JAMINAN REKLAMASI PT.

RAJABASA BATU SENTOSA


IUP OPERASI PRODUKSI BAHAN GALIAN BATUAN ANDESIT
DI DESA WAY MULI TIMUR, KECAMATAN RAJABASA, KABUPATEN LAMPU

I. Biaya Langsung
1.1. Biaya penataan kegunaan lahan yang terdiri dari :
1.1.1. Biaya Pengaturan permukaan lahan :
.- Luas Lahan 50,000 m² = 5.00 Ha
Biaya Pengaturan Permukaan Lahan : Rp/Ha
.- Biaya sewa alat Dozer 1 unit x 25 jam x 450,000
.- Biaya bahan bakar 35 liter x 25 jam x 10,000
.- Biaya operator alat 1 orang x 25 jam x 25,425
.- Biaya Pengaturan Permukaan Lahan 5 Ha x @ Rp -
1.1.2. Biaya Penebaran tanah pucuk :
.- Luas Lahan 50,000 m2 = 5.00 Ha
.- Ketebalahan tanah pucuk 30 cm = 0.30 m
Biaya pengembalian tanah pucuk :
.- Biaya sewa alat excavator 1 unit x 59 jam x 350,000
.- Biaya sewa dumptruck 3 unit x 3 hari x 185,000
.- Biaya bahan bakar Excavator 35 liter x 59 jam x 10,000
.- Biaya bahan bakar Truck 18 liter x 59 jam x 10,000
.- Biaya operator alat 1 orang x 59 jam x 25,425
.- Biaya operator dumptruck 3 orang x 59 jam x 25,425
.- Biaya Pengembalian tanah pucuk 0.3 Ha x Rp -
1.1.3. Biaya Pengendalian erosi dan pengelolaan air :
.- Luas keliling lahan 500 m2
.- Biaya pembuatan per-m2 7,500 Rp/m2
Biaya Pengendalian Erosi dan Pengelolaan Air 500 m2 x 7,500 Rp/m2
1.2. Biaya revegetasi, meliputi :
1.2.1. Biaya Analisis Kualitas Tanah :
.- Analisa laboratorium = 1 sample x @ Rp 550,000
1.2.2. Biaya Pemupukan :
.- Harga pupuk organik 1,200 Rp
.- Kebutuhan pupuk per batang 3 kg
.- Biaya Pemupukan 3 kg x @ Rp 1,200
1.2.3. Biaya Pengadaan Bibit :
.- Luas lahan 50,000 m2 = 5 Ha
.- Jarak Tanam 4m
Jumlah Bibit dan Cadangan bibit, sbb :
.- Bibit 1--Jati 3,000 x 600 btng
.- Bibit 2--Mahoni 1,500 x 300 btng
.- Bibit 3--Kakao 2,000 x 300 btng
.- Biaya Pengadaan Bibit - 0 x @ Rp 3,000
1.2.4. Biaya Penanaman :
.- Jumlah tenaga kerja 10 orang
.- Jumlah hari penanaman bibit 10 hari -
.- Upah tenaga kerja 40,000 rupiah
.- Biaya Penanaman 10 orang x @ Rp 40,000
1.2.5. Biaya Pemeliharaan tanaman :
.- Jumlah tenaga kerja 10 orang
.- Jumlah hari pemeliharaan tanaman 10 hari
.- Upah tenaga kerja pemeliharaan tanaman 40,000 rupiah
.- Biaya Pemeliharaan tanaman 10 orang x @ Rp 40,000

1.3. Biaya pencegahan dan penanggulangan air asam tambang :


Biaya analisa laborat = - sample x @ Rp -
1.4. Biaya untuk pekerjaan sipil sesuai peruntukan lahan pasca tambang :
1.4.1. .- Biaya Pekerjaan Sipil Pasca Tambang 0.1 x Rp 83,554,846
Tota

II. Biaya Tidak Langsung


2.1. Biaya mobilisasi dan demobilisasi alat-alat berat :
B. Mobilisasi-Demobilisasi : x Rp 107,630,330
2.2. Biaya perencanaan reklamasi :
B. Perencanaan Reklamasi (4 % B.Langsung): 0.04 x Rp 107,630,330
2.3. Biaya administrasi dan keuntungan kontraktor pelaksana reklamasi :
B.Administrasi & keuntungan kontraktor (5% B.Langsung): 0.05 x Rp 107,630,330
2.4. Biaya Supervisi
B.Supervisi (2% B.Langsung) 0.02 x Rp 107,630,330
Total Biay
Total Jamin
Total Jaminan Re

