KURVA - S (MASTER PROGRAM)

PEKERJAAN : XXX
LOKASI : YYY
PERIODE : -
TANGGAL : 1 OKTOBER 2019 - 31 MARET 2020
NO. SPK :

JUMLAH WAKTU PELAKSANAAN PEKERJAAN = 6 BULAN


BOBOT
NO URAIAN PEKERJAAN HARGA Okt-19 NOV 19 Des-19 Jan-20 Feb-20 Mar-20 KET.
(RP.) (%) 1 2 3 4 5 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5
Rencana 0,876 0,876 0,876 0,876 0,876
I PEKERJAAN PENDAHULUAN 6.452.600,00 4,38
Realisasi
Rencana 2,332 2,332 2,332 2,332 2,332
II PEKERJAAN PONDASI 17.175.400,00 11,66
Realisasi
Rencana 1,300 2,000 3,000 3,000 2,120 2,120 1,300
II PEKERJAAN BETON 21.853.800,00 14,84
Realisasi
Rencana 1,000 1,000 1,000 1,220 3,000 3,000 3,000 1,000
IV PEKERJAAN BATA MERAH DAN PLESTERAN 20.941.800,00 14,22
Realisasi
Rencana 1,312 1,313 1,313 1,313 1,313 1,313 1,313
V PEKERJAAN KUSEN DAN PINTU 13.530.400,00 9,19
Realisasi
Rencana 1,000 2,000 2,000 4,000 2,500 2,500 1,060
VI PEKERJAAN KAYU DAN ATAP 22.180.400,00 15,06
Realisasi
Rencana 0,250 0,700 0,700 0,700 0,300 0,100 0,100 0,100
VII PEKERJAAN PLAFOND 4.352.700,00 2,95
Realisasi
Rencana 0,500 1,319 1,319 1,046 1,046
VIII PEKERJAAN KRAMIK 7.702.400,00 5,23
Realisasi
Rencana 0,100 0,150 0,150 0,100 0,100 0,100 0,060
IX PEKERJAAN SANITASI 1.119.900,00 0,76
Realisasi
Rencana 1,035 1,300 1,200 1,200 0,885 0,590
X PEKERJAAN AIR 9.147.100,00 6,21
Realisasi
Rencana 0,800 1,300 1,300 1,300 0,840 0,700
XI PEKERJAAN LISTRIK 9.188.600,00 6,24
Realisasi
Rencana 1,100 1,200 1,300 1,300 1,300 1,200 1,100 0,770
XII PEKERJAAN PENGECATAN 13.660.700,00 9,27
Realisasi

JUMLAH = 147.305.800,00 100,00


RENCANA PROGRESS MINGGUAN (%) = 0,00 0,00 0,876 0,876 3,208 3,208 3,208 3,632 4,332 3,000 5,000 6,432 6,433 7,833 6,813 6,813 5,373 4,398 3,400 3,350 3,350 3,225 3,190 2,819 2,779 2,346 2,246 1,100 0,770
RENCANA PROGRESS KOMULATIF (%) = 0,00 0,00 0,876 1,752 4,960 8,168 11,376 15,008 19,340 22,340 27,340 33,772 40,205 48,038 54,851 61,664 67,037 71,435 74,835 78,185 81,535 84,760 87,950 90,769 93,548 95,894 98,140 99,240 100,0

REALISASI PROGRESS MINGGUAN (%) = 0,00


REALISASI PROGRESS KOMULATIF (%) = 0,00

SELISIH (DEVIASI) MINGGUAN (%) = 0,00


SELISIH (DEVIASI) KOMULATIF (%) = 0,00

DISETUJUI OLEH DIBUAT OLEH:


KONSULTAN PENGAWAS / OWNER KONTRAKTOR PELAKSANA
PT. ABC PT. XYZ

Nindy Kinanti
Project Manager XXX Project Manager