Terbilang :
Tujuh Miliar Lima Ratus Empat Puluh Delapan Juta Tiga Puluh Enam Ribu Rupiah
1 2 3 4 5 6 7 = (3 x 6) 8
I PEKERJAAN PERSIAPAN
1 Mobilisasi/ Demobilisasi Alat Berat 1.00 Ls Ls 23,000,000.00 23,000,000.00
2 Outzet Bouplank 1,500.00 m' A.5. 33,897.90 50,846,850.00
II PEKERJAAN PENGERUKAN
1 Galian tanah menggunakan Exavator Phonton 68,445.00 M3 P.5. 23,008.22 1,574,797,391.47
2 Membuang tanah hasil galian (holling jarak 1-2 km) 34,222.50 M3 P.6. 8,000.00 273,780,000.00
Jumlah = 5,580,340,940.27
Pembulatan = 5,580,340,000.00
Terbilang :
Lima Milyar Lima Ratus Delapan Puluh Juta Tiga Ratus Empat Puluh Ribu Rupiah
1 2 3 4 5 6 7 = (3 x 6) 8
I PEKERJAAN PERSIAPAN
2 Outzet Bouplank 280.00 m' A.5. 33,897.90 9,491,412.00
II PEKERJAAN DRAINASE
1 Galian tanah manual 1,050.00 M3 B.1. 24,600.00 25,830,000.00
2 Urugan Tanah Kembali 262.50 M3 B.11. 11,795.00 3,096,187.50
3 Pasangan batu kali 1 Pc : 4 Psr 400.40 M3 C.4. 686,679.80 274,946,591.92
4 Plesteran 1 Pc : 4 Psr 252.00 M2 I.3. 43,055.76 10,850,051.52
5 Plester siar 1 Pc : 4 Psr 504.00 M2 I.10. 41,278.18 20,804,202.72
6 Pasang trucuk bambu panjang 3,00 m 1,120.00 btg P.03.c 21,935.00 24,567,200.00
7 Membuat Plat Beton Jalan Masuk gang 1.80 M3 F.26. 5,692,013.90 10,245,625.02
Jumlah = 379,831,270.68
Pembulatan = 379,831,000.00
Terbilang :
Tiga Ratus Tujuh Puluh Sembilan Juta Delapan Ratus Tiga Puluh Satu Ribu Rupiah
1 2 3 4 5 6 7 = (3 x 6) 8
I PEKERJAAN PERSIAPAN
2 Outzet Bouplank 550.00 m' A.5. 33,897.90 18,643,845.00
II PEKERJAAN DRAINASE
1 Galian tanah manual 2,062.50 M3 B.1. 24,600.00 50,737,500.00
2 Urugan Tanah Kembali 515.63 M3 B.11. 11,795.00 6,081,796.88
3 Pasangan batu kali 1 Pc : 4 Psr 786.50 M3 C.4. 686,679.80 540,073,662.70
4 Plesteran 1 Pc : 4 Psr 495.00 M2 I.3. 43,055.76 21,312,601.20
5 Plester siar 1 Pc : 4 Psr 990.00 M2 I.10. 41,278.18 40,865,398.20
6 Pasang trucuk bambu panjang 3,00 m 1,100.00 btg P.03.c 21,935.00 24,128,500.00
7 Membuat Plat Beton Jalan Masuk gang 2.88 M3 F.26. 5,692,013.90 16,393,000.03
Jumlah = 718,236,304.01
Pembulatan = 718,236,000.00
Terbilang :
Tujuh Ratus Delapan Belas Juta Dua Ratus Tiga Puluh Enam Ribu Rupiah
1 2 3 4 5 6 7 = (3 x 6) 8
I PEKERJAAN PERSIAPAN
2 Outzet Bouplank 550.00 m' A.5. 33,897.90 18,643,845.00
II PEKERJAAN DRAINASE
1 Galian tanah manual 1,650.00 M3 B.1. 24,600.00 40,590,000.00
2 Urugan Tanah Kembali 412.50 M3 B.11. 11,795.00 4,865,437.50
3 Pasangan batu kali 1 Pc : 4 Psr 660.00 M3 C.4. 686,679.80 453,208,668.00
4 Plesteran 1 Pc : 4 Psr 495.00 M2 I.3. 43,055.76 21,312,601.20
5 Plester siar 1 Pc : 4 Psr 770.00 M2 I.10. 41,278.18 31,784,198.60
6 Pasang trucuk bambu panjang 3,00 m 1,100.00 btg P.03.c 21,935.00 24,128,500.00