M
CV. Yudh

ALBERTH
PT. RAJABASA BATU SENTOSA
BAHAN GALIAN BATUAN ANDESIT
N RAJABASA, KABUPATEN LAMPUNG SELATAN

= Rp 83,554,846

./jam = Rp 11,119,500.00
./liter = Rp 8,648,500.00
/Jam = Rp 628,251.75
= Rp 20,396,251.75

./jam = Rp 20,587,000
./jam = Rp 1,665,000
./liter = Rp 20,587,000
./liter = Rp 10,587,600
/Jam = Rp 1,495,499
/Jam = Rp 4,486,496
= Rp 59,408,594

= Rp 3,750,000
= Rp 15,720,000

= Rp 550,000

x 1,200 buah = Rp 4,320,000

= Rp 1,800,000
= Rp 450,000
= Rp 600,000
= Rp -

x 10 hari = Rp 4,000,000
x 10 hari = Rp 4,000,000

= Rp -
= Rp -
= Rp 8,355,485
= Rp 8,355,485
Total Biaya Langsung (A) Rp 107,630,330

= Rp 4,000,000
= Rp 4,000,000
= Rp 4,305,213
= Rp 4,305,213
= Rp 5,381,517
= Rp 5,381,517
= Rp 2,152,607
= Rp 2,152,607
Total Biaya Tidak Langsung (B) = Rp 15,839,336
Total Jaminan Reklamasi (A + B) = Rp 123,469,667
Total Jaminan Reklamasi (Dibulatkan) = Rp 50,040,000

MENGETAHUI
CV. Yudhistira Putra Amarta

ALBERTHA RAHMAYANTHIE
Pengelolaan Air (Pembuatan SP)
Pembuatan Saluran Drainase

Unit Excavator ZX320


No. Unit EX1911
Dimensi
Productivity Drainase Panjang
PA 85% Channel 214
Bucket Capacity 0,93 BCM SP
Rent Cost 350,000 per Hours Komp. I 8
Operation Cost 25,425 per Hours Komp. II 6
Pty Normal 250 BCM/Hours Komp. III 4
Pty Actual 212.5 BCM/Hours

a) Volume Tanah yang dipindahkan


Tahun
Kompartemen
2019 2020 2021 2022 2023
Komp. I 144 144 144 144 144
Komp. II 72 72 72 72 72
Komp. III 36 36 36 36 36
Total 252 252 252 252 252

b) Jam Kerja
SP 2019 2020 2021 2022 2023
Volume (m³) 252 252 252 252 252
Jam Operasi (Hours) 1.2 1.2 1.2 1.2 1.2

c) Biaya Pembuatan
Tahun 2019 2020 2021 2022 2023
Biaya (Rp) 445,210 445,210 445,210 445,210 445,210

Kebutuhan Kapur/ Tahun : 1 ton


Harga : 3,500.00 Rp/kg
Biaya : 3,500,000.00

Kebutuhan Tawas/ Tahun : 1 ton


Harga : 1,000.00 Rp/kg
Biaya : 1,000,000.00

d) Biaya Pengendalian AAT


Tahun 2019 2020 2021 2022 2023
Biaya (Rp) 4,500,000 4,500,000 4,500,000 4,500,000 4,500,000

e) Total Biaya Biaya Pencegahan dan Pengendalian AAT


Tahun 2019 2020 2021 2022 2023
Biaya (Rp) 4,945,210 4,945,210 4,945,210 4,945,210 4,945,210
Lebar Tinggi Volume
1.5 1.5 577.8

