 cm 1.250 Btg 8,750.00 10,937.50
Semen Portland 2.500 Kg 820.00 2,050.00
Seng gelombang 3 " - 5 " 1.200 Lbr - -
Pasir beton 0.005 M3 92,200.00 461.00
Koral beton 0.009 M3 122,950.00 1,106.55
Kayu meranti 5/7 cm 0.072 M3 1,434,200.00 103,262.40
Paku 2"- 5" 0.060 Kg 10,250.00 615.00
Meni besi 0.450 Kg 12,300.00 5,535.00
Jumlah 123,967.45
A.2.2 Tenaga
Tukang kayu 0.200 Oh 40,000.00 8,000.00
Pekerja 0.400 Oh 25,000.00 10,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.020 Oh 60,000.00 1,200.00
Jumlah 20,200.00
Total 144,167.45

A.3 1 M' Pagar sementara dari kawat duri tinggi 1,80 meter
A.3.1 Bahan
Dolken kayu D 8-10 / 400 cm 1.000 Btg 8,750.00 8,750.00
Semen Portland 2.000 Kg 820.00 1,640.00
Kawat duri 25.000 Kg - -
Pasir beton 0.005 M3 92,200.00 461.00
Koral beton 0.009 M3 122,950.00 1,106.55
Paku 2"- 5" 0.060 Kg 10,250.00 615.00
Jumlah 12,572.55
A.3.2 Tenaga
Tukang kayu 0.200 Oh 40,000.00 8,000.00
Pekerja 0.300 Oh 25,000.00 7,500.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.020 Oh 60,000.00 1,200.00
Jumlah 17,700.00
Total 30,272.55

A.4 1 M' Pengukuran dan pemasangan bouwplank


A.4.1 Bahan
Kayu meranti 5/7 cm 0.012 M3 1,434,200.00 17,210.40
Paku biasa 2" - 5" 0.020 Kg 10,250.00 205.00
Kayu papan meranti 3/20 cm 0.007 M3 1,690,300.00 11,832.10
Jumlah 29,247.50
A.4.2 Tenaga
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Pekerja 0.100 Oh 25,000.00 2,500.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 7,300.00
Total 36,547.50

A.5 1 M2 Pembuatan kantor sementara , dg lantai plesteran


A.5.1 Bahan
Dolken kayu D 8 - 10/400 cm 1.250 Btg 8,750.00 10,937.50
Kayu meranti 0.180 M3 1,895,150.00 341,127.00
Kayu biasa 0.850 Kg 10,250.00 8,712.50
Besi strip 1.100 Kg - -
Semen Portland 35.000 Kg 820.00 28,700.00
Pasir pasang 0.150 M3 79,400.00 11,910.00
Pasir beton 0.100 M3 92,200.00 9,220.00
Koral beton 0.150 M3 122,950.00 18,442.50
Batu merah 30.000 Bh 300.00 9,000.00
Seng plat 0.250 Lbr - -
Jendela naco 2.000 Bh - -
Kaca polos 0.080 M2 - -
Kunci tanam 0.150 Bh - -
Plywood 4 mm 0.060 Lbr - -
Jumlah 438,049.50
A.5.2 Tenaga
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Tukang batu 1.000 Oh 40,000.00 40,000.00
Pekerja 2.000 Oh 25,000.00 50,000.00
Kepala Tukang 0.300 Oh 50,000.00 15,000.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 188,000.00
Total 626,049.50

A.6 1 M2 Pembuatan gudang semen dan alat-alat


A.6.1 Bahan

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 36


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Dolken kayu D 8-10 / 400 cm 1.700 Btg 8,750.00 14,875.00


Kayu meranti 0.210 M3 1,895,150.00 397,981.50
Paku biasa 0.300 Kg 10,250.00 3,075.00
Semen Portland 10.500 Kg 820.00 8,610.00
Pasir beton 0.030 M3 92,200.00 2,766.00
Koral beton 0.050 M3 122,950.00 6,147.50
Seng gelombang BJLS 30 1.500 Lbr - -
Jumlah 433,455.00
A.6.2 Tenaga
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Pekerja 1.000 Oh 25,000.00 25,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 118,000.00
Total 551,455.00

A.7 1 M2 Pembuatan rumah jaga / konstruksi kayu


A.7.1 Bahan
Dolken kayu D 8-10 / 400 cm 3.000 Btg 8,750.00 26,250.00
Kayu meranti 0.276 M3 1,895,150.00 523,061.40
Paku biasa 0.700 Kg 10,250.00 7,175.00
Seng gelombang BJLS 32 1.500 Lbr - -
Jumlah 556,486.40
A.7.2 Tenaga
Tukang kayu 1.500 Oh 40,000.00 60,000.00
Pekerja 1.000 Oh 25,000.00 25,000.00
Kepala Tukang 0.150 Oh 50,000.00 7,500.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 95,500.00
Total 651,986.40

A.8 1 M2 Membersihkan lapangan dan perataan


A.8.1 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 5,500.00
Total 5,500.00

A.9 1 M2 Pembuatan bedeng buruh


A.9.1 Bahan
Dolken kayu D 8-10 / 400 cm 1.250 Btg 8,750.00 10,937.50
Kayu meranti 0.186 M3 1,895,150.00 352,497.90
Paku biasa 0.300 Kg 10,250.00 3,075.00
Semen Portland 18.000 Kg 820.00 14,760.00
Pasir beton 0.030 M3 92,200.00 2,766.00
Koral beton 0.050 M3 122,950.00 6,147.50
Seng gelombang BJLS 30 1.500 Lbr - -
Plywood 4 mm 1.350 Lbr - -
Jumlah 390,183.90
A.9.2 Tenaga
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Pekerja 1.000 Oh 25,000.00 25,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 118,000.00
Total 508,183.90

A.10 1 M2 Pembuatan bak adukan ukuran 40 x 50 x 20 cm


A.10.1 Bahan
Kayu terentang 0.036 M3 717,100.00 25,815.60
Paku biasa 0.080 Kg 10,250.00 820.00
Kaso meranti 5/7 cm 1.000 M3 1,434,200.00 1,434,200.00
Jumlah 1,460,835.60
A.10.2 Tenaga
Tukang kayu 0.300 Oh 40,000.00 12,000.00
Mandor 0.002 Oh 60,000.00 90.00
Jumlah 12,090.00
Total 1,472,925.60

A.11 1 M2 Pembuatan Stegger dari bambu uk. 40 x 50 x 20 cm


A.11.1 Bahan
Bambu Ø 6 - 8 / 600 cm 1.000 Btg - -
Tali ijuk 0.250 Kg - -
Jumlah -
A.11.2 Tenaga
Tukang kayu 0.017 Oh 40,000.00 680.00
Kepala Tukang 0.002 Oh 50,000.00 100.00
Pekerja 0.250 Oh 25,000.00 6,250.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 7,810.00
Total 7,810.00

A.12 1 M2 Pembuatan jalan sementara


A.12.1 Bahan
Batu belah 15 / 20 0.150 M3 112,700.00 16,905.00
Batu pecah 5/7 0.090 M3 112,700.00 10,143.00
Pasir pasang 0.010 M3 79,400.00 794.00
Jumlah 27,842.00
A.12.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 28,000.00
Total 55,842.00

A.13 1 M3 Bongkaran beton bertulang


A.13.1 Tenaga
Pekerja 6.667 Oh 25,000.00 166,675.00
Mandor 0.333 Oh 60,000.00 19,980.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 37


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Jumlah 186,655.00
Total 186,655.00

A.14 1 M3 Bongkaran dinding tembok bata merah


A.14.1 Tenaga
Pekerja 6.667 Oh 25,000.00 166,675.00
Mandor 0.033 Oh 60,000.00 1,980.00
Jumlah 168,655.00
Total 168,655.00

A.15 1 M' Pasang pagar kawat jaring galvanis, tinggi 1 m


A.15.1 Bahan
Pagar kawat jaring 0.434 Lbr - -
Jumlah -
A.15.2 Tenaga
Tukang 0.042 Oh 35,000.00 1,470.00
Pekerja 0.042 Oh 25,000.00 1,050.00
Kepala Tukang 0.004 Oh 50,000.00 200.00
Mandor 0.002 Oh 60,000.00 120.00
Jumlah 2,840.00
Total 2,840.00

A.16 1 M' Pasang pagar beton pracetak ( 5 x 50 x 213 ) cm


A.16.1 Bahan
Panel beton pracetak 0.986 Lbr - -
Kolom beton pracetak 0.525 Btg - -
Pasir beton 0.074 M3 92,200.00 6,822.80
Koral 2 / 3 0.146 M3 122,950.00 17,950.70
Semen Portland 45.000 Kg 820.00 36,900.00
Jumlah 61,673.50
A.16.2 Tenaga
Tukang batu 0.125 Oh 40,000.00 5,000.00
Pekerja 0.375 Oh 25,000.00 9,375.00
Kepala Tukang 0.012 Oh 50,000.00 600.00
Mandor 0.019 Oh 60,000.00 1,140.00
Jumlah 16,115.00
Total 77,788.50

A.17 1 M2 Bongkaran Atap Zincalum


A.17.1 Tenaga
Pekerja 0.380 Oh 25,000.00 9,500.00
Mandor 0.060 Oh 60,000.00 3,600.00
Jumlah 13,100.00
Total 13,100.00

A.18 1 M2 Bongkaran Screning Alumunium


A.18.1 Tenaga
Pekerja 0.500 Oh 25,000.00 12,500.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 15,500.00
Total 15,500.00

B ANALISA BIAYA KONSTRUKSI PEKERJAAN TANAH

B.1 1 M3 Galian tanah biasa sedalam 1 meter


B.1.1 Tenaga
Pekerja 0.400 Oh 25,000.00 10,000.00 113750
Tukang gali 0.000 Oh 30,000.00 - 140000
Kepala Tukang 0.000 Oh 50,000.00 - 157500
Mandor 0.040 Oh 60,000.00 2,400.00 175000
Jumlah 12,400.00
Total 12,400.00

B.2 1 M3 Galian tanah biasa sedalam 2 meter


B.2.1 Tenaga
Pekerja 0.526 Oh 25,000.00 13,150.00
Tukang gali 0.000 Oh 30,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.052 Oh 60,000.00 3,120.00
Jumlah 16,270.00
Total 16,270.00

B.3 1 M3 Galian tanah biasa sedalam 3 meter


B.3.1 Tenaga
Pekerja 0.735 Oh 25,000.00 18,375.00
Tukang gali 0.000 Oh 30,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.073 Oh 60,000.00 4,380.00
Jumlah 22,755.00
Total 22,755.00

B.4 1 M3 Galian tanah biasa sedalam 1.5 meter


B.4.1 Tenaga
Pekerja 0.938 Oh 25,000.00 23,437.50
Tukang gali 0.000 Oh 30,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.093 Oh 60,000.00 5,580.00
Jumlah 29,017.50
Total 29,017.50

B.5 1 M3 Galian tanah keras sedalam 1 meter


B.5.1 Tenaga
Pekerja 0.625 Oh 25,000.00 15,625.00
Tukang gali 0.000 Oh 50,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.062 Oh 60,000.00 3,720.00
Jumlah 19,345.00
Total 19,345.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 38


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

B.6 1 M3 galian tanah cadas sedalam 1 meter


B.6.1 Tenaga
Pekerja 1.250 Oh 25,000.00 31,250.00
Tukang gali 0.000 Oh 50,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.125 Oh 60,000.00 7,500.00
Jumlah 38,750.00
Total 38,750.00

B.7 1 M3 Galian tanah lumpur sedalam 1 meter


B.7.1 Tenaga
Pekerja 0.823 Oh 25,000.00 20,575.00
Tukang gali 0.000 Oh 50,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.083 Oh 60,000.00 4,980.00
Jumlah 25,555.00
Total 25,555.00

B.8 1 M2 Pekerjaan stripping setinggi 1 meter


B.8.1 Tenaga
Pekerja 0.050 Oh 25,000.00 1,250.00
Tukang gali 0.000 Oh 50,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 1,550.00
Total 1,550.00

B.9 1 M3 Pembuangan tanah sejauh 150 meter


B.9.1 Tenaga
Pekerja 0.516 Oh 25,000.00 12,900.00
Tukang gali 0.000 Oh 50,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 15,900.00
Total 15,900.00

B.10 1 Ttk Bor Strouss 2 m


B.10.1 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang gali 0.000 Oh 30,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.050 Oh 60,000.00 3,000.00
Sewa alat bantu 1.000 jam 10,000.00 10,000.00
Jumlah 38,000.00
Total 38,000.00
B.11 1 M3 Urugan kembali
B.11.1 Tenaga
Pekerja 0.192 Oh 25,000.00 4,800.00 113750
Tukang gali 0.000 Oh 50,000.00 - 140000
Kepala Tukang 0.000 Oh 50,000.00 - 157500
Mandor 0.019 Oh 60,000.00 1,140.00 175000
Jumlah 5,940.00
Total 5,940.00
B.12 1 M3 Pemadatan tanah
B.12.1 Tenaga
Pekerja 0.500 Oh 25,000.00 12,500.00 113750
Tukang gali 0.000 Oh 50,000.00 - 140000
Kepala Tukang 0.000 Oh 50,000.00 - 157500
Mandor 0.050 Oh 60,000.00 3,000.00 175000
Jumlah 15,500.00
Total 15,500.00

B.13 1 M3 Urugan pasir


B.13.1 Bahan
Pasir urug 1.200 M3 66,600.00 79,920.00 90200
Jumlah 79,920.00
B.13.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00 113750
Tukang gali 0.000 Oh 30,000.00 - 140000
Kepala Tukang 0.000 Oh 50,000.00 - 157500
Mandor 0.010 Oh 60,000.00 600.00 175000
Jumlah 8,100.00
Total 88,020.00

B.14 1 M3 Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL


B.14.1 Bahan
Pasir urug 0.330 M3 66,600.00 21,978.00
Kapur padam 0.109 M3 - -
Tanah liat 0.763 M3 46,100.00 35,174.30
Jumlah 57,152.30
B.14.2 Tenaga
Pekerja 0.833 Oh 25,000.00 20,825.00
Tukang batu 0.416 Oh 40,000.00 16,640.00
Kepala Tukang 0.040 Oh 50,000.00 2,000.00
Mandor 0.083 Oh 60,000.00 4,980.00
Jumlah 44,445.00
Total 101,597.30

B.15 1 M3 Lapisan pudel campuran 1 Kp : 5 TL


B.15.1 Bahan
Kapur padam 0.200 M3 - -
Tanah liat 1.000 M3 46,100.00 46,100.00
Jumlah 46,100.00
B.15.2 Tenaga
Pekerja 0.833 Oh 25,000.00 20,825.00
Tukang batu 0.416 Oh 40,000.00 16,640.00
Kepala Tukang 0.041 Oh 50,000.00 2,050.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 39


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Mandor 0.081 Oh 60,000.00 4,860.00


Jumlah 44,375.00
Total 90,475.00

B.16 1 M3 Pemasangan lapisan ijuk


B.16.1 Bahan
Ijuk 1.200 M3 - -
Jumlah -
B.16.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang gali 0.000 Oh 30,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 4,650.00
Total 4,650.00

B.17 1 M3 Urugan sirtu


B.17.1 Bahan
Sirtu 1.200 M3 61,500.00 73,800.00 130000
Jumlah 73,800.00
B.17.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00 113750
Tukang gali 0.000 Oh 30,000.00 - 140000
Kepala Tukang 0.000 Oh 50,000.00 - 157500
Mandor 0.025 Oh 60,000.00 1,500.00 175000
Jumlah 7,750.00
Total 81,550.00

B.18 1 M2 Pembuatan jalan sementara tebal 25 cm


B.18.1 Bahan
Batu belah 0.275 M3 112,700.00 30,992.50
Kerikil 0.030 M3 112,700.00 3,381.00
Pasir 0.050 M3 79,400.00 3,970.00
Jumlah 38,343.50
B.18.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang gali 0.000 Oh 30,000.00 -
Kepala Tukang 0.000 Oh 50,000.00 -
Mandor 0.100 Oh 60,000.00 6,000.00
Jumlah 31,000.00
Total 69,343.50

C ANALISA BIAYA KONSTRUKSI PEKERJAAN PONDASI

C.1 1 M3 Pasang pondasi batu kali,1 PC : 1 Ps


C.1.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 392.000 Kg 820.00 321,440.00
Pasir pasang 0.314 M3 79,400.00 24,931.60
Jumlah 470,341.60
C.1.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 539,341.60

C.2 1 M3 Pasang pondasi batu kali,1 PC : 2 Ps


C.2.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 267.000 Kg 820.00 218,940.00
Pasir pasang 0.427 M3 - -
Jumlah 342,910.00
C.2.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 411,910.00

C.3 1 M3 Pasang pondasi batu kali,1 PC : 2,5 Ps


C.3.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 392.000 Kg 820.00 321,440.00
Pasir pasang 0.314 M3 79,400.00 24,931.60
Jumlah 470,341.60
C.3.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 539,341.60

C.4 1 M3 Pasang pondasi batu kali,1 PC : 3 Ps


C.4.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 202.000 Kg 820.00 165,640.00
Pasir pasang 0.485 M3 79,400.00 38,509.00
Jumlah 328,119.00
C.4.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 40


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Total 397,119.00

C.5 1 M3 Pasang pondasi batu kali,1 PC : 4 Ps


C.5.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00 100,000
Semen Portland 163.000 Kg 820.00 133,660.00 1,700
Pasir pasang 0.520 M3 79,400.00 41,288.00 75,000
Jumlah 298,918.00
C.5.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00 113750
Tukang batu 0.600 Oh 40,000.00 24,000.00 140000
Kepala Tukang 0.060 Oh 50,000.00 3,000.00 157500
Mandor 0.075 Oh 60,000.00 4,500.00 175000
Jumlah 69,000.00
Total 367,918.00

C.6 1 M3 Pasang pondasi batu kali,1 PC : 5 Ps


C.6.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 136.000 Kg 820.00 111,520.00
Pasir pasang 0.544 M3 79,400.00 43,193.60
Jumlah 278,683.60
C.6.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 347,683.60

C.7 1 M3 Pasang pondasi batu kali,1 PC : 6 Ps


C.7.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 117.000 Kg 820.00 95,940.00
Pasir pasang 0.561 M3 79,400.00 44,543.40
Jumlah 264,453.40
C.7.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 333,453.40

C.8 1 M3 Pasang pondasi batu kali,1 PC : 8 Ps


C.8.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 91.000 Kg 820.00 74,620.00
Pasir pasang 0.561 M3 79,400.00 44,543.40
Jumlah 243,133.40
C.8.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 312,133.40

C.9 1 M3 Pasang pondasi batu kali,1Kp : 1 Sm, : 1 Ps


C.9.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Kapur pasang 0.229 Kg - -
Semen merah 0.229 M3 8,750.00 2,003.75
Pasir pasang 0.544 M3 79,400.00 43,193.60
Jumlah 169,167.35
C.9.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 238,167.35

C.10 1 M3 Pasang pondasi batu kali,1Kp : 1 Sm, : 2 Ps


C.10.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Kapur pasang 0.170 M3 - -
Semen merah 0.170 M3 8,750.00 1,487.50
Pasir pasang 0.340 M3 79,400.00 26,996.00
Jumlah 152,453.50
C.10.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 221,453.50

C.11 1 M3 Pasang pondasi batu kali,1 PC : 1/4 Kp : 4 Ps


C.11.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 156.000 Kg 820.00 127,920.00
Kapur pasang 0.032 M3 - -
Pasir pasang 0.584 M3 79,400.00 46,369.60
Jumlah 298,259.60
C.11.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 41


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Kepala Tukang 0.060 Oh 50,000.00 3,000.00


Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 367,259.60

C.12 1 M3 Pasang pondasi batu kali,1 PC : 3 Kp : 10 Ps


C.12.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 61.000 Kg 820.00 50,020.00
Kapur pasang 0.147 M3 - -
Pasir pasang 0.492 M3 79,400.00 39,064.80
Jumlah 213,054.80
C.12.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 282,054.80

C.13 1 M3 Pasang pondasi batu kali,1/4 PC : 1 Kp : 4 Ps


C.13.1 Bahan
Batu belah 15/ 20 cm 1.100 M3 112,700.00 123,970.00
Semen Portland 41.000 Kg 820.00 33,620.00
Kapur pasang 0.131 M3 - -
Pasir pasang 0.523 M3 79,400.00 41,526.20
Jumlah 199,116.20
C.13.2 Tenaga
Pekerja 1.500 Oh 25,000.00 37,500.00
Tukang batu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 69,000.00
Total 268,116.20

C.14 1 M3 Pasang pondasi batu kosong


C.14.1 Bahan
Batu belah 15 / 20 cm 1.200 M3 112,700.00 135,240.00
Pasir urug 0.300 M3 66,600.00 19,980.00
Jumlah 155,220.00
C.14.2 Tenaga
Pekerja 0.780 Oh 25,000.00 19,500.00
Tukang batu 0.390 Oh 40,000.00 15,600.00
Kepala Tukang 0.039 Oh 50,000.00 1,950.00
Mandor 0.039 Oh 60,000.00 2,340.00
Jumlah 39,390.00
Total 194,610.00

C.15 1 M3 Pasang pondasi siklop , 40 % batu kali


C.15.1 Bahan
Besi beton 75.000 Kg 5,000.00 375,000.00
Semen Portland 202.000 Kg 820.00 165,640.00
Pasir beton 0.320 M3 92,200.00 29,504.00
Koral beton 0.490 M3 112,700.00 55,223.00
Kawat beton 0.800 Kg 9,250.00 7,400.00
Jumlah 632,767.00
C.15.2 Tenaga
Pekerja 3.000 Oh 25,000.00 75,000.00
Tukang batu 0.850 Oh 40,000.00 34,000.00
Kepala Tukang 0.085 Oh 50,000.00 4,250.00
Mandor 0.150 Oh 60,000.00 9,000.00
Jumlah 122,250.00
Total 755,017.00

C.16 1 M3 Pasang pondasi sumuran , diameter 100 cm


C.16.1 Bahan
Batu belah 15 / 20 cm 0.450 M3 112,700.00 50,715.00
Semen Portland 280.000 Kg 820.00 229,600.00
Pasir beton 0.450 M3 92,200.00 41,490.00
Koral beton 0.670 M3 122,950.00 82,376.50
Jumlah 404,181.50
C.16.2 Tenaga
Pekerja 2.380 Oh 25,000.00 59,500.00
Tukang batu 0.300 Oh 40,000.00 12,000.00
Kepala Tukang 0.030 Oh 50,000.00 1,500.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 77,800.00
Total 481,981.50

C.17 1 M' Pembuatan tiang pancang (40 X40 ) Cm, beton bertulang
C.17.1 Bahan
Pasir urug darat 0.019 M3 66,600.00 1,265.40
Pasir beton 0.094 M3 92,200.00 8,666.80
Koral beton 0.150 M3 122,950.00 18,442.50
Semen portland 60.500 Kg 820.00 49,610.00
Besi beton 45.000 Kg 5,000.00 225,000.00
Kawat beton 0.900 Kg 9,250.00 8,325.00
Kayu kaso 5/7 0.032 M3 1,434,200.00 45,894.40
Paku 0.120 Kg 10,250.00 1,230.00
Minyak bekisting 0.090 Lt 2,600.00 234.00
Plamir tembok 0.240 Kg 10,250.00 2,460.00
Jumlah 361,128.10
C.17.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang batu 0.670 Oh 40,000.00 26,800.00
Kepala Tukang 0.067 Oh 50,000.00 3,350.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 58,150.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 42


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Total 419,278.10

C.18 1 M' Pembuatan tiang pancang ( 35 x 35 ) cm, beton bertulang


C.18.1 Bahan
Pasir urug darat 0.016 M3 66,600.00 1,065.60
Pasir beton 0.080 M3 92,200.00 7,376.00
Koral beton 0.125 M3 122,950.00 15,368.75
Semen portland 49.000 Kg 820.00 40,180.00
Besi beton 34.500 Kg 5,000.00 172,500.00
Kawat beton 0.700 Kg 9,250.00 6,475.00
Kayu kaso 5/7 0.027 M3 1,434,200.00 38,723.40
Paku 0.120 Kg 10,250.00 1,230.00
Minyak bekisting 0.090 Lt 2,600.00 234.00
Plamuur tembok 0.200 Kg 10,250.00 2,050.00
Jumlah 285,202.75
C.18.2 Tenaga
Pekerja 0.800 Oh 25,000.00 20,000.00
Tukang batu 0.500 Oh 40,000.00 20,000.00
Kepala Tukang 0.050 Oh 50,000.00 2,500.00
Mandor 0.040 Oh 60,000.00 2,400.00
Jumlah 44,900.00
Total 330,102.75

D ANALISA BIAYA KONSTRUKSI PEKERJAAN DINDING

D.1 1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 1 Ps


D.1.1 Bahan
Batu merah 5 x 11 x 22 cm 140.000 Bh 300.00 42,000.00
Semen Portland 64.030 Kg 820.00 52,504.60
Pasir pasang 0.059 M3 79,400.00 4,684.60
Jumlah 99,189.20
D.1.2 Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 27,050.00
Total 126,239.20

D.2 1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 2 Ps


D.2.1 Bahan
Batu merah 5 x 11 x 22 cm 140.000 Bh 300.00 42,000.00
Semen Portland 43.500 Kg 820.00 35,670.00
Pasir pasang 0.080 M3 79,400.00 6,352.00
Jumlah 84,022.00
D.2.2 Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 27,050.00
Total 111,072.00

D.3 1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 3 Ps


D.3.1 Bahan
Batu merah 5 x 11 x 22 cm 140.000 Bh 300.00 42,000.00
Semen Portland 32.950 Kg 820.00 27,019.00
Pasir pasang 0.091 M3 79,400.00 7,225.40
Jumlah 76,244.40
D.3.2 Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 27,050.00
Total 103,294.40

D.4 1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 4 Ps


D.4.1 Bahan
Batu merah 5 x 11 x 22 cm 140.000 Bh 300.00 42,000.00
Semen Portland 26.550 Kg 820.00 21,771.00
Pasir pasang 0.093 M3 79,400.00 7,384.20
Jumlah 71,155.20
D.4.2 Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 27,050.00
Total 98,205.20

D.5 1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 5 Ps


D.5.1 Bahan
Batu merah 5 x 11 x 22 cm 140.000 Bh 300.00 42,000.00
Semen Portland 22.200 Kg 820.00 18,204.00
Pasir pasang 0.102 M3 79,400.00 8,098.80
Jumlah 68,302.80
D.5.2 Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 27,050.00
Total 95,352.80

D.6 1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 6 Ps


D.6.1 Bahan
Batu merah 5 x 11 x 22 cm 140.000 Bh 300.00 42,000.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 43


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Semen Portland 22.200 Kg 820.00 18,204.00


Pasir pasang 0.102 M3 79,400.00 8,098.80
Jumlah 68,302.80
D.6.2 Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 27,050.00
Total 95,352.80

D.7 1 M2 Pasangan bata merah tebal 1 bata, 1 PC : 3 Kp : 10 Ps


D.7.1 Bahan
Batu merah 5 x 11 x 22 cm 140.000 Bh 300.00 42,000.00
Semen Portland 10.080 Kg 820.00 8,265.60
Pasir pasang 0.093 M3 79,400.00 7,344.50
Kapur Pasang 0.028 M3 - -
Jumlah 57,610.10
Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 27,050.00
Total 84,660.10

D.8 1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 1 Ps


D.8.1 Bahan
Batu merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00
Semen Portland 27.800 Kg 820.00 22,796.00
Pasir pasang 0.028 M3 79,400.00 2,223.20
Jumlah 46,019.20
D.8.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 59,419.20

D.9 1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 2 Ps


D.9.1 Bahan
Batu merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00
Semen Portland 18.950 Kg 820.00 15,539.00
Pasir pasang 0.038 M3 79,400.00 3,017.20
Jumlah 39,556.20
D.9.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 52,956.20

D.10 1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 3 Ps


D.10.1 Bahan
Batu merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00
Semen Portland 14.370 Kg 820.00 11,783.40
Pasir pasang 0.040 M3 79,400.00 3,176.00
Jumlah 35,959.40
D.10.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 49,359.40

D.11 1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 4 Ps


D.11.1 Bahan
Batu merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00
Semen Portland 11.500 Kg 820.00 9,430.00
Pasir pasang 0.043 M3 79,400.00 3,414.20
Jumlah 33,844.20
D.11.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 47,244.20

D.12 1 M2 Pasangan batu merah tebal 1/2 bata , 1 PC : 5 Ps


D.12.1 Bahan
Batu merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00
Semen Portland 9.680 Kg 820.00 7,937.60
Pasir pasang 0.045 M3 79,400.00 3,573.00
Jumlah 32,510.60
D.12.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 45,910.60

D.13 1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 6 Ps


D.13.1 Bahan

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 44


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Batu merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00


Semen Portland 8.320 Kg 820.00 6,822.40
Pasir pasang 0.049 M3 79,400.00 3,890.60
Jumlah 31,713.00
D.13.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 45,113.00

D.14 1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 8 Ps


D.14.1 Bahan
Batu merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00
Semen Portland 6.500 Kg 820.00 5,330.00
Pasir pasang 0.050 M3 79,400.00 3,970.00
Jumlah 30,300.00
D.14.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 43,700.00

D.15 1 M2 Pasangan bata merah tebal 1/2 bata, 1 PC : 3 Kp : 10 Ps


D.15.1 Bahan
Batu merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00
Semen Portland 4.500 Kg 820.00 3,690.00
Pasir pasang 0.050 M3 79,400.00 3,970.00
Kapur pasang 0.015 M3 - -
Jumlah 28,660.00
D.15.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 42,060.00

D.16 1 M2 Pasangan Bata Merah tebal 1/2 Bata - 1 Kp : 1 Sm : 1 Ps


D.16.1 Bahan
Bata Merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00
Semen Merah 0.018 M3 820.00 14.76
Pasir Pasang 0.018 M3 79,400.00 1,429.20
Kapur Pasang 0.018 M3 - -
Jumlah 22,443.96
D.16.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang Batu 0.100 Oh 40,000.00 4,000.00
Kep. Tukang Batu 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 35,843.96

D.17 1 M2 Pasangan Bata Merah tebal 1/2 Bata - 1 Kp : 1 Sm : 2 Ps


D.17.1 Bahan
Bata Merah 5 x 11 x 22 cm 70.000 Bh 300.00 21,000.00
Semen Merah 0.014 Kg 820.00 11.48
Pasir Pasang 0.028 M3 79,400.00 2,223.20
Kapur Pasang 0.014 M3 - -
Jumlah 23,234.68
D.17.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang Batu 0.100 Oh 40,000.00 4,000.00
Kep. Tukang Batu 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 36,634.68

D.18 1 M2 Pasangan Dinding Hollowblock ( HB 20 )


D.18.1 Bahan
Hollow blok ( HB 20 ) 12.500 Bh - -
Semen Pc 13.500 Kg 820.00 11,070.00
Pasir Pasang 0.048 M3 79,400.00 3,811.20
Besi Beton Polos 1.950 Kg 5,000.00 9,750.00
Jumlah 24,631.20
D.18.2 Tenaga
Pekerja 0.350 Oh 25,000.00 8,750.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kep. Tukang Batu 0.015 Oh 50,000.00 750.00
Mandor 0.017 Oh 60,000.00 1,020.00
Jumlah 16,520.00
Total 41,151.20

D.19 1 M2 Pasangan Dinding Hollowblock ( HB 15 )


D.19.1 Bahan
Hollowblok ( HB 15 ) 12.500 Bh - -
Semen Pc 10.450 Kg 820.00 8,569.00
Pasir Pasang 0.038 M3 79,400.00 3,017.20
Besi Beton Polos 1.950 Kg 5,000.00 9,750.00
Jumlah 21,336.20
D.19.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kep. Tukang Batu 0.012 Oh 50,000.00 600.00
Mandor 0.015 Oh 60,000.00 900.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 45


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Jumlah 14,300.00
Total 35,636.20

D.20 1 M2 Pasangan Dinding Hollowblock ( HB 10 )


D.20.1 Bahan
Hollowblok ( HB 10 ) 12.500 Bh - -
Semen Pc 7.500 Kg 820.00 6,150.00
Pasir Pasang 0.027 M3 79,400.00 2,143.80
Besi Beton Polos 1.950 Kg 5,000.00 9,750.00
Jumlah 18,043.80
D.20.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang Batu 0.100 Oh 40,000.00 4,000.00
Kep. Tukang Batu 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 13,400.00
Total 31,443.80

D.21 1 M2 Pasangan Dinding conblock ( CB 20 )


D.21.1 Bahan
Concrete block (CB.20) 12.500 Bh - -
Semen Pc 14.050 Kg 820.00 11,521.00
Pasir Beton 0.004 M3 92,200.00 368.80
Pasir pasang 0.042 M3 79,400.00 3,334.80
Besi beton polos 3.870 Kg 5,000.00 19,350.00
Paku biasa 2 " - 5 " 0.006 Kg 10,250.00 61.50
Kayu terentang 0.001 Kg 717,100.00 717.10
Kawat beton 0.030 Kg 9,250.00 277.50
Koral beton 0.005 Kg 122,950.00 614.75
Jumlah 36,245.45
D.21.2 Tenaga
Pekerja 0.370 Oh 25,000.00 9,250.00
Tukang Batu 0.157 Oh 40,000.00 6,280.00
Tukang besi 0.007 Oh 35,000.00 245.00
Kep. Tukang Batu 0.016 Oh 50,000.00 820.00
Mandor 0.019 Oh 60,000.00 1,110.00
Jumlah 17,705.00
Total 53,950.45