7 Membuat Plat Beton Jalan Masuk gang 4.32 M3 F.26. 5,692,013.90 24,589,500.05
Jumlah = 619,122,750.35
Pembulatan = 619,122,000.00
Terbilang :
Enam Ratus Sembilan Belas Juta Seratus Dua Puluh Dua Ribu Rupiah
1 2 3 4 5 6 7 = (3 x 6) 8
I PEKERJAAN PERSIAPAN
2 Outzet Bouplank 285.00 m' A.5. 33,897.90 9,660,901.50
II PEKERJAAN DRAINASE
1 Galian tanah manual 570.00 M3 B.1. 24,600.00 14,022,000.00
2 Urugan Tanah Kembali 142.50 M3 B.11. 11,795.00 1,680,787.50
3 Pasangan batu kali 1 Pc : 4 Psr 276.45 M3 C.4. 686,679.80 189,832,630.71
4 Plesteran 1 Pc : 4 Psr 256.50 M2 I.3. 43,055.76 11,043,802.44
5 Plester siar 1 Pc : 4 Psr 285.00 M2 I.10. 41,278.18 11,764,281.30
6 Pasang trucuk bambu panjang 3,00 m 570.00 btg P.03.c 21,935.00 12,502,950.00
Jumlah = 250,507,353.45
Pembulatan = 250,507,000.00
Terbilang :
Dua Ratus Lima Puluh Juta Lima Ratus Tujuh Ribu Rupiah
B.22. 1 m3 Urugan tanah dipadatkan (Pakai tanah bekas galian) dengan jarak angkat ‹ 25 m' Rp 74,680.00
F.1. 1 m3 Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 Rp 844,275.04
F.2. 1 m3 Membuat beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 Rp 996,494.97
F.3. 1 m3 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 Rp 1,055,224.70
I.10. 1 m' Plesteran finishing siar pasangan batu kali adukan 1 PC : 2 PS. Rp 41,278.18
P.5. Biaya Galian Tanah lunak dengan I unit alat kerja terdiri : ( ( 3 Backhoe + 1 unit Phonton ) Rp 23,008.22
P.8. 1 M2 STRIPPING TANGGUL (termasuk pencabutan akar pohon & rumpun bambu) Rp 1,637.08
(Menggunakan Bulldozer)
A. PEKERJAAN PERSIAPAN
B. PEKERJAAN TANAH
A. Tenaga
1. Pekerja 0.500 Oh x Rp 55,000.00 = Rp 27,500.00
2. Tukang gali - Oh x Rp 70,000.00 = Rp -
3. Kepala tukang - Oh x Rp 75,000.00 = Rp -
4. Mandor 0.050 Oh x Rp 65,000.00 = Rp 3,250.00
Jumlah ( 1 ) = Rp 30,750.00
C. PEKERJAAN PONDASI
F. PEKERJAAN BETON
1. 1 m 3 Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
A. Bahan
1. Semen Portland 230.000 Kg x Rp 1,615.00 = Rp 371,450.00
2. Pasir beton 893.000 Kg x Rp 266.36 = Rp 237,856.93
3. Koral beton (maksimum 30 mm) 1027.000 Kg x Rp 142.71 = Rp 146,568.11
4. Air 200.000 Liter x Rp 15.00 = Rp 3,000.00
Jumlah ( 1 ) = Rp 758,875.04
B. Tenaga
1. Pekerja 1.200 Oh x Rp 55,000.00 = Rp 66,000.00
11
2. 1 m 3 Membuat beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
A. Bahan
1. Semen Portland 326.000 Kg x Rp 1,615.00 = Rp 526,490.00
2. Pasir beton 760.000 Kg x Rp 266.36 = Rp 202,431.43
3. Koral beton (maksimum 30 mm) 1029.000 Kg x Rp 142.71 = Rp 146,853.54
4. Air 215.000 Liter x Rp 15.00 = Rp 3,225.00
Jumlah ( 1 ) = Rp 878,999.97
B. Tenaga
1. Pekerja 1.650 Oh x Rp 55,000.00 = Rp 90,750.00