6 3 144
4 3 72
3 3 36
Total SP 252

Volume (m³)
2024 2025
144 144 864
72 72 432
36 36 216
252 252 1,512

2024 2025 Total


252 252 1,764
1.2 1.2 8.30

2024 2025 Total


445,210 445,210 3,116,469

2024 2025 Total


4,500,000 4,500,000 31,500,000

2024 2025 Total


4,945,210 4,945,210 34,616,469
REVEGETASI
a) Data Revegetasi
Jarak Tanam : 5x5 m 30 m²
Kebutuhan Bibit Per Ha : 240 bibit/ha
Waktu Penanaman 1 batang : 10 menit
Waktu Penanaman per Ha : 40 jam
Hari yang diperlukan : 7 hari
TK yang dibutuhkan per Minggu : 2 orang

b) Input Data Revegetasi Tanaman Sisipan


Jarak Tanam : 5x5 m 30 m²
Kebutuhan Bibit Per Ha (50% pioner) : 160 bibit/ha
Waktu Penanaman 1 batang : 10 menit
Waktu Penanaman per Ha : 27 jam
Hari yang diperlukan : 4 hari
TK yang dibutuhkan per Minggu : 1 orang

c) Input Data Pemeliharaan & Perawatan Tahun ke 1


Jarak Tanam : 5x5 m 30 m²
Kebutuhan Bibit Per Ha : 100 bibit/ha (25% dari pioner dan sisipan)
Waktu Penanaman 1 batang : 10 menit
Waktu Penanaman per Ha : 17 jam
Hari yang diperlukan : 3 hari
TK yang dibutuhkan per Minggu : 1 orang

d) Input Data Pemeliharaan & Perawatan Tahun ke 2 & 3


Jarak Tanam : 5x5 m 30 m²
Kebutuhan Bibit Per Ha : 50 bibit/ha (50% dari Pemeliharaan Tahun 1)
Waktu Penanaman 1 batang : 10 menit
Waktu Penanaman per Ha : 8 jam
Hari yang diperlukan : 1 hari
TK yang dibutuhkan per Minggu : 1 orang
ALAT UNTUK REVEGETASI

JENIS Type Merek Jumlah Fungsi


Ripping & Dozing D85SS KOMATSU 1 1. Pengaturan Permukaan Lahan
2. Penataan Akhir Lahan
Excavator ZX320 HITACHI 1 1. Penebaran Tanah Pucuk
2. Loading Material untuk Revegetasi
3. Pembuatan Saluran Drainase
Overburden FM 260 TI HINO 2 1. Memuat Material untuk Revegetasi
2. Memuat Material Top Soil
Pengaturan Permukaan

Luas Lahan
Tahun I II III IV V VI
Luas Area 0 0 0.8 1.15 1.25 1.8

Unit D85SS
No. Unit DZR851

Productivity
PA 85%
Rent Cost 550,000 per Hours
Operation Cost 25,425 per Hours
Pty Normal 500 BCM/Hours
Pty Actual 425 BCM/Hours

Volume Tanah yang di Tata


Tahun 2019 2020 2021 2022 2023 2024
Volume (BCM) 0 0 1,680 2,415 2,625 3,780

Penebaran Tanah Pucuk

Unit Excavator ZX320


No. Unit EX1911

Productivity
PA 85%
Bucket Capacity 0,93 BCM
Rent Cost 350,000 per Hours
Operation Cost 25,425 per Hours
Pty Normal 250 BCM/Hours
Pty Actual 212.5 BCM/Hours

Volume Tanah yang di Tata


Tahun 2019 2020 2021 2022 2023 2024
Volume (BCM) - - 2,400 3,450 3,750 5,400

Pembuatan Saluran Drainase

Unit Excavator ZX320


No. Unit EX1911
Dimensi
Productivity Drainase Panjang Lebar Tinggi
PA 85% Channel 214 1.5 1.5
Bucket Capacity 0,93 BCM SP
Rent Cost 350,000 per Hours Komp. I 10 8 3
Operation Cost 25,425 per Hours Komp. II 8 6 3
Pty Normal 250 BCM/Hours Komp. III 6 5 3
Pty Actual 212.5 BCM/Hours Total SP

Volume Tanah yang di Pindahkan


Tahun 2019 2020 2021 2022 2023 2024
Volume (BCM) 157.77 262.95 210.36 157.77 157.77 52.59
a) Productivity
V Total
5 5.00

-
1.80

Total
10,500 10,500.00

0.30

Total
15,000 15,000.00

Dimensi Channel
Panjang 214 meter
Lebar 1.5 meter
Dalam 1.5 meter
si Volume 674.1 BCM
Volume
577.8 Dimensi SP