D.22 1 M2 Pasangan Dinding conblock ( CB 15 )


D.22.1 Bahan
Concrete block (CB 15) 12.500 Bh - -
Semen Pc 10.460 Kg 820.00 8,577.20
Pasir Beton 0.003 M3 92,200.00 276.60
Pasir pasang 0.032 M3 79,400.00 2,540.80
Besi beton polos 0.870 Kg 5,000.00 4,350.00
Paku biasa 2 " - 5 " 0.004 Kg 10,250.00 41.00
Kayu terentang 0.001 Kg 717,100.00 717.10
Kawat beton 0.020 Kg 9,250.00 185.00
Koral beton 0.004 Kg 122,950.00 491.80
Jumlah 17,179.50
D.22.2 Tenaga
Pekerja 0.340 Oh 25,000.00 8,500.00
Tukang Batu 0.130 Oh 40,000.00 5,200.00
Tukang besi 0.007 Oh 35,000.00 245.00
Kep. Tukang Batu 0.014 Oh 50,000.00 685.00
Mandor 0.017 Oh 60,000.00 1,020.00
Jumlah 15,650.00
Total 32,829.50

D.23 1 M2 Pasangan Dinding conblock ( CB 10 )


D.23.1 Bahan
Concrete block (CB 10) 12.500 Bh - -
Semen Pc 7.200 Kg 820.00 5,904.00
Pasir Beton 0.002 M3 92,200.00 184.40
Pasir pasang 0.021 M3 79,400.00 1,667.40
Besi beton polos 2.540 Kg 5,000.00 12,700.00
Paku biasa 2 " - 5 " 0.003 Kg 10,250.00 30.75
Kayu terentang 0.001 Kg 717,100.00 717.10
Kawat beton 0.015 Kg 9,250.00 138.75
Koral beton 0.003 Kg 122,950.00 368.85
Jumlah 21,711.25
D.23.2 Tenaga
Pekerja 0.340 Oh 25,000.00 8,500.00
Tukang Batu 0.107 Oh 40,000.00 4,280.00
Tukang besi 0.007 Oh 35,000.00 245.00
Kep. Tukang Batu 0.011 Oh 50,000.00 570.00
Mandor 0.017 Oh 60,000.00 1,020.00
Jumlah 14,615.00
Total 36,326.25

D.24 1 M2 Pasang Dinding Latei


D.24.1 Bahan
Bondbeam 40 x 20 x 20 cm 2.500 Bh - -
Semen Pc 5.100 Kg 820.00 4,182.00
Pasir Beton 0.080 m3 92,200.00 7,376.00
Besi Beton Polos 1.500 Kg 5,000.00 7,500.00
Koral Beton 0.150 m3 122,950.00 18,442.50
Jumlah 37,500.50
D.24.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang Batu 0.030 Oh 40,000.00 1,200.00
Tukang Besi 0.030 Oh 35,000.00 1,050.00
Kep. Tukang Batu 0.006 Oh 50,000.00 300.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 5,350.00
Total 42,850.50

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 46


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

D.25 1 M2 Pasang dinding roster / terawang ( 12 x 11 x 24 ) cm


D.25.1 Bahan
Roster / terawang 36.000 Bh - -
Semen Portland 12.800 Kg 820.00 10,496.00
Pasir pasang 0.035 M3 79,400.00 2,779.00
Jumlah 13,275.00

D.25.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 12,900.00
Total 26,175.00

D.26 1 M2 Pasang bata berongga ukuran ( 5 x 11 x 24 ) cm


D.26.1 Bahan
Bata berongga 80.000 Bh 2,050.00 164,000.00
Semen Portland 23.650 Kg 820.00 19,393.00
Pasir pasang 0.570 M3 79,400.00 45,258.00
Jumlah 228,651.00
D.26.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.150 Oh 40,000.00 6,000.00
Kepala Tukang 0.015 Oh 50,000.00 750.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 15,650.00
Total 244,301.00

D.27 1 M2 Pasang Dinding Anyaman Bambu, Rangka Kayu


D.27.1 Bahan
Bilik Bambu 1.500 m2 - -
Kayu 5/7 0.014 m3 - -
Paku 0.012 kg 10,250.00 123.00
Lis kayu 2/4 0.003 m3 - -
Jumlah 123.00
D.27.2 Tenaga
Pekerja 0.100 hr 25,000.00 2,500.00
Tukang Kayu 0.050 hr 40,000.00 2,000.00
Kep. Tukang Kayu 0.005 hr 50,000.00 250.00
Mandor 0.002 hr 60,000.00 120.00
Jumlah 4,870.00
Total 4,993.00

E ANALISA KONSTRUKSI PEKERJAAN PLESTERAN

E.1 1 M2 Plesteran 1 PC : 1 Ps , tebal 15 mm


E.1.1 Bahan
Semen Portland 12.920 Kg 820.00 10,594.40
Pasir pasang 0.013 M3 79,400.00 1,032.20
Jumlah 11,626.60
E.1.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang batu 0.150 Oh 40,000.00 6,000.00
Kepala Tukang 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 23,976.60

E.2 1 M2 Plesteran 1 PC : 2 Ps , tebal 15 mm


E.2.1 Bahan
Semen Portland 8.520 Kg 820.00 6,986.40
Pasir pasang 0.017 M3 79,400.00 1,349.80
Jumlah 8,336.20
E.2.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang batu 0.150 Oh 40,000.00 6,000.00
Kepala Tukang 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 20,686.20

E.3 1 M2 Plesteran 1 PC : 3 Ps , tebal 15 mm


E.3.1 Bahan
Semen Portland 6.480 Kg 820.00 5,313.60
Pasir pasang 0.019 M3 79,400.00 1,508.60
Jumlah 6,822.20
E.3.2 Tenaga

Pekerja 0.200 Oh 25,000.00 5,000.00


Tukang batu 0.150 Oh 40,000.00 6,000.00
Kepala Tukang 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 19,172.20

E.4 1 M2 Plesteran 1 PC : 4 Ps , tebal 15 mm


E.4.1 Bahan
Semen Portland 5.200 Kg 820.00 4,264.00
Pasir pasang 0.020 M3 79,400.00 1,588.00
Jumlah 5,852.00
E.4.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang batu 0.150 Oh 40,000.00 6,000.00
Kepala Tukang 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 18,202.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 47


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

E.5 1 M2 Plesteran 1 PC : 5 Ps , tebal 15 mm


E.5.1 Bahan
Semen Portland 4.320 Kg 820.00 3,542.40
Pasir pasang 0.022 M3 79,400.00 1,746.80
Jumlah 5,289.20
E.5.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang batu 0.150 Oh 40,000.00 6,000.00
Kepala Tukang 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 17,639.20

E.6 1 M2 Plesteran 1 PC : 6 Ps , tebal 15 mm


E.6.1 Bahan
Semen Portland 3.680 Kg 820.00 3,017.60
Pasir pasang 0.023 M3 79,400.00 1,826.20
Jumlah 4,843.80
E.6.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang batu 0.150 Oh 40,000.00 6,000.00
Kepala Tukang 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 17,193.80

E.7 1 M2 Plesteran 1 PC : 8 Ps , tebal 15 mm


E.7.1 Bahan
Semen Portland 2.880 Kg 820.00 2,361.60
Pasir pasang 0.024 M3 79,400.00 1,905.60
Jumlah 4,267.20
E.7.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang batu 0.150 Oh 40,000.00 6,000.00
Kepala Tukang 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 16,617.20

E.8 1 M2 Plesteran 1 Pc : 0,5 Kp : 3 Ps, tb.15 mm


E.8.1 Bahan
Semen PC 5.760 Kg 820.00 4,723.20
Kapur Padam 0.003 M3 - -
Pasir Pasang 0.013 M3 79,400.00 1,032.20
Jumlah 5,755.40
E.8.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kep. Tukang Batu 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 18,105.40

E.9 1 M2 Plesteran 1 Pc : 3 Kp : 10 Ps, tbl 15 mm


E.9.1 Bahan
Semen PC 1.840 Kg 820.00 1,508.80
Kapur Padam 0.006 M3 - -
Pasir Pasang 0.014 M3 79,400.00 1,111.60
Jumlah 2,620.40
E.9.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kep. Tukang Batu 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 14,970.40

E.10 1 M2 Plesteran 0,5 Pc : 1 Kp : 4 Ps, tbl 15 mm


E.10.1 Bahan
Semen PC 3.000 Kg 820.00 2,460.00
Kapur Padam 0.005 M3 - -
Pasir Pasang 0.019 M3 79,400.00 1,508.60
Jumlah 3,968.60
E.10.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kep. Tukang Batu 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 16,318.60

E.11 1 M2 Plesteran 1 Kp : 1 Sm : 1 Ps, tbl 15 mm


E.11.1 Bahan
Semen Merah 0.009 M3 8,750.00 78.75
Kapur Padam 0.009 M3 - -
Pasir Pasang 0.009 M3 79,400.00 714.60
Jumlah 793.35
E.11.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kep. Tukang Batu 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 13,143.35

E.12 1 M2 Plesteran 1 Kp : 1 Sm : 2 Ps, tbl 15 mm


E.12.1 Bahan

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 48


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Semen Merah 0.007 M3 820.00 5.74


Kapur Padam 0.007 M3 - -
Pasir Pasang 0.015 M3 79,400.00 1,191.00
Jumlah 1,196.74
E.12.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kep. Tukang Batu 0.015 Oh 50,000.00 750.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 12,350.00
Total 13,546.74

E.13 1 M2 Plesteran 1 PC : 2 Ps,tebal 20 mm


E.13.1 Bahan
Semen Portland 14.280 Kg 820.00 11,709.60
Pasir pasang 0.023 M3 79,400.00 1,826.20
Jumlah 13,535.80
E.13.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 16,000.00
Total 29,535.80

E.14 1 M2 Plesteran 1 PC : 3 Ps,tebal 20 mm


E.14.1 Bahan
Semen Portland 10.800 Kg 820.00 8,856.00
Pasir pasang 0.026 M3 79,400.00 2,064.40
Jumlah 10,920.40
E.14.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 16,000.00
Total 26,920.40

E.15 1 M2 Plesteran 1 PC : 4 Ps,tebal 20 mm


E.15.1 Bahan
Semen Portland 8.680 Kg 820.00 7,117.60
Pasir pasang 0.028 M3 79,400.00 2,223.20
Jumlah 9,340.80
E.15.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 16,000.00
Total 25,340.80

E.16 1 M2 Plesteran 1 PC : 5 Ps,tebal 20 mm


E.16.1 Bahan
Semen Portland 7.290 Kg 820.00 5,977.80
Pasir pasang 0.028 M3 79,400.00 2,223.20
Jumlah 8,201.00
E.16.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 16,000.00
Total 24,201.00

E.17 1 M2 Plesteran 1 PC : 6 Ps,tebal 20 mm


E.17.1 Bahan
Semen Portland 6.240 Kg 820.00 5,116.80
Pasir pasang 0.030 M3 79,400.00 2,382.00
Jumlah 7,498.80
E.17.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 16,000.00
Total 23,498.80

E.18 1 M2 Plesteran 1Kp:1Sm:2Ps - tb.20 mm


E.18.1 Bahan
Semen Merah 0.009 M3 - -
Kapur Padam 0.009 M3 - -
Pasir Pasang 0.018 M3 79,400.00 1,429.20
Jumlah 1,429.20
E.18.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Batu 0.200 Oh 40,000.00 8,000.00
Kep. Tukang Batu 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 16,000.00
Total 17,429.20

E.19 1 M2 Plesteran 1 PC : 2 Ps,tebal 25 mm


E.19.1 Bahan
Semen Portland 15.500 Kg 820.00 12,710.00
Pasir pasang 0.013 M3 79,400.00 1,032.20
Jumlah 13,742.20
E.19.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 49


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Tukang batu 0.200 Oh 40,000.00 8,000.00


Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 17,280.00
Total 31,022.20

E.20 1 M2 Plesteran 1 PC : 3 Ps,tebal 25 mm


E.20.1 Bahan
Semen Portland 11.750 Kg 820.00 9,635.00
Pasir pasang 0.035 M3 79,400.00 2,779.00
Jumlah 12,414.00
E.20.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 17,280.00
Total 29,694.00

E.21 1 M2 Plesteran 1 PC : 4 Ps,tebal 25 mm


E.21.1 Bahan
Semen Portland 9.480 Kg 820.00 7,773.60
Pasir pasang 0.038 M3 79,400.00 3,017.20
Jumlah 10,790.80
E.21.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 17,280.00
Total 28,070.80

E.22 1 M2 Plesteran 1 PC : 5 Ps,tebal 25 mm


E.22.1 Bahan
Semen Portland 7.940 Kg 820.00 6,510.80
Pasir pasang 0.039 M3 79,400.00 3,096.60
Jumlah 9,607.40
E.22.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 17,280.00
Total 26,887.40

E.23 1 M2 Plesteran 1 PC : 2 Ps,tebal 30 mm


E.23.1 Bahan
Semen Portland 18.650 Kg 820.00 15,293.00
Pasir pasang 0.035 M3 79,400.00 2,779.00
Jumlah 18,072.00
E.23.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 20,150.00
Total 38,222.00

E.24 1 M2 Plesteran 1 PC : 3 Ps,tebal 30 mm


E.24.1 Bahan
Semen Portland 14.150 Kg 820.00 11,603.00
Pasir pasang 0.039 M3 79,400.00 3,096.60
Jumlah 14,699.60
E.24.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 20,150.00
Total 34,849.60

E.25 1 M2 Plesteran 1 PC : 4 Ps,tebal 30 mm


E.25.1 Bahan
Semen Portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Jumlah 12,666.40
E.25.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 20,150.00
Total 32,816.40

E.26 1 M2 Plesteran 1 PC : 5 Ps,tebal 30 mm


E.26.1 Bahan
Semen Portland 8.190 Kg 820.00 6,715.80
Pasir pasang 0.045 M3 79,400.00 3,573.00
Jumlah 10,288.80
E.26.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 20,150.00
Total 30,438.80

E.27 1 M2 Berapen 1 PC : 3 Ps,tebal 30 mm

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 50


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

E.27.1 Bahan
Semen Portland 7.070 Kg 820.00 5,797.40
Pasir pasang 0.021 M3 79,400.00 1,667.40
Jumlah 7,464.80
E.27.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang batu 0.070 Oh 40,000.00 2,800.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 7,380.00
Total 14,844.80

E.28 1 M2 Berapen 1 PC : 5 Ps,tebal 15 mm


E.28.1 Bahan
Semen Portland 5.670 Kg 820.00 4,649.40
Pasir pasang 0.023 M3 79,400.00 1,826.20
Jumlah 6,475.60
E.28.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang batu 0.070 Oh 40,000.00 2,800.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 7,380.00
Total 13,855.60

E.29 1 M2 Plesteran Beton 1 PC : 2 Ps,tebal 15 mm


E.29.1 Bahan
Semen Portland 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Jumlah 9,055.20
E.29.2 Tenaga
Pekerja 0.260 Oh 25,000.00 6,500.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 16,280.00
Total 25,335.20

E.30 1 M2 Plesteran Beton 1 PC : 3 Ps,tebal 15 mm


E.30.1 Bahan
Semen Portland 7.070 Kg 820.00 5,797.40
Pasir pasang 0.021 M3 79,400.00 1,667.40
Jumlah 7,464.80
E.30.2 Tenaga
Pekerja 0.260 Oh 25,000.00 6,500.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 16,280.00
Total 23,744.80

E.31 1 M2 Plesteran Skoning 1 PC : 2 Ps


E.31.1 Bahan
Semen Portland 0.500 Kg 820.00 410.00
Pasir pasang 0.002 M3 79,400.00 158.80
Jumlah 568.80
E.31.2 Tenaga
Pekerja 0.057 Oh 25,000.00 1,425.00
Tukang batu 0.038 Oh 40,000.00 1,520.00
Kepala Tukang 0.038 Oh 50,000.00 1,900.00
Mandor 0.002 Oh 60,000.00 120.00
Jumlah 4,965.00
Total 5,533.80

E.32 1 M2 Plesteran Granito 1 PC warna : 2 Granito, tebal 10 mm


E.32.1 Bahan
Semen warna 0.144 Kg - -
Batu Granito 15.000 Kg - -
Jumlah -
E.32.2 Tenaga
Pekerja 0.050 Oh 25,000.00 1,250.00
Tukang batu 0.020 Oh 40,000.00 800.00
Kepala Tukang 0.002 Oh 50,000.00 100.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 2,450.00
Total 2,450.00

E.33 1 M2 Plesteran Teraso 1 PC warna : 2 batu teraso, tebal 10 mm


E.33.1 Bahan
Semen warna 0.440 Kg - -
Batu teraso 11.500 Kg - -
Jumlah -
E.33.2 Tenaga
Pekerja 0.450 Oh 25,000.00 11,250.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.025 Oh 60,000.00 1,500.00
Jumlah 21,750.00
Total 21,750.00

E.34 1 M2 Plesteran Ciprat, 1 PC : 2 Ps


E.34.1 Bahan
Semen Portland 4.320 Kg 820.00 3,542.40
Pasir pasang 0.016 M3 79,400.00 1,270.40
Jumlah 4,812.80
E.34.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang batu 0.100 Oh 40,000.00 4,000.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 51


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Kepala Tukang 0.010 Oh 50,000.00 500.00


Mandor 0.015 Oh 60,000.00 900.00
Jumlah 11,650.00
Total 16,462.80

E.35 1 M2 Plesteran Siar Adukan 1 PC : 2 Ps


E.35.1 Bahan
Semen Portland 4.320 Kg 820.00 3,542.40
Pasir pasang 0.016 M3 79,400.00 1,270.40
Jumlah 4,812.80
E.35.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang batu 0.070 Oh 40,000.00 2,800.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 7,380.00
Total 12,192.80

E.36 1 M2 Plesteran Waterproof Batacote 3 lapis


E.36.1 Bahan
Semen Portland 0.500 Kg 820.00 410.00
Batacote 2.900 Kg - -
Pasir pasang 0.006 M3 79,400.00 476.40
Jumlah 886.40
E.36.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00
Tukang batu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.015 Oh 60,000.00 900.00
Jumlah 17,400.00
Total 18,286.40

F ANALISA BIAYA KONSTRUKSI PEKERJAAN KAYU

F.1 1 M3 Pasang kusen pintu dan jendela kayu jati


F.1.1 Bahan
Kayu jati balok 1.100 M3 - -
Jumlah -
F.1.2 Tenaga
Pekerja 6.000 Oh 25,000.00 150,000.00
Tukang kayu 20.000 Oh 40,000.00 800,000.00
Kepala Tukang 2.000 Oh 50,000.00 100,000.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 1,068,000.00
Total 1,068,000.00

F.2 1 M3 Pasang kusen pintu dan jendela kayu kamper


F.2.1 Bahan
Kayu kamper balok 1.200 M3 - -
Jumlah -
F.2.2 Tenaga
Pekerja 6.000 Oh 25,000.00 150,000.00
Tukang kayu 18.000 Oh 40,000.00 720,000.00
Kepala Tukang 2.000 Oh 50,000.00 100,000.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 988,000.00
Total 988,000.00

F.3 1 M3 Pasang kusen pintu dan jendela kayu borneo


F.3.1 Bahan
Kayu borneo balok 1.200 M3 1,895,150.00 2,274,180.00
Jumlah 2,274,180.00
F.3.2 Tenaga
Pekerja 6.000 Oh 25,000.00 150,000.00
Tukang kayu 18.000 Oh 40,000.00 720,000.00
Kepala Tukang 2.000 Oh 50,000.00 100,000.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 988,000.00
Total 3,262,180.00

F.4 1 M3 Pasang kusen pintu dan jendela kayu damar laut


F.4.1 Bahan
Kayu borneo damar laut balok 1.200 M3 1,895,150.00 2,274,180.00
Jumlah 2,274,180.00
F.4.2 Tenaga
Pekerja 6.000 Oh 25,000.00 150,000.00
Tukang kayu 18.000 Oh 40,000.00 720,000.00
Kepala Tukang 2.000 Oh 50,000.00 100,000.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 988,000.00
Total 3,262,180.00

F.5 1 M2 Pasang pintu klamp kayu kamper


F.5.1 Bahan
Kayu kamper papan 0.036 M3 - -
Paku biasa 2 " - 5 " 0.050 Kg 10,250.00 512.50
Jumlah 512.50
F.5.2 Tenaga
Pekerja 0.350 Oh 25,000.00 8,750.00
Tukang kayu 1.050 Oh 40,000.00 42,000.00
Kepala Tukang 0.105 Oh 50,000.00 5,250.00
Mandor 0.018 Oh 60,000.00 1,080.00
Jumlah 57,080.00
Total 57,592.50

F.6 1 M2 Pasang pintu klamp kayu borneo


F.6.1 Bahan
Kayu borneo papan 0.036 M3 1,690,300.00 60,850.80

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 52


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Paku biasa 2 " - 5 " 0.050 Kg 10,250.00 512.50


Jumlah 61,363.30
F.6.2 Tenaga
Pekerja 0.350 Oh 25,000.00 8,750.00
Tukang kayu 1.050 Oh 40,000.00 42,000.00
Kepala Tukang 0.105 Oh 50,000.00 5,250.00
Mandor 0.018 Oh 60,000.00 1,080.00
Jumlah 57,080.00
Total 118,443.30

F.7 1 M2 Pasang pintu Panel kayu jati


F.7.1 Bahan
Kayu jati papan 0.040 M3 - -
Jumlah -
F.7.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang kayu 2.500 Oh 40,000.00 100,000.00
Kepala Tukang 0.250 Oh 50,000.00 12,500.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 140,500.00
Total 140,500.00

F.8 1 M2 Pasang pintu panel kayu kamper


F.8.1 Bahan
Kayu kamper papan 0.040 M3 - -
Jumlah -
F.8.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang kayu 2.500 Oh 40,000.00 100,000.00
Kepala Tukang 0.250 Oh 50,000.00 12,500.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 140,500.00
Total 140,500.00

F.9 1 M2 Pasang pintu dan jendela kaca kayu jati


F.9.1 Bahan
Kayu jati papan 0.035 M3 - -
Jumlah -
F.9.2 Tenaga
Pekerja 0.800 Oh 25,000.00 20,000.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.040 Oh 60,000.00 2,400.00
Jumlah 112,400.00
Total 112,400.00

F.10 1 M2 Pasang pintu dan jendela kaca kayu kamper


F.10.1 Bahan
Kayu kamper papan 0.035 M3 - -
Jumlah -
F.10.2 Tenaga
Pekerja 0.800 Oh 25,000.00 20,000.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.040 Oh 60,000.00 2,400.00
Jumlah 112,400.00
Total 112,400.00

F.11 1 M2 Pasang pintu dan jendela kaca kayu borneo


F.11.1 Bahan
Kayu borneo papan 0.035 M3 1,690,300.00 59,160.50
Jumlah 59,160.50
F.11.2 Tenaga
Pekerja 0.800 Oh 25,000.00 20,000.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.040 Oh 60,000.00 2,400.00
Jumlah 112,400.00
Total 171,560.50

F.12 1 M2 Pasang pintu dan jendela jalusi kayu jati


F.12.1 Bahan
Kayu jati papan 0.064 M3 - -
Jumlah -
F.12.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang kayu 3.000 Oh 40,000.00 120,000.00
Kepala Tukang 0.300 Oh 50,000.00 15,000.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 178,000.00
Total 178,000.00

F.13 1 M2 Pasang pintu dan jendela jalusi kayu kamper


F.13.1 Bahan
Kayu kamper papan 0.064 M3 - -
Jumlah -
F.13.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang kayu 3.000 Oh 40,000.00 120,000.00
Kepala Tukang 0.300 Oh 50,000.00 15,000.00
Mandor 0.500 Oh 60,000.00 30,000.00
Jumlah 190,000.00
Total 190,000.00

F.14 1 M2 Pasang pintu Playwood rangkap,rangka kayu jati


F.14.1 Bahan
Kayu jati papan 0.020 M3 - -
Paku biasa 1/2 " - 1" 0.030 Kg 10,250.00 307.50

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 53


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Lem Kayu 0.300 Ltr - -


Playwood 4' X 3' x 4 mm 1.000 Lbr - -
Jumlah 307.50
F.14.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 106,800.00
Total 107,107.50

F.15 1 M2 Pasang pintu Playwood rangkap,rangka kayu kamper


F.15.1 Bahan
Kayu kamper papan 0.020 M3 - -
Paku biasa 1/2 " - 1" 0.030 Kg 10,250.00 307.50
Lem Kayu 0.300 Ltr - -
Playwood 4' X 3' x 4 mm 1.000 Lbr - -
Jumlah 307.50
F.15.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 106,800.00
Total 107,107.50

F.16 1 M2 Pasang jalusi mati kusen kayu jati


F.16.1 Bahan
Kayu jati papan 0.060 M3 - -
Paku biasa 1/2 " - 1" 0.150 Kg 10,250.00 1,537.50
Jumlah 1,537.50
F.16.2 Tenaga
Pekerja 0.500 Oh 25,000.00 12,500.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.025 Oh 60,000.00 1,500.00
Jumlah 104,000.00
Total 105,537.50

F.17 1 M2 Pasang jalusi mati kusen kayu kamper


F.17.1 Bahan
Kayu kamper papan 0.060 M3 - -
Paku biasa 1/2 " - 1" 0.150 Kg 10,250.00 1,537.50
Jumlah 1,537.50
F.17.2 Tenaga
Pekerja 0.500 Oh 25,000.00 12,500.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.025 Oh 60,000.00 1,500.00
Jumlah 104,000.00
Total 105,537.50

F.18 1 M2 Pasang pintu plywood rangkap, rangka kayu borneo


F.18.1 Bahan
Kayu borneo papan 0.020 M3 1,690,300.00 33,129.88
Paku biasa 1/2 " - 1 " 0.030 Kg 10,250.00 307.50
Lem kayu 0.300 Ltr - -
Play wood 4' x 3' x 4 mm 1.000 Lbr - -
Jumlah 33,437.38
F.18.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 106,800.00
Total 140,237.38

F.19 1 M2 Pasang pintu teakwood rangkap, rangka kayu jati


F.19.1 Bahan
Kayu jati papan 0.020 M3 - -
Paku biasa 1/2 " - 1 " 0.300 Kg 10,250.00 3,075.00
Lem kayu 0.300 Ltr - -
Teakwood 4' x 8' x 4 mm 1.000 Lbr - -
Jumlah 3,075.00
F.19.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 106,800.00
Total 109,875.00

F.20 1 M2 Pasang pintu teakwood rangkap, rangka kayu kamper


F.20.1 Bahan
Kayu kamper papan 0.020 M3 - -
Paku biasa 1/2 " - 1 " 0.300 Kg 10,250.00 3,075.00
Lem kayu 0.300 Ltr - -
Teakwood 4' x 3' x 4 mm 1.000 Lbr - -
Jumlah 3,075.00
F.20.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang kayu 2.000 Oh 40,000.00 80,000.00
Kepala Tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 106,800.00
Total 109,875.00

F.21 1 M2 Pasang pintu playwood & formika, rangka kayu jati

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 54


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

F.21.1 Bahan
Kayu jati papan 0.020 M3 - -
Paku biasa 1/2 " - 1 " 0.300 Kg 10,250.00 3,075.00
Lem kayu 0.800 Ltr - -
Playwood 4' x 8' x 4 mm 1.000 Lbr - -
Formika 0.500 Lbr - -
Jumlah 3,075.00
F.21.2 Tenaga
Pekerja 0.800 Oh 25,000.00 20,000.00
Tukang kayu 2.500 Oh 40,000.00 100,000.00
Kepala Tukang 0.250 Oh 50,000.00 12,500.00
Mandor 0.040 Oh 60,000.00 2,400.00
Jumlah 134,900.00
Total 137,975.00

F.22 1 M2 Pasang pintu playwood & formika, rangka kayu kamper


F.22.1 Bahan
Kayu kamper papan 0.020 M3 - -
Paku biasa 1/2 " - 1 " 0.300 Kg 10,250.00 3,075.00
Lem kayu 0.800 Ltr - -
Playwood 4' x 8' x 4 mm 1.000 Lbr - -
Formika 4' x 3' 0.500 Lbr - -
Jumlah 3,075.00
F.22.2 Tenaga
Pekerja 0.800 Oh 25,000.00 20,000.00
Tukang kayu 2.500 Oh 40,000.00 100,000.00
Kepala Tukang 0.250 Oh 50,000.00 12,500.00
Mandor 0.040 Oh 60,000.00 2,400.00
Jumlah 134,900.00
Total 137,975.00

F.23 1 M2 Pasang pintu teakwood & formika , rangka kayu jati


F.23.1 Bahan
Kayu jati papan 0.020 M3 - -
Paku biasa 1/2 " - 1 " 0.300 Kg 10,250.00 3,075.00
Lem kayu 0.800 Ltr - -
Teakwood 4' x '8' x 4' mm 0.500 Lbr - -
formika 4' x 8' 0.500 Lbr - -
Jumlah 3,075.00
F.23.2 Tenaga
Pekerja 0.800 Oh 25,000.00 20,000.00
Tukang kayu 2.500 Oh 40,000.00 100,000.00
Kepala Tukang 0.250 Oh 50,000.00 12,500.00
Mandor 0.040 Oh 60,000.00 2,400.00
Jumlah 134,900.00
Total 137,975.00

F.24 1 M2 Pasang pintu teakwood & formika, rangka kayu kamper (Divernis)
F.24.1 Bahan
Kayu kamper papan 0.020 M3 - -
Paku biasa 1/2 " - 1 " 0.300 Kg 10,250.00 3,075.00
Lem kayu 0.800 Ltr - -
Teakwood 4' x '8' x 4' mm 0.500 Lbr - -
Vernis 0.500 Ltr - -
formika 4' x 8' 0.500 Lbr - -
Jumlah 3,075.00
F.24.2 Tenaga
Pekerja 0.800 Oh 25,000.00 20,000.00
Tukang kayu 2.500 Oh 40,000.00 100,000.00
Kepala Tukang 0.250 Oh 50,000.00 12,500.00
Mandor 0.040 Oh 60,000.00 2,400.00
Jumlah 134,900.00
Total 137,975.00

F.25 1 M2 Pasang pintu formika double , rangka kayu jati


F.25.1 Bahan
Kayu jati papan 0.020 M3 - -
Paku biasa 1/2 " - 1 " 0.300 Kg 10,250.00 3,075.00
Lem kayu 1.200 Ltr - -
Playwood 4' x '8' x 4' mm 1.000 Lbr - -
formika 4' x 8' 1.000 Lbr - -
Jumlah 3,075.00
F.25.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang kayu 2.600 Oh 40,000.00 104,000.00
Kepala Tukang 0.260 Oh 50,000.00 13,000.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 145,000.00
Total 148,075.00

F.26 1 M2 Pasang pintu formika double , rangka kayu kamper


F.26.1 Bahan
Kayu kamper papan 0.020 M3 - -
Paku biasa 1/2 " - 1 " 0.300 Kg 10,250.00 3,075.00
Lem kayu 1.200 Ltr - -
Playwood 4' x '8' x 4' mm 1.000 Lbr - -
formika 4' x 8' 1.000 Lbr - -
Jumlah 3,075.00
F.26.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang kayu 2.600 Oh 40,000.00 104,000.00
Kepala Tukang 0.260 Oh 50,000.00 13,000.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 145,000.00
Total 148,075.00

F.27 1 M3 Pasang Konstruksi kuda - kuda kayu jati


F.27.1 Bahan

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 55


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Kayu jati balok 1.100 M3 - -


Besi strip 15.000 Kg - -
Paku biasa 2 " - 5 " 0.800 Kg 10,250.00 8,200.00
Jumlah 8,200.00
F.27.2 Tenaga
Pekerja 4.000 Oh 25,000.00 100,000.00
Tukang kayu 12.000 Oh 40,000.00 480,000.00
Kepala Tukang 1.200 Oh 50,000.00 60,000.00
Mandor 0.200 Oh 60,000.00 12,000.00
Jumlah 652,000.00
Total 660,200.00

F.28 1 M3 Pasang Konstruksi kuda - kuda kayu kamper


F.28.1 Bahan
Kayu kamper balok 1.100 M3 - -
Besi strip 15.000 Kg - -
Paku biasa 2 " - 5 " 0.800 Kg 10,250.00 8,200.00
Jumlah 8,200.00
F.28.2 Tenaga
Pekerja 4.000 Oh 25,000.00 100,000.00
Tukang kayu 12.000 Oh 40,000.00 480,000.00
Kepala Tukang 1.200 Oh 50,000.00 60,000.00
Mandor 0.200 Oh 60,000.00 12,000.00
Jumlah 652,000.00
Total 660,200.00

F.29 1 M3 Pasang Konstruksi kuda - kuda kayu borneo


F.29.1 Bahan
Kayu borneo balok 1.100 M3 1,895,150.00 2,084,665.00
Besi strip 15.000 Kg 717,100.00 10,756,500.00
Paku biasa 2 " - 5 " 0.800 Kg 10,250.00 8,200.00
Jumlah 12,849,365.00
F.29.2 Tenaga
Pekerja 4.000 Oh 25,000.00 100,000.00
Tukang kayu 12.000 Oh 40,000.00 480,000.00
Kepala Tukang 1.200 Oh 50,000.00 60,000.00
Mandor 0.200 Oh 60,000.00 12,000.00
Jumlah 652,000.00
Total 13,501,365.00

