KEBUTUHAN ARMADA UNTUK SUPLAY BATU BELAH

PROYEK EMBUN DI CILACAP

KONTRAK PENGIRIMAN BATU BELAH PERSEDIAAN ARMADA DAN HASIL RITASE PER JML. HARI

SHIF KE
NO KETERANGAN JML. KUBIKASI DAYA MUAT TOTAL RITASE 1 (SATU) HARI DAN JML. BATU KERJA/OPS.

BATU PER 1 DT KESELURUHAN

6,000 M3 : 5 M3 = 1,200 rit : I 20 unit X 8 rit = 160 rit Atau 800 M3 8

H
LA
BE
TU
6,000 M3 : 5 M3 = 1,200 rit : I 15 unit X 8 rit = 120 rit Atau 600 M3 10
BA
N
1
HA
TU

6,000 M3 : 5 M3 = 1,200 rit : I 10 unit X 8 rit = 80 rit Atau 400 M3 15


BU
KE
L
TA

6,000 M3 : 5 M3 = 1,200 rit : I 8 unit X 8 rit = 64 rit Atau 320 M3 19