2. Tukang batu 0.275 Oh x Rp 70,000.00 = Rp 19,250.00
3. Kepala tukang 0.028 Oh x Rp 75,000.00 = Rp 2,100.00
4. Mandor 0.083 Oh x Rp 65,000.00 = Rp 5,395.00
Jumlah ( 2 ) = Rp 117,495.00
Jumlah (1 + 2 ) = Rp 996,494.97
3. 1 m 3 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
A. Bahan
1. Semen Portland 371.000 Kg x Rp 1,615.00 = Rp 599,165.00
2. Pasir beton 698.000 Kg x Rp 266.36 = Rp 185,917.29
3. Koral beton (maksimum 30 mm) 1047.000 Kg x Rp 142.71 = Rp 149,422.41
4. Air 215.000 Liter x Rp 15.00 = Rp 3,225.00
Jumlah ( 1 ) = Rp 937,729.70
B. Tenaga
1. Pekerja 1.650 Oh x Rp 55,000.00 = Rp 90,750.00
2. Tukang batu 0.275 Oh x Rp 70,000.00 = Rp 19,250.00
3. Kepala tukang 0.028 Oh x Rp 75,000.00 = Rp 2,100.00
4. Mandor 0.083 Oh x Rp 65,000.00 = Rp 5,395.00
Jumlah ( 2 ) = Rp 117,495.00
Jumlah (1 + 2 ) = Rp 1,055,224.70
Jumlah (1 + 2 ) = Rp 15,776.28
I. PEKERJAAN PLESTERAN
10. 1 m ' Plesteran finishing siar pasangan batu kali adukan 1 PC : 2 PS.
A. Bahan
1. Semen portland 6.3400 Kg x Rp 1,615.00 = Rp 10,239.10
2. Pasir pasang (cepu) 0.0120 M3 x Rp 161,590.00 = Rp 1,939.08
Jumlah ( 1 ) = Rp 12,178.18
B. Tenaga
1. Pekerja 0.300 Oh x Rp 55,000.00 = Rp 16,500.00
2. Tukang batu 0.150 Oh x Rp 70,000.00 = Rp 10,500.00
3. Kepala tukang 0.015 Oh x Rp 75,000.00 = Rp 1,125.00
4. Mandor 0.015 Oh x Rp 65,000.00 = Rp 975.00
Jumlah ( 2 ) = Rp 29,100.00
Jumlah (1 + 2 ) = Rp 41,278.18
** Perhitungan Produktifitas
Produksi Per Siklus (q)
q = (tinggi sudut)² x Lebar Sudut x faktor Sudut
= 1,20² x 3,10 x 0,80 = 3.5712 M³
Cn = 40 + 40 = 0,83 Menit
14
87,50 125
Biaya Produksi
A. Upah
1. Sewa Alat 1.00000 Jam x Rp 375,000.00 = Rp 375,000.00
2. Operator 1.00000 Oh x Rp 10,000.00 = Rp 10,000.00
3. Pekerja 2.00000 Oh x Rp 7,857.14 = Rp 15,714.29
Jumlah ( 1 ) Rp 400,714.29
B. Bahan Bakar / Olie
1. Solar 20.00000 Lt x Rp 11,000.00 = Rp 220,000.00
2. Pelumas 0.50000 Lt x Rp 26,000.00 = Rp 13,000.00
Jumlah ( 2 ) = Rp 233,000.00
Jumlah (1 + 2 ) = Rp 633,714.29
2. Bahan
- Solar 20.000 lt x Rp 11,000.00 = Rp 220,000.00
- Pelumas 0.119 lt x Rp 26,000.00 = Rp 3,094.00
- Hidrolic Olie 0.240 lt x Rp 38,000.00 = Rp 9,120.00
- Greese 0.089 kg x Rp 110,000.00 = Rp 9,790.00
- Transmisi 0.040 kg x Rp 60,000.00 = Rp 2,400.00
- Filter 0.008 bh x Rp 350,000.00 = Rp 2,905.00
Jumlah 2 Rp 247,309.00
Cycle Time = 33 dt
= 0,55 menit
* Faktor Koreksi :
- Efisiensi Kerja = 0.84 (a)
- Kondisi Kerja dan Tata Laksana = 0.65 (b)
- Faktor Swing dan Kedalaman Galian
- Tanah Biasa = 8.00
- Kedalaman Optimum = 5/8 = 63.00 %
- Swing 90º = 0.82 (c)
Faktor Pengisian = 0.60 (d)
** Koreksi Total = (a x b x c x d) = 0.27
** Produksi Bersih/Jam = 218,18 x 0,27 x 0,80 m³ = 46.89 m³
*** 1 m³ Harga Galian Tanah Biasa Dengan Back Hoe = Rp 655,880.43 = Rp 13,988.09 A.Dk
(A / B) 46.89