F.30 1 M3 Pasang konstruksi kuda kuda kayu kruing


F.30.1 Bahan
Kayu kruing balok 1.100 M3 - -
Besi strip 15.000 Kg - -
Paku biasa 2 " - 5 " 0.800 Kg 10,250.00 8,200.00
Jumlah 8,200.00
F.30.2 Tenaga
Pekerja 4.000 Oh 25,000.00 100,000.00
Tukang kayu 12.000 Oh 40,000.00 480,000.00
Kepala Tukang 1.200 Oh 50,000.00 60,000.00
Mandor 0.200 Oh 60,000.00 12,000.00
Jumlah 652,000.00
Total 660,200.00

F.31 1 M2 Pasang kaso dan reng genteng kodok kayu kamper


F.31.1 Bahan
Kayu kamper balok 0.012 M3 - -
Paku biasa 2 " - 5 " 0.150 Kg 10,250.00 1,537.50
Jumlah 1,537.50
F.31.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 7,300.00
Total 8,837.50

F.32 1 M2 Pasang kaso dan reng genteng kodok kayu borneo


F.32.1 Bahan
Kayu borneo balok 0.012 M3 1,895,150.00 22,741.80
Paku biasa 2 " - 5 " 0.150 Kg 10,250.00 1,537.50
Jumlah 24,279.30
F.32.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 7,300.00
Total 31,579.30

F.33 1 M2 Pasang kaso dan reng genteng monier kayu jati


F.33.1 Bahan
Kayu jati balok 0.014 M3 - -
Paku biasa 2 " - 5 " 0.150 Kg 10,250.00 1,537.50
Jumlah 1,537.50
F.33.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 7,300.00
Total 8,837.50

F.34 1 M2 Pasang kaso dan reng genteng monier kayu kamper


F.34.1 Bahan
Kayu kamper balok 0.014 M3 - -
Paku biasa 2 " - 5 " 0.150 Kg 10,250.00 1,537.50
Jumlah 1,537.50

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 56


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

F.34.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 7,300.00
Total 8,837.50

F.35 1 M2 Pasang kaso dan reng genteng beton kayu borneo


F.35.1 Bahan
Kayu borneo balok 0.014 M3 1,895,150.00 26,532.10
Paku biasa 2 " - 5 " 0.150 Kg 10,250.00 1,537.50
Jumlah 28,069.60
F.35.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 7,300.00
Total 35,369.60

F.36 1 M2 Pasang kaso dan reng atap sirap kayu kamper


F.36.1 Bahan
Kayu kamper balok 0.165 M3 - -
Paku biasa 2 " - 5 " 0.200 Kg 10,250.00 2,050.00
Jumlah 2,050.00
F.36.2 Tenaga
Pekerja 0.120 Oh 25,000.00 3,000.00
Tukang kayu 0.120 Oh 40,000.00 4,800.00
Kepala Tukang 0.012 Oh 50,000.00 600.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 8,760.00
Total 10,810.00

F.37 1 M2 Pasang kaso dan reng atap sirap kayu borneo


F.37.1 Bahan
Kayu borneo balok 0.165 M3 1,895,150.00 312,699.75
Paku biasa 2 " - 5 " 0.200 Kg 10,250.00 2,050.00
Jumlah 314,749.75
F.37.2 Tenaga
Pekerja 0.120 Oh 25,000.00 3,000.00
Tukang kayu 0.120 Oh 40,000.00 4,800.00
Kepala Tukang 0.012 Oh 50,000.00 600.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 8,760.00
Total 323,509.75

F.38 1 M2 Pasang rangka langit langit (1.00 x 1.0 ) M, Kayu Jati


F.38.1 Bahan
Kayu jati balok 0.012 M3 - -
Paku biasa 2 " - 5 " 0.100 Kg 10,250.00 1,025.00
Jumlah 1,025.00
F.38.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 19,500.00
Total 20,525.00

F.39 1 M2 Pasang rangka langit langit ( 1.00 x 1.00 ) M, Kayu Kamper


F.39.1 Bahan
Kayu kamper balok 0.012 M3 - -
Paku biasa 2 " - 5 " 0.100 Kg 10,250.00 1,025.00
Jumlah 1,025.00
F.39.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 19,500.00
Total 20,525.00

F.40 1 M2 Pasang rangka langit langit ( 1.00 x 1.00 ) M, Kayu Borneo


F.40.1 Bahan
Kayu borneo balok 0.012 M3 1,895,150.00 22,741.80
Paku biasa 2 " - 5 " 0.100 Kg 10,250.00 1,025.00
Jumlah 23,766.80
F.40.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 19,500.00
Total 43,266.80

F.41 1 M2 Pasang rangka langit langit ( 30 x 60 ) cm kayu jati


F.41.1 Bahan
Kayu jati balok 0.023 M3 - -
Paku biasa 2 " - 5 " 0.150 Kg 10,250.00 1,537.50
Jumlah 1,537.50
F.41.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang kayu 0.300 Oh 40,000.00 12,000.00
Kepala Tukang 0.030 Oh 50,000.00 1,500.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 19,100.00
Total 20,637.50

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 57


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

F.42 1 M2 Pasang rangka langit langit ( 30 x 60 ) cm, Kayu Kamper


F.42.1 Bahan
Kayu kamper balok 0.023 M3 - -
Paku biasa 2 " - 5 " 0.150 Kg 10,250.00 1,537.50
Jumlah 1,537.50
F.42.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang kayu 0.300 Oh 40,000.00 12,000.00
Kepala Tukang 0.030 Oh 50,000.00 1,500.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 19,100.00
Total 20,637.50

F.43 1 M2 Pasang rangka langit langit ( 30 x 60 ) cm, Kayu Borneo


F.43.1 Bahan
Kayu borneo balok 0.023 M3 1,895,150.00 43,588.45
Paku biasa 2 " - 5 " 0.150 Kg 10,250.00 1,537.50
Jumlah 45,125.95
F.43.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang kayu 0.300 Oh 40,000.00 12,000.00
Kepala Tukang 0.030 Oh 50,000.00 1,500.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 19,100.00
Total 64,225.95

F.44 1 M2 Pasang rangka langit langit ( 30 x 30 ) cm kayu jati


F.44.1 Bahan
Kayu jati balok 0.027 M3 - -
Paku biasa 2 " - 5 " 0.200 Kg 10,250.00 2,050.00
Jumlah 2,050.00
F.44.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang kayu 0.350 Oh 40,000.00 14,000.00
Kepala Tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 22,750.00
Total 24,800.00

F.45 1 M2 Pasang rangka langit langit ( 30 x 30 ) cm, kayu kamper


F.45.1 Bahan
Kayu kamper balok 0.027 M3 - -
Paku biasa 2 " - 5 " 0.200 Kg 10,250.00 2,050.00
Jumlah 2,050.00
F.45.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang kayu 0.350 Oh 40,000.00 14,000.00
Kepala Tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 22,750.00
Total 24,800.00

F.46 1 M2 Pasang rangka langit-langit ( 30 x 30 ) cm , kayu borneo


F.46.1 Bahan
Kayu borneo balok 0.027 M3 1,895,150.00 51,169.05
Paku biasa 2 " - 5 " 0.200 Kg 10,250.00 2,050.00
Jumlah 53,219.05
F.46.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang kayu 0.350 Oh 40,000.00 14,000.00
Kepala Tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 22,750.00
Total 75,969.05

F.47 1 M' Pasang lisplang ukuran ( 3 x 20 ) Cm kayu jati


F.47.1 Bahan
Kayu jati papan 0.007 M3 - -
Paku biasa 2 " - 5 " 0.050 Kg 10,250.00 512.50
Jumlah 512.50
F.47.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 11,800.00
Total 12,312.50

F.48 1 M' Pasang lisplang uk. ( 3 x 20 ) Cm kayu kamper


F.48.1 Bahan
Kayu kamper papan 0.007 M3 - -
Paku biasa 2 " - 5 " 0.050 Kg 10,250.00 512.50
Jumlah 512.50
F.48.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 11,800.00
Total 12,312.50

F.49 1 M' Pasang lisplang ukuran ( 3 x 30 ) Cm kayu jati


F.49.1 Bahan
Kayu jati papan 0.011 M3 - -
Paku biasa 2 " - 5 " 0.050 Kg 10,250.00 512.50
Jumlah 512.50
F.49.2 Tenaga

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 58


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Pekerja 0.110 Oh 25,000.00 2,750.00


Tukang kayu 0.220 Oh 40,000.00 8,800.00
Kepala Tukang 0.022 Oh 50,000.00 1,100.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 12,950.00
Total 13,462.50

F.50 1 M' Pasang lisplang uk. ( 3 x 30 ) Cm kayu kamper


F.50.1 Bahan
Kayu kamper papan 0.011 M3 - -
Paku biasa 2 " - 5 " 0.050 Kg 10,250.00 512.50
Jumlah 512.50
F.50.2 Tenaga
Pekerja 0.110 Oh 25,000.00 2,750.00
Tukang kayu 0.220 Oh 40,000.00 8,800.00
Kepala Tukang 0.022 Oh 50,000.00 1,100.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 12,950.00
Total 13,462.50

F.51 1 M' Pasang lisplang uk. 2 x ( 3 x 20 ) Cm kayu kamper


F.51.1 Bahan
Kayu kamper papan 0.015 M3 - -
Paku biasa 2 " - 5 " 0.060 Kg 10,250.00 615.00
Jumlah 615.00
F.51.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 19,500.00
Total 20,115.00

F.52 1 M' Pasang lisplang uk. 2 x ( 2 x 20 ) Cm kayu kamper


F.52.1 Bahan
Kayu kamper papan 0.009 M3 - -
Paku biasa 2 " - 5 " 0.060 Kg 10,250.00 615.00
Jumlah 615.00
F.52.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 10,000.00
Total 10,615.00

F.53 1 M' Pasang lisplang uk. 2 x ( 2 x 20 ) Cm kayu borneo


F.53.1 Bahan
Kayu borneo papan 0.009 M3 1,690,300.00 14,874.64
Paku biasa 2 " - 5 " 0.060 Kg 10,250.00 615.00
Jumlah 15,489.64
F.53.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.050 Oh 60,000.00 3,000.00
Jumlah 10,000.00
Total 25,489.64

F.54 1 M2 Pasang rangka dinding pemisah kayu kamper


F.54.1 Bahan
Kayu kamper balok 0.020 M3 - -
Kayu kamper papan 0.007 M3 - -
Paku biasa 2 " - 5 " 0.100 Kg 10,250.00 1,025.00
Jumlah 1,025.00
F.54.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.450 Oh 40,000.00 18,000.00
Kepala Tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 28,500.00
Total 29,525.00

F.55 1 M2 Pasang rangka dinding pemisah kayu borneo


F.55.1 Bahan
Kayu borneo balok 0.020 M3 1,895,150.00 36,955.43
Kayu borneo papan 0.007 M3 1,690,300.00 11,832.10
Paku biasa 2 " - 5 " 0.100 Kg 10,250.00 1,025.00
Jumlah 49,812.53
F.55.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.450 Oh 40,000.00 18,000.00
Kepala Tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 28,500.00
Total 78,312.53

F.56 1 M2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper


F.56.1 Bahan
Kayu kamper balok 0.020 M3 - -
Kayu kamper papan 0.007 M3 - -
Paku biasa 2 " - 5 " 0.100 Kg 10,250.00 1,025.00
Jumlah 1,025.00
F.56.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.450 Oh 40,000.00 18,000.00
Kepala Tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.075 Oh 60,000.00 4,500.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 59


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Jumlah 28,500.00
Total 29,525.00

F.57 1 M2 Pasang dinding pemisah playwood rangkap, rangka kayu kamper


F.57.1 Bahan
Kayu kamper balok 0.020 M3 - -
Kayu kamper papan 0.007 M3 - -
Paku biasa 2 " - 5 " 0.100 Kg 10,250.00 1,025.00
lem kayu 0.560 lt - -
Playwood 4' x 8' x 4 mm 1.000 Lbr - -
Jumlah 1,025.00
F.57.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang kayu 0.600 Oh 40,000.00 24,000.00
Kepala Tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 32,600.00
Total 33,625.00

F.58 1 M2 Pasang dinding lambriziring dari papan jati


F.58.1 Bahan
Kayu jati balok 0.007 M3 - -
Paku biasa 2 " - 5 " 0.100 Kg 10,250.00 1,025.00
paku sekrup 3,5" 0.150 kg 350.00 52.50
Jumlah 1,077.50
F.58.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang kayu 1.800 Oh 40,000.00 72,000.00
Kepala Tukang 0.180 Oh 50,000.00 9,000.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 97,800.00
Total 98,877.50

F.59 1 M2 Pasang Playwood tebal 4 mm untuk dinding


F.59.1 Bahan
Playwood 4' x 8' x 4mm 0.400 Lbr - -
Paku biasa 1/2 '" - 1" 0.050 Kg 10,250.00 512.50
Jumlah 512.50
F.59.2 Tenaga
Pekerja 0.025 Oh 25,000.00 625.00
Tukang kayu 0.075 Oh 40,000.00 3,000.00
Kepala Tukang 0.008 Oh 50,000.00 375.00
Mandor 0.001 Oh 60,000.00 78.00
Jumlah 4,078.00
Total 4,590.50

F.60 1 M' Pasang List Plafond kayu profil


F.60.1 Bahan
Kayu profil 1.050 M' - -
Jumlah -
F.60.2 Tenaga
Pekerja 0.021 Oh 25,000.00 525.00
Tukang kayu 0.021 Oh 40,000.00 840.00
Kepala Tukang 0.002 Oh 50,000.00 100.00
Mandor 0.001 Oh 60,000.00 60.00
Jumlah 1,525.00
Total 1,525.00

G ANALISA BIAYA KONTRUKSI PEKERJAAN BETON

G.1 1M3 Membuat beton tumbuk, 1Pc : 3 Ps : 5 Kr


G.1.1 Bahan
Semen portland 218.000 Kg 820.00 178,760.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.870 M3 122,950.00 106,966.50
Jumlah 333,670.50
G.1.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 57,300.00
Total 390,970.50

G.2 1M3 Membuat beton tumbuk, 1Pc : 3 Ps : 6 Kr


G.2.1 Bahan
Semen portland 197.000 Kg 820.00 161,540.00
Pasir beton 0.470 M3 92,200.00 43,334.00
Koral beton 0.940 M3 122,950.00 115,573.00
Jumlah 320,447.00
G.2.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 57,300.00
Total 377,747.00

G.3 1M3 Membuat beton tumbuk, 1Pc : 4 Ps : 6 Kr


G.3.1 Bahan
Semen portland 173.000 Kg 820.00 141,860.00
Pasir beton 0.570 M3 92,200.00 52,554.00
Koral beton 0.870 M3 122,950.00 106,966.50
Jumlah 301,380.50
G.3.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 60


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Mandor 0.080 Oh 60,000.00 4,800.00


Jumlah 57,300.00
Total 358,680.50

G.4 1M3 Membuat lantai kerja beton tumbuk, 1Pc : 3 Ps : 5 Kr, tbl 5 cm
G.4.1 Bahan
Semen portland 10.000 Kg 820.00 8,200.00
Pasir beton 0.026 M3 92,200.00 2,397.20
Koral beton 0.040 M3 122,950.00 4,918.00
Jumlah 15,515.20
G.4.2 Tenaga
Pekerja 1.150 Oh 25,000.00 28,750.00
Tukang Batu 0.020 Oh 40,000.00 800.00
Kepala Tukang 0.002 Oh 50,000.00 100.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 30,010.00
Total 45,525.20

G.5 1M3 Membuat beton bertulang , 1Pc : 2 Ps : 3 Kr


G.5.1 Bahan
Semen portland 232.000 Kg 820.00 190,240.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.780 M3 122,950.00 95,901.00
Jumlah 334,085.00
G.5.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 57,300.00
Total 391,385.00

G.6 1M3 Membuat beton bertulang , 1Pc : 2 Ps : 4 Kr


G.6.1 Bahan
Semen portland 280.000 Kg 820.00 229,600.00
Pasir beton 0.450 M3 92,200.00 41,490.00
Koral beton 0.900 M3 122,950.00 110,655.00
Jumlah 381,745.00
G.6.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 57,300.00
Total 439,045.00

G.7 1M3 Membuat beton bertulang , 1Pc : 2 Ps : 2,5 Kr


G.7.1 Bahan
Semen portland 352.000 Kg 820.00 288,640.00
Pasir beton 0.560 M3 92,200.00 51,632.00
Koral beton 0.700 M3 122,950.00 86,065.00
Jumlah 426,337.00
G.7.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 57,300.00
Total 483,637.00

G.8 1M3 Membuat beton bertulang, 1Pc : 1,5 Ps : 3 Kr


G.8.1 Bahan
Semen portland 357.000 Kg 820.00 292,740.00
Pasir beton 0.420 M3 92,200.00 38,724.00
Koral beton 0.540 M3 122,950.00 66,393.00
Jumlah 397,857.00
G.8.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 57,300.00
Total 455,157.00

G.9 1M3 Membuat beton bertulang , 1Pc : 1,5 Ps : 2,5 Kr


G.9.1 Bahan
Semen portland 386.000 Kg 820.00 316,520.00
Pasir beton 0.470 M3 92,200.00 43,334.00
Koral beton 0.780 M3 122,950.00 95,901.00
Jumlah 455,755.00
G.9.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 57,300.00
Total 513,055.00

G.10 1M3 Membuat beton bertulang 1 Pc : 1 Ps : 2 Kr


G.10.1 Bahan
Semen portland 479.000 Kg 820.00 392,780.00
Pasir beton 0.370 M3 92,200.00 34,114.00
Koral beton 0.740 M3 122,950.00 90,983.00
Jumlah 517,877.00
G.10.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 61


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Mandor 0.080 Oh 60,000.00 4,800.00


Jumlah 57,300.00
Total 575,177.00

G.11 1M3 Membuat tiang pancang prestressed beton


G.11.1 Bahan
Semen portland 440.000 Kg 820.00 360,800.00
Pasir beton 0.500 M3 92,200.00 46,100.00
Koral beton 0.800 M3 122,950.00 98,360.00
Rapidrant 2.460 gln -
Jumlah 505,260.00
G.11.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 57,300.00
Total 562,560.00

G.12 1M3 Membuat beton dengan puzzdith - 100 XR


G.12.1 Bahan
Semen portland 336.000 Kg 820.00 275,520.00
Pasir beton 0.540 M3 92,200.00 49,788.00
Koral beton 0.810 M3 122,950.00 99,589.50
Puzzidith 100 XR 1.000 lt -
Jumlah 424,897.50
G.12.2 Tenaga
Pekerja 1.650 Oh 25,000.00 41,250.00
Tukang Batu 0.250 Oh 40,000.00 10,000.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.080 Oh 60,000.00 4,800.00
Jumlah 57,300.00
Total 482,197.50

G.13 1m3 Membuat beton bertulang , 1Pc : 2 Ps : 3 Kr


G.13.1 Bahan
Semen portland 336.000 Kg 820.00 275,520.00
Pasir beton 0.540 M3 92,200.00 49,788.00
Koral beton 0.810 M3 122,950.00 99,589.50
Jumlah 424,897.50
G.13.2 Tenaga
Pekerja 2.000 Oh 25,000.00 50,000.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala Tukang 0.035 Oh 50,000.00 1,750.00
Mandor 1.000 Oh 60,000.00 60,000.00
Jumlah 125,750.00
Total 550,647.50

G.14 1m3 Membuat beton bertulang , 1Pc : 2 Ps : 4 Kr


G.14.1 Bahan
Semen portland 291.000 Kg 820.00 238,620.00
Pasir beton 0.470 M3 92,200.00 43,334.00
Koral beton 0.930 M3 122,950.00 114,343.50
Jumlah 396,297.50
G.14.2 Tenaga
Pekerja 2.000 Oh 25,000.00 50,000.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala Tukang 0.035 Oh 50,000.00 1,750.00
Mandor 1.000 Oh 60,000.00 60,000.00
Jumlah 125,750.00
Total 522,047.50

G.15 1M3 Membuat beton bertulang, 1Pc : 1,5 Ps : 3 Kr


G.15.1 Bahan
Semen portland 367.000 Kg 820.00 300,940.00
Pasir beton 0.440 M3 92,200.00 40,568.00
Koral beton 0.880 M3 122,950.00 108,196.00
Jumlah 449,704.00
G.15.2 Tenaga
Pekerja 2.000 Oh 25,000.00 50,000.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala Tukang 0.035 Oh 50,000.00 1,750.00
Mandor 1.000 Oh 60,000.00 60,000.00
Jumlah 125,750.00
Total 575,454.00

G.16 1M3 Membuat beton bertulang , 1Pc : 1,5 Ps : 2,5 Kr


G.16.1 Bahan
Semen portland 400.000 Kg 820.00 328,000.00
Pasir beton 0.480 M3 92,200.00 44,256.00
Koral beton 0.800 M3 122,950.00 98,360.00
Jumlah 470,616.00
G.16.2 Tenaga
Pekerja 2.000 Oh 25,000.00 50,000.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala Tukang 0.035 Oh 50,000.00 1,750.00
Mandor 1.000 Oh 60,000.00 60,000.00
Jumlah 125,750.00
Total 596,366.00

G.17 1M3 Membuat beton bertulang 1 Pc : 1 Ps : 1 Kr


G.17.1 Bahan
Semen portland 615.000 Kg 820.00 504,300.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.520 M3 122,950.00 63,934.00
Jumlah 616,178.00
G.17.2 Tenaga
Pekerja 2.000 Oh 25,000.00 50,000.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 62


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Tukang Batu 0.350 Oh 40,000.00 14,000.00


Kepala Tukang 0.035 Oh 50,000.00 1,750.00
Mandor 1.000 Oh 60,000.00 60,000.00
Jumlah 125,750.00
Total 741,928.00

G.18 1M3 Membuat beton kedap air dengan strorox - 100


G.18.1 Bahan
Semen portland 400.000 Kg 820.00 328,000.00
Pasir beton 0.480 M3 92,200.00 44,256.00
Koral beton 0.800 M3 122,950.00 98,360.00
Strorox 100 1.200 gln -
Jumlah 470,616.00
G.18.2 Tenaga
Pekerja 2.000 Oh 25,000.00 50,000.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala Tukang 0.035 Oh 50,000.00 1,750.00
Mandor 1.000 Oh 60,000.00 60,000.00
Jumlah 125,750.00
Total 596,366.00

G.19 1M' Memasang PVC Waterstop lebar 150 mm


G.19.1 Bahan
Waterstop lebar 150 mm 1.050 M' - -
Jumlah -
G.19.2 Tenaga
Pekerja 0.050 Oh 25,000.00 1,250.00
Tukang Batu 0.030 Oh 40,000.00 1,200.00
Kepala Tukang 0.003 Oh 50,000.00 150.00
Mandor 0.002 Oh 60,000.00 120.00
Jumlah 2,720.00
Total 2,720.00

G.20 1M' Memasang PVC Waterstop lebar 200 mm


G.20.1 Bahan
Waterstop lebar 200 mm 1.050 M' - -
Jumlah -
G.20.2 Tenaga
Pekerja 0.050 Oh 25,000.00 1,250.00
Tukang Batu 0.035 Oh 40,000.00 1,400.00
Kepala Tukang 0.004 Oh 50,000.00 175.00
Mandor 0.002 Oh 60,000.00 120.00
Jumlah 2,945.00
Total 2,945.00

G.21 1M' Memasang PVC Waterstop lebar 230 mm


G.21.1 Bahan
Waterstop lebar 230 mm 1.050 M' - -
Jumlah -
G.21.2 Tenaga
Pekerja 0.550 Oh 25,000.00 13,750.00
Tukang Batu 0.035 Oh 40,000.00 1,400.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 15,330.00
Total 15,330.00

G.22 1M' Memasang PVC Waterstop lebar 250 mm


G.22.1 Bahan
Waterstop lebar 250 mm 1.050 M' - -
Jumlah -
G.22.2 Tenaga
Pekerja 0.550 Oh 25,000.00 13,750.00
Tukang Batu 0.035 Oh 40,000.00 1,400.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 15,330.00
Total 15,330.00

G.23 1M' Memasang PVC Waterstop lebar 300 mm


G.23.1 Bahan
Waterstop lebar 300 mm 1.050 M' - -
Jumlah -
G.23.2 Tenaga
Pekerja 0.550 Oh 25,000.00 13,750.00
Tukang Batu 0.035 Oh 40,000.00 1,400.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 15,330.00
Total 15,330.00

G.24 1M' Memasang PVC Waterstop lebar 320 mm


G.24.1 Bahan
Waterstop lebar 320 mm 1.050 M' - -
Jumlah -
G.24.2 Tenaga
Pekerja 0.550 Oh 25,000.00 13,750.00
Tukang Batu 0.035 Oh 40,000.00 1,400.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 15,330.00
Total 15,330.00

G.25 1 Kg Pembesian dengan besi polos atau besi ulir


G.25.1 Bahan
Besi beton (polos/ulir) 1.050 Kg 5,000.00 5,250.00 10500
Kawat beton 0.015 Kg 9,250.00 138.75 13400
Jumlah 5,388.75
G.25.2 Tenaga
Pekerja 0.007 Oh 25,000.00 175.00 113750
Tukang Besi 0.007 Oh 35,000.00 245.00 140000
Kepala Tukang 0.001 Oh 50,000.00 35.00 157500

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 63


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Mandor 0.000 Oh 60,000.00 18.00 175000


Jumlah 473.00
Total 5,861.75

G.26 1 Kg Kabel presstressed polos / strands


G.26.1 Bahan
Besi presstressed polos 1.050 Kg - -
Kawat beton 0.010 Kg 9,250.00 92.50
Jumlah 92.50
G.26.2 Tenaga
Pekerja 0.005 Oh 25,000.00 125.00
Tukang Besi 0.005 Oh 35,000.00 175.00
Kepala Tukang 0.001 Oh 50,000.00 25.00
Mandor 0.000 Oh 60,000.00 18.00
Jumlah 343.00
Total 435.50

G.27 1 Kg Jaring kawat baja


G.27.1 Bahan
Besi jaring kawat baja 1.020 Kg 5,000.00 5,100.00
Kawat beton 0.805 Kg 9,250.00 7,446.25
Jumlah 12,546.25
G.27.2 Tenaga
Pekerja 0.025 Oh 25,000.00 625.00
Tukang Besi 0.025 Oh 35,000.00 875.00
Kepala Tukang 0.003 Oh 50,000.00 125.00
Mandor 0.002 Oh 60,000.00 90.00
Jumlah 1,715.00
Total 14,261.25

G.28 1 M2 Pasang bekisting untuk pondasi


G.28.1 Bahan
Kayu terentang 0.040 M3 717,100.00 28,684.00
Paku biasa 2" - 5" 0.300 Kg 10,250.00 3,075.00
Minyak bekisting 0.100 Lt 2,600.00 260.00
Jumlah 32,019.00
G.28.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00
Tukang Kayu 0.260 Oh 40,000.00 10,400.00
Kepala Tukang 0.026 Oh 50,000.00 1,300.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 19,500.00
Total 51,519.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 64


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

G.29 1 M2 Pasang bekisting untuk sloof


G.29.1 Bahan
Kayu terentang 0.045 M3 717,100.00 32,269.50
Paku biasa 2" - 5" 0.300 Kg 10,250.00 3,075.00
Minyak bekisting 0.100 Lt 2,600.00 260.00
Jumlah 35,604.50
G.29.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00
Tukang Kayu 0.260 Oh 40,000.00 10,400.00
Kepala Tukang 0.026 Oh 50,000.00 1,300.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 19,500.00
Total 55,104.50

G.30 1 M2 Pasang bekisting untuk kolom


G.30.1 Bahan
Kayu terentang 0.040 M3 717,100.00 28,684.00
Paku biasa 2" - 5" 0.400 Kg 10,250.00 4,100.00
Minyak bekisting 0.200 Lt 2,600.00 520.00
Balok kayu borneo 0.015 M3 1,895,150.00 28,427.25
Plywood tebal 9 mm 0.350 Lbr 82,000.00 28,700.00
Dolken kayu galam Ø-8 cm-10/4 m 2.000 Btg 8,750.00 17,500.00
Jumlah 107,931.25
G.30.2 Tenaga
Pekerja 0.300 Oh 25,000.00 7,500.00
Tukang kayu 0.330 Oh 40,000.00 13,200.00
Kepala Tukang 0.033 Oh 50,000.00 1,650.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 22,710.00
Total 130,641.25

G.31 1 M2 Pasang bekisting untuk balok


G.31.1 Bahan
Kayu terentang 0.040 M3 717,100.00 28,684.00
Paku biasa 2" - 5" 0.400 Kg 10,250.00 4,100.00
Minyak bekisting 0.200 Lt 2,600.00 520.00
Balok kayu borneo 0.018 M3 1,895,150.00 34,112.70
Plywood tebal 9 mm 0.350 Lbr 82,000.00 28,700.00
Dolken kayu galam Ø-8 cm-10/4 m 2.000 Btg 8,750.00 17,500.00
Jumlah 113,616.70
G.31.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang kayu 0.330 Oh 40,000.00 13,200.00
Kepala Tukang 0.033 Oh 50,000.00 1,650.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 23,210.00
Total 136,826.70

G.32 1 M2 Pasang bekisting untuk lantai


G.32.1 Bahan
Kayu terentang 0.040 M3 717,100.00 28,684.00
Paku biasa 2" - 5" 0.400 Kg 10,250.00 4,100.00
Minyak bekisting 0.200 Lt 2,600.00 520.00
Balok kayu borneo 0.015 M3 1,895,150.00 28,427.25
Plywood tebal 9 mm 0.350 Lbr - -
Dolken kayu galam Ø-8 cm-10/4 m 6.000 Btg 8,750.00 52,500.00
Jumlah 114,231.25
G.32.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang Batu 0.330 Oh 40,000.00 13,200.00
Kepala Tukang 0.033 Oh 50,000.00 1,650.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 23,210.00
Total 137,441.25

G.33 1 M2 Pasang bekisting untuk dinding


G.33.1 Bahan
Kayu terentang 0.030 M3 717,100.00 21,513.00
Paku biasa 2" - 5" 0.400 Kg 10,250.00 4,100.00
Minyak bekisting 0.200 Lt 2,600.00 520.00
Balok kayu borneo 0.020 M3 1,895,150.00 37,903.00
Plywood tebal 9 mm 0.350 Lbr - -
Dolken kayu galam Ø-8 cm-10/4 m 3.000 Btg 8,750.00 26,250.00
Formtie/ penjaga jarak bekisting/ spacer 4.000 Btg - -
Jumlah 90,286.00
G.33.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang Batu 0.330 Oh 40,000.00 13,200.00
Kepala Tukang 0.033 Oh 50,000.00 1,650.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 23,210.00
Total 113,496.00

G.34 1 M2 Pasang bekisting untuk tangga


G.34.1 Bahan
Kayu terentang 0.030 M3 717,100.00 21,513.00
Paku biasa 2" - 5" 0.400 Kg 10,250.00 4,100.00
Minyak bekisting 0.150 Lt 2,600.00 390.00
Balok kayu borneo 0.015 M3 1,895,150.00 28,427.25
Plywood tebal 9 mm 0.350 Lbr - -
Dolken kayu galam Ø-8 cm-10/4 m 2.000 Btg 8,750.00 17,500.00
Jumlah 71,930.25
G.34.2 Tenaga
Pekerja 0.320 Oh 25,000.00 8,000.00
Tukang kayu 0.330 Oh 40,000.00 13,200.00
Kepala Tukang 0.033 Oh 50,000.00 1,650.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 23,210.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 65


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Total 95,140.25

G.35 1 M3 Membuat beton dengan mutu K 175


G.35.1 Bahan
Semen portland 350.000 Kg 820.00 287,000.00
Pasir beton 0.540 M3 92,200.00 49,788.00
Koral beton 0.810 M3 122,950.00 99,589.50
Jumlah 436,377.50
G.35.2 Tenaga
Pekerja 6.000 Oh 25,000.00 150,000.00
Tukang Batu 1.000 Oh 40,000.00 40,000.00
Kepala Tukang 0.100 Oh 50,000.00 5,000.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 213,000.00
Total 649,377.50

G.36 1 M3 Membuat beton dengan mutu K 225


G.36.1 Bahan
Semen portland 388.000 Kg 820.00 318,160.00
Pasir beton 0.650 M3 92,200.00 59,930.00
Koral beton 0.650 M3 122,950.00 79,917.50
Jumlah 458,007.50
G.36.2 Tenaga
Pekerja 6.000 Oh 25,000.00 150,000.00
Tukang Batu 1.000 Oh 40,000.00 40,000.00
Kepala Tukang 0.100 Oh 50,000.00 5,000.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 213,000.00
Total 671,007.50

G.37 1 M3 Membuat beton dengan mutu K 275


G.37.1 Bahan
Semen portland 400.000 Kg 820.00 328,000.00
Pasir beton 0.400 M3 92,200.00 36,880.00
Koral beton 0.820 M3 122,950.00 100,819.00
Jumlah 465,699.00
G.37.2 Tenaga
Pekerja 6.000 Oh 25,000.00 150,000.00
Tukang Batu 1.000 Oh 40,000.00 40,000.00
Kepala Tukang 0.100 Oh 50,000.00 5,000.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 213,000.00
Total 678,699.00