240
144
90 214 meter
474 481.5

2025 Total
52.59 1,051.80 1,051.80
Kebutuhan Harga Satuan
No. Komponen Biaya Satuan Total Harga (Rp)
Per Ha (Rp)
1 Penanaman Pionir
1.1 Pohon Tanaman Pioneer Bibit 240 23,125.00 5,550,000.00
1.2 Penebaran Biji Cover Crop kg 3 121,500.00 364,500.00
1.3 Pupuk kg 20 7,500.00 150,000.00
1.4 Kapur/ Dolomit kg 50 3,000.00 150,000.00
1.5 Insektisida (Marshal 200) Liter 1 145,000.00 145,000.00
1.6 Tenaga Kerja HOK 12 100,000.00 1,200,000.00
2 Penanaman Sisipan
2.1 Pohon Tanaman Sisipan Bibit 160 9,843.75 1,575,000.00
2.2 Pupuk kg 5 7,500.00 37,500.00
2.3 Kapur/ Dolomit kg 12.5 3,000.00 37,500.00
2.4 Insektisida (Marshal 200) Liter 1 145,000.00 145,000.00
2.5 Tenaga Kerja HOK 3 100,000.00 300,000.00
3 Perawatan Tahun ke 1
3.1 Pupuk kg 26.3 7,500.00 197,250.00
3.2 Pohon untuk penyulaman Pioneer Bibit 100 23,125.00 2,312,500.00
3.3 Biji Cover Crop kg 0.8 121,500.00 97,200.00
3.4 Tenaga Kerja HOK 4 100,000.00 400,000.00
4 Perawatan Tahun ke 2
4.1 Pupuk kg 26.3 7,500.00 197,250.00
4.2 Pohon untuk penyulaman Pioneer Bibit 50 23,125.00 1,156,250.00
4.3 Tenaga Kerja HOK 2 100,000.00 200,000.00
5 Perawatan Tahun ke 3
5.1 Pupuk kg 26.3 7,500.00 197,250.00
5.2 Pohon untuk penyulaman lokal Bibit 80 9,843.75 787,500.00
5.3 Tenaga Kerja HOK 2 100,000.00 200,000.00
Uji Labolatorium
1. Uji Kualitas Tanah kering (PUTK) Sample 2 1,411,300.00
2. Uji Ulang Pra Penanaman Sample 1 822,800.00
Biaya Revegetasi lahan Per Ha (Rp) 17,633,800.00
Tempat :
Balai Penelitian Tanah
Jln. Tentara Pelajar No. 12 Bogor Jawa Barat 16114
balittanah@litbang.pertanian.go.id
Telp : '+622518336757
Pupuk Revegetasi (Pohon)
3
7,500.00 Mangga Jeruk Durian

720 10,206,000.00 5,184,000.00 9,396,000.00


9 35.00 20.00 25.00
60 450,000.00
150 450,000.00
3 435,000.00
36

480
15 112,500.00
38 112,500.00
3 435,000.00
9

79 591,750.00
300 1,822,500.00 1,620,000.00 1,566,000.00
2
12

79 591,750.00
150 911,250.00 810,000.00 783,000.00
6

79 591,750.00
240
6
562,500.00 10,206,000.00 5,184,000.00 9,396,000.00
1,775,250.00

52,901,400.00
1,411,300.00 Perawatan P 6,021,000.00
822,800.00 Perawatan S 291,600.00
2,234,100.00 Perawatan L 1,377,000.00
Revegetasi (Pohon)

Rambutan Gaharu Sengon LCC

4,860,000.00 25 m2
20.00 1,093,500.00 10,000.00 m2
400 batang pohon

40,500.00 mangga irwin


36,000.00 jeruk santang
16,200.00 Gaharu
3,110,400.00 1,944,000.00 33,750.00 Rambutan Garuda
6,750.00 Sengon
121,500.00 Cover Crop
3,000.00 dolomit
145,000.00 Insektisida
52,200.00 Durian