C. Biaya operasional 1 backhoe dengan alat bantu phonton per jam
1. Upah
- Sewa Alat Exavator (Backhoe) = Rp 375,000.00
- Sewa Phonton = Rp 190,000.00
- Operator 0.14286 Oh x Rp 70,000.00 = Rp 10,000.00
- Pembantu Operator 0.14286 Oh x Rp 55,000.00 = Rp 7,857.14
- Pekerja 0.28571 Oh x Rp 55,000.00 = Rp 15,714.29
Jumlah 1 = Rp 598,571.43
2. Bahan
- Solar 20.000 lt x Rp 11,000.00 = Rp 220,000.00
- Pelumas 0.119 lt x Rp 26,000.00 = Rp 3,094.00
- Hidrolic Olie 0.240 lt x Rp 38,000.00 = Rp 9,120.00
- Greese 0.089 kg x Rp 110,000.00 = Rp 9,790.00
- Transmisi 0.040 kg x Rp 60,000.00 = Rp 2,400.00
- Filter 0.008 bh x Rp 350,000.00 = Rp 2,905.00
Jumlah 2 Rp 247,309.00
D. Biaya Galian Tanah lunak dengan I unit alat kerja terdiri : ( ( 3 Backhoe + 1 unit Phonton )
a. Biaya Operasional :
(2xA)+D= 2x Rp 655,880.43 + Rp 845,880.43 = Rp 2,157,641.29
= Rp 23,008.22 B.Dk
III. BULLDOZER
A. PRODUKSI BULLDOZER PER JAM
1. Menggunakan Bulldozer (320) HP
- Jarak gusur = 40.00
- Jenis tanah = Liat berpasir
- Efisiensi kerja = 0.75
- Kecepatan maju R1 Lo = 7.00
- Kecepatan mundur R2 Lo = 10.00
- Faktor konversi volume tanah
Lepas f = 7.00
Asli f = 10.00
2. Perhitungan produktifitas
- q = (tinggi sudut)^2 x lebar sudut x faktor sudut
- q = 1,20^2 x 3,10 x 0,80 = 3.57 m3
40.00 40.00
Cn + + 0.05 = 0.83 menit
87.50 125.00
2. Bahan
- Solar 20.000 lt x Rp 11,000.00 = Rp 220,000.00
- Pelumas 0.500 lt x Rp 26,000.00 = Rp 13,000.00
Jumlah 2 Rp 233,000.00
= Rp 3,274.16
* STRIPING DENGAN KEDALAMAN UNTUK 1M2
- 0,10 M' = 0,10 x Rp. 3,274.16 = Rp 327.42
- 0,50 M' = 0,50 x Rp. 3,274.16 = Rp 1,637.08
B. Upah
1. Mandor 0.00100 Oh x Rp 65,000.00 = Rp 65.00
2. Kepala Tukang 0.00500 Oh x Rp 75,000.00 = Rp 375.00
3. Tukang 0.01000 Oh x Rp 70,000.00 = Rp 700.00
4. Pekerja 0.03000 Oh x Rp 55,000.00 = Rp 1,650.00
Jumlah ( 2 ) Rp 2,790.00
C. Peralatan
1. Alat pancang manual tripod dan penumbuk 0.01000 hari x Rp 50,000.00 = Rp 500.00
Jumlah ( 3 ) Rp 500.00
Jumlah (1 + 2 +3 ) = Rp 21,935.00
18
Upah Tenaga
1 2 3 4 5
1 Pekerja / hari 55,000
2 Kepala Tukang / hari 75,000
3 Sopir / hari 70,000
4 Jaga Malam / hari 55,000
5 Tukang / hari 70,000
6 Operator / Masinis / hari 70,000
7 Mandor / hari 65,000
8 Pembantu masinis / hari 55,000
9 Pemasak aspal / hari 70,000
10 Pekerja Semi Terlatih / hari 55,000
11 Pekerja Terlatih / hari 55,000
Harga Bahan
1 2 3 4 5
1 Batu belah gunung / m3 161,590
2 Batu krokol / m3 149,160
3 Batu pecah / belah kali / m3 161,590
4 Batu pecah 5/7 / m3 190,000
5 Batu pecah 4/6 / m3 190,000
6 Batu pecah 3/5 / m3 190,000
7 Batu pecah 2/3 / m3 192,665 berat isi kerikil 1350 kg/m3