G.38 1 M2 Pasang jembatan cor


G.38.1 Bahan
Kayu terentang 0.026 M3 717,100.00 18,931.44
Paku biasa 2" - 5" 0.600 Kg 10,250.00 6,150.00
Dolken kayu galam Ø-8 cm-10/4 m 0.500 Btg 8,750.00 4,375.00
Jumlah 29,456.44
G.38.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.050 Oh 40,000.00 2,000.00
Kepala Tukang 0.005 Oh 50,000.00 250.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,420.00
Total 35,876.44

G.39 1 M3 membuat beton Pondasi Strouss Ø 30


Beton K225 1.000 m3 671,007.50 671,007.50
Besi beton 5 Ø 16, Ø 8-15 140.921 kg 5,861.75 826,043.29
Total 1,497,050.79

G.40 1 M3 membuat beton Pile Cap 120 x 120 x 40


Beton K225 1.000 m3 671,007.50 671,007.50
Besi beton Ø 16-150 197.280 kg 5,861.75 1,156,406.04
Bekisting 1.920 m2 51,519.00 98,916.48
Total 1,926,330.02

G.41 1 M3 membuat beton Sloof 20/30


Beton K225 1.000 m3 671,007.50 671,007.50
Besi beton 6 Ø 14, Ø 10-150 179.583 kg 5,861.75 1,052,670.80
Bekisting 10.000 m2 55,104.50 551,045.00
Total 2,274,723.30

G.42 1 M3 membuat beton Kolom 15/15 (praktis)


Beton K175 1.000 m3 649,377.50 649,377.50
Besi beton 4 Ø 10, Ø 6-200 131.894 kg 5,861.75 773,128.91
Bekisting 26.667 m2 130,641.25 3,483,766.67
Total 4,906,273.08

G.43 1 M3 membuat beton Kolom 30/50 komposit (WF bahan lama)


Beton K225 1.000 m3 671,007.50 671,007.50
Besi beton 6 Ø 6, Ø 6-200 10.239 kg 5,861.75 60,017.47
Bekisting 10.667 m2 136,826.70 1,459,484.80
Total 2,190,509.77

G.44 1 M3 membuat beton Balok 15/15 (ring balk)


Beton K175 1.000 m3 649,377.50 649,377.50
Besi beton 4 Ø 10, Ø 6-200 131.894 kg 5,861.75 773,128.91
Bekisting 13.333 m2 136,826.70 1,824,356.00
Total 3,246,862.41

G.45 1 M3 Membuat pondasi beton bertulang ( 150 kg besi + bekisting )


G.45.1 Bahan
Kayu terentang 0.200 M3 717,100.00 143,420.00
Paku biasa 2"-5" 1.500 Kg 10,250.00 15,375.00
Minyak bekisting 0.400 Lt 2,600.00 1,040.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 66


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Besi beton polos 150.000 Kg 5,000.00 750,000.00


Kawat beton 2.250 Kg 9,250.00 20,812.50
Semen portland 323.000 Kg 820.00 264,860.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.780 M3 122,950.00 95,901.00
Jumlah 1,339,352.50
G.45.2 Tenaga
Pekerja 3.900 Oh 25,000.00 97,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Tukang kayu 1.040 Oh 40,000.00 41,600.00
Tukang besi 1.050 Oh 35,000.00 36,750.00
Kepala Tukang 0.245 Oh 50,000.00 12,250.00
Mandor 0.165 Oh 60,000.00 9,900.00
Jumlah 212,000.00
Total 1,551,352.50

G.46 1 M3 Membuat sloof beton bertulang ( 200 kg besi + bekisting )


G.46.1 Bahan
Kayu terentang 0.270 M3 717,100.00 193,617.00
Paku biasa 2"-5" 2.000 Kg 10,250.00 20,500.00
Minyak bekisting 0.600 Lt 2,600.00 1,560.00
Besi beton polos 200.000 Kg 5,000.00 1,000,000.00
Kawat beton 3.000 Kg 9,250.00 27,750.00
Semen portland 323.000 Kg 820.00 264,860.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.780 M3 122,950.00 95,901.00
Jumlah 1,652,132.00
G.46.2 Tenaga
Pekerja 4.850 Oh 25,000.00 121,250.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Tukang kayu 1.560 Oh 40,000.00 62,400.00
Tukang besi 1.400 Oh 35,000.00 49,000.00
Kepala Tukang 0.331 Oh 50,000.00 16,550.00
Mandor 0.170 Oh 60,000.00 10,200.00
Jumlah 273,400.00
Total 1,925,532.00

G.47 1 M3 Membuat kolom beton bertulang ( 300 kg besi + bekisting )


G.47.1 Bahan
Kayu terentang 0.400 M3 717,100.00 286,840.00
Paku biasa 2"-5" 4.000 Kg 10,250.00 41,000.00
Minyak bekisting 2.000 Lt 2,600.00 5,200.00
Besi beton polos 300.000 Kg 5,000.00 1,500,000.00
Kawat beton 4.500 Kg 9,250.00 41,625.00
Semen portland 323.000 Kg 820.00 264,860.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.780 M3 122,950.00 95,901.00
Kayu borneo balok 0.150 M3 1,895,150.00 284,272.50
Plywood 9 mm 3.500 Lbr 82,000.00 287,000.00
Dolken kayu galam Ø-8 cm-10/4 m 20.000 Btg 8,750.00 175,000.00
Jumlah 3,029,642.50
G.47.2 Tenaga
Pekerja 7.300 Oh 25,000.00 182,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Tukang kayu 3.300 Oh 40,000.00 132,000.00
Tukang besi 2.100 Oh 35,000.00 73,500.00
Kepala Tukang 0.570 Oh 50,000.00 28,500.00
Mandor 0.250 Oh 60,000.00 15,000.00
Jumlah 445,500.00
Total 3,475,142.50

G.48 1 M3 Membuat balok beton bertulang ( 200 kg besi + bekisting )


G.48.1 Bahan
Kayu terentang 0.320 M3 717,100.00 229,472.00
Paku biasa 2"-5" 3.200 Kg 10,250.00 32,800.00
Minyak bekisting 1.600 Lt 2,600.00 4,160.00
Besi beton polos 200.000 Kg 5,000.00 1,000,000.00
Kawat beton 3.000 Kg 9,250.00 27,750.00
Semen portland 323.000 Kg 820.00 264,860.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.780 M3 122,950.00 95,901.00
Kayu borneo balok 0.140 M3 1,895,150.00 265,321.00
Plywood 9 mm 2.800 Lbr 82,000.00 229,600.00
Dolken kayu galam Ø-8 cm-10/4 m 16.000 Btg 8,750.00 140,000.00
Jumlah 2,337,808.00
G.48.2 Tenaga
Pekerja 5.960 Oh 25,000.00 149,000.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Tukang kayu 2.800 Oh 40,000.00 112,000.00
Tukang besi 1.400 Oh 35,000.00 49,000.00
Kepala Tukang 0.455 Oh 50,000.00 22,750.00
Mandor 0.208 Oh 60,000.00 12,480.00
Jumlah 359,230.00
Total 2,697,038.00

G.49 1 M3 Membuat balok beton bertulang ( 150 kg besi + bekisting )


G.49.1 Bahan
Kayu terentang 0.320 M3 717,100.00 229,472.00
Paku biasa 2"-5" 3.200 Kg 10,250.00 32,800.00
Minyak bekisting 1.600 Lt 2,600.00 4,160.00
Besi beton polos 150.000 Kg 5,000.00 750,000.00
Kawat beton 2.250 Kg 9,250.00 20,812.50
Semen portland 323.000 Kg 820.00 264,860.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.780 M3 122,950.00 95,901.00
Kayu borneo balok 0.120 M3 1,895,150.00 227,418.00
Plywood 9 mm 2.800 Lbr 82,000.00 229,600.00
Dolken kayu galam Ø-8 cm-10/4 m 32.000 Btg 8,750.00 280,000.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 67


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Jumlah 2,182,967.50
G.49.2 Tenaga
Pekerja 5.800 Oh 25,000.00 145,000.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Tukang kayu 2.800 Oh 40,000.00 112,000.00
Tukang besi 1.050 Oh 35,000.00 36,750.00
Kepala Tukang 0.420 Oh 50,000.00 21,000.00
Mandor 0.185 Oh 60,000.00 11,100.00
Jumlah 339,850.00
Total 2,522,817.50

G.50 1 M3 Membuat dinding beton bertulang ( 150 kg besi + bekisting )


G.50.1 Bahan
Kayu terentang 0.240 M3 717,100.00 172,104.00
Paku biasa 2"-5" 3.200 Kg 10,250.00 32,800.00
Minyak bekisting 1.600 Lt 2,600.00 4,160.00
Besi beton polos 150.000 Kg 5,000.00 750,000.00
Kawat beton 2.250 Kg 9,250.00 20,812.50
Semen portland 323.000 Kg 820.00 264,860.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.780 M3 122,950.00 95,901.00
Kayu borneo balok 0.160 M3 1,895,150.00 303,224.00
Plywood 9 mm 2.800 Lbr 82,000.00 229,600.00
Dolken kayu galam Ø-8 cm-10/4 m 24.000 Btg 8,750.00 210,000.00
Jumlah 2,131,405.50
G.50.2 Tenaga
Pekerja 5.600 Oh 25,000.00 140,000.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Tukang kayu 2.640 Oh 40,000.00 105,600.00
Tukang besi 1.050 Oh 35,000.00 36,750.00
Kepala Tukang 0.400 Oh 50,000.00 20,000.00
Mandor 0.193 Oh 60,000.00 11,580.00
Jumlah 327,930.00
Total 2,459,335.50

G.51 1 M3 Membuat tangga beton bertulang ( 200 kg + bekisting )


G.51.1 Bahan
Kayu terentang 0.250 M3 717,100.00 179,275.00
Paku biasa 2"-5" 3.000 Kg 10,250.00 30,750.00
Minyak bekisting 1.200 Lt 2,600.00 3,120.00
Besi beton polos 200.000 Kg 5,000.00 1,000,000.00
Kawat beton 3.000 Kg 9,250.00 27,750.00
Semen portland 323.000 Kg 820.00 264,860.00
Pasir beton 0.520 M3 92,200.00 47,944.00
Koral beton 0.780 M3 122,950.00 95,901.00
Kayu borneo balok 0.105 M3 1,895,150.00 198,990.75
Plywood 9 mm 2.500 Lbr 82,000.00 205,000.00
Dolken kayu galam Ø-8 cm-10/4 m 14.000 Btg 8,750.00 122,500.00
Jumlah 2,176,090.75
G.51.2 Tenaga
Pekerja 5.600 Oh 25,000.00 140,000.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Tukang kayu 2.300 Oh 40,000.00 92,000.00
Tukang besi 1.400 Oh 35,000.00 49,000.00
Kepala Tukang 0.405 Oh 50,000.00 20,250.00
Mandor 0.202 Oh 60,000.00 12,120.00
Jumlah 327,370.00
Total 2,503,460.75

G.52 1 M' Membuat kolom penguat beton bertulang ( 11 X 11 ) cm


G.52.1 Bahan
Kayu terentang 0.002 M3 717,100.00 1,434.20
Paku biasa 2"-5" 0.010 Kg 10,250.00 102.50
Besi beton polos 3.000 Lt 2,600.00 7,800.00
Kawat beton 0.450 Kg 5,000.00 2,250.00
Semen PC 4.000 Kg 9,250.00 37,000.00
Pasir beton 0.006 M3 92,200.00 553.20
Koral beton 0.009 M3 122,950.00 1,106.55
Jumlah 50,246.45
G.52.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang Batu 0.020 Oh 40,000.00 800.00
Tukang kayu 0.020 Oh 40,000.00 800.00
Tukang besi 0.020 Oh 35,000.00 700.00
Kepala Tukang 0.006 Oh 50,000.00 300.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 4,280.00
Total 54,526.45

G.53 1 M' Membuat ring balok beton bertulang ( 10 X 15 ) cm


G.53.1 Bahan
Kayu albasiah 0.003 M3 717,100.00 2,151.30
Paku biasa 2"-5" 0.020 Kg 10,250.00 205.00
Besi beton polos 3.600 Kg 5,000.00 18,000.00
Kawat beton 0.050 Kg 9,250.00 462.50
Semen portland 5.500 Kg 820.00 4,510.00
Pasir beton 0.009 M3 92,200.00 829.80
Koral beton 0.015 M3 122,950.00 1,844.25
Jumlah 28,002.85
G.53.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang Batu 0.033 Oh 40,000.00 1,320.00
Tukang kayu 0.033 Oh 40,000.00 1,320.00
Tukang besi 0.033 Oh 35,000.00 1,155.00
Kepala Tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 7,095.00
Total 35,097.85

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 68


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

H ANALISA BIAYA KONSTRUKSI PEKERJAAN PENUTUP ATAP

H.1 1 M2 Pas. Atap Genteng Palentong Kecil


H.1.1 Bahan
Genteng Palentong 25.000 Bh - -
Jumlah -
H.1.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Kayu 0.075 Oh 40,000.00 3,000.00
Kepala Tukang 0.008 Oh 50,000.00 400.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 7,630.00
Total 7,630.00

H.2 1 M2 Pas. Atap Genteng Kodok / Glazzur


H.2.1 Bahan
Genteng Kodok 25.000 Bh - -
Jumlah -
H.2.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Kayu 0.075 Oh 40,000.00 3,000.00
Kepala Tukang 0.008 Oh 50,000.00 400.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 7,630.00
Total 7,630.00

H.3 1 M2 Pas. Atap Genteng Pelentong Super / Besar


H.3.1 Bahan
Genteng Pelentong Super 12.000 Bh - -
Jumlah -
H.3.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Kayu 0.060 Oh 40,000.00 2,400.00
Kepala Tukang 0.006 Oh 50,000.00 300.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 6,930.00
Total 6,930.00

H.4 1 M2 Pas. Genteng Bubung Palentong


H.4.1 Bahan
Genteng Bubung Palentong 5.000 Bh - -
Semen Pc 8.000 Kg 820.00 6,560.00
Pasir Pasang 0.032 M3 79,400.00 2,540.80
Jumlah 9,100.80
H.4.2 Tenaga
Pekerja 0.400 Oh 25,000.00 10,000.00
Tukang Kayu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.002 Oh 60,000.00 120.00
Jumlah 19,120.00
Total 28,220.80

H.5 1 M' Pas. Bubung Genteng Kodok Glazuur


H.5.1 Bahan
Genteng Bubung Kodok 5.000 Bh - -
Semen Pc 8.000 Kg 820.00 6,560.00
Pasir Pasang 0.032 M3 79,400.00 2,540.80
Jumlah 9,100.80
H.5.2 Tenaga
Pekerja 0.400 Oh 25,000.00 10,000.00
Tukang Kayu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.002 Oh 60,000.00 120.00
Jumlah 19,120.00
Total 28,220.80

H.6 1 M' Pas. Bubung Genteng Pelentong Besar


H.6.1 Bahan
Genteng Bubung Pelentong 4.000 Bh - -
Semen Pc 8.000 Kg 820.00 6,560.00
Pasir Pasang 0.032 M3 79,400.00 2,540.80
Jumlah 9,100.80
Tenaga
Pekerja 0.400 Oh 25,000.00 10,000.00
Tukang Kayu 0.200 Oh 40,000.00 8,000.00
Kepala Tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.002 Oh 60,000.00 120.00
Jumlah 19,120.00
Total 28,220.80

H.7 1 M2 Pas. Rooflight Fiberglass ( 180 x 90 cm )


H.7.1 Bahan
Rooflight Fiberglass 0.600 Lbr - -
Paku 1/2"-1" 0.050 Kg 10,250.00 512.50
Jumlah 512.50
H.7.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.067 Oh 40,000.00 2,680.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,950.00
Total 7,462.50

H.8 1 M2 Pas. Atap Asbes Gel ( 2.5 x 0.92m )X 5 mm


H.8.1 Bahan
Asbes Gelombang 0.500 Lbr - -
Paku Pancing 60x230 0.120 Kg - -
Jumlah -

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 69


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

H.8.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.075 Oh 40,000.00 3,000.00
Kepala Tukang 0.008 Oh 50,000.00 400.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 7,380.00
Total 7,380.00

H.9 1 M2 Pas. Atap Asbes Gel ( 2,25 x 0,92 m ) X 5 mm


H.9.1 Bahan
Asbes Gelombang 0.600 Lbr - -
Paku Pancing 60 x 230 0.120 Kg - -
Jumlah -
H.9.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.075 Oh 40,000.00 3,000.00
Kepala Tukang 0.008 Oh 50,000.00 400.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 7,380.00
Total 7,380.00

H.10 1 M2 Pas. Atap Asbes Gel ( 2 x 0.92m) X 5 mm


H.10.1 Bahan
Asbes Gelombang 0.600 Lbr - -
Paku Pancing 60 x 230 0.120 Kg - -
Jumlah -
H.10.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.070 Oh 40,000.00 2,800.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 7,070.00
Total 7,070.00

H.11 1 M2 Pas. Atap Asbes Gel ( 1.8 x 0.92 m) X 5 mm


H.11.1 Bahan
Asbes Gelombang 0.750 Lbr - -
Paku Pancing 60 x 230 0.120 Kg - -
Jumlah -
H.11.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.070 Oh 40,000.00 2,800.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 7,070.00
Total 7,070.00

H.12 1 M2 Pas. Atap Asbes Gel ( 3 x 1.05m) X 4 mm


H.12.1 Bahan
Asbes Gelombang 0.350 Lbr - -
Paku Pancing 0.120 Kg - -
Jumlah -
H.12.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.070 Oh 40,000.00 2,800.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 7,070.00
Total 7,070.00

H.13 1 M2 Pas. Atap Asbes Gel ( 2.7 x 1.05 m ) X 4 mm


H.13.1 Bahan
Asbes Gelombang 0.420 Lbr - -
Paku Pancing 0.120 Kg - -
Jumlah -
H.13.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.070 Oh 40,000.00 2,800.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 7,070.00
Total 7,070.00

H.14 1 M2 Pas. Atap Asbes Gel ( 2.4 x 1.05 m ) X 4 mm


H.14.1 Bahan
Asbes Gelombang 0.440 Lbr - -
Paku Pancing 0.120 Kg - -
Jumlah -
H.14.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.067 Oh 40,000.00 2,680.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,950.00
Total 6,950.00

H.15 1 M2 Pas. Atap Asbes Gel ( 2.1 x 1.05 m ) X 4 mm


H.15.1 Bahan
Asbes Gelombang 0.510 Lbr - -
Paku Pancing 0.120 Kg - -
Jumlah -
H.15.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.067 Oh 40,000.00 2,680.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,950.00
Total 6,950.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 70


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

H.16 1 M2 Pas. Atap Asbes Gel ( 1.5 x 1.05 m ) X 4 mm


H.16.1 Bahan
Asbes Gelombang 0.800 Lbr - -
Paku Pancing 0.120 Kg - -
Jumlah -
H.16.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.067 Oh 40,000.00 2,680.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,950.00
Total 6,950.00

H.17 1 M2 Pas. Atap Asbes Gel ( 3 x 1.08 m) X 6 mm


H.17.1 Bahan
Asbes Gelombang 0.370 Lbr - -
Paku Pancing 0.120 Kg - -
Jumlah -
H.17.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.067 Oh 40,000.00 2,680.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,950.00
Total 6,950.00

H.18 1 M2 Pas. Atap Asbes Gel ( 2.7 x 1.08 m) X 6 mm


H.18.1 Bahan
Asbes Gelombang 0.380 Lbr - -
Paku Pancing 0.120 Kg - -
Jumlah -
H.18.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.067 Oh 40,000.00 2,680.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,950.00
Total 6,950.00

H.19 1 M2 Pas. Atap Asbes Gel ( 2.4 x 1.08 m) X 6 mm


H.19.1 Bahan
Asbes Gelombang 0.460 Lbr - -
Paku Pancing 0.120 Kg - -
Jumlah -
H.19.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.067 Oh 40,000.00 2,680.00
Kepala Tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,950.00
Total 6,950.00

H.20 1 M2 Pas. Atap Asbes Gel ( 2.1x 1.08 m ) X 6 mm


H.20.1 Bahan
Asbes Gelombang 0.490 Lbr - -
Paku Pancing 0.120 Kg - -
Jumlah -
H.20.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Kayu 0.067 Oh 40,000.00 2,680.00
Kepala tukang 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,950.00
Total 6,950.00

H.21 1 M2 Pas. Atap Asbes Gel ( 1.8 x 1.08 m ) X 6 mm


H.21.1 Bahan
Asbes Gelombang 0.570 Lbr - -
Paku Kancing 60x230 0.120 Kg - -
Jumlah -
H.21.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang Batu 0.067 Oh 40,000.00 2,680.00
Kep. Tukang Batu 0.007 Oh 50,000.00 350.00
Mandor 0.007 Oh 60,000.00 420.00
Jumlah 6,950.00
Total 6,950.00

H.22 1 M2 Pas. Bubung Stel Gel ( 0.92 m )


H.22.1 Bahan
Bubung Stel Gelombang 2.400 Lbr - -
Paku Sekerup 3,5" 6.000 Bh 350.00 2,100.00
Jumlah 2,100.00
H.22.2 Tenaga -
Pekerja 0.084 Oh 25,000.00 2,100.00
Tukang Kayu 0.125 Oh 40,000.00 5,000.00
Kep. Tukang Kayu 0.013 Oh 50,000.00 650.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 7,990.00
Total 10,090.00

H.23 1 M2 Pas. Nok Stel Gelombang ( 1.05 m )


H.23.1 Bahan
Nok Stel Gelombang 2.100 - -
Paku Sekerup 3,5" 6.000 350.00 2,100.00
Jumlah 2,100.00
H.23.2 Tenaga -

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 71


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Pekerja 0.084 Oh 25,000.00 2,100.00


Tukang Kayu 0.125 Oh 40,000.00 5,000.00
Kep. Tukang Kayu 0.013 Oh 50,000.00 650.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 7,990.00
Total 10,090.00

H.24 1 M2 Pas. Nok Stel Gelombang ( 1.08 m )


H.24.1 Bahan
Nok Stel Gelombang 2.050 lbr - -
Paku Sekerup 3,5" 6.000 bh 350.00 2,100.00
Jumlah 2,100.00
H.24.2 Tenaga -
Pekerja 0.084 Oh 25,000.00 2,100.00
Tukang Kayu 0.125 Oh 40,000.00 5,000.00
Kep. Tukang Kayu 0.013 Oh 50,000.00 650.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 7,990.00
Total 10,090.00

H.25 1 M2 Pas. Nok Paten ( 0.92 m' )


H.25.1 Bahan
Nok Paten 2.400 lbr - -
Paku Sekerup 3,5" 6.000 bh 350.00 2,100.00
Jumlah 2,100.00
H.25.2 Tenaga
Pekerja 0.084 Oh 25,000.00 2,100.00
Tukang Kayu 0.125 Oh 40,000.00 5,000.00
Kep. Tukang Kayu 0.013 Oh 50,000.00 650.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 7,990.00
Total 10,090.00

H.26 1 M2 Pas. Nok Paten ( 1.05 m' )


H.26.1 Bahan
Nok Paten 1.200 lbr - -
Paku Sekerup 3,5" 6.000 bh 350.00 2,100.00
Jumlah 2,100.00
H.26.2 Tenaga
Pekerja 0.084 Oh 25,000.00 2,100.00
Tukang Kayu 0.125 Oh 40,000.00 5,000.00
Kep. Tukang Kayu 0.013 Oh 50,000.00 650.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 7,990.00
Total 10,090.00

H.27 1 M2 Pas. Nok Paten 1,08 m


H.27.1 Bahan
Nok paten 1.200 lbr - -
Paku Sekerup 3,5" 6.000 bh 350.00 2,100.00
Jumlah 2,100.00
H.27.2 Tenaga
Pekerja 0.084 Oh 25,000.00 2,100.00
Tukang Kayu 0.125 Oh 40,000.00 5,000.00
Kep. Tukang Kayu 0.013 Oh 50,000.00 650.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 7,990.00
Total 10,090.00

H.28 1 M2 Pas. Nok Stel Rata ( 0,92 m )


H.28.1 Bahan
Nok Stel rata 1.100 lbr - -
Paku Sekerup 3,5" 6.000 bh 350.00 2,100.00
Jumlah 2,100.00
Tenaga
Pekerja 0.084 Oh 25,000.00 2,100.00
Tukang Kayu 0.125 Oh 40,000.00 5,000.00
Kep. Tukang Kayu 0.013 Oh 50,000.00 650.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 7,990.00
Total 10,090.00
H.29 1 M2 Pas. Nok Stel Rata ( 1,05 m )
H.29.1 Bahan
Nok Stel rata 1.100 lbr - -
Paku Sekerup 3,5" 6.000 bh 350.00 2,100.00
Jumlah 2,100.00
H.29.2 Tenaga -
Pekerja 0.084 Oh 25,000.00 2,100.00
Tukang Kayu 0.125 Oh 40,000.00 5,000.00
Kep. Tukang Kayu 0.013 Oh 50,000.00 650.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 7,990.00
Total 10,090.00

H.30 1 M2 Pas.atap Genteng Beton


H.30.1 Bahan
Genteng Beton 11.000 Bj - -
Paku 2"-5" 0.030 kg 10,250.00 307.50
Jumlah 307.50
H.30.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang Kayu 0.100 Oh 40,000.00 4,000.00
Kep. Tukang Kayu 0.010 Oh 50,000.00 500.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 10,100.00
Total 10,407.50
H.31 1 M2 Pas.atap Genteng aspal
H.31.1 Bahan

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 72


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Genteng Aspal 6.900 lbr - -


Plywood 4" X 8" X 6 mm 0.350 lbr - -
Paku biasa 1/2" - 1" 0.030 kg 8,750.00 262.50
Plastic aerator 0.500 bh - -
Jumlah 262.50
H.31.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang Kayu 0.300 Oh 40,000.00 12,000.00
Kep. Tukang Kayu 0.003 Oh 50,000.00 150.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 17,750.00
Total 18,012.50

H.32 1 M2 Pas. Atap genteng metal


H.32.1 Bahan
Genteng metal 1.020 lbr - -
Paku biasa 2" - 5" 0.200 kg 10,250.00 2,050.00
Jumlah 2,050.00
H.32.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang Kayu 0.100 Oh 40,000.00 4,000.00
Kep. Tukang Kayu 0.010 Oh 50,000.00 500.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 10,100.00
Total 12,150.00

H.33 1 M2 Pas. Atap sirap


H.33.1 Bahan
Genteng Sirap 60.000 bh - -
Paku biasa 1/2" - 1" 0.200 kg 8,750.00 1,750.00
Jumlah 1,750.00
H.33.2 Tenaga
Pekerja 0.166 Oh 25,000.00 4,150.00
Tukang Kayu 0.250 Oh 40,000.00 10,000.00
Kep. Tukang Kayu 0.025 Oh 50,000.00 1,250.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 15,880.00
Total 17,630.00

H.33 1 M2 Pas. Atap sirap


H.33.1 Bahan
Genteng Sirap 60.000 bh - -
Paku biasa 1/2" - 1" 0.200 kg 8,750.00 1,750.00
Jumlah 1,750.00
H.33.2 Tenaga
Pekerja 0.166 Oh 25,000.00 4,150.00
Tukang Kayu 0.250 Oh 40,000.00 10,000.00
Kep. Tukang Kayu 0.025 Oh 50,000.00 1,250.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 15,880.00
Total 17,630.00

H.34 1 M2 Pas. Nok genteng beton


H.34.1 Bahan
Nok Genteng Beton 3.500 bh - -
Paku biasa 2" X 5" 0.050 kg 10,250.00 512.50
Semen Abu-abu 10.800 kg 820.00 8,856.00
Pasir Pasang 0.032 m3 79,400.00 2,540.80
Semen Warna 1.000 kg - -
Jumlah 11,909.30
H.34.2 Tenaga
Pekerja 0.400 Oh 25,000.00 10,000.00
Tukang Kayu 0.200 Oh 40,000.00 8,000.00
Kep. Tukang Kayu 0.020 Oh 50,000.00 1,000.00
Mandor 0.020 Oh 60,000.00 1,200.00
Jumlah 20,200.00
Total 32,109.30

H.35 1 M2 Pas. Nok genteng aspal


H.35.1 Bahan
Genteng Aspal 2.000 bh - -
Paku biasa 1/2" - 1" 0.050 kg 8,750.00 437.50
Kayu borneo balok 0.004 m3 1,895,150.00 6,633.03
Jumlah 7,070.53
H.35.2 Tenaga
Pekerja 0.125 Oh 25,000.00 3,125.00
Tukang Kayu 0.250 Oh 40,000.00 10,000.00
Kep. Tukang Kayu 0.025 Oh 50,000.00 1,250.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 14,735.00
Total 21,805.53

H.36 1 m' Pasang nok genteng metal


H.36.1 Bahan
Genteng decra bond 1.100 bh - -
Paku biasa 1/2" - 1" 0.050 kg 8,750.00 437.50
Jumlah 437.50
H.36.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang kayu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 13,780.00
Total 14,217.50

H.37 1 m' Pasang nok sirap


H.37.1 Bahan
Seng plat 3" x 6" bjs 28 0.400 lbr - -

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 73


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Paku biasa 1/2" - 1" 0.060 kg 8,750.00 525.00


Paku biasa 2" - 5" 0.050 kg 10,250.00 512.50
Kayu borneo papan tebal 3 cm 0.004 m3 1,690,300.00 6,761.20
Jumlah 7,798.70
H.37.2 Tenaga
Pekerja 0.125 Oh 25,000.00 3,125.00
Tukang kayu 0.250 Oh 40,000.00 10,000.00
Kepala tukang 0.003 Oh 50,000.00 125.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 13,610.00
Total 21,408.70

H.38 1 m' Atap Seng Gelombang


H.38.1 Bahan
Seng Gelombang plat 3" x 6" bjs 28 0.700 lbr - -
Paku biasa 1/2" - 1" 0.020 kg 8,750.00 175.00
Jumlah 175.00
H.38.2 Tenaga
Pekerja 0.120 Oh 25,000.00 3,000.00
Tukang kayu 0.060 Oh 40,000.00 2,400.00
Kepala tukang 0.006 Oh 50,000.00 300.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 6,060.00
Total 6,235.00

H.39 1 m' Pas. Atap Nok Seng


H.39.1 Bahan
Seng plat 3" x 6" bjls 28 0.300 lbr - -
Paku biasa 1/2" - 1" 0.040 kg 8,750.00 350.00
Jumlah 350.00
H.39.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.070 Oh 40,000.00 2,800.00
Kepala tukang 0.008 Oh 50,000.00 400.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 7,310.00
Total 7,660.00

H.40 1 m' Pas. Atap Aluminium


H.40.1 Bahan
Atap aluminium Gelombang TB 0,55 1.050 lbr - -
Paku hak panjang 15 cm 0.020 kg - -
Jumlah -
H.40.2 Tenaga -
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.750 Oh 40,000.00 30,000.00
Kepala tukang 0.008 Oh 50,000.00 400.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 34,510.00
Total 34,510.00

H.41 1 m' Pas.nok Aluminium


H.41.1 Bahan
Nok Standrant 40 cm,18 SWG 22 1.200 lbr - -
Paku hak panjang 15 cm 0.040 kg - -
Jumlah -
H.41.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 1.000 Oh 40,000.00 40,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 43,600.00
Total 43,600.00

H.42 1 m' Pas. Aluminium foil / sisalation


H.42.1 Bahan
sisalation / aluminium foil 1.050 m2 4,950.00 5,197.50
Jumlah 5,197.50
H.42.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.050 Oh 40,000.00 2,000.00
Kepala tukang 0.005 Oh 50,000.00 250.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 6,480.00
Total 11,677.50

H.43 1 M2 Pasang atap Zincalum


H.43.1 Bahan
Zincalum 1.050 M2 49,375.00 51,843.75
mur 3/8 x 1,5 cm 8.000 bh 750.00 6,000.00
Jumlah 57,843.75
H.43.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Besi 0.250 Oh 35,000.00 8,750.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 18,250.00
Total 76,093.75

H.44 1 M2 Pasang Glaswool


H.44.1 Bahan
Glaswool 1.050 M2 9,750.00 9,750.00
Jumlah 9,750.00
H.44.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Besi 0.050 Oh 35,000.00 1,750.00
Kepala tukang 0.005 Oh 50,000.00 250.00
Mandor 0.008 Oh 60,000.00 480.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 74


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Jumlah 6,230.00
Total 15,980.00

H.45 1 M2 Pasang Roof mash (kawat kasa)


H.45.1 Bahan
Roof mash (Kawat kasa) 1.050 M2 7,250.00 7,250.00
Jumlah 7,250.00
H.45.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Besi 0.050 Oh 35,000.00 1,750.00
Kepala tukang 0.005 Oh 50,000.00 250.00
Mandor 0.008 Oh 60,000.00 480.00
Jumlah 6,230.00
Total 13,480.00

I Analisa Biaya Kontruksi Pekerjaan


Langit- langit
I.1 1 m2 langit langit asbes (1,00 X 1,00)M,
Tebal 6 mm
I.1.1 Bahan
Plat Asbes tebal 6 mm 1.100 lbr - -
Paku 0.010 kg - -
Jumlah -
I.1.2 Tenaga
Pekerja 0.030 Oh 25,000.00 750.00
Tukang kayu 0.070 Oh 40,000.00 2,800.00
Kepala tukang 0.007 Oh 50,000.00 350.00
Mandor 0.002 Oh 60,000.00 90.00
Jumlah 3,990.00
Total 3,990.00