1,012,500.00
291,600.00

506,250.00

972,000.00 405,000.00

4,860,000.00 3,110,400.00 1,944,000.00 1,093,500.00 29,646,000.00


5,054,400.00
batang pohon

mangga irwin
jeruk santang

Rambutan Garuda

Cover Crop 10.76667

Insektisida
TABEL 1.1
RENCANA BIAYA REKLAMASI PT. RAJABASA BATU SEN

No. Deskripsi Biaya 2019 2020


1 Biaya Langsung
1.1 Biaya Penatagunaan Lahan
a). Biaya Pengaturan Permukaan Lahan - -
b). Biaya Penebaran Tanah Pucuk - -
c). Biaya Pengendalian Erosi dan Pengelolaan Air 309,704 516,173
d). Biaya Penataan Akhir Lahan - -
1.2 Biaya Revegetasi
a). Analisis Kualitas Tanah - -
b). Pemupukan - -
c). Pengadaan Bibit
A. Tanaman Pioneer - -
B. Tanaman Sisipan - -
C. Cover Crop (LCC) - -
d). Penanaman
e). Pemeliharaan Tanaman
1.3 Biaya Penanggulangan Air Asam Tambang 4,945,210 4,945,210
1.4 Biaya Pekerjaan Sipil Sesuai peruntukan lahan - -
pasca tambang
Subtotal Biaya Langsung 5,254,913 5,461,382
2 Biaya Tidak Langsung
2.1 Biaya Mobilisasi dan Demobilisasi alat 131,373 136,535
(sebesar 2,5 % dari biaya langsung atau
berdasarkan perhitungan)
2.2 Perencanaan Reklamasi 262,746 273,069
(sebesar 2 % s.d 10% dari biaya langsung)
2.3 Biaya Administrasi dan Keuntungan Kontraktor 367,844 382,297
(sebesar 3 % s.d 14% dari biaya langsung)
2.4 Biaya Supervisi 262,746 273,069
(sebesar 2 % s.d 7% dari biaya langsung)
Subtotal Biaya Tidak Langsung 1,024,708 1,064,970
Total ( 1+2 ) 6,279,622 6,526,352
Total Jaminan Reklamasi
Total Pembulatan Jaminan Reklamasi
TABEL 1.1
MASI PT. RAJABASA BATU SENTOSA

2021 2022 2023 2024 2025

2,020,024 2,525,029 4,292,550 5,050,059 1,262,515


7,590,241 9,487,801 16,129,262 18,975,602 4,743,901
412,938 309,704 309,704 103,235 103,235
220,062 275,077 467,631 550,154 137,539

- - - 1,411,300 822,800
- - - 562,500 1,775,250

- - 29,646,000 - 6,021,000
- - 5,054,400 - 291,600
- - 1,093,500 - 1,377,000

4,945,210 4,945,210 4,945,210 4,945,210 4,945,210


- - - - -

15,188,474 17,542,821 61,938,256 31,598,060 21,480,048

379,712 438,571 1,548,456 789,951 537,001

759,424 877,141 3,096,913 1,579,903 1,074,002

1,063,193 1,227,997 4,335,678 2,211,864 1,503,603

759,424 877,141 3,096,913 1,579,903 1,074,002

2,961,752 3,420,850 12,077,960 6,161,622 4,188,609


18,150,226 20,963,671 74,016,216 37,759,681 25,668,658
Reklamasi Rp 189,364,426
minan Reklamasi Rp 190,000,000
Pengaturan Permukaan

Luas Lahan
Tahun I II III
Luas Area 0 0 0.4
Unit D85SS
No. Unit DZR851

Productivity
PA 85%
Rent Cost 450,000 per Hours
Operation Cost 25,425 per Hours
Fuel 10,000 per Liter
Pty Normal 500 BCM/Hours
Pty Actual 425 BCM/Hours

a) Volume Tanah yang di Tata


Tahun 2019 2020 2021
Volume (BCM) - - 1,200

b) Productivity Unit
Correction Factor
Correction Factor Operator Material EWH
0.85 0.9 1.2 0.85
Productivity Unit Dozer 425 BCM/Hours

c) EWH
Tahun 2019 2020 2021
EWH - - 3

d) Biaya Penataan Lahan


Tahun 2019 2020 2021
Biaya (Rp) - - 2,020,024

Penebaran Tanah Pucuk


Luas Lahan
Tahun I II III
Luas Area 0 0 0.4
DIGGER
Unit Excavator ZX320
No. Unit EX1911
Productivity
PA 85%
Bucket Capacity 0.93 BCM
Rent Cost 350,000 per Hours
Operation Cost 25,425 per Hours
Fuel 10,000 per Hours
Pty Normal 190.5 BCM/Hours
Pty Actual 162 BCM/Hours
a) Volume Tanah yang di Tata
Tahun 2019 2020 2021
Volume (BCM) - - 1,200
b) Productivity Unit
Kapasitas Bucket Bersih
Pty bersih Bucket (BCM) Pty Actual (BCM) FC
1,120 0,93 1.2
EWH 45 menit/jam
CT 0.18 menit
Pty Act 194.31 BCM/Hours
c) Jam Operasi Alat
Tahun 2019 2020 2021
Jam Operasi - - 6.18
d) Biaya Penebaran Top Soil
Tahun 2019 2020 2021
Biaya (Rp) - - 4,171,221