8 Batu pecah 1/2 / m3 192,665 berat isi kerikil 1350 kg/m3
9 Batu pecah 1/1 / m3 192,665
10 Batu pecah 1 - 0,50 / m3 200,000
11 Batu pecah 0,50 - 0,50 / m3 200,000
12 Pasir beton (muntilan) / m3 372,900 berat isi pasir 1400 kg/m3
13 Pasir pasang /m 3
161,590
14 Pasir Lokal/Pasir Urug / m3 99,440
20 Pasir Lokal Hitam / m3 161,590
21 Pasir batu (Sirtu) / m3 111,870
22 Tanah biasa / m3 55,935
23 Tanah urug padas / m3 62,160
24 Tanah urug pilihan / m3 62,160
25 Kapur Pasang / m3 300,000
26 P.C ( 50 kg) / kg 1,615
27 Kayu bakar / m3 115,000
28 Kayu begesting / m3 2,983,200 dibagi 72 btg
29 Kayu begesting/Ky. Meranti / btg 70,000
30 Kayu kruing / m3 7,000,000
31 Papan Kayu kruing / m3 7,750,000
35 Papan kayu bengkirai / m3 10,500,000
36 Kayu kamfer / m3 9,500,000
37 Papan kayu kamfer / m3 11,000,000
38 Kayu bulat (dolken) 0 20 / m3 4,000,000
39 Kayu bulat (dolken) 0 10 / m3 4,000,000
40 Triplek 3 mm / lbr 60,000
41 Triplek 6 mm / lbr 77,000
42 Multiplek tebal 9 mm / lbr 150,000
43 Teakwood 1,20 x 2,40 m / lbr 135,000
44 Besi beton polos / kg 13,651
45 Besi Beton Ulir / kg 13,673
46 Besi setrip / kg 18,888
47 Aluminium plat uk. 1 x 2 m / lbr 130,000
19
1 2 3 4 5
48 Kawat beton / kg 31,075
49 Paku / kg 18,645
50 Paku Sumbat /bh 770
51 Paku beton / bh 1,100
52 Paku Payung / kg 28,000
53 Solar / ltr 11,000 Sesuai Pemerintah
54 Bensin / ltr 11,500 Sesuai Pemerintah
55 Pelumas / ltr 26,000
56 Minyak tanah / ltr 12,000 Sesuai Pemerintah
57 Sewa excavator / jam 375,000
58 Hydrolic Oil / ltr 38,000
59 Greese / kg 110,000
60 Transmisi / kg 60,000
61 Filter / filter 350,000
62 Alat Bantu / Sewa Ponton / jam 190,000
63 Sewa Stamper per jam /jam 55,000
64 Air / tangki 120,000 isi tangki 8000 liter
65 Minyak Bekisting / ltr 30,000
66 Besi jaring kawat baja / kg 18,000
67 kayu terentang (kayu klas III) / m3 1,050,000
68 Plywood 1,20 x 2,40 m Tebal 4 mm / lbr 80,000
69 Dolken kayu galam Ø-8-10/4 m / btg 27,500
75 Bambu Ø 6 – 8 /600 cm / btg 18,645
76 Tali ijuk / kg 9,000
77 Pipa Stainlessteel Ф 3 " / Batang 450,000
78 Pipa Stainlessteel Ф 2 " / Batang 250,000
79 Pipa Stainlessteel Ф 1 " / Batang 140,000
80 Pipa Stainlessteel Ф 1/2 " / Batang 140,000
81 Atap Galvalum Tebal 0,4 mm / m2 110,000
82 PVC Waterstop lebar 150 mm /m1 78,000
83 PVC Waterstop lebar 200 mm / m2 102,000
84 Paku Sekrup Gypsum /kg 45,000
85 Plywood 1,20 x 2,40 m Tebal 94 mm / lbr 135,000
MRICAN
kiri kanan
Pas batu kali 1.7 1500 1100 4,420.00
Plesteran 1.7 1500 1100 4,420.00
Siar 2.7 1500 1100 7,020.00
Trucuk 2 1500 1100 5,200.00
GANG WANGANDOWO
Pas batu kali 0.97 285 276.45
Plesteran 0.9 285 256.50
Siar 1 285 285.00
Trucuk 2 285 570.00
Galian tanah 2 285 570.00
k dicetak