I.2 1 m2 langit langit asbes (1,00 X 1,00)M,


Tebal 5 mm
I.2.1 Bahan
Plat Asbes tebal 5 mm 1.100 lbr - -
Paku 0.010 kg - -
Jumlah -
I.2.2 Tenaga
Pekerja 0.030 Oh 25,000.00 750.00
Tukang kayu 0.070 Oh 40,000.00 2,800.00
Kepala tukang 0.007 Oh 50,000.00 350.00
Mandor 0.002 Oh 60,000.00 90.00
Jumlah 3,990.00
Total 3,990.00

I.3 1 m2 langit langit asbes (1,00 X 1,00)M,


Tebal 4 mm
I.3.1 Bahan
Plat Asbes tebal 4 mm 1.100 lbr - -
Paku 0.010 kg - -
Jumlah -
I.3.2 Tenaga
Pekerja 0.030 Oh 25,000.00 750.00
Tukang kayu 0.070 Oh 40,000.00 2,800.00
Kepala tukang 0.007 Oh 50,000.00 350.00
Mandor 0.002 Oh 60,000.00 90.00
Jumlah 3,990.00
Total 3,990.00

I.4 1 m2 langit langit asbes (1,00 X 1,00)M,


Tebal 3.5 mm
I.4.1 Bahan
Plat Asbes tebal 3.5 mm 1.100 lbr - -
Paku 0.010 kg - -
Jumlah -
I.4.2 Tenaga
Pekerja 0.030 Oh 25,000.00 750.00
Tukang kayu 0.070 Oh 40,000.00 2,800.00
Kepala tukang 0.007 Oh 50,000.00 350.00
Mandor 0.002 Oh 60,000.00 90.00
Jumlah 3,990.00
Total 3,990.00

I.5 1 m2 langit langit akustik (30 X 30)CM,


I.5.1 Bahan
Akustik ukuran 30 x 30 cm 11.500 lbr - -
Paku kg -
Paku Pancing 0.120 Kg - -
Jumlah -
I.5.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang kayu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 7,080.00
Total 7,080.00

I.6 1 M2 Langit-langit Akustik ( 30 X 60 ) cm


I.6.1 Bahan
Akustik ukuran 30 x 60 cm 5.800 Lbr - -
Paku 0.050 Kg - -
Jumlah -
I.6.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 6,180.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 75


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Total 6,180.00

I.7 1 m2 Langit-langit Akustik ( 60 X 120 ) cm


I.7.1 Bahan
Akustik arm strong ukuran 60 x120 cm 1.500 Lbr - -
Paku 0.050 Kg - -
Jumlah -
I.7.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 6,180.00
Total 6,180.00

I.8 1 M2 Langit-langit Plywood ( 30 X 60 ) cm, tebal 4 mm


I.8.1 Bahan
Plywood 4' x 8' x 4 mm 0.360 Lbr - -
Paku 0.030 Kg - -
Jumlah -
I.8.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.004 Oh 60,000.00 210.00
Jumlah 6,460.00
Total 6,460.00

I.9 1 M2 Langit-langit Plywood ( 30 X 60 ) cm, tebal 6mm


I.9.1 Bahan
Plywood ukuran 4' x 8' x 6 mm 0.360 Lbr - -
Paku 0.030 Kg - -
Jumlah -
I.9.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.004 Oh 60,000.00 210.00
Jumlah 6,460.00
Total 6,460.00

I.10 1 M2 Langit-langit Plywood ( 60 X 120 ) cm, tebal 4 mm


I.10.1 Bahan
Plywood ukuran 4' x 8' x 4 mm 0.375 Lbr - -
Paku 0.030 Kg - -
Jumlah -
I.10.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.004 Oh 60,000.00 210.00
Jumlah 6,460.00
Total 6,460.00

I.11 1 M2 Langit-langit Plywood ( 60 X 120 ) cm, tebal 6 mm


I.11.1 Bahan
Plywood ukuran 4' x 8' x 6 mm 0.375 Lbr - -
Paku 0.030 Kg - -
Jumlah -
I.11.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.004 Oh 60,000.00 210.00
Jumlah 6,460.00
Total 6,460.00

I.12 1 M2 Langit-langit Teakwood ( 30 X 60 ) cm, tebal 4mm


I.12.1 Bahan
Teakwood ukuran 4' x 8' x 4 mm 0.360 Lbr - -
Paku 0.030 Kg - -
Jumlah -
I.12.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.004 Oh 60,000.00 210.00
Jumlah 6,460.00
Total 6,460.00

I.13 1 M2 Langit-langit Teakwood ( 60 X 120 ) cm, tebal 4 mm


I.13.1 Bahan
Teakwood ukuran 4' x 8' x 4 mm 0.375 Lbr - -
Paku 0.030 Kg - -
Jumlah -
I.13.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.004 Oh 60,000.00 210.00
Jumlah 6,460.00
Total 6,460.00

I.14 1 M2 Langit langit lat kayu jati


I.14.1 Bahan
Kayu jati papan 0.024 M3 - -
Paku 0.010 Kg - -
Paku sekrup 0.050 Kg 350.00 17.50

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 76


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Jumlah 17.50
I.14.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang kayu 0.600 Oh 40,000.00 24,000.00
Kepala tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 32,600.00
Total 32,617.50

I.15 1 M2 Langit langit lat kayu ramin


I.15.1 Bahan
Kayu ramin 0.024 Lbr - -
Paku 0.010 Kg - -
Paku sekrup 0.050 Kg 350.00 17.50
Jumlah 17.50
I.15.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang kayu 0.600 Oh 40,000.00 24,000.00
Kepala tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 32,600.00
Total 32,617.50

I.16 1 M2 Langit langit lat kayu kamper


I.16.1 Bahan
Kayu kamper papan 0.024 Lbr - -
Paku 0.010 Kg - -
Paku sekrup 0.050 Kg 350.00 17.50
Jumlah 17.50
I.16.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang kayu 0.600 Oh 40,000.00 24,000.00
Kepala tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 32,600.00
Total 32,617.50

I.17 1 M2 Langit- langit soft board


I.17.1 Bahan
Soft board 4' X 8' X 4 mm 0.350 M3 - -
Paku biasa 0.030 Kg - -
Jumlah -
I.17.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 19,680.00
Total 19,680.00

I.18 1 M2 Langit- langit akustik 60 X 120 cm + rangka allumunium


I.18.1 Bahan
Profil Alluminium"T" 3.600 M' - -
Kawat seng polos 0.150 Kg - -
Ramset / dina bolt 1.000 Bh - -
Akustik arm strong 60 X 120 cm 1.500 Lbr - -
Jumlah -
I.18.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.050 Oh 50,000.00 2,500.00
Mandor 0.008 Oh 60,000.00 450.00
Jumlah 26,700.00
Total 26,700.00

I.19 1 M' List Langit-Langit Kayu Profil


I.19.1 Bahan
Lis Kayu Profil 1.100 M - -
Paku 0.010 Kg 10,250.00 102.50
Jumlah 102.50
I.19.2 Tenaga
Pekerja 0.050 Oh 25,000.00 1,250.00
Tukang Kayu 0.050 Oh 40,000.00 2,000.00
Kepala tukang 0.005 Oh 50,000.00 250.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 3,680.00
Total 3,782.50

I.20 1 M2 Langit-langit asbes (1 x 1) m, tebal 3.2 mm, rangka borneo


I.20.1 Bahan
Kayu borneo, balok 0.012 M3 717,100.00 8,605.20
Paku biasa 0.060 Kg - -
Asbes 1.00 X 1.00 m 1.100 Lbr - -
Jumlah 8,605.20
I.20.2 Tenaga
Pekerja 0.180 Oh 25,000.00 4,500.00
Tukang kayu 0.320 Oh 40,000.00 12,800.00
Kepala tukang 0.032 Oh 50,000.00 1,600.00
Mandor 0.009 Oh 60,000.00 540.00
Jumlah 19,440.00
Total 28,045.20

I.21 1M2 Langit-Langit Playwood 4 mm + Rangka Kayu Borneo


I.21.1 Bahan
Kayu Borneo 0.023 M3 717,100.00 16,493.30
Paku biasa 2" - 5 " 0.060 Kg 8,750.00 525.00
Plywood 4' X 8' X 4 mm 0.390 Lbr - -
Jumlah 17,018.30

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 77


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

I.21.2 Tenaga
Pekerja 0.270 Oh 25,000.00 6,750.00
Tukang kayu 0.400 Oh 40,000.00 16,000.00
Kepala tukang 0.040 Oh 50,000.00 2,000.00
Mandor 0.014 Oh 60,000.00 810.00
Jumlah 25,560.00
Total 42,578.30

I.22 1 M2 Langit-Langit Akustik ( 30 x 60 ) cm + Rangka Kayu Borneo


I.22.1 Bahan
Kayu borneo, balok 0.023 M3 717,100.00 16,493.30
Paku 0.060 Kg 8,750.00 525.00
Akustik 30 X 60 cm 5.800 Lbr - -
Jumlah 17,018.30
I.22.2 Tenaga
Pekerja 0.260 Oh 25,000.00 6,500.00
Tukang kayu 0.400 Oh 40,000.00 16,000.00
Kepala tukang 0.040 Oh 50,000.00 2,000.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 25,280.00
Total 42,298.30

I.23 1 M2 Langit-Langit Akustik ( 30 x 30 ) cm + Rangka Kayu Borneo


I.23.1 Bahan
Kayu borneo, balok 0.027 M3 717,100.00 19,361.70
Paku 0.060 Kg 8,750.00 525.00
Akustik 30 X 30 cm 11.500 Lbr - -
Jumlah 19,886.70
I.23.2 Tenaga
Pekerja 0.310 Oh 25,000.00 7,750.00
Tukang kayu 0.470 Oh 40,000.00 18,800.00
Kepala tukang 0.047 Oh 50,000.00 2,350.00
Mandor 0.016 Oh 60,000.00 930.00
Jumlah 29,830.00
Total 49,716.70

I.24 1 M2 Langit-Langit Gypsum board, tebal 9 mm


I.24.1 Bahan
Gypsum Board ( 120 X 240 X 9) mm 0.364 Lbr - -
Paku Sekrup 0.110 Kg 350.00 38.50
Jumlah 38.50
I.24.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang kayu 0.050 Oh 40,000.00 2,000.00
Kepala tukang 0.005 Oh 50,000.00 250.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 5,050.00
Total 5,088.50

I.25 1 M2 Pasang lisplang Zincalum


I.25.1 Bahan
Zincalum 1.050 M2 49,375.00 51,843.75
mur 3/8 x 1,5 cm 6.000 bh 750.00 4,500.00
Jumlah 56,343.75
I.25.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Besi 0.250 Oh 35,000.00 8,750.00
Kepala Tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.075 Oh 60,000.00 4,500.00
Jumlah 18,250.00
Total 74,593.75

J Analisa Biaya Konstruksi Pekerjaan Pipa dan Sanitasi

J.1 Memasang 1 buah kloset duduk/ monoblok


J.1.1 Bahan
Kloset duduk/monoblok 1.000 Bh - 0.00
Perlengkapan 6% harga kloset 0.00
Jumlah -
J.1.2 Tenaga
Pekerja 3.300 Oh 25,000.00 82,500.00
Tukang batu 1.100 Oh 40,000.00 44,000.00
Kepala tukang 0.001 Oh 50,000.00 50.00
Mandor 0.160 Oh 60,000.00 9,600.00
Jumlah 136,150.00
Total 136,150.00

J.2 Memasang 1 buah kloset jongkok porselen


J.2.1 Bahan
Kloset jongkok porselen 1.000 Bh - 0.00
Semen portland 6.000 Kg 820.00 4,920.00
Pasir pasang 0.010 M3 79,400.00 794.00
Jumlah 5,714.00
J.2.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang batu 1.500 Oh 40,000.00 60,000.00
Kepala tukang 1.500 Oh 50,000.00 75,000.00
Mandor 0.160 Oh 60,000.00 9,600.00
Jumlah 169,600.00
Total 175,314.00

J.3 Memasang 1 buah kloset jongkok teraso


J.3.1 Bahan
Kloset jongkok teraso 1.000 Bh - 0.00
Bata merah 5x11x22 cm 7.000 Bh 300.00 2,100.00
Semen portland 6.000 Kg 820.00 4,920.00
Pasir pasang 0.010 M3 79,400.00 794.00
Jumlah 7,814.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 78


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang batu 1.500 Oh 40,000.00 60,000.00
Kepala tukang 0.300 Oh 50,000.00 15,000.00
Mandor 0.110 Oh 60,000.00 6,600.00
Jumlah 106,600.00
Total 114,414.00

J.4 Memasang 1 buah urinoir


J.4.1 Bahan
Urinoir 1.000 Bh - 0.00
Perlengkapan 0.300 hrg 0.00 0.00
Semen portland 6.000 Kg 820.00 4,920.00
Pasir pasang 0.010 M3 79,400.00 794.00
Jumlah 5,714.00
J.4.2 Tenaga
Pekerja 1.000 Oh 25,000.00 25,000.00
Tukang batu 1.000 Oh 40,000.00 40,000.00
Kepala tukang 0.100 Oh 50,000.00 5,000.00
Mandor 0.100 Oh 60,000.00 6,000.00
Jumlah 76,000.00
Total 81,714.00

J.5 Memasang 1 buah wastafel


J.5.1 Bahan
Wastafel 1.000 Bh - 0.00
Perlengkapan 0.120 hrg 0.00 0.00
Semen abu-abu 6.000 Kg 820.00 4,920.00
Pasir pasang 0.010 M3 79,400.00 794.00
Jumlah 5,714.00
J.5.2 Tenaga
Pekerja 1.200 Oh 25,000.00 30,000.00
Tukang batu 1.450 Oh 40,000.00 58,000.00
Kepala tukang 0.150 Oh 50,000.00 7,500.00
Mandor 0.100 Oh 60,000.00 6,000.00
Jumlah 101,500.00
Total 107,214.00

J.6 Memasang 1 buah bak mandi teraso volume 0,30 M3


J.6.1 Bahan
Bak teraso 1.000 Bh - 0.00
Semen portland 6.000 Kg 820.00 4,920.00
Pasir pasang 0.010 M3 1,588.00 15.88
Jumlah 4,935.88
J.6.2 Tenaga
Pekerja 2.100 Oh 25,000.00 52,500.00
Tukang batu 0.750 Oh 40,000.00 30,000.00
Kepala tukang 0.070 Oh 50,000.00 3,500.00
Mandor 0.110 Oh 60,000.00 6,600.00
Jumlah 92,600.00
Total 97,535.88

J.7 Memasang 1 buah bak mandi Fibreglass volume 0.3 m2


J.7.1 Bahan
Bak fibreglass 1.000 Bh - 0.00
Perlengkapan 0.180 Hrg 0.00 0.00
Jumlah -
J.7.2 Tenaga
Pembantu Tukang 1.800 Oh 25,000.00 45,000.00
Tukang batu 2.700 Oh 40,000.00 108,000.00
Kepala tukang 0.540 Oh 50,000.00 27,000.00
Mandor 0.110 Oh 60,000.00 6,600.00
Jumlah 186,600.00
Total 186,600.00

J.8 Memasang 1 buah bak mandi batu bata volume 0,3 M3


J.8.1 Bahan
Batu bata 0.400 M3 300.00 120.00
Semen portland 120.000 Kg 820.00 98,400.00
Pasir pasang 0.300 M3 1,588.00 476.40
Porselen (11 x 11) cm 360.000 Bh - 0.00
Semen nat 6.000 Kg - 0.00
Jumlah 98,996.40
J.8.2 Tenaga
Pekerja 6.000 Oh 25,000.00 150,000.00
Tukang batu 3.000 Oh 40,000.00 120,000.00
Kepala tukang 0.300 Oh 50,000.00 15,000.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 303,000.00
Total 401,996.40

J.9 Memasang 1 buah bak beton volume 1 M3


J.9.1 Bahan
Beton 1:1 1/2 : 2 1/2 0.900 M3 - 0.00
Besi Beton 180.000 Kg 5,000.00 900,000.00
Kayu Cetakan 8.000 M3 717,100.00 5,736,800.00
Ubin Porselen 5.000 M2 - 0.00
Perlengkapan 0.100 hrg 0.00 0.00
Jumlah 6,636,800.00
J.9.2 Tenaga
Pekerja 3.500 Oh 25,000.00 87,500.00
Tukang batu 4.500 Oh 40,000.00 180,000.00
Kepala tukang 0.900 Oh 50,000.00 45,000.00
Mandor 0.900 Oh 60,000.00 54,000.00
Jumlah 366,500.00
Total 7,003,300.00

J.10 Memasang 1m' Pipa beton, diameter 15 cm - 20 cm

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 79


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

J.10.1 Bahan
Pipa Beton 1.100 Bh - 0.00
Batu Bata 0.027 M3 300.00 8.10
Semen Portland 3.920 Kg 820.00 3,214.40
Pasir Pasang 0.056 M3 79,400.00 4,446.40
Pasir Urug 0.024 M3 66,600.00 1,598.40
Jumlah 9,267.30
J.10.2 Tenaga
Pekerja 0.140 Oh 25,000.00 3,500.00
Tukang batu 0.070 Oh 40,000.00 2,800.00
Kepala tukang 0.007 Oh 50,000.00 350.00
Mandor 0.070 Oh 60,000.00 4,200.00
Jumlah 10,850.00
Total 20,117.30

J.11 Memasang 1m' Pipa beton, diameter 30 cm - 100 cm


J.11.1 Bahan
Pipa Beton 1.100 Bh - 0.00
Batu Bata 0.550 M3 300.00 165.00
Semen Portland 10.300 Kg 820.00 8,446.00
Pasir Pasang 0.061 M3 79,400.00 4,843.40
Pasir Urug 0.069 M3 66,600.00 4,595.40
Jumlah 18,049.80
J.11.2 Tenaga
Pekerja 0.380 Oh 25,000.00 9,500.00
Tukang batu 0.190 Oh 40,000.00 7,600.00
Kepala tukang 0.019 Oh 50,000.00 950.00
Mandor 0.019 Oh 60,000.00 1,140.00
Jumlah 19,190.00
Total 37,239.80

J.12 Memasang 1 buah bak kontrol pasangan batu bata uk. (30 x 30)cm tinggi 35 cm
J.12.1 Bahan
Batu bata 0.145 M3 300.00 43.50
Semen portland 44.000 Kg 820.00 36,080.00
Pasir pasang 0.070 M3 79,400.00 5,558.00
Batu kerikil 0.070 M3 - 0.00
Besi beton 1.600 Kg 5,000.00 8,000.00
Pasir beton 0.060 M3 92,200.00 5,532.00
Jumlah 55,213.50
J.12.2 Tenaga
Pekerja 3.200 Oh 25,000.00 80,000.00
Tukang batu 1.015 Oh 40,000.00 40,600.00
Kepala tukang 0.002 Oh 50,000.00 75.00
Mandor 0.016 Oh 60,000.00 960.00
Jumlah 121,635.00
Total 176,848.50

J.13 Memasang 1 buah bak kontrol pasangan batu bata uk. (45 x 45 )cm tinggi 50 cm
J.13.1 Bahan
Batu bata 0.250 M3 300.00 75.00
Semen portland 77.000 Kg 820.00 63,140.00
Pasir pasang 0.130 M3 79,400.00 10,322.00
Batu kerikil 0.020 M3 - 0.00
Besi beton 2.600 Kg 5,000.00 13,000.00
Pasir beton 0.090 M3 92,200.00 8,298.00
Jumlah 94,835.00
J.13.2 Tenaga
Pekerja 1.420 Oh 25,000.00 35,500.00
Tukang batu 0.473 Oh 40,000.00 18,920.00
Kepala tukang 0.047 Oh 50,000.00 2,350.00
Mandor 0.071 Oh 60,000.00 4,260.00
Jumlah 61,030.00
Total 155,865.00

J.14 Memasang 1 buah bak kontrol pasangan batu bata uk. (60 x 60)cm tinggi 65 cm
J.14.1 Bahan
Batu bata 0.371 M3 300.00 111.30
Semen portland 114.000 Kg 820.00 93,480.00
Pasir pasang 0.184 M3 1,588.00 292.19
Batu koral 0.033 M3 122,950.00 4,057.35
Besi beton 4.850 Kg 5,000.00 24,250.00
Pasir beton 0.120 M3 92,200.00 11,064.00
Jumlah 133,254.84
J.14.2 Tenaga
Pekerja 2.160 Oh 25,000.00 54,000.00
Tukang batu 0.720 Oh 40,000.00 28,800.00
Kepala tukang 0.072 Oh 50,000.00 3,600.00
Mandor 0.108 Oh 60,000.00 6,480.00
Tukang gali 0.100 Oh 30,000.00 3,000.00
Jumlah 95,880.00
Total 229,134.84

J.15 Memasang 1 m' pipa galvanis diameter 1/2"


J.15.1 Bahan
Pipa galvanis 1.200 M' - 0.00
Perlengkapan 0.350 hrg - 0.00
Jumlah -
J.15.2 Tenaga
Pekerja 0.054 Oh 25,000.00 1,350.00
Tukang batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.027 Oh 60,000.00 1,620.00
Jumlah 7,020.00
Total 7,020.00

J.16 Memasang 1 m' pipa galvanis diameter 3/4"


J.16.1 Bahan

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 80


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Pipa galvanis 1.200 M' - 0.00


Perlengkapan 0.350 hrg - 0.00
Jumlah -
J.16.2 Tenaga
Pekerja 0.054 Oh 25,000.00 1,350.00
Tukang batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.027 Oh 60,000.00 1,620.00
Jumlah 7,020.00
Total 7,020.00

J.17 Memasang 1 m' pipa galvanis diameter 1"


J.17.1 Bahan
Pipa galvanis 1.200 M' - 0.00
Perlengkapan 0.350 hrg - 0.00
Jumlah -
J.17.2 Tenaga
Pekerja 0.054 Oh 25,000.00 1,350.00
Tukang batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.027 Oh 60,000.00 1,620.00
Jumlah 7,020.00
Total 7,020.00

J.18 Memasang 1 m' pipa galvanis diameter 2"


J.18.1 Bahan
Pipa galvanis 1.200 M' - 0.00
Perlengkapan 0.350 hrg - 0.00
Jumlah -
J.18.2 Tenaga
Pekerja 0.054 Oh 25,000.00 1,350.00
Tukang batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.027 Oh 60,000.00 1,620.00
Jumlah 7,020.00
Total 7,020.00

J.19 Memasang 1 m' pipa galvanis diameter 3"


J.19.1 Bahan
Pipa galvanis 1.200 M' - 0.00
Perlengkapan 0.350 hrg - 0.00
Jumlah -
J.19.2 Tenaga
Pekerja 0.108 Oh 25,000.00 2,700.00
Tukang batu 0.180 Oh 40,000.00 7,200.00
Kepala tukang 0.018 Oh 50,000.00 900.00
Mandor 0.005 Oh 60,000.00 324.00
Jumlah 11,124.00
Total 11,124.00

J.20 Memasang 1 m' pipa galvanis diameter 4"


J.20.1 Bahan
Pipa galvanis 1.200 M' - 0.00
Perlengkapan 0.350 hrg - 0.00
Jumlah -
J.20.2 Tenaga
Pekerja 0.108 Oh 25,000.00 2,700.00
Tukang batu 0.180 Oh 40,000.00 7,200.00
Kepala tukang 0.018 Oh 50,000.00 900.00
Mandor 0.005 Oh 60,000.00 324.00
Jumlah 11,124.00
Total 11,124.00

J.21 Memasang 1 m' pipa PVC tipe AW diameter 1/2"


J.21.1 Bahan
Pipa PVC 1.200 M' - 0.00
Perlengkapan 0.350 hrg - 0.00
Jumlah -
J.21.2 Tenaga
Pekerja 0.135 Oh 25,000.00 3,375.00
Tukang batu 0.225 Oh 40,000.00 9,000.00
Kepala tukang 0.023 Oh 50,000.00 1,125.00
Mandor 0.007 Oh 60,000.00 408.00
Jumlah 13,908.00
Total 13,908.00

J.22 Memasang 1 m' pipa PVC tipe AW diameter 3/4"


J.22.1 Bahan
Pipa PVC 1.200 M' - 0.00
Perlengkapan 0.350 hrg - 0.00
Jumlah -
J.22.2 Tenaga
Pekerja 0.036 Oh 25,000.00 900.00
Tukang batu 0.060 Oh 40,000.00 2,400.00
Kepala tukang 0.006 Oh 50,000.00 300.00
Mandor 0.002 Oh 60,000.00 108.00
Jumlah 3,708.00
Total 3,708.00

J.23 Memasang 1 m' pipa PVC tipe AW diameter 1"


J.23.1 Bahan
Pipa PVC 1.200 M' - 0.00
Perlengkapan 0.350 hrg - 0.00
Jumlah -
J.23.2 Tenaga
Pekerja 0.036 Oh 25,000.00 900.00
Tukang batu 0.060 Oh 40,000.00 2,400.00
Kepala tukang 0.006 Oh 50,000.00 300.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 81


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Mandor 0.002 Oh 60,000.00 108.00


Jumlah 3,708.00
Total 3,708.00

J.24 Memasang 1 m' pipa PVC tipe AW diameter 2"


J.24.1 Bahan
Pipa PVC 1.20 M' - 0.00
Perlengkapan 0.35 hrg - 0.00
Jumlah -
J.24.2 Tenaga
Pekerja 0.05 Oh 25,000.00 1,350.00
Tukang batu 0.09 Oh 40,000.00 3,600.00
Kepala tukang 0.01 Oh 50,000.00 450.00
Mandor 0.00 Oh 60,000.00 162.00
Jumlah 5,562.00
Total 5,562.00

J.25 Memasang 1 m' pipa PVC tipe AW diameter 3"


J.25.1 Bahan
Pipa PVC 1.20 M' - 0.00
Perlengkapan 0.35 hrg - 0.00
Jumlah -
J.25.2 Tenaga
Pekerja 0.08 Oh 25,000.00 2,025.00
Tukang batu 0.14 Oh 40,000.00 5,400.00
Kepala tukang 0.01 Oh 50,000.00 675.00
Mandor 0.00 Oh 60,000.00 246.00
Jumlah 8,346.00
Total 8,346.00

J.26 Memasang 1 m' pipa PVC tipe AW diameter 4"


J.26.1 Bahan
Pipa PVC 1.20 M' - 0.00
Perlengkapan 0.35 hrg - 0.00
Jumlah -
J.26.2 Tenaga
Pekerja 0.08 Oh 25,000.00 2,025.00
Tukang batu 0.14 Oh 40,000.00 5,400.00
Kepala tukang 0.01 Oh 50,000.00 675.00
Mandor 0.00 Oh 60,000.00 246.00
Jumlah 8,346.00
Total 8,346.00

J.27 Memasang 1 m' pipa PVC tipe D 4"


J.27.1 Bahan
Pipa PVC 1.200 M' 30,250.00 36,300.00
Perlengkapan 0.350 hrg 36,300.00 12,705.00
Jumlah 49,005.00
J.27.2 Tenaga
Pekerja 0.081 Oh 25,000.00 2,025.00
Tukang batu 0.135 Oh 40,000.00 5,400.00
Kepala tukang 0.014 Oh 50,000.00 675.00
Mandor 0.004 Oh 60,000.00 246.00
Jumlah 8,346.00
Total 57,351.00

J.28 Memasang 1 buah bak cuci piring stainles steel


J.28.1 Bahan
Bak Cuci Steinless Steal 1.000 Bh - -
Water Drain + Aksesoris 1.000 set - -
Jumlah -
J.28.2 Tenaga
Pekerja 0.030 Oh 25,000.00 750.00
Tukang Batu 0.300 Oh 40,000.00 12,000.00
Kepala tukang 0.030 Oh 50,000.00 1,500.00
Mandor 0.002 Oh 60,000.00 90.00
Jumlah 14,340.00
Total 14,340.00
J.29 Memasang 1 buah Bak Cuci Piring Teraso
J.29.1 Bahan
Bak Cuci Teraso 1.000 Bh - -
Water Drain + Aksesoris 1.000 set - -
Semen Pc 20.000 Kg 820.00 16,400.00
Pasir Pasang 0.050 M3 79,400.00 3,970.00
Jumlah 20,370.00
J.29.2 Tenaga
Pekerja 0.050 Oh 25,000.00 1,250.00
Tukang Batu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.050 Oh 50,000.00 2,500.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 23,900.00
Total 44,270.00
J.30 Memasang 1 bh kran diameter 3/4" atau 1/2"
J.30.1 Bahan
Kran air 1.000 Bh - -
Seal tape 0.025 Bh - -
Jumlah -
J.30.2 Tenaga
Pekerja 0.010 Oh 25,000.00 250.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 5,050.00
Total 5,050.00
J.31 Memasang 1 bh Floor drain
J.31.1 Bahan
Floor drain 1.000 Bh - -
Jumlah -

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 82


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

J.31.2 Tenaga
Pekerja 0.010 Oh 25,000.00 250.00
Tukang batu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 5,050.00
Total 5,050.00

K ANALISA BIAYA KONSTRUKSI PEKERJAAN BESI DAN ALLUMUNIUM

K.1 1Kg Pasang Rangka Atap Baja


K.1.1 Bahan
Besi Plat 1.100 Kg 10,250.00 11,275.00
Meni besi 0.080 Kg 12,300.00 984.00
Jumlah 12,259.00
K.1.2 Tenaga
Tukang besi 0.006 Oh 35,000.00 210.00
Pekerja 0.060 Oh 25,000.00 1,500.00
Kepala tukang 0.006 Oh 50,000.00 300.00
Mandor 0.000 Oh 60,000.00 18.00
Jumlah 2,028.00
Total 14,287.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 83


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

K.2 1Kg Pasang kolom WF memakai bahan lama


K.2.1 Bahan
Besi profil WF 1.100 Kg 10,250.00 11,275.00
Meni besi 0.080 Kg 12,300.00 984.00
Jumlah 12,259.00
K.2.2 Tenaga
Tukang besi 0.006 Oh 35,000.00 210.00
Pekerja 0.060 Oh 25,000.00 1,500.00
Kepala tukang 0.006 Oh 50,000.00 300.00
Mandor 0.000 Oh 60,000.00 18.00
Jumlah 2,028.00
Total 14,287.00

K.3 1Kg Pasang Rangka Atap Baja


K.3.1 Bahan
Besi profil C 1.100 Kg 12,300.00 13,530.00
Meni besi 0.080 Kg 12,300.00 984.00
Jumlah 14,514.00
K.3.2 Tenaga
Tukang besi 0.006 Oh 35,000.00 210.00
Pekerja 0.060 Oh 25,000.00 1,500.00
Kepala tukang 0.006 Oh 50,000.00 300.00
Mandor 0.000 Oh 60,000.00 18.00
Jumlah 2,028.00
Total 16,542.00

K.4 1Kg Pasang Rangka Screening (bahan lama)


K.4.1 Bahan
Besi profil C 1.100 Kg 12,300.00 13,530.00
Meni besi 0.080 Kg 12,300.00 984.00
Jumlah 14,514.00
K.4.2 Tenaga
Tukang besi 0.006 Oh 35,000.00 210.00
Pekerja 0.060 Oh 25,000.00 1,500.00
Kepala tukang 0.006 Oh 50,000.00 300.00
Mandor 0.000 Oh 60,000.00 18.00
Jumlah 2,028.00
Total 16,542.00

K.5 ( 1 Kg Fabrikasi & Pemasangan Besi Siku )


K.5.1 Bahan :
Besi Siku L 1.100 kg 10,250.00 11,275.00
Meni besi 0.080 Kg 12,300.00 984.00
Elektoda 0.050 kg 12,300.00 615.00
Jumlah 12,874.00
K.5.2 Upah :
Mandor 0.016 Hr 35,000.00 560.00
Tukang las 0.010 Hr 25,000.00 252.50
Pekerja 0.004 Hr 50,000.00 175.00
Jumlah 987.50
Total 13,861.50

K.6 1M2 Pasang Pintu Besi Baja


K.6.1 Bahan
Pintu besi baja 1.000 M2 - -
Jumlah -
K.6.2 Tenaga
Tukang besi konstruksi 0.650 Oh 35,000.00 22,750.00
Pekerja 0.650 Oh 25,000.00 16,250.00
Kepala tukang 0.065 Oh 50,000.00 3,250.00
Mandor 0.032 Oh 60,000.00 1,920.00
Jumlah 44,170.00
Total 44,170.00

K.7 1 M2 Pasang Jendela Besi


K.7.1 Bahan
Jendela besi 1.000 M2 - -
Jumlah -
K.7.2 Tenaga
Tukang besi konstruksi 1.050 Oh 35,000.00 36,750.00
Pekerja 1.050 Oh 25,000.00 26,250.00
Kepala tukang 0.105 Oh 50,000.00 5,250.00
Mandor 0.005 Oh 60,000.00 315.00
Jumlah 68,565.00
Total 68,565.00

K.8 1 M2 Pasang Jendela Besi Tahan Api


K.8.1 Bahan
Jendela Besi Tahan Api 1.000 M2 - -
Jumlah -
K.8.2 Tenaga
Tukang besi konstruksi 1.200 Oh 25,000.00 30,000.00
Pekerja 1.022 Oh 35,000.00 35,770.00
Kepala tukang 0.120 Oh 50,000.00 6,000.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 72,130.00
Total 72,130.00