HAULER
Unit DT FM260 TI
No. Unit DT 2001
DT 2002
Productivity
PA 85%
Vessel Capacity 28 BCM
Rent Cost 170,000 per Hours
Operation Cost 25,425 per Hours
Fuel 10,000 per Hours
Pty Actual 23.8 BCM/Hours
a) Productivity Unit
Waktu Edar Ang. Isi Kosong Pemuatan
10.6 3.67 3.33 2.93
n Unit Waktu Edar Pemuatan
1.12 10.6 8
Jadi Kebutuhan DT 1 Unit
Pty Unit 95 m³/jam
b) Jam Operasi Alat
Tahun 2019 2020 2021
Jam Operasi - - 12.60
d) Biaya Pengangkutan Top Soil
Tahun 2019 2020 2021
Biaya (Rp) - - 3,419,020

Pembuatan Saluran Drainase

Unit Excavator ZX320


No. Unit EX1911

Productivity
PA 85%
Bucket Capacity 0.93 BCM
Rent Cost 350,000 per Hours
Operation Cost 25,425 per Hours
Pty Normal 250 BCM/Hours
Pty Actual 212.5 BCM/Hours
Volume Tanah yang di Pindahkan
Tahun 2019 2020 2021
Volume (BCM) 158 263 210

a) Productivity
Pty Bucket Pty Min CF
0.87 0.93 0.9
EWH 45 menit/jam
Cycle Time 0.5 menit
Pty Unit 191.25 bcm/jam

b) Jam Operasi Unit


Tahun 2019 2020 2021
Jam Operasi 0.82 1.37 1.10

c) Biaya Pembuatan Drainase


Tahun 2019 2020 2021
Biaya (Rp) 309,704 516,173 412,938

Penataan Akhir Lahan


Productivity
Unit D85SS
No. Unit DZR851
PA 85%
Blits Capacity 6.1 BCM
Rent Cost 450,000 per Hours
Operation Cost 25,425 per Hours
Pty Normal 500 BCM/Hours
Pty Actual 425 BCM/Hours

a) Productivity Unit
Correction Factor Operator Material EWH
0.85 0.9 1.2 0.85
Productivity Actual 425 BCM/Hours

b) Jam Operasi Alat


Tahun 2019 2020 2021
Jam Operasi - - 0.46

c) Biaya Penataan Akhir Lahan


Tahun 2019 2020 2021
Biaya 0 0 220,062

No. Rincian Pekerjaan Biaya (Rp)


1 Pengaturan Permukaan Lahan 15,150,176
2 Penebaran Tanah Pucuk 56,926,806
3 Pengendalian Erosi dan Water Management 2,064,690
4 Penataan Akhir Lahan 1,650,463
Total Biaya Langsung 75,792,136
IV V VI VII Total
0.5 0.85 1 0.25 3

9000

2022 2023 2024 2025 Total


1,500 2,550 3,000 750 9,000 9,000.00

Slope Dencity
1 0.9

2022 2023 2024 2025 Total


4 6 7 2 19.41 21.18

2022 2023 2024 2025 Total


2,525,029 4,292,550 5,050,059 1,262,515 15,150,176

IV V VI VII Total
0.5 0.85 1 0.25 3

2022 2023 2024 2025 Total


1,500 2,550 3,000 750 9,000 9,000.00
2022 2023 2024 2025 Total
7.72 13.12 15.44 3.86 46.32