K.9 1 M2 Pasang Pintu Gulung Besi


K.9.1 Bahan
Pintu gulung besi 1.000 M2 - -
Jumlah -
K.9.2 Tenaga
Tukang besi konstruksi 1.200 Oh 35,000.00 42,000.00
Pekerja 1.200 Oh 25,000.00 30,000.00
Kepala tukang 0.120 Oh 50,000.00 6,000.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 78,360.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 84


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Total 78,360.00

K.10 1 M2 Pasang Pintu Lipat


K.10.1 Bahan
Pintu Lipat 1.000 M2 - -
Jumlah -
K.10.2 Tenaga
Tukang besi konstruksi 1.050 Oh 35,000.00 36,750.00
Pekerja 1.050 Oh 25,000.00 26,250.00
Kepala tukang 0.105 Oh 50,000.00 5,250.00
Mandor 0.005 Oh 60,000.00 312.00
Jumlah 68,562.00
Total 68,562.00

K.11 1 M2 Pasang Pintu Sunscreen Allumunium


K.11.1 Bahan
Sunscreen Allumunium 1.000 M2 - -
Jumlah -
K.11.2 Tenaga
Tukang besi konstruksi 0.800 Oh 35,000.00 28,000.00
Pekerja 0.080 Oh 25,000.00 2,000.00
Kepala tukang 0.080 Oh 50,000.00 4,000.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 34,240.00
Total 34,240.00

K.12 1 M2 Pasang Rolling door


K.12.1 Bahan
Rolling door 1.000 M2 - -
Jumlah -
K.12.2 Tenaga
Tukang besi konstruksi 1.500 Oh 35,000.00 52,500.00
Pekerja 1.050 Oh 25,000.00 26,250.00
Kepala tukang 0.105 Oh 50,000.00 5,250.00
Mandor 0.005 Oh 60,000.00 312.00
Jumlah 84,312.00
Total 84,312.00

K.13 1 M2 Pasang Pintu Alumunium


K.13.1 Bahan
Pintu Alumunium 1.000 M2 - -
Jumlah -
K.13.2 Tenaga
Tukang besi konstruksi 1.050 Oh 25,000.00 26,250.00
Pekerja 1.050 Oh 50,000.00 52,500.00
Kepala tukang 0.105 Oh 50,000.00 5,250.00
Mandor 0.005 Oh 60,000.00 312.00
Jumlah 84,312.00
Total 84,312.00

K.14 1M2 Pasang Venetions blinds


K.14.1 Bahan
Venetions Blinds 1.000 M2 - -
Jumlah -
K.14.2 Tenaga
Tukang kayu 0.350 Oh 25,000.00 8,750.00
Pekerja 0.350 Oh 50,000.00 17,500.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.002 Oh 60,000.00 105.00
Jumlah 28,105.00
Total 28,105.00

K.15 1 M2 Pasang Vertikal blinds


K.15.1 Bahan
Vertical Blinds 1.000 M2 - -
Jumlah -
K.15.2 Tenaga
Tukang kayu 0.350 Oh 40,000.00 14,000.00
Pekerja 0.350 Oh 25,000.00 8,750.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.002 Oh 60,000.00 105.00
Jumlah 24,605.00
Total 24,605.00

K.16 1 M2 Pasang Terali Besi


K.16.1 Bahan
Besi Strip 2 x 3 11.500 M' - -
Jumlah -
K.16.2 Tenaga
Pekerja 1.200 Oh 25,000.00 30,000.00
Tukang Las 1.200 Oh 35,000.00 42,000.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.001 Oh 60,000.00 36.00
Jumlah 72,636.00
Total 72,636.00

K.17 1 M2 Pasang Kawat Harmonika


K.17.1 Bahan
Kawat Harmonika 1.100 M2 - -
Paku 1/2"-1" 0.020 Kg 8,750.00 175.00
Kayu Kamper Papan 0.002 M3 - -
Jumlah 175.00
K.17.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang Kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.001 Oh 60,000.00 30.00
Jumlah 7,030.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 85


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Total 7,205.00

K.18 1 M2 Pasang Kawat Nyamuk


K.18.1 Bahan
Kawat Nyamuk 1.100 M2 - -
Paku 1/2"-1" 0.020 Kg 8,750.00 175.00
Kayu Kamper Papan 0.002 M3 - -
Jumlah 175.00
K.18.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang Kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.001 Oh 60,000.00 30.00
Jumlah 7,030.00
Total 7,205.00

K.19 1 M2 Pasang Kawat Kassa


K.19.1 Bahan
Kawat Kassa 1.100 M2 - -
Paku 1/2"-1" 0.020 Kg 8,750.00 175.00
Kayu Kamper Papan 0.002 M3 - -
Jumlah 175.00
K.19.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang Kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.001 Oh 60,000.00 30.00
Jumlah 7,030.00
Total 7,205.00

K.20 1 M2 Pasang Kawat Burung


K.20.1 Bahan
Kawat Burung 1.100 M2 - -
Paku 1/2"-1" 0.020 Kg 8,750.00 175.00
Kayu Kamper Papan 0.002 M3 - -
Jumlah 175.00
K.20.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang Kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.001 Oh 60,000.00 30.00
Jumlah 7,030.00
Total 7,205.00

K.21 1 M2 Pasang Jendela Nako & Tralis


K.21.1 Bahan
Jendela Nako 1.100 M2 - -
Paku 1/2"-1" atau sekrup 0.020 Kg 8,750.00 175.00
Besi Strip 0.025 M2 - -
Jumlah 175.00
K.21.2 Tenaga
Pekerja 0.200 Oh 25,000.00 5,000.00
Tukang Kayu 0.200 Oh 40,000.00 8,000.00
Kepala tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.001 Oh 60,000.00 60.00
Jumlah 14,060.00
Total 14,235.00

K.22 1 M2 Pasang Seng Talang Datar


K.22.1 Bahan
Seng Plat 3"× 6" BJLS 1.000 Lbr 37,800.00 37,800.00
Paku biasa 1/2" - 1" 0.015 Kg 8,750.00 131.25
Kayu borneo, papan 0.010 M3 717,100.00 6,884.16
Flincote/ meni besi 0.280 Kg 12,300.00 3,444.00
Jumlah 48,259.41
K.22.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Besi 0.400 Oh 35,000.00 14,000.00
Kepala tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.001 Oh 60,000.00 75.00
Jumlah 19,075.00
Total 67,334.41

K.23 1 M' Pasang Talang Miring, Seng BJLS 28


K.23.1 Bahan
Seng plat 3' x 6' bjls 28 0.500 Lbr 37,800.00 18,900.00
Paku biasa 1/2" - 1" 0.015 Kg 8,750.00 131.25
Kayu borneo, papan 0.019 M3 717,100.00 13,624.90
Flincote/ meni besi 0.300 Kg 12,300.00 3,690.00
Jumlah 36,346.15
K.23.2 Tenaga
Pekerja 0.040 Oh 25,000.00 1,000.00
Tukang kayu 0.400 Oh 40,000.00 16,000.00
Kepala tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.001 Oh 60,000.00 75.00
Jumlah 18,325.00
Total 54,671.15

K.24 1 M' Pasang Talang 1/2 lingkaran D-10 cm, Seng BJLS 28
K.24.1 Bahan
Seng plat 3' x 6' bjls 28 0.300 Lbr 37,800.00 11,340.00
Paku biasa 1/2" - 1" 0.100 Kg 8,750.00 875.00
Kayu borneo, papan 0.019 M3 717,100.00 13,624.90
Besi Strip 0.500 Kg - -
Jumlah 25,839.90
K.24.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.250 Oh 40,000.00 10,000.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 86


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Kepala tukang 0.025 Oh 50,000.00 1,250.00


Mandor 0.001 Oh 60,000.00 75.00
Jumlah 15,075.00
Total 40,914.90

K.25 1 M' Pasang Talang 1/2 lingkaran D-10 cm, Seng BJLS 24
K.25.1 Bahan
Seng plat 3' x 6' bjls 28 0.300 Lbr 37,800.00 11,340.00
Paku biasa 1/2" - 1" 0.100 Kg 8,750.00 875.00
Kayu borneo, papan 0.019 M3 717,100.00 13,624.90
Besi Strip 0.500 Kg - -
Jumlah 25,839.90
K.25.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang kayu 0.250 Oh 40,000.00 10,000.00
Kepala tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.001 Oh 60,000.00 75.00
Jumlah 15,075.00
Total 40,914.90

L. ANALISA BIAYA PEKERJAAN KUNCI DAN KACA

L.1 1 Buah Pasang Kunci Tanam Antik


L.1.1 Bahan
Kunci tanam antik 1.000 Bh - -
Jumlah -
L.1.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang Kayu 0.600 Oh 40,000.00 24,000.00
Kepala tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 28,680.00
Total 28,680.00

L.2 1 Buah Pasang Kunci Tanam Biasa


L.2.1 Bahan
Kunci tanam biasa 1.000 Bh - -
Jumlah -
L.2.2 Tenaga
Pekerja 0.010 Oh 25,000.00 250.00
Tukang Kayu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.005 Oh 60,000.00 300.00
Jumlah 21,050.00
Total 21,050.00

L.3 1 Buah Pasang Kunci Tanam Kamar Mandi


L.3.1 Bahan
Kunci tanam kamar mandi 1.000 Bh - -
Jumlah -
L.3.2 Tenaga
Pekerja 0.005 Oh 25,000.00 125.00
Tukang Kayu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.005 Oh 50,000.00 250.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 20,525.00
Total 20,525.00

L.4 1 Buah Pasang Kunci Silinder


L.4.1 Bahan
Kunci silinder 1.000 Bh - -
Jumlah -
L.4.2 Tenaga
Pekerja 0.005 Oh 25,000.00 125.00
Tukang Kayu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.005 Oh 50,000.00 250.00
Mandor 0.000 Oh 60,000.00 15.00
Jumlah 20,390.00
Total 20,390.00

L.5 1 Buah Pasang Engsel Pintu


L.5.1 Bahan
Engsel pintu 1.000 Bh - -
Jumlah -
L.5.2 Tenaga
Pekerja 0.015 Oh 25,000.00 375.00
Tukang Kayu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,170.00
Total 7,170.00

L.6 1 Buah Pasang Engsel Jendela kupu-kupu


L.6.1 Bahan
Engsel jendela 1.000 Bh - -
Jumlah -
L.6.2 Tenaga
Pekerja 0.010 Oh 25,000.00 250.00
Tukang Kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.001 Oh 60,000.00 30.00
Jumlah 4,780.00
Total 4,780.00

L.7 1 Buah Pasang Engsel Angin


L.7.1 Bahan
Engsel angin 1.000 Bh - -
Jumlah -

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 87


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

L.7.2 Tenaga
Pekerja 0.020 Oh 25,000.00 500.00
Tukang Kayu 0.200 Oh 40,000.00 8,000.00
Kepala tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 10,100.00
Total 10,100.00

L.8 1 Buah Pasang Spring Knip


L.8.1 Bahan
Spring knip 1.000 Bh - -
Jumlah -
L.8.2 Tenaga
Pekerja 0.015 Oh 25,000.00 375.00
Tukang Kayu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,170.00
Total 7,170.00

L.9 1 Buah Pasang Kait Angin


L.9.1 Bahan
Kait angin 1.000 Bh - -
Jumlah -
L.9.2 Tenaga
Pekerja 0.015 Oh 25,000.00 375.00
Tukang Kayu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,170.00
Total 7,170.00

L.10 1 Buah Pasang door closer


L.10.1 Bahan
Door closer 1.000 Bh - -
Jumlah -
L.10.2 Tenaga
Pekerja 0.050 Oh 25,000.00 1,250.00
Tukang Kayu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.050 Oh 50,000.00 2,500.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 23,900.00
Total 23,900.00

L.11 1 Buah Pasang Kunci Selot


L.11.1 Bahan
Kunci selot 1.000 Bh - -
Jumlah -
L.11.2 Tenaga
Pekerja 0.020 Oh 25,000.00 500.00
Tukang Kayu 0.200 Oh 40,000.00 8,000.00
Kepala tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.001 Oh 60,000.00 60.00
Jumlah 9,560.00
Total 9,560.00

L.12 1 Buah Pasang Pegangan Pintu/Door holder


L.12.1 Bahan
Door holder 1.000 Bh - -
Jumlah -
L.12.2 Tenaga
Pekerja 0.050 Oh 25,000.00 1,250.00
Tukang Kayu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.050 Oh 50,000.00 2,500.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 23,900.00
Total 23,900.00

L.13 1 Buah Pasang door stop


L.13.1 Bahan
Door stop 1.000 Bh - -
Jumlah -
L.13.2 Tenaga
Pekerja 0.010 Oh 25,000.00 250.00
Tukang Kayu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.010 Oh 50,000.00 500.00
Mandor 0.001 Oh 60,000.00 30.00
Jumlah 4,780.00
Total 4,780.00

L.14 1 Buah Pasang Rel Pintu Dorong


L.14.1 Bahan
Rel Pintu Dorong 1.000 Bh - -
Jumlah -
L.14.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang Kayu 0.600 Oh 40,000.00 24,000.00
Kepala tukang 0.060 Oh 50,000.00 3,000.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 28,680.00
Total 28,680.00

L.15 1 Buah Pasang Kunci Lemari


L.15.1 Bahan
Kunci Lemari 1.000 Bh - -
Jumlah -
L.15.2 Tenaga
Pekerja 0.025 Oh 25,000.00 625.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 88


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Tukang Kayu 0.250 Oh 40,000.00 10,000.00


Kepala tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.001 Oh 60,000.00 75.00
Jumlah 11,950.00
Total 11,950.00

L.16 1 M2 Pasang Kaca, tebal 3 mm


L.16.1 Bahan
Kaca 1.100 M2 - -
Jumlah -
L.16.2 Tenaga
Pekerja 0.015 Oh 25,000.00 375.00
Tukang Kayu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,170.00
Total 7,170.00

L.17 1 M2 Pasang Kaca, tebal 5 mm


L.17.1 Bahan
Kaca 1.100 M2 - -
Jumlah -
L.17.2 Tenaga
Pekerja 0.015 Oh 25,000.00 375.00
Tukang Kayu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,170.00
Total 7,170.00

L.18 1 M2 Pasang Kaca, tebal 8mm


L.18.1 Bahan
Kaca 1.100 M2 - -
Jumlah -
L.18.2 Tenaga
Pekerja 0.017 Oh 25,000.00 412.50
Tukang Kayu 0.165 Oh 40,000.00 6,600.00
Kepala tukang 0.017 Oh 50,000.00 825.00
Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,882.50
Total 7,882.50

L.19 1 M2 Pasang Kaca Buram, tebal 12 mm


L.19.1 Bahan
Kaca Buram 1.100 M2 - -
Sealent 0.050 Kg - -
Jumlah -
L.19.2 Tenaga
Pekerja 0.025 Oh 25,000.00 625.00
Tukang Kayu 0.250 Oh 40,000.00 10,000.00
Kepala tukang 0.025 Oh 50,000.00 1,250.00
Mandor 0.001 Oh 60,000.00 75.00
Jumlah 11,950.00
Total 11,950.00

L.20 1 M2 Pasang Kaca Cermin, tebal 5 mm


L.20.1 Bahan
Kaca cermin 1.100 M2 - -
Jumlah -
L.20.2 Tenaga
Pekerja 0.015 Oh 25,000.00 375.00
Tukang Kayu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,170.00
Total 7,170.00

L.21 1 M2 Pasang Kaca Cermin, tebal 6mm


L.21.1 Bahan
Kaca cermin 1.100 M2 - -
Jumlah -
L.21.2 Tenaga
Pekerja 0.015 Oh 25,000.00 375.00
Tukang Kayu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,170.00
Total 7,170.00

L.22 1 M2 Pasang Kaca Cermin, tebal 8mm


L.22.1 Bahan
Kaca cermin 1.100 M2 - -
Jumlah -
L.22.2 Tenaga
Pekerja 0.017 Oh 25,000.00 412.50
Tukang Kayu 0.017 Oh 40,000.00 660.00
Kepala tukang 0.017 Oh 50,000.00 825.00
Mandor 0.001 Oh 60,000.00 48.00
Jumlah 1,945.50
Total 1,945.50

L.23 1 M2 Pasang Kaca "wireglass", tebal 5 mm


L.23.1 Bahan
Kaca wireglass 1.100 M2 - -
Jumlah -
L.23.2 Tenaga
Pekerja 0.015 Oh 25,000.00 375.00
Tukang Kayu 0.150 Oh 40,000.00 6,000.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 89


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Kepala tukang 0.015 Oh 50,000.00 750.00


Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,170.00
Total 7,170.00

L.24 1 M2 Pasang Kaca Patri /painting, tebal 5 mm


L.24.1 Bahan
Kaca patri 1.100 M2 - -
Jumlah -
L.24.2 Tenaga
Pekerja 0.015 Oh 25,000.00 375.00
Tukang Kayu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.001 Oh 60,000.00 45.00
Jumlah 7,170.00
Total 7,170.00

M ANALISA BIAYA PEKERJAAN PENUTUP LANTAI DAN DINDING

M.1 1 M2 Pasang Lantai Ubin pc abu-abu ukuran 40 X 40 cm


M.1.1 Bahan
Ubin abu-abu 40 x 40 cm 6.630 Bh - -
Semen portland 9.800 Kg 820.00 8,036.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Jumlah 9,743.10
M.1.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 12,400.00
Total 22,143.10

M.2 1 M2 Pasang Lantai Ubin pc abu-abu ukuran 30 X 30 cm


M.2.1 Bahan
Ubin abu-abu 30 X 30 cm 11.870 Bh - -
Semen portland 10.000 Kg 820.00 8,200.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Jumlah 9,907.10
M.2.2 Tenaga
Pekerja 0.260 Oh 25,000.00 6,500.00
Tukang Batu 0.125 Oh 40,000.00 5,000.00
Kepala tukang 0.013 Oh 50,000.00 625.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 12,905.00
Total 22,812.10

M.3 1 M2 Pasang Lantai Ubin pc abu-abu ukuran 20 X 20 cm


M.3.1 Bahan
Ubin abu-abu 20 X 20 cm 26.500 Bh - -
Semen portland 10.400 Kg 820.00 8,528.00
Pasir pasang 0.014 M3 79,400.00 1,071.90
Jumlah 9,599.90
M.3.2 Tenaga
Pekerja 0.270 Oh 25,000.00 6,750.00
Tukang Batu 0.130 Oh 40,000.00 5,200.00
Kepala tukang 0.013 Oh 50,000.00 650.00
Mandor 0.014 Oh 60,000.00 810.00
Jumlah 13,410.00
Total 23,009.90

M.4 1 M2 Pasang Lantai Ubin warna ukuran 40 X 40 cm


M.4.1 Bahan
Ubin abu-abu 40 X 40 cm 6.630 Bh - -
Semen portland 8.160 Kg 820.00 6,691.20
Pasir pasang 0.023 M3 79,400.00 1,826.20
Semen warna 0.900 Kg - -
Jumlah 8,517.40
M.4.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 12,400.00
Total 20,917.40

M.5 1 M2 Pasang Lantai Ubin warna ukuran 30 X 30 cm


M.5.1 Bahan
Ubin warna 30 X 30 cm 11.870 Bh - -
Semen portland 8.360 Kg 820.00 6,855.20
Pasir pasang 0.023 M3 79,400.00 1,826.20
Semen warna 0.900 Kg - -
Jumlah 8,681.40
M.5.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 12,400.00
Total 21,081.40

M.6 1 M2 Pasang Lantai Ubin warna ukuran 20 X 20 cm


M.6.1 Bahan
Ubin warna 20 X 20 cm 26.500 Bh - -
Semen portland 8.760 Kg 820.00 7,183.20
Pasir pasang 0.023 M3 79,400.00 1,826.20
Semen warna 0.900 Kg - -

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 90


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Jumlah 9,009.40
M.6.2 Tenaga
Pekerja 0.270 Oh 25,000.00 6,750.00
Tukang Batu 0.130 Oh 40,000.00 5,200.00
Kepala tukang 0.013 Oh 50,000.00 650.00
Mandor 0.014 Oh 60,000.00 810.00
Jumlah 13,410.00
Total 22,419.40

M.7 1 M2 Pasang Lantai Ubin Teraso ukuran 40 X 40 cm


M.7.1 Bahan
Ubin teraso 40 X 40 cm 6.250 Bh - -
Semen portland 8.800 Kg 820.00 7,216.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Semen warna 0.900 Kg - -
Jumlah 8,923.10
M.7.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 12,400.00
Total 21,323.10

M.8 1 M2 Pasang Lantai Ubin Teraso ukuran 30 X 30 cm


M.8.1 Bahan
Ubin teraso 30 X 30 cm 1.870 Bh - -
Semen portland 10.000 Kg 820.00 8,200.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Semen warna 1.540 Kg - -
Jumlah 9,907.10
M.8.2 Tenaga
Pekerja 0.260 Oh 25,000.00 6,500.00
Tukang Batu 0.125 Oh 40,000.00 5,000.00
Kepala tukang 0.013 Oh 50,000.00 625.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 12,905.00
Total 22,812.10

M.9 1 M2 Pasang Lantai Ubin Granito ukuran 40 X 40 cm


M.9.1 Bahan
Ubin granito 40 X 40 cm 6.930 Bh - -
Semen portland 9.800 Kg 820.00 8,036.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Semen warna 1.300 Kg - -
Jumlah 9,743.10
M.9.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 12,400.00
Total 22,143.10

M.10 1 M2 Pasang Lantai Ubin Granito ukuran 30 X 30 cm


M.10.1 Bahan
Ubin granito 30 X 30 cm 11.870 Bh - -
Semen portland 10.000 Kg 820.00 8,200.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Semen warna 1.500 Kg - -
Jumlah 9,907.10
M.10.2 Tenaga
Pekerja 0.260 Oh 25,000.00 6,500.00
Tukang Batu 0.125 Oh 40,000.00 5,000.00
Kepala tukang 0.013 Oh 50,000.00 625.00
Mandor 0.013 Oh 60,000.00 780.00
Jumlah 12,905.00
Total 22,812.10

M.11 1 M2 Pasang Lantai Ubin Teralux Kerang uk. 40 X 40 cm


M.11.1 Bahan
Ubin teralux kerang 40 X 40 cm 6.250 Bh - -
Semen portland 8.800 Kg 820.00 7,216.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Semen warna 1.300 Kg - -
Jumlah 8,923.10
M.11.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 12,400.00
Total 21,323.10

M.12 1 M2 Pasang Lantai Ubin Teralux Kerang uk. 30 X 30 cm


M.12.1 Bahan
Ubin teralux kerang 30 X 30 cm 11.807 Bh - -
Semen portland 10.000 Kg 820.00 8,200.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Semen warna 1.125 Kg - -
Jumlah 9,907.10
M.12.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 12,400.00
Total 22,307.10

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 91


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

M.13 1 M2 Pasang Lantai Ubin Teralux Marmer uk. 60 X 60 cm


M.13.1 Bahan
Ubin teralux marmer 60 X 60 cm 5.600 Bh - -
Semen portland 8.190 Kg 820.00 6,715.80
Pasir pasang 0.045 M3 79,400.00 3,573.00
Semen warna 1.000 Kg - -
Jumlah 10,288.80
M.13.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.013 Oh 60,000.00 750.00
Jumlah 12,400.00
Total 22,688.80

M.14 1 M2 Pasang Lantai Ubin Teralux Marmer uk. 40 X 40 cm


M.14.1 Bahan
Ubin teralux marmer 40 X 40 cm 6.250 Bh - -
Semen portland 8.800 Kg 820.00 7,216.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Semen warna 1.300 Kg - -
Jumlah 8,923.10
M.14.2 Tenaga
Pekerja 0.672 Oh 25,000.00 16,800.00
Tukang Batu 0.224 Oh 40,000.00 8,960.00
Kepala tukang 0.022 Oh 50,000.00 1,100.00
Mandor 0.034 Oh 60,000.00 2,040.00
Jumlah 28,900.00
Total 37,823.10

M.15 1 M2 Pasang Lantai Ubin Teralux Marmer uk. 30 X 30 cm


M.15.1 Bahan
Ubin teralux marmer 30 X 30 cm 11.870 Bh - -
Semen portland 10.000 Kg 820.00 8,200.00
Pasir pasang 0.022 M3 79,400.00 1,707.10
Semen warna 1.500 Kg - -
Jumlah 9,907.10
M.15.2 Tenaga
Pekerja 0.700 Oh 25,000.00 17,500.00
Tukang Batu 0.340 Oh 40,000.00 13,600.00
Kepala tukang 0.034 Oh 50,000.00 1,700.00
Mandor 0.035 Oh 60,000.00 2,100.00
Jumlah 34,900.00
Total 44,807.10

M.16 1 M' Pasang Plint Ubin Pc abu-abu ukuran 15 X 20 cm


M.16.1 Bahan
Plint Ubin 15 X 20 cm 5.300 Bh - -
Semen portland 1.560 Kg 820.00 1,279.20
Pasir pasang 0.004 M3 79,400.00 317.60
Jumlah 1,596.80
M.16.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang Batu 0.030 Oh 40,000.00 1,200.00
Kepala tukang 0.003 Oh 50,000.00 150.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 3,030.00
Total 4,626.80

M.17 1 M' Pasang Plint Ubin pc abu-abu ukuran 10 X 30 cm


M.17.1 Bahan
Plint Ubin 10 X 30 cm 3.530 Bh - -
Semen portland 1.560 Kg 820.00 1,279.20
Pasir pasang 0.003 M3 79,400.00 238.20
Jumlah 1,517.40
M.17.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang Batu 0.030 Oh 40,000.00 1,200.00
Kepala tukang 0.003 Oh 50,000.00 150.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 3,030.00
Total 4,547.40

M.18 1 M' Pasang Plint Ubin pc abu-abu ukuran 10 X 40 cm


M.18.1 Bahan
Plint Ubin 10 X 40 cm 2.650 Bh - -
Semen portland 1.560 Kg 820.00 1,279.20
Pasir pasang 0.003 M3 79,400.00 238.20
Jumlah 1,517.40
M.18.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang Batu 0.030 Oh 40,000.00 1,200.00
Kepala tukang 0.003 Oh 50,000.00 150.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 3,030.00
Total 4,547.40

M.19 1 M' Pasang Plint Ubin pc warna ukuran 10 X 20 cm


M.19.1 Bahan
Plint Ubin pc warna 10 X 20 cm 5.300 Bh - -
Semen portland 1.200 Kg 820.00 984.00
Pasir pasang 0.003 M3 79,400.00 238.20
Semen warna 0.190 Kg - -
Jumlah 1,222.20
M.19.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang Batu 0.030 Oh 40,000.00 1,200.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 92


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Kepala tukang 0.003 Oh 50,000.00 150.00


Mandor 0.003 Oh 60,000.00 180.00
Jumlah 3,030.00
Total 4,252.20

M.20 1 M' Pasang Plint Ubin pc warna ukuran 10 X 30 cm


M.20.1 Bahan
Plint Ubin pc warna 10 X 30 cm 3.330 Bh - -
Semen portland 1.650 Kg 820.00 1,353.00
Pasir pasang 0.003 M3 79,400.00 254.08
Semen warna 0.100 Kg - -
Jumlah 1,607.08
M.20.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang Batu 0.030 Oh 40,000.00 1,200.00
Kepala tukang 0.003 Oh 50,000.00 150.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 3,030.00
Total 4,637.08

M.21 1 M' Pasang Plint Ubin pc warna ukuran 10 X 40 cm


M.21.1 Bahan
Plint Ubin pc warna 10 X 40 cm 2.650 Bh - -
Semen portland 1.200 Kg 820.00 984.00
Pasir pasang 0.003 M3 79,400.00 238.20
Semen warna 0.100 Kg - -
Jumlah 1,222.20
M.21.2 Tenaga
Pekerja 0.080 Oh 25,000.00 2,000.00
Tukang Batu 0.040 Oh 40,000.00 1,600.00
Kepala tukang 0.004 Oh 50,000.00 200.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 4,040.00
Total 5,262.20

M.22 1 M' Pasang Plint Ubin Teraso ukuran 10 X 30 cm


M.22.1 Bahan
Plint Ubin teraso 10 X 30 cm 3.530 Bh - -
Semen portland 1.560 Kg 820.00 1,279.20
Pasir pasang 0.003 M3 79,400.00 238.20
Semen warna 0.190 Kg - -
Jumlah 1,517.40
M.22.2 Tenaga
Pekerja 0.080 Oh 25,000.00 2,000.00
Tukang Batu 0.040 Oh 40,000.00 1,600.00
Kepala tukang 0.004 Oh 50,000.00 200.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 4,040.00
Total 5,557.40

M.23 1 M' Pasang Plint Ubin Teraso ukuran 10 X 40 cm


M.23.1 Bahan
Plint Ubin teraso 10 X 40 cm 2.650 Bh - -
Semen portland 1.200 Kg 820.00 984.00
Pasir pasang 0.003 M3 79,400.00 238.20
Semen warna 0.100 Kg - -
Jumlah 1,222.20
M.23.2 Tenaga
Pekerja 0.080 Oh 25,000.00 2,000.00
Tukang Batu 0.040 Oh 40,000.00 1,600.00
Kepala tukang 0.004 Oh 50,000.00 200.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 4,040.00
Total 5,262.20

M.24 1 M' Pasang Plint Ubin Granito ukuran 10 X 40 cm


M.24.1 Bahan
Plint Ubin granito 10 X 40 cm 2.650 Bh - -
Semen portland 1.200 Kg 820.00 984.00
Pasir pasang 0.003 M3 79,400.00 238.20
Semen warna 0.100 Kg - -
Jumlah 1,222.20
M.24.2 Tenaga
Pekerja 0.060 Oh 25,000.00 1,500.00
Tukang Batu 0.030 Oh 40,000.00 1,200.00
Kepala tukang 0.003 Oh 50,000.00 150.00
Mandor 0.003 Oh 60,000.00 180.00
Jumlah 3,030.00
Total 4,252.20

M.25 1 M' Pasang Plint Ubin Granito ukuran 10 X 30 cm


M.25.1 Bahan
Plint Ubin granito 10 X 30 cm 3.330 Bh - -
Semen portland 1.650 Kg 820.00 1,353.00
Pasir pasang 0.003 M3 79,400.00 254.08
Semen warna 0.100 Kg - -
Jumlah 1,607.08
M.25.2 Tenaga
Pekerja 0.900 Oh 25,000.00 22,500.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 26,820.00
Total 28,427.08

M.26 1 M' Pasang Plint ubin teralux kerang uk. 10 X 40 cm


M.26.1 Bahan
Plint Ubin teralux kerang 10 X 40 cm 2.500 Bh - -

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 93


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Semen portland 1.650 Kg 820.00 1,353.00


Pasir pasang 0.003 M3 79,400.00 254.08
Semen warna 0.100 Kg - -
Jumlah 1,607.08
M.26.2 Tenaga
Pekerja 0.900 Oh 25,000.00 22,500.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 26,820.00
Total 28,427.08

M.27 1 M' Pasang Plint Ubin Teralux Kerang uk. 10 X 30 cm


M.27.1 Bahan
Plint Ubin teralux kerang 10 X 30 cm 3.330 Bh - -
Semen portland 1.650 Kg 820.00 1,353.00
Pasir pasang 0.003 M3 79,400.00 254.08
Semen warna 0.100 Kg - -
Jumlah 1,607.08
M.27.2 Tenaga
Pekerja 0.900 Oh 25,000.00 22,500.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 26,820.00
Total 28,427.08

M.28 1 M' Pasang Plint Ubin Teralux Marmer uk. 10 X 60 cm


M.28.1 Bahan
Plint Ubin teralux marmer 10 X 60 cm 1.700 Bh - -
Semen portland 1.650 Kg 820.00 1,353.00
Pasir pasang 0.003 M3 79,400.00 254.08
Semen warna 0.100 Kg - -
Jumlah 1,607.08
M.28.2 Tenaga
Pekerja 0.900 Oh 25,000.00 22,500.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 26,820.00
Total 28,427.08

M.29 1 M' Pasang Plint Ubin Teralux Marmer uk. 10 X 40 cm


M.29.1 Bahan
Plint Ubin teralux marmer 10 X 40 cm 2.500 Bh - -
Semen portland 1.650 Kg 820.00 1,353.00
Pasir pasang 0.003 M3 79,400.00 254.08
Semen warna 0.100 Kg - -
Jumlah 1,607.08
M.29.2 Tenaga
Pekerja 0.900 Oh 25,000.00 22,500.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 26,820.00
Total 28,427.08

M.30 1 M' Pasang Plint Ubin Teralux Marmer uk. 10 X 30 cm


M.30.1 Bahan
Plint Ubin teralux marmer 10 X 30 cm 3.330 Bh - -
Semen portland 1.650 Kg 820.00 1,353.00
Pasir pasang 0.003 M3 79,400.00 254.08
Semen warna 0.100 Kg - -
Jumlah 1,607.08
M.30.1 Tenaga
Pekerja 0.900 Oh 25,000.00 22,500.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 26,820.00
Total 28,427.08

M.31 1 M2 Pasang teraso cor ditempat


M.31.1 Bahan
Bahan teraso cor 0.004 M3 - -
Jumlah -
M.31.2 Tenaga
Pekerja 0.900 Oh 25,000.00 22,500.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 26,820.00
Total 26,820.00

M.32 1 M2 Pasang Teralux cor ditempat, tebal 3 cm


M.32.1 Bahan
Bahan teralux cor 0.004 M3 - -
Jumlah -
M.32.2 Tenaga
Pekerja 0.900 Oh 25,000.00 22,500.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 26,820.00
Total 26,820.00

M.33 1 M2 Pasang Ubin Tahan Asam


M.33.1 Bahan

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 94


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Ubin tahan asam 1.050 M2 - -


Semen tahan asam 14.140 Kg - -
Pasir 0.040 M3 79,400.00 3,176.00
Jumlah 3,176.00
M.33.2 Tenaga
Pekerja 0.270 Oh 25,000.00 6,750.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.014 Oh 60,000.00 810.00
Jumlah 14,310.00
Total 17,486.00

M.34 1 M2 Pasang Lantai Keramik Artistik 10 X 20 cm


M.34.1 Bahan
Ubin keramik artistik 10 X 20 cm 50.000 Bh - -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40
M.34.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.35 1 M2 Pasang Lantai Keramik Artistik 10 X 10 cm


M.35.1 Bahan
Ubin keramik artistik 10 X 10 cm 50.000 Bh -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 2.000 Kg - -
Jumlah 12,666.40
M.35.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.36 1 M2 Pasang Lantai Keramik Artistik 5 X 20 cm


M.36.1 Bahan
Ubin keramik artistik 5 X 20 cm 100.000 Bh -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40
M.36.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.37 1 M' Pasang Plint Keramik Artistik 10 X 20 cm


M.37.1 Bahan
Plint keramik artistik 10 X 20 cm 5.000 Bh - -
Semen portland 1.650 Kg 820.00 1,353.00
Pasir pasang 0.003 M3 79,400.00 254.08
Semen warna 0.100 Kg - -
Jumlah 1,607.08
M.37.2 Tenaga
Pekerja 0.090 Oh 25,000.00 2,250.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 6,570.00
Total 8,177.08

M.38 1 M' Pasang Plint Keramik Artistik 10 X 10 cm


M.38.1 Bahan
Plint keramik artistik 10 X 10 cm 0.000 Bh - -
Semen portland 1.650 Kg 820.00 1,353.00
Pasir pasang 0.003 M3 79,400.00 254.08
Semen warna 0.120 Kg - -
Jumlah 1,607.08
M.38.2 Tenaga
Pekerja 0.090 Oh 25,000.00 2,250.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00
Mandor 0.005 Oh 60,000.00 270.00
Jumlah 6,570.00
Total 8,177.08

M.39 1 M' Pasang Plint Keramik Artistik 5 X 20 cm


M.39.1 Bahan
Plint keramik artistik 5 X 20 cm 5.000 Bh - -
Semen portland 0.850 Kg 820.00 697.00
Pasir pasang 0.002 M3 79,400.00 174.68
Semen warna 0.080 Kg - -
Jumlah 871.68
M.39.2 Tenaga
Pekerja 0.090 Oh 25,000.00 2,250.00
Tukang Batu 0.090 Oh 40,000.00 3,600.00
Kepala tukang 0.009 Oh 50,000.00 450.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 95


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Mandor 0.005 Oh 60,000.00 270.00


Jumlah 6,570.00
Total 7,441.68
M.40 1 M' Internal cove artistik ( 5 X 5 X 20 ) cm
M.40.1 Bahan
Internal cove 5 X 5 X 20 cm 10.000 Bh - -
Semen portland 1.415 Kg 820.00 1,160.30
Pasir pasang 0.039 M3 79,400.00 3,096.60
Semen warna 1.200 Kg - -
Jumlah 4,256.90
M.40.2 Tenaga
Pekerja 0.750 Oh 25,000.00 18,750.00
Tukang Batu 0.450 Oh 40,000.00 18,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.038 Oh 60,000.00 2,250.00
Jumlah 41,250.00
Total 45,506.90

M.41 1 M' Pasang Plint Vinyl tanpa adukan


M.41.1 Bahan
Lt vinyl karet 30 X 30 Kw l 3.500 Bh - -
Lem vinyl 0.080 Kg - -
Jumlah -
M.41.2 Tenaga
Pekerja 0.080 Oh 25,000.00 2,000.00
Tukang Batu 0.080 Oh 40,000.00 3,200.00
Kepala tukang 0.008 Oh 50,000.00 400.00
Mandor 0.004 Oh 60,000.00 240.00
Jumlah 5,840.00
Total 5,840.00

M.42 1 M2 Pasang Lantai Keramik 10 X 20 cm


M.42.1 Bahan
Ubin keramik artistik 10 X 20 cm 50.000 Bh - -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40
M.42.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.43 1 M2 Pasang Lantai Keramik Artistik 15 X 15 cm


M.43.1 Bahan
Ubin keramik 15 X 15 cm 44.000 Bh - -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40
M.43.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.44 1 M2 Pasang Lantai Keramik 20 X 20 cm


M.44.1 Bahan
Ubin keramik 20 x 20 cm 25.000 Bh - -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40
M.44.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.45 1 M2 Pasang Lantai Keramik Artistik 25 X 25 cm


M.45.1 Bahan
Ubin keramik 25 X 25 cm 16.000 Bh - -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40
M.45.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.46 1 M2 Pasang Lantai Keramik 15 X 20 cm


M.46.1 Bahan
Ubin keramik 15 X 20 cm 35.000 Bh - -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 96


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

M46.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.47 1 M2 Pasang Lantai Keramik 33 x 33 cm


M.47.1 Bahan
Ubin keramik 33 X 33 cm 10.000 Bh - -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40
M.47.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.48 1 M2 Pasang Lantai Keramik 33 x 33 cm Anti Slip


M.48.1 Bahan
Ubin keramik 33 X 33 cm anti slip 10.000 Bh - -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40
M.48.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.49 1 M2 Pasang Lantai Keramik 10 x 33 cm


M.49.1 Bahan
Ubin keramik 10 X 33 cm 33.000 Bh - -
Semen portland 11.380 Kg 820.00 9,331.60
Pasir pasang 0.042 M3 79,400.00 3,334.80
Semen warna 1.500 Kg - -
Jumlah 12,666.40
M.49.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,716.40

M.50 1 M2 Pasang Lantai Mosaik 30 X 30 cm, ex lokal


M.50.1 Bahan
Mosaik 30 x 30 cm 12.000 Bh - -
Semen portland 14.150 Kg 820.00 11,603.00
Pasir pasang 0.039 M3 79,400.00 3,096.60
Semen warna 2.000 Kg - -
Jumlah 14,699.60
M.50.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 47,749.60

M.51 1 M2 Pasang Lantai Marmer


M.51.1 Bahan
Marmer 1.052 Bh - -
Semen portland 14.150 Kg 820.00 11,603.00
Pasir pasang 0.039 M3 79,400.00 3,096.60
Semen warna 2.000 Kg - -
Jumlah 14,699.60
M.51.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 47,749.60

M.52 1 M2 Pasang Lantai Karpet 100 % wool


M.52.1 Bahan
Feltex carpet 100 % wool T - 21 1.050 M2 - -
Lem vinyl 0.350 Kg - -
Jumlah -
M.52.2 Tenaga
Pekerja 0.170 Oh 25,000.00 4,250.00
Tukang 0.170 Oh 40,000.00 6,800.00
Kepala tukang 0.017 Oh 50,000.00 850.00
Mandor 0.009 Oh 60,000.00 510.00
Jumlah 12,410.00
Total 12,410.00

M.53 1 M2 Pasang Lantai Karpet 80 % wool, 20 % nylon


M.53.1 Bahan

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 97


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Carpet 80 % wool, 20 % nylon 1.050 M2 - -


Lem vinyl 0.350 Kg - -
Jumlah -
M.53.2 Tenaga
Pekerja 0.170 Oh 25,000.00 4,250.00
Tukang 0.170 Oh 40,000.00 6,800.00
Kepala tukang 0.017 Oh 50,000.00 850.00
Mandor 0.009 Oh 60,000.00 510.00
Jumlah 12,410.00
Total 12,410.00

M.54 1 M2 Pasang Underlyer, tebal 6 mm


M.54.1 Bahan
Underlyer tebal 6 mm/ rubber corugated 1.050 M2 -
Jumlah -
M.54.2 Tenaga
Pekerja 0.120 Oh 25,000.00 3,000.00
Tukang 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 8,760.00
Total 8,760.00

M.55 1 M2 Pasang Lantai Karpet


M.55.1 Bahan
Carpet 1.050 M3 - -
Lem vinyl 0.350 Kg - -
Jumlah -
M.55.2 Tenaga
Pekerja 0.170 Oh 25,000.00 4,250.00
Tukang 0.170 Oh 40,000.00 6,800.00
Kepala tukang 0.017 Oh 50,000.00 850.00
Mandor 0.009 Oh 60,000.00 510.00
Jumlah 12,410.00
Total 12,410.00

M.56 1 M2 Pasang Lantai Parquet Jati


M.56.1 Bahan
Parquet jati 1.050 M2 - -
Lem vinyl 0.600 Kg - -
Jumlah -
M.56.2 Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.033 Oh 60,000.00 1,950.00
Jumlah 33,950.00
Total 33,950.00

M.57 1 M2 Pasang Gymfloor


M.57.1 Bahan
Gymfloor 1.050 M2 - -
Lem vinyl 0.600 Kg - -
Jumlah -
M.57.2 Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.033 Oh 60,000.00 1,950.00
Jumlah 33,950.00
Total 33,950.00

M.58 1 M2 Pasang Dinding Porselin 11 X 11 cm, putih


M.58.1 Bahan
Porselin 11 x 11 cm 83.000 Bh - -
Semen abu - abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.58.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.050 Oh 50,000.00 2,500.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 39,800.00
Total 48,855.20

M.59 1 M2 Pasang Dinding Porselin 11 X 11 cm, warna


M.59.1 Bahan
Porselin 11 x11 cm warna 83.000 Bh - -
Semen abu - abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.59.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.050 Oh 50,000.00 2,500.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 39,800.00
Total 48,855.20

M.60 1 M2 Pasang Dinding Porselin 15 x 15 cm, putih


M.60.1 Bahan
Porselin 15 x15 cm, putih 45.000 Bh - -
Semen abu - abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 98


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Jumlah 9,055.20
M.60.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.450 Oh 40,000.00 18,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 37,050.00
Total 46,105.20

M.61 1 M2 Pasang Dinding Porselin 15 x 15 cm, warna


M.61.1 Bahan
Porselin 15 x15 cm, warna 45.000 Bh - -
Semen abu - abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.61.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.450 Oh 40,000.00 18,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 37,050.00
Total 46,105.20

M.62 1 M2 Pasang Dinding Porselin 10 x 20 cm, warna


M.62.1 Bahan
Porselin 10 x 20 cm, warna 50.000 Bh - -
Semen abu - abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.62.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.450 Oh 40,000.00 18,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 37,050.00
Total 46,105.20

M.63 1 M2 Pasang Dinding Porselin 20 x 20 cm, warna


M.63.1 Bahan
Porselin 20 x 20 cm warna 25.000 Bh - -
Semen abu - abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.63.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.450 Oh 40,000.00 18,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 37,050.00
Total 46,105.20

M.64 1 M2 Pasang Dinding Keramik Artistik 10 X 20 cm


M.64.1 Bahan
Keramik artistik 10 X 20 cm 100.000 M2 - -
Semen abu - abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.64.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.450 Oh 40,000.00 18,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 37,050.00
Total 46,105.20

M.65 1 M2 Pasang Dinding Keramik Artistik 5 X 20 cm


M.65.1 Bahan
Keramik artistik 5 X 20 cm 100.000 M2 - -
Semen abu - abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.65.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.450 Oh 40,000.00 18,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 37,050.00
Total 46,105.20

M.66 1 M2 Pasang Dinding Keramik 10 X 20 cm


M.66.1 Bahan
Keramik 10 X 20 cm 50.000 M2 - -
Semen abu-abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.66.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.450 Oh 40,000.00 18,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 37,050.00
Total 46,105.20

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 99


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

M.67 1 M2 Pasang Dinding Keramik 15 X 15 cm


M.67.1 Bahan
Keramik 15 X 15 cm 45.000 M2 - -
Semen abu-abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.67.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.450 Oh 40,000.00 18,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 37,050.00
Total 46,105.20
M.68 1 M2 Pasang Dinding Keramik 20 X 20 cm
M.68.1 Bahan
Keramik 20 X 20 cm 25.000 M2 - -
Semen abu-abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.68.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.100 Oh 40,000.00 4,000.00
Kepala tukang 0.045 Oh 50,000.00 2,250.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 23,050.00
Total 32,105.20

M.69 1 M2 Pasang Dinding Keramik 10 X 20 cm


M.69.1 Bahan
Keramik 10 X 20 cm 50.000 M2 - -
Semen abu-abu 9.300 Kg 820.00 7,626.00
Pasir pasang 0.018 M3 79,400.00 1,429.20
Semen warna 1.500 Kg - -
Jumlah 9,055.20
M.69.2 Tenaga
Pekerja 0.600 Oh 25,000.00 15,000.00
Tukang Batu 0.125 Oh 40,000.00 5,000.00
Kepala tukang 0.013 Oh 50,000.00 625.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 22,425.00
Total 31,480.20

M.70 1 M2 Pasang Dinding Marmer


M.70.1 Bahan
Marmer 1.020 M2 - -
Paku pancing 60 x 230 2.000 Bh - -
Semen abu-abu 12.440 Kg 820.00 10,200.80
Pasir pasang 0.025 M3 79,400.00 1,985.00
Semen warna 1.500 Kg - -
Jumlah 12,185.80
M.70.2 Tenaga
Pekerja 0.720 Oh 25,000.00 18,000.00
Tukang Batu 0.650 Oh 40,000.00 26,000.00
Kepala tukang 0.065 Oh 50,000.00 3,250.00
Mandor 0.035 Oh 60,000.00 2,100.00
Jumlah 49,350.00
Total 61,535.80

M.71 1 M2 Pasang Dinding Bata Pelapis 7 x 3 x 24 cm


M.71.1 Bahan
Bata pelapis dinding 60.000 Bh - -
Semen abu-abu 12.440 Kg 820.00 10,200.80
Pasir pasang 0.025 M3 79,400.00 1,985.00
Jumlah 12,185.80
M.71.2 Tenaga
Pekerja 0.650 Oh 25,000.00 16,250.00
Tukang Batu 0.500 Oh 40,000.00 20,000.00
Kepala tukang 0.050 Oh 50,000.00 2,500.00
Mandor 0.300 Oh 60,000.00 18,000.00
Jumlah 56,750.00
Total 68,935.80

M.72 1 M2 Pasang Dinding Bata Klinker 5 x 5 x 24 cm


M.72.1 Bahan
Bata pelapis klinker 80.000 Bh - -
Semen abu-abu 12.440 Kg 820.00 10,200.80
Pasir pasang 0.025 M3 79,400.00 1,985.00
Jumlah 12,185.80
M.72.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,235.80

M.73 1 M2 Pasang Dinding Batu Paros


M.73.1 Bahan
Batu paros 1.050 M2 - -
Semen abu-abu 11.750 Kg 820.00 9,635.00
Pasir pasang 0.035 M3 79,400.00 2,779.00
Jumlah 12,414.00
M.73.2 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 100


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Kepala tukang 0.035 Oh 50,000.00 1,750.00


Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,464.00

M.74 1 M2 Pasang Dinding Batu Tempel Hitam


M.74.1 Bahan
Batu tempel hitam 1.050 M2 - -
Semen abu-abu 11.750 Kg 820.00 9,635.00
Pasir pasang 0.035 M3 79,400.00 2,779.00
Jumlah 12,414.00
M.74.1 Tenaga
Pekerja 0.620 Oh 25,000.00 15,500.00
Tukang Batu 0.350 Oh 40,000.00 14,000.00
Kepala tukang 0.035 Oh 50,000.00 1,750.00
Mandor 0.030 Oh 60,000.00 1,800.00
Jumlah 33,050.00
Total 45,464.00

M.75 1 M2 Pasang Lantai vinyl karet 30 x 30 cm KL I


M.75.1 Bahan
Vinyl karet 30 x 30 cm KL I 11.050 Bh - -
Lem vinyl 0.350 Kg - -
Jumlah -
M.75.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.008 Oh 60,000.00 450.00
Jumlah 10,950.00
Total 10,950.00

M.76 1 M2 Pasang Lantai vinyl karet 30 x 30 cm KL II


M.76.1 Bahan
Vinyl karet 30 x 30 cm KL II 11.050 Bh - -
Lem vinyl 0.350 Kg - -
Jumlah -
M.76.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.008 Oh 60,000.00 450.00
Jumlah 10,950.00
Total 10,950.00

M.77 1 M2 Pasang Lantai vinyl asbes 30 x 30 cm


M.77.1 Bahan
Vinyl asbes 30 x 30 cm 11.050 Bh - -
Lem vinyl 0.350 Kg - -
Jumlah -
M.77.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.008 Oh 60,000.00 450.00
Jumlah 10,950.00
Total 10,950.00

M.78 1 M2 Pasang Lantai vinyl motif kembang 30 x 30 cm


M.78.1 Bahan
Vinyl motif kembang 30 x 30 cm 11.050 Bh - -
Lem vinyl 0.350 Kg - -
Jumlah -
M.78.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang Batu 0.150 Oh 40,000.00 6,000.00
Kepala tukang 0.015 Oh 50,000.00 750.00
Mandor 0.008 Oh 60,000.00 450.00
Jumlah 10,950.00
Total 10,950.00

M.79 1 M2 Pasang Wall Covering lebar 50 cm


M.79.1 Bahan
Vinyl wall covering, lebar 50 cm 1.100 M2 - -
Lem 0.250 Kg - -
Jumlah -
M.79.2 Tenaga
Pekerja 0.750 Oh 25,000.00 18,750.00
Tukang Batu 0.170 Oh 40,000.00 6,800.00
Kepala tukang 0.017 Oh 50,000.00 850.00
Mandor 0.009 Oh 60,000.00 510.00
Jumlah 26,910.00
Total 26,910.00

M.80 1 M2 Floor Hardener Ferrovax


M.80.1 Bahan
Floor hardener ferrovax 3.000 Kg - -
Jumlah -
M.80.2 Tenaga
Pekerja 0.120 Oh 25,000.00 3,000.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 8,760.00
Total 8,760.00

M.81 1 M2 Floor Hardener Mastercron


M.81.1 Bahan

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 101


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Mastercron "S" 5.000 Kg - -


Jumlah -
M.81.2 Tenaga
Pekerja 0.120 Oh 25,000.00 3,000.00
Tukang Batu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 8,760.00
Total 8,760.00

M.82 1 M2 Plint Kayu 2 x 10 cm


M.82.1 Bahan
Kayu jati papan 0.002 M3 - -
Paku skrup 3,5" 0.050 Kg 350.00 17.50
Jumlah 17.50
M.82.2 Tenaga
Pekerja 0.120 Oh 25,000.00 3,000.00
Tukang kayu 0.120 Oh 40,000.00 4,800.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 8,760.00
Total 8,777.50

N ANALISA BIAYA KONSTRUKSI PEKERJAAN PENGECATAN

N.1 1 M2 Mengikis/ mengerok Permukaan Cat Tembok Lama


N.1.1 Bahan
Soda api 0.050 Kg - -
Jumlah -
N.1.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang cat 0.000 Oh 35,000.00 -
Kepala tukang 0.000 Oh 50,000.00 -
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 3,900.00
Total 3,900.00

N.2 1 M2 Mencuci Bidang Permukaan Tembok yg pernah dicat


N.2.1 Bahan
Sabun 0.050 Kg - -
Jumlah -
N.2.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang cat 0.000 Oh 35,000.00 -
Kepala tukang 0.000 Oh 50,000.00 -
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 3,900.00
Total 3,900.00

N.3 1 M2 Mengerok Karat Cat Lama Permukaan Baja dgn Cara Manual
N.3.1 Bahan
Sabun 0.050 Kg - -
Jumlah -
N.3.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang cat 0.000 Oh 35,000.00 -
Kepala tukang 0.000 Oh 50,000.00 -
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 3,900.00
Total 3,900.00

N.4 1 M2 Menyabun Permukaan Tembok Lama


N.4.1 Bahan
Sabun 0.050 Kg - -
Jumlah -
N.4.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang cat 0.000 Oh 35,000.00 -
Kepala tukang 0.000 Oh 50,000.00 -
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 3,900.00
Total 3,900.00

N.5 1 M2 Mengerok Karat atau Cat Lama Permukaan Baja dgn


Panca Pasir (Sanblasting) dgn Tingkat Kebersihan Sa 2,5
N.5.1 Bahan
Pasir silika 40.000 Kg - -
BBM 10.000 Ltr - -
Jumlah -
N.5.2 Sewa peralatan
Kompresor, balsting pot, selang dan nozzle hari -
Jumlah -
N.5.3 Tenaga
Pekerja 1.600 Oh 25,000.00 40,000.00
Tukang cat 1.600 Oh 35,000.00 56,000.00
Kepala tukang 0.800 Oh 50,000.00 40,000.00
Mandor 0.500 Oh 60,000.00 30,000.00
Jumlah 166,000.00
Total 166,000.00

N.6 1 M2 Mendempul dan Menggosok Kayu


N.6.1 Bahan
Dempul jadi 0.080 Kg - -
Minyak cat 0.020 Kg - -
Batu apung 0.010 Kg -
Jumlah -
N.6.2 Tenaga

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 102


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Pekerja 0.040 Oh 25,000.00 1,000.00


Tukang cat 0.040 Oh 35,000.00 1,400.00
Kepala tukang 0.004 Oh 50,000.00 200.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 2,750.00
Total 2,750.00

N.7 1 M2 Pengecatan Bidang Kayu Lama


N.7.1 Bahan
Plamir 0.150 Kg - -
Cat dasar 0.170 Kg - -
Cat penutup 0.170 Kg - -
Jumlah -
N.7.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang cat 0.075 Oh 35,000.00 2,625.00
Kepala tukang 0.008 Oh 50,000.00 375.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 4,900.00
Total 4,900.00

N.8 1 M2 Pengecatan Bid. Kayu Baru (1 lapis plamir), 1 lapis cat dasar,
2 lapis cat penutup
N.8.1 Bahan
Cat Meni 0.200 Kg - -
Plamir 0.150 Kg - -
Cat dasar 0.170 Kg - -
Cat penutup 2 kali 0.260 Kg - -
Jumlah -
N.8.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang cat 0.009 Oh 35,000.00 315.00
Kepala tukang 0.006 Oh 50,000.00 300.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 2,515.00
Total 2,515.00

N.9 1 M2 Pengecatan Besi, 1 lapis cat dasar, 2 lapis cat penutup


N.9.1 Bahan
Cat Meni 0.200 Kg 12,300.00 2,460.00
Plamir 0.150 Kg -
Cat dasar 0.170 Kg 28,700.00 4,879.00
Cat penutup 2 kali 0.260 Kg 28,700.00 7,462.00
Jumlah 14,801.00
N.9.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang cat 0.009 Oh 35,000.00 315.00
Kepala tukang 0.006 Oh 50,000.00 300.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 2,515.00
Total 17,316.00

N.10 1 M2 Pengecatan Bid. Kayu Baru (1 lapis plamir), 1 lapis cat dasar,
3 lapis cat penutup
N.10.1 Bahan
Cat Meni 0.200 Kg - -
Plamir 0.150 Kg - -
Cat dasar 0.170 Kg - -
Cat penutup 3 kali 0.350 Kg - -
Jumlah -
N1.10.2 Tenaga
Pekerja 0.070 Oh 25,000.00 1,750.00
Tukang cat 0.105 Oh 35,000.00 3,675.00
Kepala tukang 0.004 Oh 50,000.00 200.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 5,775.00
Total 5,775.00

N.11 1 M2 Pelaburan Bidang Kayu dengan Teak Oil


N.11.1 Bahan
Teak oil 0.360 Ltr - -
Jumlah -
N.11.2 Tenaga
Pekerja 0.040 Oh 25,000.00 1,000.00
Tukang cat 0.063 Oh 35,000.00 2,205.00
Kepala tukang 0.063 Oh 50,000.00 3,150.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 6,505.00
Total 6,505.00

N.12 1 M2 Pelaburan Bidang Kayu dengan Politur


N.12.1 Bahan
Politur 0.150 Ltr - -
Politur jadi 0.372 Ltr - -
Ampelas 2.000 Lbr - -
Jumlah -
N.12.2 Tenaga
Pekerja - Oh 25,000.00 -
Tukang cat 0.060 Oh 35,000.00 2,100.00
Kepala tukang 0.016 Oh 50,000.00 800.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 3,050.00
Total 3,050.00

N.13 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter


N.13.1 Bahan
Residu atau ter 0.350 Ltr 2,600.00 910.00
Jumlah 910.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 103


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

N.13.2 Tenaga
Pekerja 0.100 Oh 25,000.00 2,500.00
Tukang cat - Oh 35,000.00
Kepala tukang - Oh 50,000.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 2,860.00
Total 3,770.00

N.14 1 M2 Pelaburan Bidang Kayu dengan Vernis


N.14.1 Bahan
Vernis 0.150 Ltr - -
Dempul 0.050 Kg - -
Ampelas 0.100 Lbr - -
Kuas 0.010 Bh 4,000.00 40.00
Jumlah 40.00
N.14.2 Tenaga
Pekerja 0.160 Oh 25,000.00 4,000.00
Tukang cat 0.160 Oh 35,000.00 5,600.00
Kepala tukang 0.016 Oh 50,000.00 800.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 10,550.00
Total 10,590.00

N.15 1 M2 Pengecatan Tembok Baru


(1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
N.15.1 Bahan
Plamir 0.100 Kg 10,250.00 1,025.00
Cat dasar 0.100 Kg 12,500.00 1,250.00
Cat penutup 2 kali 0.260 Kg 12,500.00 3,250.00
Jumlah 5,525.00
N.15.2 Tenaga
Pekerja 0.020 Oh 25,000.00 500.00
Tukang cat 0.063 Oh 35,000.00 2,205.00
Kepala tukang 0.006 Oh 50,000.00 315.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 3,170.00
Total 8,695.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 104


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

N.16 1 M2 pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
N.16.1 Bahan
Cat dasar 0.120 Kg - -
Cat penutup 2 kali 0.180 Kg - -
Jumlah -
N.16.2 Tenaga
Pekerja 0.028 Oh 25,000.00 700.00
Tukang cat 0.042 Oh 35,000.00 1,470.00
Kepala tukang 0.004 Oh 50,000.00 210.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 2,530.00
Total 2,530.00

N.17 1 M2 Melabur Tembok dengan Kalkarium


N.17.1 Bahan
Kalkarium 0.100 Kg - -
Jumlah -
N.17.2 Tenaga
Pekerja 0.028 Oh 25,000.00 700.00
Tukang cat 0.042 Oh 35,000.00 1,470.00
Kepala tukang 0.004 Oh 50,000.00 210.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 2,530.00
Total 2,530.00

N.18 1 M2 Melabur Tembok dengan Kapur Sirih


N.18.1 Bahan
Ampelas 0.100 Lbr - -
Alang-alang 0.250 Ikat - -
Perancah kayu 0.002 M3 - -
Kapur sirih 0.150 Kg - -
Jumlah -
N.18.2 Tenaga
Pekerja 0.150 Oh 25,000.00 3,750.00
Tukang cat 0.001 Oh 35,000.00 35.00
Kepala tukang 0.000 Oh 50,000.00 5.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 3,940.00
Total 3,940.00

N.19 1 M2 Melabur Tembok Lama dgn Kapur Sirih ( utk pemeliharaan )


N.19.1 Bahan
Perancah kayu 0.002 M3 - -
Kapur sirih 0.300 Kg - -
Jumlah -
N.19.2 Tenaga
Pekerja 0.040 Oh 25,000.00 1,000.00
Tukang cat 0.005 Oh 35,000.00 175.00
Kepala tukang 0.001 Oh 50,000.00 25.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 1,350.00
Total 1,350.00

N.20 1 M2 Pemasangan dengan Wall paper


N.20.1 Bahan
Wall paper 1.200 M3 - -
Perekat 0.200 Kg - -
Jumlah -
N.20.2 Tenaga
Pekerja 0.020 Oh 25,000.00 500.00
Tukang cat 0.200 Oh 35,000.00 7,000.00
Kepala tukang 0.002 Oh 50,000.00 100.00
Mandor 0.003 Oh 60,000.00 150.00
Jumlah 7,750.00
Total 7,750.00

N.21 1 M2 Pengecatan Permukaan Baja dengan Meni Besi


N.21.1 Bahan
Meni besi 0.100 Kg 12,300.00 1,230.00
Kuas 0.010 Bh 4,000.00 40.00
Jumlah 1,270.00
N.21.2 Tenaga
Pekerja 0.020 Oh 25,000.00 500.00
Tukang cat 0.200 Oh 35,000.00 7,000.00
Kepala tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 9,100.00
Total 10,370.00

N.22 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah


N.22.1 Bahan
Meni besi 0.100 Kg 12,300.00 1,230.00
Kuas 0.010 Bh 4,000.00 40.00
Perancah kayu 0.002 M3 - -
Jumlah 1,270.00
N.22.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang cat 0.225 Oh 35,000.00 7,875.00
Kepala tukang 0.023 Oh 50,000.00 1,125.00
Mandor 0.008 Oh 60,000.00 450.00
Jumlah 15,700.00
Total 16,970.00

N.23 1 M2 Pengecatan Permukaan Baja lapis Seng (galbani) secara Manual


Sistem 4 lapis Cat Konvensional dgn tebal 200 um
N.23.1 Bahan
Meni (read lead ) A 0.100 Kg 12,300.00 1,230.00
Meni (read lead ) B 0.100 Kg 12,300.00 1,230.00

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 105


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN

JUMLAH HARGA SATUAN


NO JENIS PEKERJAAN KOEF STN HARGA BAHAN
(Rp) (Rp)

Aluminium C 0.040 Kg -
Aluminium B 0.040 Kg -
Pengencer 0.010 Ltr - -
Perancah kayu 0.002 M3 - -
Jumlah 2,460.00
N.23.2 Tenaga
Pekerja 0.006 Oh 25,000.00 150.00
Tukang cat 0.006 Oh 35,000.00 210.00
Kepala tukang 0.023 Oh 50,000.00 1,125.00
Mandor 0.008 Oh 60,000.00 450.00
Jumlah 1,935.00
Total 4,395.00

N.24 1 M2 Pengecatan Permukaan Baja Lapis Seng (galbani) secara Manual


Sistem 1 Lapis Cat Mutakhir dgn tebal 200 um
N.24.1 Bahan
Cat 0.300 Kg 28,700.00 8,610.00
Jumlah 8,610.00
N.24.2 Tenaga
Pekerja 0.006 Oh 25,000.00 150.00
Tukang cat 0.060 Oh 35,000.00 2,100.00
Kepala tukang 0.012 Oh 50,000.00 600.00
Mandor 0.006 Oh 60,000.00 360.00
Jumlah 3,210.00
Total 11,820.00

N.25 1 M2 Pengecatan Permukaan Baja Lapis Seng (galbani) secara Manual


Sistem 3 Lapis Cat Konvensional dgn tebal 200 um
N.25.1 Bahan
Cat dasar 0.110 Kg -
Cat antara 0.170 Kg -
Cat Penutup 0.080 Kg -
Jumlah -
N.25.2 Tenaga
Pekerja 0.500 Oh 25,000.00 12,500.00
Tukang cat 0.800 Oh 35,000.00 28,000.00
Kepala tukang 0.300 Oh 50,000.00 15,000.00
Mandor 0.200 Oh 60,000.00 12,000.00
Jumlah 67,500.00
Total 67,500.00

N.26 1 M2 Pengecatan Permukaan Baja Lapis Seng (galbani) secara Semprot


(airless sptay) dgn Sistem 1 Lapis Cat Mutakhir dgn tebal 200 um
N.26.1 Bahan
Cat dasar 0.300 Kg -
Jumlah -
N.26.2 Tenaga
Pekerja 0.400 Oh 25,000.00 10,000.00
Tukang cat 0.700 Oh 35,000.00 24,500.00
Kepala tukang 0.200 Oh 50,000.00 10,000.00
Mandor 0.200 Oh 60,000.00 12,000.00
Jumlah 56,500.00
Total 56,500.00

O ANALISA BIAYA KONSTRUKSI PEKERJAAN PINTU BESI

O.1 1 M2 Membuat Kusen & Daun Pintu Plat Baja


O.1.1 Bahan
Kusen & Daun Pintu Plat Baja 1.050 m2 966,165.00 1,014,473.25
meni besi 0.010 Kg 12,300.00 123.00
Jumlah 1,014,596.25
O.1.2 Tenaga
Pekerja 0.250 Oh 25,000.00 6,250.00
Tukang Besi 0.250 Oh 35,000.00 8,750.00
Kepala tukang 0.020 Oh 50,000.00 1,000.00
Mandor 0.010 Oh 60,000.00 600.00
Jumlah 16,600.00
Total 1,031,196.25

O.2 1 UNIT RESAPAN Ø 1.00 M x 2.00 M


Galian Tanah 3.077 m3 16,270.00 50,066.04
Pasangan Bata 1 : 3 0.377 m3 103,294.40 38,921.33
Bata merah 1.130 m3 300.00 339.12
Plat Tutup Beton 0.094 m3 -
Ijuk 20.000 kg - -
Jumlah 89,326.49
Total 89,326.49

O.3 1 UNIT SEPTICKTANK 1.00 M x 2.100 M x 100 M


Galian Tanah 3.500 m3 16,270.00 56,945.00
Pasangan Bata 1 : 3 0.984 m3 103,294.40 101,641.69
Plesteran 16.400 m2 19,172.20 314,424.08
Kolom 12/12 & Ring Balk 12/12 0.351 m3 4,906,273.08 1,723,868.11
Plat Tutup Beton 0.252 m3 -
Rabatan 8 cm 0.168 m3 45,525.20 7,648.23
Pipa Udara 2.000 m' 3,708.00 7,416.00
Jumlah 2,211,943.11
Total 2,211,943.11

Analisa SNI Standart Sipil Proyek .....................04/13/2019 Hal : 106


DAFTAR HARGA BAHAN SIPIL
NAMA PROYEK : Pembangunan Rumah Persemayanan
PEKERJAAN : ……………………………………………………………
TAHUN ANGGARAN : 2006

HSPK
NO NAMA BAHAN SAT
Rp.