2022 2023 2024 2025 Total


5,214,027 8,863,845 10,428,053 2,607,013 31,284,159

q
Loading Time
ct Hauling isi
Dump & Back ct Dump Disposal
0.67 ct Dumping
ct Hauling Kosong

ctr

Fvc

2022 2023 2024 2025 Total Ptr


15.75 26.77 31.49 7.87 94

2022 2023 2024 2025 Total


4,273,775 7,265,417 8,547,549 2,136,887 25,642,647

Dimensi Drainas Panjang Lebar Tinggi Volume


Channel 214 1.5 1.5 577.8
SP
Kompartemen I 10 8 3 240
Kompartemen II 8 6 3 144
Kompartemen III 6 5 3 90
Total SP 474
2022 2023 2024 2025 Total
158 158 53 53 1,052

2022 2023 2024 2025 Total


0.82 0.82 0.27 0.27 5

2022 2023 2024 2025 Total


309,704 309,704 103,235 103,235 2,064,690

Slope Dencity
1 0.9

2022 2023 2024 2025 Total


0.58 0.98 1.16 0.29 3

2022 2023 2024 2025 Total


275,077 467,631 550,154 137,539 1,650,463
a) Biaya Pengaturan Permukaan Lahan : 0
1. Biaya sewa alat Dozer 1 450,000 19 8,735,294.12
2. Biaya bahan bakar 24 10,000 19 4,658,823.53
3. Biaya operator alat 1 25,425 19 493,544.12
Total Biaya Pengaturan Permukaan 13,887,661.76

Sewa Excavator 1 350,000 46 16,211,208.89


Fuel 30 10,000 46 13,895,321.91
Operator 1 25,425 46 1,177,628.53
31,284,159.33
17,852,014.82

Sewa Hauler 1 170,000 94 16,060,606.06


Fuel 7.6 10,000 94 7,180,035.65
Operator 1 25,425 94 2,402,005.35
25,642,647.06

40,000,000.00 240
166,666.67

8.00 pas
176 detik/pas
220 detik
25 detik
15 detik
200 detik

10.6 menit/ trip

Rvc/Svc
92%

=(60/Ctr)*Svc*Fvc*Ma*Eu
95.26 m³/jam
9,000.00
No. Deskripsi Biaya 2019 2020 2021 2022
2 Biaya Tidak Langsung
2.1 Biaya Mobilisasi dan Demobilisasi alat 131,373 136,535 379,712 438,571
(sebesar 2,5 % dari biaya langsung atau
berdasarkan perhitungan)
Total Biaya Mobilisasi & Demobilisasi

No. Deskripsi Biaya 2019 2020 2021 2022


2 Biaya Tidak Langsung
2.2 Perencanaan Reklamasi 262,746 273,069 759,424 877,141
(sebesar 2 % s.d 10% dari biaya langsung)
Total Biaya Perencanaan Reklamasi

No. Deskripsi Biaya 2019 2020 2021 2022


2 Biaya Tidak Langsung
2.3 Biaya Administrasi dan Keuntungan Kontraktor 367,844 382,297 1,063,193 1,227,997
(sebesar 3 % s.d 14% dari biaya langsung)
Total Biaya Administrasi dan Keuntungan Kontraktor

No. Deskripsi Biaya 2019 2020 2021 2022


2 Biaya Tidak Langsung
2.4 Biaya Supervisi 262,746 273,069 759,424 877,141
(sebesar 2 % s.d 7% dari biaya langsung)
Total Biaya Supervisi
2023 2024 2025

1,548,456 789,951 537,001

3,961,599

2023 2024 2025

3,096,913 1,579,903 1,074,002

7,923,198

2023 2024 2025

4,335,678 2,211,864 1,503,603

11,092,477

2023 2024 2025

3,096,913 1,579,903 1,074,002

7,923,198
No. Deskripsi Biaya 2019 2020 2021
1 Biaya Langsung Rp 5,254,913 Rp 5,461,382 Rp 15,188,474
2 Biaya Tidak Langsung Rp 1,024,708 Rp 1,064,970 Rp 2,961,752
Total Biaya Reklamasi Rp 6,279,622 Rp 6,526,352 Rp 18,150,226
2022 2023 2024 2025
Rp 17,542,821 Rp 61,938,256 Rp 31,598,060 Rp 21,480,048
Rp 3,420,850 Rp 12,077,960 Rp 6,161,622 Rp 4,188,609
Rp 20,963,671 Rp 74,016,216 Rp 37,759,681 Rp 25,668,658
I II III IV V VI VII
Tahun Total
2019 2020 2021 2022 2023 2024 2025
Luas Area 0 0 0.4 0.5 0.85 1 0.25 3