BATU
1 1 M' Pagar sementara dari kayu tinggi 2 meter M3 139,672.45
2 1 M' Pagar sementara dari sebng gelombang tinggi 2 mete M3 144,167.45
3 1 M' Pagar sementara dari kawat duri tinggi 1,80 meter M3 30,272.55
4 1 M' Pengukuran dan pemasangan bouwplank M3 36,547.50
5 1 M2 Pembuatan kantor sementara , dengan lantai pleste M3 626,049.50
6 1 M2 Pembuatan gudang semen dan alat alat M3 551,455.00
7 1 M2 Pembuatan rumah jaga / konstruksi kayu M3 651,986.40
8 1 M2 Membersihkan lapangan dan perataan M3 5,500.00
9 1 M2 Pembuatan bedeng buruh M3 508,183.90
10 1 M2 Pembuatan bak adukan ukuran 40 x 50 x 20 cm M3 1,472,925.60
11 1 M2 Pembuatan Stegger dari bambu M3 7,810.00
12 1 M2 Pembuatan jalan sementara M3 55,842.00
13 1 M3 Bongkaran beton bertulang M2 186,655.00
14 1 M3 Bongkaran dinding tembok bata merah Kg 168,655.00
15 1 M2 Pasang pagar kawat jaring galvanis panjang 240 cm Kg 2,840.00
16 1 M ' Pasang pagar beton pracetak ( 5 x 50 x 213 cm ) M2 77,788.50
1 M2 Bongkaran Atap Zincalum M2 13,100.00
1 M2 Bongkaran Screning Alumunium M2 15,500.00

B PEKERJAAN TANAH
1 M3 Galian tanah biasa sedalam 1 meter M3 16,270.00
1 M3 Galian tanah biasa sedalam 2 meter M3 16,270.00
1 M3 Galian tanah biasa sedalam 1.5 meter M3 29,017.50
1 M3 Galian tanah biasa sedalam 3 meter M3 22,755.00
1 M3 Galian tanah keras sedalam 1 meter M3 19,345.00
1 M3 galian tanah cadas sedalam 1 meter M3 38,750.00
1 M3 Galian tanah lumpur sedalam 1 meter M3 25,555.00
1 M2 Pekerjaan stripping setinggi 1 meter M3 1,550.00
1 M3 Pembuangan tanah sejauh 150 meter M3 15,900.00
1 Ttk Bor Strouss 2 m Ttk 38,000.00
1 M3 Urugan kembali M3 5,940.00
1 M3 Pemadatan tanah M3 15,500.00
1 M3 Urugan pasir M3 88,020.00
1 M3 Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL M3 101,597.30
1 M3 Lapisan pudel campuran 1 Kp : 5 TL M3 90,475.00
1 M3 Pemasangan lapisan ijuk M3 4,650.00
1 M3 Urugan sirtu M3 81,550.00
1 M2 Pembuatan jalan sementara tebal 25 cm M2 69,343.50

C PEKERJAAN PONDASI
1 M3 Pasang pondasi batu kali,1 PC : 1 Ps M3 539,341.60
1 M3 Pasang pondasi batu kali,1 PC : 2 Ps M3 411,910.00
1 M3 Pasang pondasi batu kali,1 PC : 2,5 Ps M3 539,341.60
1 M3 Pasang pondasi batu kali,1 PC : 3 Ps M3 397,119.00
1 M3 Pasang pondasi batu kali,1 PC : 4 Ps M3 367,918.00
1 M3 Pasang pondasi batu kali,1 PC : 5 Ps M3 347,683.60
1 M3 Pasang pondasi batu kali,1 PC : 6 Ps M3 333,453.40
1 M3 Pasang pondasi batu kali,1 PC : 8 Ps M3 312,133.40
1 M3 Pasang pondasi batu kali,1Kp : 1 Sm, : 1 Ps M3 238,167.35
1 M3 Pasang pondasi batu kali,1Kp : 1 Sm, : 2 Ps M3 221,453.50
1 M3 Pasang pondasi batu kali,1 PC : 1/4 Kp : 4 Ps M3 367,259.60
1 M3 Pasang pondasi batu kali,1 PC : 3 Kp : 10 Ps M3 282,054.80
1 M3 Pasang pondasi batu kali,1/4 PC : 1 Kp : 4 Ps M3 268,116.20
1 M3 Pasang pondasi batu kosong M3 194,610.00
1 M3 Pasang pondasi siklop , 40 % batu kali M3 755,017.00
1 M3 Pasang pondasi sumuran , diameter 100 cm M3 481,981.50
1 M' Pembuatan tiang pancang (40 X40 ) Cm, beton bertu M' 419,278.10
1 M' Pembuatan tiang pancang ( 35 x 35 ) cm, beton bert M' 330,102.75

D PEKERJAAN DINDING
1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 1 Ps M2 126,239.20
1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 2 Ps M2 111,072.00
1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 3 Ps M2 103,294.40
1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 4 Ps M2 98,205.20
1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 5 Ps M2 95,352.80
1 M2 Pasangan bata merah tebal 1 bata ,1 PC : 6 Ps M2 95,352.80
1 M2 Pasangan bata merah tebal 1 bata, 1 PC : 3 Kp : 10 M2 84,660.10
1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 1 Ps M2 59,419.20
Harga Bahan Proyek ....... 04/13/2019 HAL : 107
HSPK
NO NAMA BAHAN SAT
Rp.
1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 2 Ps M2 52,956.20
1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 3 Ps M2 49,359.40
1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 4 Ps M2 47,244.20
1 M2 Pasangan batu merah tebal 1/2 bata , 1 PC : 5 Ps M2 45,910.60
1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 6 Ps M2 45,113.00
1 M2 Pasangan bata merah tebal 1/2 bata ,1 PC : 8 Ps M2 43,700.00
1 M2 Pasangan bata merah tebal 1/2 bata, 1 PC : 3 Kp : M2 42,060.00
1 M2 Pasangan Bata Merah tebal 1/2 Bata - 1 Kp : 1 Sm : M2 35,843.96
1 M2 Pasangan Bata Merah tebal 1/2 Bata - 1 Kp : 1 Sm : M2 36,634.68
1 M2 Pasangan Dinding Hollowblock ( HB 20 ) M2 41,151.20
1 M2 Pasangan Dinding Hollowblock ( HB 15 ) M2 35,636.20
1 M2 Pasangan Dinding Hollowblock ( HB 10 ) M2 31,443.80
1 M2 Pasangan Dinding conblock ( CB 20 ) M2 53,950.45
1 M2 Pasangan Dinding conblock ( CB 15 ) M2 32,829.50
1 M2 Pasangan Dinding conblock ( CB 10 ) M2 36,326.25
1 M2 Pasang Dinding Latei M2 42,850.50
1 M2 Pasang dinding roster / terawang ( 12 x 11 x 24 ) c M2 26,175.00
1 M2 Pasang bata berongga ukuran ( 5 x 11 x 24 ) cm M2 244,301.00
1 M2 Pasang Dinding Anyaman Bambu, Rangka Kayu M2 4,993.00

E PEKERJAAN PLESTERAN
1 M2 Plesteran 1 PC : 1 Ps , tebal 15 mm M2 23,976.60
1 M2 Plesteran 1 PC : 2 Ps , tebal 15 mm M2 20,686.20
1 M2 Plesteran 1 PC : 3 Ps , tebal 15 mm M2 19,172.20
1 M2 Plesteran 1 PC : 4 Ps , tebal 15 mm M2 18,202.00
1 M2 Plesteran 1 PC : 5 Ps , tebal 15 mm M2 17,639.20
1 M2 Plesteran 1 PC : 6 Ps , tebal 15 mm M2 17,193.80
1 M2 Plesteran 1 PC : 8 Ps , tebal 15 mm M2 16,617.20
1 M2 Plesteran 1 Pc : 0,5 Kp : 3 Ps, tb.15 mm M2 18,105.40
1 M2 Plesteran 1 Pc : 3 Kp : 10 Ps, tbl 15 mm M2 14,970.40
1 M2 Plesteran 0,5 Pc : 1 Kp : 4 Ps, tbl 15 mm M2 16,318.60
1 M2 Plesteran 1 Kp : 1 Sm : 1 Ps, tbl 15 mm M2 13,143.35
1 M2 Plesteran 1 Kp : 1 Sm : 2 Ps, tbl 15 mm M2 13,546.74
1 M2 Plesteran 1 PC : 3 Ps,tebal 20 mm M2 26,920.40
1 M2 Plesteran 1 PC : 4 Ps,tebal 20 mm M2 25,340.80
1 M2 Plesteran 1 PC : 5 Ps,tebal 20 mm M2 24,201.00
1 M2 Plesteran 1 PC : 6 Ps,tebal 20 mm M2 23,498.80
1 M2 Plesteran 1Kp:1Sm:2Ps - tb.20 mm M2 17,429.20
1 M2 Plesteran 1 PC : 2 Ps,tebal 25 mm M2 31,022.20
1 M2 Plesteran 1 PC : 3 Ps,tebal 25 mm M2 29,694.00
1 M2 Plesteran 1 PC : 4 Ps,tebal 25 mm M2 28,070.80
1 M2 Plesteran 1 PC : 5 Ps,tebal 25 mm M2 26,887.40
1 M2 Plesteran 1 PC : 2 Ps,tebal 30 mm M2 38,222.00
1 M2 Plesteran 1 PC : 3 Ps,tebal 30 mm M2 34,849.60
1 M2 Plesteran 1 PC : 4 Ps,tebal 30 mm M2 32,816.40
1 M2 Plesteran 1 PC : 5 Ps,tebal 30 mm M2 30,438.80
1 M2 Berapen 1 PC : 3 Ps,tebal 30 mm M2 14,844.80
1 M2 Berapen 1 PC : 5 Ps,tebal 15 mm M2 13,855.60
1 M2 Plesteran Beton 1 PC : 2 Ps,tebal 15 mm M2 25,335.20
1 M2 Plesteran Beton 1 PC : 3 Ps,tebal 15 mm M2 23,744.80
1 M2 Plesteran Skoning 1 PC : 2 Ps M2 5,533.80
1 M2 Plesteran Granito 1 PC warna : 2 Granito, tebal 10 M2 2,450.00
1 M2 Plesteran Teraso 1 PC warna : 2 batu teraso, tebal M2 21,750.00
1 M2 Plesteran Ciprat, 1 PC : 2 Ps M2 16,462.80
1 M2 Plesteran Siar Adukan 1 PC : 2 Ps M2 12,192.80
1 M2 Plesteran Waterproof Batacote 3 lapis M2 18,286.40

F PEKERJAAN KAYU
1 M3 Pasang kusen pintu dan jendela kayu jati M3 1,068,000.00
1 M3 Pasang kusen pintu dan jendela kayu kamper M3 988,000.00
1 M3 Pasang kusen pintu dan jendela kayu borneo M3 3,262,180.00
1 M3 Pasang kusen pintu dan jendela kayu damar laut M3 3,262,180.00
1 M2 Pasang pintu klamp kayu kamper M3 57,592.50
1 M2 Pasang pintu klamp kayu borneo M3 118,443.30
1 M2 Pasang pintu Panel kayu jati M3 140,500.00
1 M2 Pasang pintu panel kayu kamper M3 140,500.00
1 M2 Pasang pintu dan jendela kaca kayu jati M3 112,400.00
1 M2 Pasang pintu dan jendela kaca kayu kamper M3 112,400.00
1 M2 Pasang pintu dan jendela kaca kayu borneo M3 171,560.50
1 M2 Pasang pintu dan jendela jalusi kayu jati M3 178,000.00
1 M2 Pasang pintu dan jendela jalusi kayu kamper M3 190,000.00
1 M2 Pasang pintu Playwood rangkap,rangka kayu jati M3 107,107.50
1 M2 Pasang pintu Playwood rangkap,rangka kayu kamper M3 107,107.50
1 M2 Pasang jalusi mati kusen kayu jati M3 105,537.50
1 M2 Pasang jalusi mati kusen kayu kamper M3 105,537.50
1 M2 Pasang pintu plywood rangkap, rangka kayu borne M3 140,237.38

Harga Bahan Proyek ....... 04/13/2019 HAL : 108


HSPK
NO NAMA BAHAN SAT
Rp.
1 M2 Pasang pintu teakwood rangkap, rangka kayu jati M3 109,875.00
1 M2 Pasang pintu teakwood rangkap, rangka kayu kamp M3 109,875.00
1 M2 Pasang pintu playwood & formika, rangka kayu jati M3 137,975.00
1 M2 Pasang pintu playwood & formika, rangka kayu ka M3 137,975.00
1 M2 Pasang pintu teakwood & formika , rangka kayu jat M3 137,975.00
1 M2 Pasang pintu teakwood & formika, rangka kayu kamp M3 137,975.00
1 M2 Pasang pintu formika double , rangka kayu jati M3 148,075.00
1 M2 Pasang pintu formika double , rangka kayu kamper M3 148,075.00
1 M3 Pasang Konstruksi kuda - kuda kayu jati M3 660,200.00
1 M3 Pasang Konstruksi kuda - kuda kayu kamper M3 660,200.00
1 M3 Pasang Konstruksi kuda - kuda kayu borneo M3 13,501,365.00
1 M3 Pasang konstruksi kuda kuda kayu kruing M3 660,200.00
1 M2 Pasang kaso dan reng genteng kodok kayu kamper M3 8,837.50
1 M2 Pasang kaso dan reng genteng kodok kayu borneo M3 31,579.30
1 M2 Pasang kaso dan reng genteng monier kayu jati M3 8,837.50
1 M2 Pasang kaso dan reng genteng monier kayu kamper M3 8,837.50
1 M2 Pasang kaso dan reng genteng beton kayu borneo M3 35,369.60
1 M2 Pasang kaso dan reng atap sirap kayu kamper M3 10,810.00
1 M2 Pasang kaso dan reng atap sirap kayu borneo M3 323,509.75
1 M2 Pasang rangka langit langit (1.00 x 1.0 ) M, Kayu Ja M3 20,525.00
1 M2 Pasang rangka langit langit ( 1.00 x 1.00 ) M, Kay M3 20,525.00
1 M2 Pasang rangka langit langit ( 1.00 x 1.00 ) M, Kayu M3 43,266.80
1 M2 Pasang rangka langit langit ( 30 x 60 ) cm kayu jati M3 20,637.50
1 M2 Pasang rangka langit langit ( 30 x 60 ) cm, Kayu Kamper M3 20,637.50
1 M2 Pasang rangka langit langit ( 30 x 60 ) cm, Kayu Bo M3 64,225.95
1 M2 Pasang rangka langit langit ( 30 x 30 ) cm kayu jati M3 24,800.00
1 M2 Pasang rangka langit langit ( 30 x 30 ) cm, kayu k M3 24,800.00
1 M2 Pasang rangka langit-langit ( 30 x 30 ) cm , kayu b M3 75,969.05
1 M' Pasang lisplang ukuran ( 3 x 20 ) Cm kayu jati M 12,312.50
1 M' Pasang lisplang uk. ( 3 x 20 ) Cm kayu kamper M 12,312.50
1 M' Pasang lisplang ukuran ( 3 x 30 ) Cm kayu jati M 13,462.50
1 M' Pasang lisplang uk. ( 3 x 30 ) Cm kayu kamper M 13,462.50
1 M' Pasang lisplang uk. 2 x ( 3 x 20 ) Cm kayu kamper M 20,115.00
1 M' Pasang lisplang uk. 2 x ( 2 x 20 ) Cm kayu kamper M 10,615.00
1 M' Pasang lisplang uk. 2 x ( 2 x 20 ) Cm kayu borneo M 25,489.64
1 M2 Pasang rangka dinding pemisah kayu kamper M 29,525.00
1 M2 Pasang rangka dinding pemisah kayu borneo M2 78,312.53
1 M2 Pasang dinding pemisah teakwood rangkap, rangk M2 29,525.00
1 M2 Pasang dinding pemisah playwood rangkap, rangk M2 33,625.00
1 M2 Pasang dinding lambriziring dari papan jati M2 98,877.50
1 M2 Pasang Playwood tebal 4 mm untuk dinding M2 4,590.50
1 M' Pasang List Plafond kayu profil M 1,525.00

G PEKERJAAN BETON
1M3 Membuat beton tumbuk, 1Pc : 3 Ps : 5 Kr M3 390,970.50
1M3 Membuat beton tumbuk, 1Pc : 3 Ps : 6 Kr M3 377,747.00
1M3 Membuat beton tumbuk, 1Pc : 4 Ps : 6 Kr M3 358,680.50
1M3 Membuat lantai kerja beton tumbuk, 1Pc : 3 Ps : 5 K M3 45,525.20
1M3 Membuat beton bertulang , 1Pc : 2 Ps : 3 Kr M3 391,385.00
1M3 Membuat beton bertulang , 1Pc : 2 Ps : 4 Kr M3 439,045.00
1M3 Membuat beton bertulang , 1Pc : 2 Ps : 2,5 Kr M3 483,637.00
1M3 Membuat beton bertulang, 1Pc : 1,5 Ps : 3 Kr M3 455,157.00
1M3 Membuat beton bertulang , 1Pc : 1,5 Ps : 2,5 Kr M3 513,055.00
1M3 Membuat beton bertulang 1 Pc : 1 Ps : 2 Kr M3 575,177.00
1M3 Membuat tiang pancang prestressed beton M3 562,560.00
1M3 Membuat beton dengan puzzdith - 100 XR M3 482,197.50
1m3 Membuat beton bertulang , 1Pc : 2 Ps : 3 Kr M3 550,647.50
1m3 Membuat beton bertulang , 1Pc : 2 Ps : 4 Kr M3 522,047.50
1M3 Membuat beton bertulang, 1Pc : 1,5 Ps : 3 Kr M3 575,454.00
1M3 Membuat beton bertulang , 1Pc : 1,5 Ps : 2,5 Kr M3 596,366.00
1M3 Membuat beton bertulang 1 Pc : 1 Ps : 1 Kr M3 741,928.00
1M3 Membuat beton kedap air dengan strorox - 100 M3 596,366.00
1M' Memasang PVC Waterstop lebar 150 mm M 2,720.00
1M' Memasang PVC Waterstop lebar 200 mm M 2,945.00
1M' Memasang PVC Waterstop lebar 230 mm M 15,330.00
1M' Memasang PVC Waterstop lebar 250 mm M 15,330.00
1M' Memasang PVC Waterstop lebar 300 mm M 15,330.00
1M' Memasang PVC Waterstop lebar 320 mm M 15,330.00
1 Kg Pembesian dengan besi polos atau besi ulir KG 5,861.75
1 Kg Kabel presstressed polos / strands KG 435.50
1 Kg Jaring kawat baja KG 14,261.25
1 M2 Pasang bekisting untuk pondasi M2 51,519.00
1 M2 Pasang bekisting untuk sloof M2 55,104.50
1 M2 Pasang bekisting untuk kolom M2 130,641.25
1 M2 Pasang bekisting untuk balok M2 136,826.70
1 M2 Pasang bekisting untuk lantai M2 137,441.25
1 M2 Pasang bekisting untuk dinding M2 113,496.00
Harga Bahan Proyek ....... 04/13/2019 HAL : 109
HSPK
NO NAMA BAHAN SAT
Rp.
1 M2 Pasang bekisting untuk tangga M2 95,140.25
1 M3 Membuat beton dengan mutu K 175 M3 649,377.50
1 M3 Membuat beton dengan mutu K 225 M3 671,007.50
1 M3 Membuat beton dengan mutu K 275 M3 678,699.00
1 M2 Pasang jembatan cor M2 35,876.44
1 M3 membuat beton Pondasi Strouss Ø 30 M3 1,497,050.79
1 M3 membuat beton Pile Cap 120 x 120 x 40 M3 1,926,330.02
1 M3 membuat beton Sloof 20/30 M3 2,274,723.30
1 M3 membuat beton Kolom 15/15 (praktis) M3 4,906,273.08
1 M3 membuat beton Kolom 30/50 komposit (WF bahan l M3 2,190,509.77
1 M3 membuat beton Balok 15/15 (ring balk) M3 3,246,862.41
1 M3 Membuat pondasi beton bertulang ( 150 kg besi + be M3 1,551,352.50
1 M3 Membuat sloof beton bertulang ( 200 kg besi + bekisting ) M3 1,925,532.00
1 M3 Membuat kolom beton bertulang ( 300 kg besi + beki M3 3,475,142.50
1 M3 Membuat balok beton bertulang ( 200 kg besi + beki M3 2,697,038.00
1 M3 Membuat balok beton bertulang ( 150 kg besi + beki M3 2,522,817.50
1 M3 Membuat dinding beton bertulang ( 150 kg besi + be M3 2,459,335.50
1 M3 Membuat tangga beton bertulang ( 200 kg + bekisti M3 2,503,460.75
1 M' Membuat kolom penguat beton bertulang ( 11 X 11 M 54,526.45
1 M' Membuat ring balok beton bertulang ( 10 X 15 ) cm M 35,097.85

H PEKERJAAN PENUTUP ATAP


1 M2 Pas. Atap Genteng Palentong Kecil M2 7,630.00
1 M2 Pas. Atap Genteng Kodok / Glazzur M2 7,630.00
1 M2 Pas. Atap Genteng Pelentong Super / Besar M2 6,930.00
1 M2 Pas. Genteng Bubung Palentong M2 28,220.80
1 M' Pas. Bubung Genteng Kodok Glazuur M' 28,220.80
1 M' Pas. Bubung Genteng Pelentong Besar M' 28,220.80
1 M2 Pas. Rooflight Fiberglass ( 180 x 90 cm ) M2 7,462.50
1 M2 Pas. Atap Asbes Gel ( 2.5 x 0.92m )X 5 mm M2 7,380.00
1 M2 Pas. Atap Asbes Gel ( 2,25 x 0,92 m ) X 5 mm M2 7,380.00
1 M2 Pas. Atap Asbes Gel ( 2 x 0.92m) X 5 mm M2 7,070.00
1 M2 Pas. Atap Asbes Gel ( 1.8 x 0.92 m) X 5 mm M2 7,070.00
1 M2 Pas. Atap Asbes Gel ( 3 x 1.05m) X 4 mm M2 7,070.00
1 M2 Pas. Atap Asbes Gel ( 2.7 x 1.05 m ) X 4 mm M2 7,070.00
1 M2 Pas. Atap Asbes Gel ( 2.4 x 1.05 m ) X 4 mm M2 6,950.00
1 M2 Pas. Atap Asbes Gel ( 2.1 x 1.05 m ) X 4 mm M2 6,950.00
1 M2 Pas. Atap Asbes Gel ( 1.5 x 1.05 m ) X 4 mm M2 6,950.00
1 M2 Pas. Atap Asbes Gel ( 3 x 1.08 m) X 6 mm M2 6,950.00
1 M2 Pas. Atap Asbes Gel ( 2.7 x 1.08 m) X 6 mm M2 6,950.00
1 M2 Pas. Atap Asbes Gel ( 2.4 x 1.08 m) X 6 mm M2 6,950.00
1 M2 Pas. Atap Asbes Gel ( 2.1x 1.08 m ) X 6 mm M2 6,950.00
1 M2 Pas. Atap Asbes Gel ( 1.8 x 1.08 m ) X 6 mm M2 6,950.00
1 M2 Pas. Bubung Stel Gel ( 0.92 m ) M2 10,090.00
1 M2 Pas. Nok Stel Gelombang ( 1.05 m ) M2 10,090.00
1 M2 Pas. Nok Stel Gelombang ( 1.08 m ) M2 10,090.00
1 M2 Pas. Nok Paten ( 0.92 m' ) M2 10,090.00
1 M2 Pas. Nok Paten ( 1.05 m' ) M2 10,090.00
1 M2 Pas. Nok Paten 1,08 m M2 10,090.00
1 M2 Pas. Nok Stel Rata ( 0,92 m ) M2 10,090.00
1 M2 Pas. Nok Stel Rata ( 1,05 m ) M2 10,090.00
1 M2 Pas.atap Genteng Beton M2 10,407.50
1 M2 Pas.atap Genteng aspal M2 18,012.50
1 M2 Pas. Atap genteng metal M2 12,150.00
1 M2 Pas. Atap sirap M2 17,630.00
1 M2 Pas. Atap sirap M2 17,630.00
1 M2 Pas. Nok genteng beton M2 32,109.30
1 M2 Pas. Nok genteng aspal M2 21,805.53
1 m' Pasang nok genteng metal M 14,217.50
1 m' Pasang nok sirap M 21,408.70
1 m' Atap Seng Gelombang M 6,235.00
1 m' Pas. Atap Nok Seng M 7,660.00
1 m' Pas. Atap Aluminium M 34,510.00
1 m' Pas.nok Aluminium M 43,600.00
1 m' Pas. Aluminium foil / sisalation M 11,677.50
1 M2 Pasang atap Zincalum M2 76,093.75
1 M2 Pasang Glaswool M2 15,980.00
1 M2 Pasang Roof mash (kawat kasa) M2 13,480.00

I PEKERJAAN LANGIT - LANGIT


1 m2 langit langit asbes (1,00 X 1,00)M, tebal 6 m M2 3,990.00
1 m2 langit langit asbes (1,00 X 1,00)M, tebal 5 m M2 3,990.00
1 m2 langit langit asbes (1,00 X 1,00)M, tebal 4 mm M2 3,990.00
1 m2 langit langit asbes (1,00 X 1,00)M, tebal 3.5 mm M2 3,990.00
1 m2 langit langit akustik (30 X 30)CM, M2 7,080.00
1 M2 Langit-langit Akustik ( 30 X 60 ) cm M2 6,180.00

Harga Bahan Proyek ....... 04/13/2019 HAL : 110


HSPK
NO NAMA BAHAN SAT
Rp.
1 m2 Langit-langit Akustik ( 60 X 120 ) cm M2 6,180.00
1 M2 Langit-langit Plywood ( 30 X 60 ) cm, tebal 4 mm M2 6,460.00
1 M2 Langit-langit Plywood ( 30 X 60 ) cm, tebal 6mm M2 6,460.00
1 M2 Langit-langit Plywood ( 60 X 120 ) cm, tebal 4 mm M2 6,460.00
1 M2 Langit-langit Plywood ( 60 X 120 ) cm, tebal 6 mm M2 6,460.00
1 M2 Langit-langit Teakwood ( 30 X 60 ) cm, tebal 4mm M2 6,460.00
1 M2 Langit-langit Teakwood ( 60 X 120 ) cm, tebal 4 mm M2 6,460.00
1 M2 Langit langit lat kayu jati M2 32,617.50
1 M2 Langit langit lat kayu ramin M2 32,617.50
1 M2 Langit langit lat kayu kamper M2 32,617.50
1 M2 Langit- langit soft board M2 19,680.00
1 M2 Langit- langit akustik 60 X 120 cm + rangka allum M2 26,700.00
1 M' List Langit-Langit Kayu Profil M 3,782.50
1 M2 Langit-langit asbes (1 x 1) m, tebal 3.2 mm, rangka M2 28,045.20
1M2 Langit-Langit Playwood 4 mm + Rangka Kayu Borneo M2 42,578.30
1 M2 Langit-Langit Akustik ( 30 x 60 ) cm + Rangka Kay M2 42,298.30
1 M2 Langit-Langit Akustik ( 30 x 30 ) cm + Rangka Kayu M2 49,716.70
1 M2 Langit-Langit Gypsum board, tebal 9 mm M2 5,088.50
1 M2 Pasang lisplang Zincalum M2 74,593.75

J PEKERJAAN PIPA DAN SANITASI


Memasang 1 buah kloset duduk/ monoblok Bh 136,150.00
Memasang 1 buah kloset jongkok porselen Bh 175,314.00
Memasang 1 buah kloset jongkok teraso Bh 114,414.00
Memasang 1 buah urinoir Bh 81,714.00
Memasang 1 buah wastafel Bh 107,214.00
Memasang 1 buah bak mandi teraso volume 0,30 M3 Bh 97,535.88
Memasang 1 buah bak mandi Fibreglass volume 0.3 m2 Bh 186,600.00
Memasang 1 buah bak mandi batu bata volume 0,3 M3 Bh 401,996.40
Memasang 1 buah bak beton volume 1 M3 M3 7,003,300.00
Memasang 1m' Pipa beton, diameter 15 cm - 20 cm M 20,117.30
Memasang 1m' Pipa beton, diameter 30 cm - 100 cm M 37,239.80
Memasang 1 buah bak kontrol pasangan batu bata uk. (30 Bh 176,848.50
Memasang 1 buah bak kontrol pasangan batu bata uk. (45 Bh 155,865.00
Memasang 1 buah bak kontrol pasangan batu bata uk. (60 Bh 229,134.84
Memasang 1 m' pipa galvanis diameter 1/2" M 7,020.00
Memasang 1 m' pipa galvanis diameter 3/4" M 7,020.00
Memasang 1 m' pipa galvanis diameter 1" M 7,020.00
Memasang 1 m' pipa galvanis diameter 2" M 7,020.00
Memasang 1 m' pipa galvanis diameter 3" M 11,124.00
Memasang 1 m' pipa galvanis diameter 4" M 11,124.00
Memasang 1 m' pipa PVC tipe AW diameter 1/2" M 13,908.00
Memasang 1 m' pipa PVC tipe AW diameter 3/4" M 3,708.00
Memasang 1 m' pipa PVC tipe AW diameter 1" M 3,708.00
Memasang 1 m' pipa PVC tipe AW diameter 2" M 5,562.00
Memasang 1 m' pipa PVC tipe AW diameter 3" M 8,346.00
Memasang 1 m' pipa PVC tipe AW diameter 4" M 8,346.00
Memasang 1 m' pipa PVC tipe D 4" M 57,351.00
Memasang 1 buah bak cuci piring stainles steel Bh 14,340.00
Memasang 1 buah Bak Cuci Piring Teraso Bh 44,270.00
Memasang 1 bh kran diameter 3/4" atau 1/2" Bh 5,050.00
Memasang 1 bh Floor drain Bh 5,050.00

K PEKERJAAN BESI DAN ALLUMUNIUM


1Kg Pasang Rangka Atap Baja Kg 14,287.00
1Kg Pasang kolom WF memakai bahan lama Kg 14,287.00
1Kg Pasang Rangka Atap Baja Kg 16,542.00
1Kg Pasang Rangka Screening (bahan lama) Kg 16,542.00
1 Kg Fabrikasi & Pemasangan Besi Siku Kg 13,861.50
1M2 Pasang Pintu Besi Baja M2 44,170.00
1 M2 Pasang Jendela Besi M2 68,565.00
1 M2 Pasang Jendela Besi Tahan Api M2 72,130.00
1 M2 Pasang Pintu Gulung Besi M2 78,360.00
1 M2 Pasang Pintu Lipat M2 68,562.00
1 M2 Pasang Pintu Sunscreen Allumunium M2 34,240.00
1 M2 Pasang Rolling door M2 84,312.00
1 M2 Pasang Pintu Alumunium M2 84,312.00
1M2 Pasang Venetions blinds M2 28,105.00

Harga Bahan Proyek ....... 04/13/2019 HAL : 111


HSPK
NO NAMA BAHAN SAT
Rp.
1 M2 Pasang Vertikal blinds M2 24,605.00
1 M2 Pasang Terali Besi M2 72,636.00
1 M2 Pasang Kawat Harmonika M2 7,205.00
1 M2 Pasang Kawat Nyamuk M2 7,205.00
1 M2 Pasang Kawat Kassa M2 7,205.00
1 M2 Pasang Kawat Burung M2 7,205.00
1 M2 Pasang Jendela Nako & Tralis M2 14,235.00
1 M2 Pasang Seng Talang Datar M2 67,334.41
1 M' Pasang Talang Miring, Seng BJLS 28 M 54,671.15
1 M' Pasang Talang 1/2 lingkaran D-10 cm, Seng BJLS 2 M 40,914.90
1 M' Pasang Talang 1/2 lingkaran D-10 cm, Seng BJLS 2 M 40,914.90

L PEKERJAAN KUNCI DAN KACA


1 Buah Pasang Kunci Tanam Antik Bh 28,680.00
1 Buah Pasang Kunci Tanam Biasa Bh 21,050.00
1 Buah Pasang Kunci Tanam Kamar Mandi Bh 20,525.00
1 Buah Pasang Kunci Silinder Bh 20,390.00
1 Buah Pasang Engsel Pintu Bh

Harga Bahan Proyek ....... 04/13/2019 HAL : 112


HSPK
NO NAMA BAHAN SAT
Rp.

Harga Bahan Proyek ....... 04/13/2019 HAL : 113


HSPK
NO NAMA BAHAN SAT
Rp.

Harga Bahan Proyek ....... 04/13/2019 HAL : 114

Anda mungkin juga menyukai